You are on page 1of 9

F-109

HOLD POINTS

FORM
ITEM DESCRIPTION ATTACHMENTS
PMI SRF RFI IR CPR QCIR OTHERS
I. PRE-CONSTRUCTION STAGE
a. Master Construction Schedule & S-Curve /
b. Manpower Loading /
c. Equipment Loading /
a. Construction Methodology /
e. Project Execution Plan (Tower Crane Location, /
Contractor's, NSC's & Owner's Temfacil
Location, etc.)
b. For Construction Drawing (FCD) /
g. House Rules / Work Restrictions /
c. Construction Shop Drawing (CSD) /
i. Submittal Log /
d. Material Testing
d.1 Rebars /
d.2 Ready Mix /
d.2.1 Cement Ratio per design mix
d.3 CHB /
d.4 Other materials as specified
e. Site Control Points Turn Over /
f. Material Submittals / physical samples
g. Material Delivery Check / gate pass delivery receipts
&qcir
h. Setting Out Plan
h.1 Foundation /
h.2 Column /
h.3 Beam /
h.4 Wall /
i. Cutting List
i.1 Foundation & Tie Beams /
i.2 Column /
i.3 Beams/Girders /
i.4 Shear Walls /
i.5 Slabs /
i.6 Others /

II. CONSTRUCTION STAGE

ARCHITECTURAL

EELHI

ITEM ITEM DESCRIPTION TRADE TOLERANCE WORK


INSPECTION
COMMENCEMENT
REQUEST
NOTICE

1 Masonry Works
1.01 CHB Testing ST √
1.02 Rubbed Concrete (smooth finish ceiling) AR 6mm max √

Concreting of Zocallo (For T&B only)


1.03 Inspection of wall setting-out AR zero √
1.04 Inspection of dowels and waterstop prior to AR zero
pouring
EELHI

ITEM ITEM DESCRIPTION TRADE TOLERANCE WORK


INSPECTION
COMMENCEMENT
REQUEST
NOTICE
1.05 Inspection of wall drain and lavatory drain PL zero
setting-out
1.06 CHB Laying AR zero √
Inspection of wall setting-out prior to CHB laying
1.07 Inspection of CHB Laying before last CHB layer AR √
1.08 Concreting of Stiffener Column ST √
Inspection of Rebars prior to enclosure and
pouring
1.09 Concreting of Lintel Beam ST √
Inspection of Rebars prior to enclosure and
pouring
Prior to plastering
1.10 Inspection of box-setting EE Horizontal +/- 5mm Vertical +/- 0mm √
1.11 Inspection of box-setting AU Horizontal +/- 5mm Vertical +/- 0mm
1.12 Inspection of Waterline and Sanitary/Plumbing PL
stub-outs
1.13 Inspection of "butones" AR 25mm max ; 12mm min ; 25 -37mm √
with wiremesh ; 37+ mm to demolish
wall
Plastering Works Proper
1.20 Inspection of Plumbness & Areas with Kapak AR +/- 3mm ; zero for kapak √
1.21 Inspection of Structural Members to CHB, joint AR 12mm gap +/-3mm
connection backer rod prior to sealant
1.22 Inspection of Applied Sealant AR 12mm gap +/-3mm
1.23 Inspection of applied sealant prior to paining AR 12mm gap +/-3mm √
2 Waterproofing Works
2.0 Water plug / sealant & stub outs AR √
2.1 1st Coat AR √
2.2 2nd Coat/more than 2 coats AR √
2.3 Leak Test AR √
3 Floor Finishes
3.1 Floor Topping AR 25mm minimum ; 25mm to 50mm with √
Inspection of wiremesh butones and thickness welded wiremesh ; 50mm+ provide
of topping, and slope temperature bars
3.2 Dustproofing Application (before application) AR √
3.3 Dustproofing Application (after application) AR √
3.4 Epoxy Flooring Coating (before application) AR √
3.5 Epoxy Flooring Coating (after application) AR √
4 Tiling Works
4.1 Tile Setting-Out AR zero √
Inspection of reference point and elevation prior
to tile installation.
4.2 Tile Installation (after installation) AR √
4.3 Slope to Drain AR no water ponding √
5 Dry Wall Works
5.01 Inspection of wall setting-out AR zero √
5.02 Installation of framing and board (one-side only) AR √
5.03 Installation of box-setting EE Horizontal +/- 5mm Vertical +/- 0mm
5.04 Installation of Aircon drain and water line PL
5.05 Installation of box-setting AU Horizontal +/- 5mm Vertical +/- 0mm
5.06 Installation of batt insulation. AR
5.07 Sanding / Sealant / Ready to receive paint AR 12mm gap +/-3mm √
Prior to enclosure of dry wall ( all tests should be completed and EELHI inspected )
5.06 Inspection of installed Batt Insulation AR
5.07 Inspection of installed framing AR
5.08 Inspection of box-setting EE Horizontal +/- 5mm Vertical +/- 0mm
5.09 Installation of installed aircon drain and water PL F-102 ER
line (Dry Wall)
EELHI

ITEM ITEM DESCRIPTION TRADE TOLERANCE WORK


INSPECTION
COMMENCEMENT F-102 ER
REQUEST
NOTICE (Dry Wall)
5.10 Witness for testing - Hydrotest PL
5.11 Inspection of box-setting AU Horizontal +/- 5mm Vertical +/- 0mm
5.12 Application of Fire Rated Sealant of MEPF MEPF
6 Ceiling Works
6.1 Installation of framing AR √
6.2 Installation of duct works ME
6.3 Installation of wires and droppings EE
6.4 Installation of water line and sanitary line PL
6.5 Installation of cross main branch line and FP
droppings
6.6 Installation of wires and droppings AU
Prior to Ceiling Enclosure ( all tests should
be completed and EELHI inspected )
6.7 Inspection of installed framing AR
6.8 Inspection of installed duct works incl whole ME
system
6.9 Witness for testing - Air flow ME
6.10 Inspection of installed wires and droppings EE
6.11 Inspection of installed water line and sanitary PL
line F-102 ER
6.12 Witness for testing - Hydrotest PL (CEILING)
6.13 Inspection of installed cross main branch line FP
and droppings
6.14 Witness for testing - Hydrotest FP
6.15 Inspection of installed wires and droppings AU
6.16 Application of Fire Rated Sealant of MEPF MEPF

7 Doors and Windows


7.1 Acceptance of Doors and Hardware AR √
7.2 Door Jamb Installation AR
7.3 Door Panel Installation AR √
Inspection of plumbness for the door jamb.
7.4 Door Accessories Installation AR
7.5 Inspection of installed door accessories AR
Meal Louver / Window Installation
7.6 Louver / Window Installation AR √
7.7 Inspection of installed Louver / Window AR √
7.8 Sealant Works AR
7.9 Leak Tests on Windows AR √
8 Metal Works
8.01 Stair Railing Installation (before installation) AR √
8.02 Stair Railing Installation (after installation) AR √
8.03 Stair Nosing Installation (before installation) AR √
8.04 Stair Nosing Installation (after installation) AR √
8.05 Corner Guard Installation AR √
Inspection of Complete Mock up installation.
8.06 Trench Grating Installation AR √

Structural Steel Works ( MEPFS works enlosed on ST steel must be tested and EELHI approved

8.07 Structural Steel Works Installation ( before ) ST √


8.08 Weld Testing / Torque Tests ST √
9 Painting Works
Exterior Wall Paints
9.1 Concrete Neutralizer (before application) AR √
9.2 Primer/ 1st Coat (before application) AR √
9.3 Final Coat AR √
9.4 Handover AR √
Interior Wall Paint (on Concrete)
EELHI

ITEM ITEM DESCRIPTION TRADE TOLERANCE WORK


INSPECTION
COMMENCEMENT
REQUEST
NOTICE
9.5 Concrete Neutralizer (before application) AR √
9.6 1st Coat & 2nd Coat AR √
9.7 Handover AR √
Interior Wall Paint (on Gypsum)
9.8 1st Coat & 2nd Coat AR √
9.9 Handover AR √
Interior Ceiling Paint (on Slab Soffit)
9.10 Concrete Neutralizer (before application) AR √
9.11 1st Coat & 2nd Coat AR √
9.12 Handover AR √
Interior Ceiling Paint (on Gypsum)
9.13 1st Coat (before application) AR √
9.14 2nd Coat AR √
9.15 Handover AR √
Metal Works
9.16 1st Coat/2nd Coat/3rd Coat AR √
9.17 Handover AR √
Pavement Markings
9.18 Layout and Setting Out AR √
9.19 1st Coat/2nd Coat/3rd Coat AR √
9.20 Handover AR √
10 Pre-Cast
Prior to Pouring of Pre-Cast
10.01 Inspection of Pre-Cast Wall - Setting-Out AR zero √
10.02 Inspection of Pre-Cast Wall - Block-Out of TED ME
at KED
10.03 Inspection of Pre-Cast Wall - Electrical EE
Embedments
10.04 Inspection of Pre-Cast Wall - Aircon drain PL
10.05 Inspection of Pre-Cast Corner Ledge - AR
Setting-Out
10.06 Inspection of Pre-Cast ACU Ledge - Setting-Out AR
Precast ACU ledge
10.07 Inspection of rebars prior to pouring ST √
10.08 Inspection of piping for aircon drain, elevation, PL
setting-out, alignment prior to pouring
10.09 Plugging of all connections & Waterproofing of AR √
ACU ledge
10.10 Leak Test / Flow Test PL √
Prior to pouring of Slab
10.12 Setting out & Installation of Precast Wall ST zero √
10.11 Inspection of Precast Designed Structural ST
Connections
During finishing phase
10.12 Inspection of pre-cast termination AR √
10.13 Inspection of pre-cast groove AR √
10.14 Inspection of Pre-Cast joint filler and backer rod AR √
and sealant
11 Others
For Wheelstop Installation
11.01 Inspection of Fabrication & Setting-Out prior to AR √
installation
For Lavatory Ledge
11.02 Inspection of rebars prior to pouring ST √
11.03 Inspection of formworks setting-out and elevation AR
prior to pouring
11.04 Inspection of all stub-outs PL
For Island/Curbs
EELHI

ITEM ITEM DESCRIPTION TRADE TOLERANCE WORK


INSPECTION
COMMENCEMENT
REQUEST
NOTICE
11.05 Inspection of setting-out prior to formworks AR zero √
installation
11.06 Inspection of rebars prior to pouring ST
For Pipe Chase
11.07 Inspection of setting-out prior to zocalo AR zero √
installation and CHB laying.
11.08 CHB Laying last layer AR √
11.09 Tool Joint / Plastering AR
11.10 Cast back of opening AR
Plumbing Works
11.11 Installation of Sanitary Riser, Soil, Sewer, PL √
Waste, Storm
11.12 Installation of Vent Stack Riser PL √
11.13 Installation of Ubolt bracket PL √
11.14 Installation of water line (CWL, HWL) PL √
11.15 Leak Test PL √
For Window Opening
11.16 Inspection of window opening prior to installation AR √
For OSM
11.17 Material Delivery check AR QCIR

STRUCTURAL

EELHI

ITEM ITEM DESCRIPTION TRADE TOLERANCE WORK


INSPECTION
COMMENCEMENT
REQUEST
NOTICE

1 Excavation
1.1 Gridline Setting Out AR √
1.2 Inspection of excavation setting-out and elevation AR √
prior to rebar installation.
1.3 Slope Protection Works ( During ) ST √
2 Footing and Footing Tie Beam
2.1 Soil Poisoning IN before ; IR after √
2.2 Inspection of Lean Concrete / gravel bedding /
F-104 CPR
polythelene sheet / spacers
2.3 Inspection of rebar prior to pouring. ST
2.4 Inspection of column setting-out prior to pouring. AR √
3 Column / Shearwall
3.1 Inspection of rebar and spacers prior to ST
enclosure.
F-103 FER
3.2 Inspection of roughing ins and box-setting EE
3.3 Inspection of roughing ins and box-setting AU
3.4 Inspection of plumbness prior to pouring. AR F-104 CPR
3.5 Stripping of Form ST F-105 FSR
3.6 Removal of Permanent Shoring ST √
4 Slab
4.01 Inspection of wall setting-out prior to bottom bar AR √
installation
4.02 Inspection of Formworks layout and Elevation, ST F-104 CPR
Camber
4.03 Inspection of rebars for beam and girders prior to ST F-104 CPR
installation of pipe sleeves
4.04 Inspection of rebars for slab prior to pouring ST F-104 CPR
4.05 Inspection of block-outs for riser and block-out for ME F-101 IR &
refrigerant F-104 CPR
4.06 Inspection of roughing ins and box-setting EE F-101 IR &
F-104 CPR
4.07 Inspection of stub outs PL F-101 IR &
EELHI

ITEM ITEM DESCRIPTION TRADE TOLERANCE WORK


INSPECTION
COMMENCEMENT
REQUEST
NOTICE
F-104 CPR
4.08 Inspection of elevation for pipe sleeves and FP F-101 IR &
block-outs for riser F-104 CPR
4.09 Inspection of roughing ins and box-setting AU F-101 IR &
F-104 CPR
4.10 Inspection of ST finish elevation prior to pouring. AR F-104 CPR
4.11 Stripping of Form ST F-105 FSR
4.11 Removal of Permanent Shoring ST √
4.12 Application of approve curing ST √
compound/methodology
5 Parapet
5.1 Inspection of wall setting-out prior to rebar AR
installation and formworks installation at one side F-103 FER
5.2 Inspection of rebar prior to enclosure ST
5.3 Inspection of plumbness prior to pouring AR F-104 CPR
5.4 Stripping of Form ST
F-105 FSR
5.5 Removal of Permanent Shoring ST
6 Stairs
6.1 Inspection of setting-out prior to formworks and AR √
rebar installation
6.2 Inspection of rebar for RC wall and stiffener ST F-103 FER
column prior to enclosure
6.3 Inspection of rebar prior to pouring ST
6.4 Inspection of roughing ins and box-setting EE F-104 CPR
6.5 Inspection of setting-out prior to pouring AR
6.6 Stripping of Form ST
F-105 FSR
6.7 Removal of Permanent Shoring ST
7 Rebar Testing ST √
8 Concrete Cylinder Testing ST √

FIRE PROTECTION

EELHI

ITEM ITEM DESCRIPTION TRADE TOLERANCE WORK


INSPECTION
COMMENCEMENT
REQUEST
NOTICE

Line Checking ( Crossmain, Feedmain &


1.0
Branchline)
1.1 Pipe Sleeving FP √
1.2 Pipe support FP
1.3 Welding Works FP

1.4 Pipe and primer paint FP
1.5 Treading fabrication of branchline FP
1.6 Installation of Crossmain, Feedmain & Branchline FP √
2.0 Droppings
2.1 Location FP

2.2 Elevation FP
2.3 Hydrotesting FP √
3.0 Fire Hose Cabinet & Fire Extinguisher
3.1 Location FP

3.2 Elevation FP
4.0 Sprinkler Heads
4.1 Location FP

4.2 Elevation FP
5.0 Risers
5.1 Block-outs FP √
5.2 Supports FP

5.3 Piping welding FP
5.4 Hydrotesting FP √
EELHI

ITEM ITEM DESCRIPTION TRADE TOLERANCE WORK


INSPECTION
COMMENCEMENT
REQUEST
NOTICE
5.5 Painting FP √
6.0 Pumps (Fire Pump/ Jockey Pump)
6.1 Installation inspection FP √
6.2 Automatic fire alarm testing FP
6.3 Testing Commissioning -Manual FP √
6.4 Testing Commissioning -Automatic FP

PLUMBING / SANITARY

EELHI

ITEM ITEM DESCRIPTION TRADE TOLERANCE WORK


INSPECTION
COMMENCEMENT
REQUEST
NOTICE

1.0 Line Checking Cold Waterline


1.1 Block-outs/Stub-outs PL

1.2 Pipe Sleeving PL
1.3 Sealant PL √
1.4 Pipe support PL √
1.5 piping PL √
1.6 Hydrotesting PL √
2.0 Line Checking Storm Drainage
1.1 Block-outs PL √
1.2 supports PL √
1.3 piping PL √
1.4 Gravity Test PL √
3.0 Line Checking Waste, Soil & Vent
1.1 Block-outs/Stub-outs PL √
1.2 Pipe Sleeving PL √
1.3 Pipe support PL √
1.4 Flood Test/Gravity Test PL √
4.0 Installation of Fixtures
1.1 Water closet & accessories PL
1.2 Lavatory & accessories PL √
1.3 Shower Set PL
1.4 Grease trap PL

1.5 Kitchen sink PL
1.6 Testing PL √
5.0 Overhead Water Tank
1.1 support PL

1.2 piping PL
1.3 Testing PL √
Installation of Pumps ( Boster Pump & Transfer
6.0
Pumps)
1.1 support PL
1.2 Welding Works PL √
1.3 Piping PL
1.4 Testing PL √
7.0 Testing and Commissioning PL √

MECHANICAL

EELHI

ITEM ITEM DESCRIPTION TRADE TOLERANCE WORK


INSPECTION
COMMENCEMENT
REQUEST
NOTICE

1.0 Mechanical System (Smoke Exhaust Damper)

1.1 Block-out ME
1.2 Location & lay-out ME √
EELHI

ITEM ITEM DESCRIPTION TRADE TOLERANCE WORK


INSPECTION
COMMENCEMENT
REQUEST
NOTICE √
1.3 Dimension ME
1.4 Installation of Support ME √
1.5 Installation of Duct ME √
1.6 Application of Sealant ME

1.7 Inspection and Testing ME
1.8 Commissioning ME √
2.0 Exhaust Duct Riser
2.1 Block-out ME
2.2 Location & lay-out ME √
2.3 Dimension ME
2.4 Installation of Support ME

2.5 Installation of Duct ME
2.6 Application of Sealant ME

2.7 Inspection and Testing ME
3.0 Chase for Stairwell Pressurization Air Duct
3.1 Block-out ME
3.2 Location & lay-out ME √
3.3 Dimension ME
3.4 Installation of Duct ME

3.5 Installation of Support ME
3.6 Application of Sealant ME

3.7 Inspection and Testing ME
3.8 Commissioning ME √

4.0 Refrigerant Suction/ Refrigerant Liquid (RS/RL)

4.1 Sleeving ME

4.2 Location & lay-out ME
4.3 Installation of Refrigerant Tubing ME

4.4 Installation of support ME
4.5 Inspection and Testing ME

4.6 Commissioning ME
5.0 Smoke Exhaust Fan (SMEF)
5.1 Check Location and Lay-Out ME √
5.2 Prepare Concrete Padding ME √
5.3 Install The Fan ME √
5.5 Inspection and Testing ME √
5.6 Commissioning ME √
6.0 Acu & Fcu
6.1 Check Location and Lay-Out ME √
6.2 Prepare Concrete Padding ME √
6.3 Install The ACU & FCU ME √
6.4 Inspection and Testing ME √
7.0 Turbo Fan
7.1 Check Location and Lay-Out ME √
7.2 Install The Fan ME √
7.3 Inspection and Testing ME √
8.0 Toilet & Kitchen Exhaust Duct (TED & KED)
8.1 Check Location and Lay-Out ME √
8.2 Install The Fan ME √
8.3 Inspection and Testing ME √
9.0 Diesel Storage Tank
9.1 Check Location and Lay-Out ME √
9.2 Prepare Concrete Padding ME
9.3 fabric ation of tank ME √
9.4 Installation of tank ME
9.5 Inspection and Testing ME √
EELHI

ITEM ITEM DESCRIPTION TRADE TOLERANCE WORK


INSPECTION
COMMENCEMENT
REQUEST
NOTICE
ELECTRICAL

EELHI

ITEM ITEM DESCRIPTION TRADE Tolerance WORK


INSPECTION
COMMENCEMENT
REQUEST
NOTICE

A Feeders / Risers / Branch Circuits


1.0 Roughing-ins Works
1.1 Size and type of Conduits EE
1.2 Location of installation ( Setting out ) EE

1.3 Hangers and Supports / Painting EE
1.4 Fire stopping Sealant EE
2.0 Wiring Works
2.1 Size and Type of Wires and Cables EE
2.2 Visual Inspection EE

2.3 Termination / Splicing Works EE
2.4 Insulation resistance testing ( megger test ) EE
B Panelboards / ECB / Switcgears
1.0 Dry Type Transformers
1.1 Delivery and visual inspection EE
1.2 Ratings / Specifications EE
1.3 Test results from supplier EE
1.4 Factory Acceptance test EE √
1.5 Installation works EE
1.6 Testing and Commissioning EE
1.7 Terminations and Energization EE
2.0 Lighting Fixtures Installation Works
2.1 Delivery and visual inspection EE
2.2 Ratings / Specifications EE
2.3 Location and mounting elevation EE √
2.4 Hangers and Supports / Painting EE
2.5 Testing and Commissioning EE
3.0 Wiring Devices Installation
3.1 Delivery and visual inspection EE
3.2 Ratings / Specifications EE

3.2 Location and mounting elevation EE
3.3 Testing and Commissioning EE
4.0 Lightning Protecttion
4.1 Delivery and visual inspection EE
4.2 Test results from supplier EE

4.3 Factory Acceptance test EE
4.4 Location and setting of Arrester EE
5.0 Grounding System
5.1 Size and type of riser conduits EE
5.2 Location of riser conduit EE
5.3 Location and setting out of ground rods EE √
5.4 Continuity test EE
5.5 Earth resistance test EE

NOTE : One check ( √ ) = one inspection

You might also like