INSPECTION & TEST PLAN PAGE 1-2
Date 25/12/ 2023
ITP Title INSPECTION & TEST PLAN FOR SITE FENCE & GATE ITP NO. SEP-WAD-CIV-ITP-0003
3 Concrete Work
Pre-pour concrete inspection. Applicable for both post footing & anchor
3.1 As per Construction Drawing H/R H/R H/R H/R
beam frame work
Concrete Placing Mix design, Concrete quality check on site,
3.2 H/R H/R H/R S
third party test, concrete curing
4 Earth Work
Excavation & Ground Leveling Approved Drawings (IFSC) backfilling and compaction of the first
4.1 W W W W
` layer up to anchor beam bottom level
Survey Work
5 Precast installation
Line, Straining, Corner, End, Bracing, Posts As per MOS & drawing
5.1 H/R H/R H/R H
Installation.
Backfilling & compaction As per specification backfilling and compaction of the first
5.2 H/R H/R H/R W
layer up to anchor beam bottom level
Anchor Beams Installation. As per specification
5.3 H/R H/R H/R W
6 Chain link
Final backfilling & Chain link installation
6.1 As per specification H/R W/R W/R
S
7 COMPONENTS INSTALATION
8.3 Pre-pour inspection for gate As per Construction Drawing H/R W/R W/R H/R
8.4 Final inspection for gate As per Construction Drawing H/R W/R W/R H/R
H: For Hold point, SEPCO will raise and submit RFI to owner, if owner did not attend the inspection then SEPCO will proceed the work to next stage through owner permission.
W: For witness point, SEPCO will raise and submit RFI to owner, if owner did not attend the inspection then SEPCO will proceed the work to next stage without owner permission.
1 Drawings available
2 Material Approval
REMARKS:
Note tick all check items column under Yes - Satisfactory; No - Not Satisfactory; NA - Not Applicable.
Signature
Name
Description
Location
SEP-WAD-CIV-ITP-0003_rev04 Item No: Rev
ITP NO
Note:
Signature
Name
Title
Date
Excavation Checklist
Department RFI No.
Description
KKS No. Drawing No.
Location
ITP NO SEP-WAD-CIV-ITP-0003_rev04 Item No: Rev:
SN Description Accepted Rejected Remarks
1 Line and slope according to drawing
2 Depth of excavation
Note:
EPC
ISSUED BY Sub-Contractor SEPCO QC Owner
Construction
Signature
Name
Title
Date
1 Concrete
5 Thoroughly compacted
Note:
EPC
ISSUED BY Sub-Contractor SEPCO QC Owner
Construction
Signature
Name
Title
Date
3 Removing formwork
Concrete surface (no honeycomb, no crack, no twisting, no sagging, no bulging and no exposed
4 rebar)
5
Note:
EPC
ISSUED BY Sub-Contractor SEPCO QC Owner
Construction
Signature
Name
Title
Date
Note:
EPC
ISSUED BY Sub-Contractor SEPCO QC Owner
Construction
Signature
Name
Title
Date
1 Brace posts
2 Brace posts
3 V-Arms
4 Top Rail
5 Clips
Barbed Wire
6
7 Concertina Wire
Note:
EPC
ISSUED BY Sub-Contractor SEPCO QC Owner
Construction
Signature
Name
Title
Date
Note:
EPC
ISSUED BY Sub-Contractor SEPCO QC Owner
Construction
Signature
Name
Title
Date
1 Check the overall condition of the gate, inspecting for any visible
defects, damage, or signs of wear.
2 Test the gate's opening and closing mechanisms to ensure smooth
operation
3 Verify that the gate is properly aligned with the fence and that it
opens and closes evenly.
4 Check the finish and coating of the gate for uniformity and durability
5
6
7
Note:
EPC
ISSUED BY Sub-Contractor SEPCO QC Owner
Construction
Signature
Name
Title
Date