You are on page 1of 182

ATLANTIS THE PALM

AQUAVENTURE EXPANSION PHASE III


DUBAI, UAE

MEPF GENERAL REQUIREMENTS AND SCOPE OF WORKS

REV. A
ISSUED FOR TENDER ADDENDUM
12th SEPTEMBER 2019

Revision Date By Description Resp. Consult


A 2019.09.12 KJH Issued for Tender Addendum WME NOTE: THIS DOCUMENT TO BE READ IN CONJUNCTION
WITH THE MEP DRAWING PACKAGE.

SCALE: SHEET DATE STARTED: CHECKED: STAGE:


SIZE:

NTS A4 2019 04 11 KJH TA01


DWG № Rev:

18176-MEP-SPC-0-001-00 A
Error: Reference source not found
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

TABLE OF CONTENTS:
01 | INTRODUCTION.......................................................................................................................................... 5
1.1| PROJECT DESCRIPTION.............................................................................................................................. 5
1.2| APPROVED VENDORS / MANUFACTURERS...........................................................................................7
1.3| DEFINITIONS................................................................................................................................................. 7
1.4| ABBREVIATIONS.......................................................................................................................................... 9
02 | TENDER ACTIONS.................................................................................................................................... 10
2.1| REVIEW OF TENDER DRAWINGS............................................................................................................10
2.2| DISCREPANCIES IN TENDER DOCUMENTS..........................................................................................11
2.3| PRECEDENCE BETWEEN DRAWINGS, SPECIFICATION AND DOCUMENTS..................................12
2.4| INFORMATION TO BE SUBMITTED WITH TENDER............................................................................12
03 | TECHNICAL REQUIREMENTS..............................................................................................................13
3.1| SUMMARY OF WORK................................................................................................................................ 13
3.2| OPERATING CONDITIONS........................................................................................................................13
3.3| SPECIALIST INSTALLERS.........................................................................................................................13
3.4| CONTRACTORS DESIGN RESPONSIBILITY...........................................................................................14
3.5| CONTRACTORS CALCULATIONS............................................................................................................17
3.6| SERVICES COORDINATION......................................................................................................................18
3.7| FINAL EQUIPMENT LOCATION...............................................................................................................19
3.8| BUILDERS WORK....................................................................................................................................... 20
3.9| SUPPORTS AND SLEEVES.........................................................................................................................21
3.10| PLANT AND EQUIPMENT..........................................................................................................................21
3.11| PLANT WARRANTIES................................................................................................................................22
04 | QUALITY REQUIREMENTS....................................................................................................................23
4.1| STATUTORY REQUIREMENTS.................................................................................................................23
4.2| GOVERNING STANDARDS........................................................................................................................23
4.3| ATLANTIS THE PALM GUIDELINES.......................................................................................................23
4.4| APPROVALS PERMITS AND FEES...........................................................................................................24
4.5| QUALITY ASSURANCE..............................................................................................................................24
4.6| MANAGEMENT OF THE WORKS.............................................................................................................25
4.7| COMMISSIONING PROJECT MANAGEMENT........................................................................................26
05 | HEALTH, SAFETY AND ENVIRONMENT REQUIREMENTS...........................................................27
5.1| HEALTH AND SAFETY...............................................................................................................................27
5.2| NOISE............................................................................................................................................................ 28
5.3| FIRE PRECAUTIONS................................................................................................................................... 28
5.4| PROHIBITIED MATERIALS AND SUBSTANCES....................................................................................29
5.5| ISOLATION OF POLLUTANT SOURCES..................................................................................................30
06 | ADMINISTRATIVE REQUIREMENTS...................................................................................................31
6.1| SUMMARY................................................................................................................................................... 31
6.2| PROJECT QUALITY PLAN (PQP)..............................................................................................................31
6.3| CONSTRUCTION PROGRESS DOCUMENTATION.................................................................................32
6.4| PHOTOGRAPHS........................................................................................................................................... 33
6.5| MATERIAL AND DRAWING SUBMITTAL PROCEDURES...................................................................33
6.6| ALTERNATIVE MANUFACTURER’S EQUIPMENT...............................................................................36
6.7| MANUFACTURERS TECHNICAL DATA..................................................................................................36
07 | DOCUMENTATION REQUIREMENTS..................................................................................................38
7.1| DOCUMENTS AND DRAWINGS ON SITE...............................................................................................38
7.2| CONTRACTORS WORKING DRAWINGS................................................................................................38
08 | EXECUTION AND CLOSE-OUT REQUIREMENTS.............................................................................42

September 2019 General Requirements and Scope of Works Tender Addendum


Page 3 of 182 Rev. A
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

8.1| PROGRAM OF WORKS...............................................................................................................................42


8.2| WORKING HOURS...................................................................................................................................... 43
8.3| SITE SUPERVISION..................................................................................................................................... 43
8.4| EXECUTION OF THE WORKS...................................................................................................................43
8.5| INSPECTION BEFORE CONCEALMENT..................................................................................................44
09 | INSPECTION, TESTING AND COMMISSIONING...............................................................................45
9.1| GENERAL..................................................................................................................................................... 45
9.2| MANUFACTURER TESTS...........................................................................................................................45
9.3| SITE TESTS................................................................................................................................................... 46
9.4| TEST NOTICES.............................................................................................................................................47
9.5| SAFETY PRACTICES FOR TESTING........................................................................................................48
9.6| COMMISSIONING........................................................................................................................................48
9.7| ENHANCED COMMISSIONING.................................................................................................................52
9.8| SYSTEM DEMONSTRATION.....................................................................................................................53
9.9| AUTHORITY AND SERVICE PROVIDER NOTICES...............................................................................53
010 | HANDOVER, OPERATION & MAINTENANCE...................................................................................54
10.1| INSTRUCTION OF EMPLOYERS STAFF..................................................................................................54
10.2| RECORD DOCUMENTATION....................................................................................................................55
10.3| RECORD DRAWINGS AND SCHEDULE..................................................................................................56
10.4| PLANT ROOM DRAWINGS, SCHEMATICS AND INSTRUCTIONS......................................................57
10.5| OPERATION AND MAINTENANCE MANUALS.....................................................................................58
10.6| ELECTRONIC OPERATING & MAINTENANCE MANUALS.................................................................64
10.7| CLOSE OUT PROCEDURES........................................................................................................................65
10.8| DEFECTS LIABILITY.................................................................................................................................. 65
10.9| CONTINUED OPERATIONAL SUPPORT..................................................................................................66
011 | SUSTAINABILITY REQUIREMENTS.....................................................................................................67
11.1| SCOPE OF WORKS...................................................................................................................................... 67
11.2| SUSTAINABLE DESIGN............................................................................................................................. 67
012 | METERING STRATEGY...........................................................................................................................68
12.1| CHILLED WATER METERING...................................................................................................................68
12.2| LOW TEMPERATURE HOT WATER (LTHW) METERING....................................................................68
12.3| ELECTRICITY METERING.........................................................................................................................68
12.4| WATER METERING.................................................................................................................................... 68
12.5| GAS METERING...........................................................................................................................................68
013 | MECHANICAL SERVICES.......................................................................................................................69
13.1| SCOPE OF WORKS...................................................................................................................................... 69
13.2| THERMAL INSULATION............................................................................................................................70
13.3| CHILLED WATER SYSTEM.......................................................................................................................72
13.4| LTHW SYSTEM............................................................................................................................................ 74
13.5| VENTILATION AND AIR CONDITIONING SYSTEM.............................................................................78
13.6| TOILET VENTILATION..............................................................................................................................80
13.7| SMOKE VENTILATION – B01....................................................................................................................80
13.8| BUILDING MANAGEMENT SYSTEM.......................................................................................................80
014 | PLUMBING SERVICES.............................................................................................................................84
14.1| SCOPE OF WORKS...................................................................................................................................... 84
14.2| DOMESTIC COLD WATER SYSTEMS......................................................................................................84
14.3| DOMESTIC HOT WATER SYSTEMS.........................................................................................................87
14.4| STORM WATER DRAINAGE......................................................................................................................88
14.5| IRRIGATION WATER SUPPLY..................................................................................................................88
14.6| SOIL AND WASTE DRAINAGE.................................................................................................................88
14.7| LEAK DETECTION SYSTEMS...................................................................................................................92

September 2019 General Requirements and Scope of Works Tender Addendum


Page 4 of 182 Rev. A
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

14.8| LIQUEFIED PETROLEUM GAS (LPG) SYSTEM......................................................................................92


015 | FIRE PROTECTION SYSTEM..................................................................................................................94
15.1| SCOPE OF WORKS...................................................................................................................................... 94
15.2| FIRE PROTECTION SYSTEM DETAILS....................................................................................................94
016 | ELECTRICAL SERVICES.........................................................................................................................97
16.1| SCOPE OF WORKS...................................................................................................................................... 97
16.2| MV SUPPLY.................................................................................................................................................. 98
16.3| INCOMING LV SUPPLY..............................................................................................................................98
16.4| LOW VOLTAGE (LV) SWITCHGEAR.......................................................................................................99
16.5| POWER FACTOR CORRECTION CAPACITORS....................................................................................103
16.6| HARMONIC STUDY AND MITIGATION................................................................................................104
16.7| ELECTRONIC SURGE PROTECTION DEVICES (SPDS).......................................................................104
16.8| LV DISTRIBUTION SYSTEM...................................................................................................................105
16.9| EARTHING AND BONDING SYSTEMS..................................................................................................108
16.10| SMALL POWER DISTRIBUTION AND PROVISION OF ACCESSORIES............................................109
16.11| STAND BY POWER SYSTEM...................................................................................................................111
16.12| UNINTERRUPTED POWER SUPPLY (UPS) SYSTEM...........................................................................113
16.13| EMERGENCY LIGHTING SYSTEM.........................................................................................................113
16.14| LIGHTNING PROTECTION SYSTEM......................................................................................................114
16.15| LIGHTING AND CONTROLS....................................................................................................................115
16.16| INTERNAL LIGHTING CONTROL SYSTEMS........................................................................................117
16.17| EXTERNAL LIGHTING AND CONTROL................................................................................................117
16.18| FIRE DETECTION AND VOICE ALARM SYSTEM................................................................................117
16.19| DISABLED TOILET ALARM SYSTEM....................................................................................................120
017 | APPENDIX A: DESIGN CRITERIA AND PARAMETERS.................................................................121
17.1| BUILDING SERVICES MEP......................................................................................................................121
17.2| UTILITIES................................................................................................................................................... 121
17.3| OPERATION AND MAINTENANCE........................................................................................................131
17.4| MAINTENANCE STRATEGY...................................................................................................................132
018 | APPENDIX B: SCHEDULE OF APPROVED MANUFACTURERS FOR MECHANICAL.............136
18.1| HVAC SERVICES....................................................................................................................................... 136
18.2| PUBLIC HEALTH....................................................................................................................................... 140
18.3| FIRE PROTECTION....................................................................................................................................144
18.4| GAS SERVICES.......................................................................................................................................... 148
019 | APPENDIX C: SCHEDULE OF APPROVED MANUFACTURERS FOR ELECTRICAL
SERVICES..................................................................................................................................................................... 155
19.1| ELECTRICAL.............................................................................................................................................. 155
020 | APPENDIX D: SCHEDULE OF GUARANTEES, WARRANTIES AND SPARES............................161
20.1| GENERAL................................................................................................................................................... 161
20.2| SCHEDULE OF EXTRA MATERIALS.....................................................................................................161
20.3| SCHEDULE OF WARRANTIES................................................................................................................172
END OF SCOPE OF WORKS..................................................................................................................................... 183

September 2019 General Requirements and Scope of Works Tender Addendum


Page 5 of 182 Rev. A
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

SECTION 01 11 99 - GENERAL REQUIREMENTS AND SCOPE OF


WORKS
01 | INTRODUCTION

1.1| PROJECT DESCRIPTION


A Aquaventure Waterpark Phase 3 is the extension of the existing ‘Aquaventure’ water park at Atlantis The Palm
(ATP), to create a third phase of the development with additional facilities for visitors.

B The development will be realized on an existing plot, PJCRC19-27B owned by ATP. The infrastructure
requirements of the new development will be provided from the existing ATP infrastructure on the overall ATP
plot, with additional capacity requested from utility providers if and where required.

C The new phase of the water park will offer additional slides, a river ride, cliff dive experience and the
accompanying retail and support facilities.

D The stipulated development area is understood to be 22,000 m² as per the RFP and will include land reclamation
undertaken as part of a separate contract. The contractor shall refer the Architectural documentation for the final
development area.

E The scope of works for the WME MEPF building services shall be the mechanical, electrical, public health and fire
engineering requirements within the buildings on the Phase 3 development of the water park, Aquaventure. This
will include a white box fit out of the retail premises and within the specialist plantrooms, the MEPF design of the
spaces for the specialist equipment design by others.

1 Full MEPF Design;


a. B1 – Triton Tower
b. B2 – Athena / Kids Tower
c. B3 – TRA Entry Building
d. B4 – Dolphin Bay Locker Room
e. B5 – F&B #1
f. B6 – F&B #2
g. B7 – Towel Kiosk [A+B+C]
h. B8 – Kids WC
i. B9 – Prayer Rooms
j. B11 – Retail Kiosk [A+B]
k. B12 – LTHW Boiler Room
l. B21 – LV Room / Generator / ‘DEWA’ Transformer Room
m. B22 – Fire Water Tank and Pump Room
n. B23 – Irrigation Water Tank and Pump Room
2 White Box Fit Out
a. B03 – Retail Digi Photo
b. B10 – Retail Digi Photo
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

3 Design of Plantrooms with provision of service requirements for extension by specialist;


a. B1 – Triton Tower Basement
b. B2 – Athena / Kids Tower Basement
c. B8 – Kids WC Basement
d. B13 – Wave MEP Room
e. B14 – Wave MEP Room
F Building B09 is an extension of the existing Dolphin Experience Centre, building W25-14. All the service
requirements for this building, will be sourced from within the existing building as an extension of the existing.

G Building B18 is a shade structure at the toddlers slide complex and does not have any MEPF design associated with
it. Any lighting in this area, is provided engineering circuiting from local buildings as part of the external lighting
design package.

H Buildings B19 and B20, the River Surge Tanks, have no MEPF design associated with them. The provision of
potable water as required, is provided within the infrastructure design package.

I Buildings B04, B05 and B10 are collectively known as ‘Dolphin Village’. These will source infrastructure
connections from a combination of extension of local infrastructure and new connections from the main
development area. The power source will be from existing panels within the Dolphin Experience Centre, building
W25-14, and the contractor shall be required to submit a full method statement for approval, prior to undertaking
any works to make these new connections and associated reconfiguration of the LV Distribution in this area.

J Building B24, known as the RMU Room, will source infrastructure connections from existing services within
building W25-10, and the contractor shall be required to submit a full method statement for approval, prior to
undertaking any works to make these new connections and associated reconfiguration of the LV Distribution in this
area.

K Further, the MEPF design will include for site wide services across the phase 3 water park development, in
coordination with the provisions by the infrastructure designer.

1 Power, Water and Drainage for ‘Carts’


2 General power outlets
3 Electrical supply requirements for external lighting power requirements
4 Potable Water for Bib Taps
5 Cooled cold water for External Showers
6 Drainage for External Shower – refer to infrastructure package
L This Specification describes the following:

1 Scope of Works
2 Description of the Engineering Services
3 Standards and Codes
M This Document shall be read in conjunction with:

1 General Conditions of Contract and any schedules, supplementary specifications, drawings and other
documents issued with it and enumerated in the invitation to Tender.
2 Architectural, Structural, Mechanical, Plumbing, Fire Protection, Electrical, Communications and Security
drawings.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

N MEPF Standard Specifications:

1 Division 10 – Specialties
2 Division 21 – Fire Suppression
3 Division 22 – Plumbing
4 Division 23 – HVAC
5 Division 25 – Integrated Automation
6 Division 26 – Electrical
7 Division 27 – Communications
8 Division 28 – Electronic Safety and Security
9 Division 33 – Utilities
O General Conditions of Contract and any schedules, supplementary specifications, drawings and other documents
issued with it and enumerated in the invitation to Tender.

P Items which are described in the Specifications and not indicated on the Tender Drawings or vice versa shall be
deemed to be included within the contract works. Contractors are reminded that the time for queries or clarification
of information in the Specifications or on the drawings is during the tender period. Claims for additional costs to the
Contract due to this procedure being ignored shall not be considered for payment.

1.2| APPROVED VENDORS / MANUFACTURERS


A The project is an expansion of the existing waterpark, and therefore there shall be a requirement to extend existing
site wide services and interface with existing systems. The following list is by the client, and represents
manufactures presently utilised within the Waterpark, and therefore the clients preferred vendors.

1 Switchboards and Panelboards – Tamco / Siemens


2 Cables – Ducab
3 Circuit Breakers – Siemens / ABB
4 Light Fittings and Drivers – Truelux
5 LED Lamps – Soraa / Toshiba
6 Lighting Control – Eaton Light
7 Fire Alarm – Notifier
8 Data Cable – Panduit
9 BMS – Siemens
10 Pumps – Grundfos
11 Drainage System – Hepworth
12 Hydronic Pipes – Hepworth / George Fisher
13 UPS – Liebert
14 FCU and AHU – Trosten
B The contractor shall be permitted to utilise alternatives, on an equal and approved basis only.

1.3| DEFINITIONS
A The following shall identify definitions for the project:

1 Employer: shall mean client name


2 Project Manager: shall mean Project Manager name
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

3 Architect: shall mean architect name or their representative appointed on their behalf
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

4 Contract Administrator (CA): is a term used throughout this specification and the Architect / Project
Manager shall carry out these duties.
5 Engineer: shall mean WME Consulting or their representatives who are appointed on behalf of CI to
represent the Contract Administrator (CA) on mechanical and electrical engineering services matters.
6 Contractor: shall mean the person or persons appointed to carry out the Works shown on the drawings and
described in the specifications and as deemed to be included in the contract.
7 Works: all services shown on the drawings and described in the specification shall be deemed to be included
in the contract.
8 Competent person: shall be a person, by reason of theoretical and practical training or actual experience or
both, is competent to perform the task or function or assume the responsibility in question and is authorized
to perform such a task or function.
9 Design process: shall be all the activities necessary to convert design input into design output.
10 Review: give notice and submit details to the CA for his comment and review, which shall be granted in
writing only. In the event of the CA not accepting that submittal, resubmit alternative details for review or
modify that submittal in accordance with the CA comments. Review of any submittal by the CA shall not
mean that the CA is responsible for the correctness of the submittal or its suitability for purpose and does not
relieve any contract responsibilities.
11 System: shall mean all equipment, accessories, controls, supports and ancillary items, including supply,
installation, connection, testing, commissioning and setting to work necessary for that section of the Works
to function.
12 Elsewhere: shall mean detailed or specified elsewhere in other clauses, sections, shown on the drawings or
contained in the specification or conditions of contract.
13 Terminal Units: shall mean those terminal units such as radiators, convectors, fan coil units, induction units,
variable or constant volume air boxes and other like equipment.
14 Ancillaries: shall mean all specified fittings, accessories, inserts, test points, bracketing, terminal equipment
connected to and installed in the engineering services system.
15 Concealed services: shall mean installations within builder‘s ducts/risers, trenches, cavities, ceiling voids or
floor voids.
16 Exposed services: shall mean installations within plant rooms, external or unprotected within occupied areas
or areas within a building with limited finishes.
17 Reviewed: Reviewed by the Engineer; normally a design or piece of equipment must be shown to have
operated successfully for not less than two years under conditions generally similar to those required by this
Contract. Facilities shall be given at the tender stage, if required by the Engineer, to enable him to evaluate
the equipment‘s features and performance. The review of a design or piece of equipment shall be without
prejudice to the acceptance tests required after installation.
18 Size: When related to pipe work means nominal size which generally approximates to the bore of steel tubes
and the outside diameter of copper tubes.
19 Complete installation: shall mean not only the major items of plant and equipment conveyed by this
specification, but all the incidental sundry components necessary for the complete execution of the works
and for the proper operation of the installation, with their labour charges, whether or not these sundry
components are mentioned in detail in the tender documents issued in connection with the contract.
20 “As indicated” “where indicated”, and “unless otherwise indicated”, refer to items or requirements
which are, or may be given elsewhere in the tender documents issued in connection with the contract, (e.g.
on a drawing, in a supplementary specification or in a schedule to this specification).
21 Provide: Design, Supply, install, testing and commissioning.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

22 Remove: Remove complete with all ancillary devices and equipment. Dispose of off-site in an
environmentally safe manner. Ensure that equipment is completely isolated from any energy sources prior to
removal. All piping and wiring shall be removed back to the nearest isolating point.
23 AHU means air handling unit, equipment that includes a fan or blower, heating, and/or cooling coils,
regulator controls, condensate drain pans and air filters to blow psychometrically conditioned air to a
dedicated area.
24 Energy Meter means set of instruments installed inside the Cooling Station to measure the rate of enthalpy
change in the chilled water by measuring flow rate and temperature different which indicates bulk rate of
consumption of cooling.
25 FCU means fan coil unit, equipment that includes a fan or blower, heating and/or cooling coils, regulator
controls, condensate drain pans and air filters to blow temperature controlled air to a dedicated area.

1.4| ABBREVIATIONS
A Generally, the following abbreviations are used throughout this specification:

1 AHJ Authority Having Jurisdiction


2 ANSI American National Standards Institute
3 ASHRAE American Society of Heating Refrigeration & Air Conditioning Engineers
4 ASME American Society of Mechanical Engineers
5 ASPE American Institute Plumbing Engineers
6 ASTM American Society for Testing and Materials
7 AWWA American Water Works Association
8 BS British Standard
9 BSRIA The Building Services Research and Information Association
10 CA Clients Appointed Commissioning Authority
11 CDM The Construction (Design and Management) Regulations (UK)
12 CFD Computational Fluid Dynamics
13 CIBSE Chartered Institute of Building Services Engineers
14 COSHH Control of Substances Hazardous to Health Regulations (UK)
15 CSA Canadian Standards Association
16 DCD Dubai Civil Defence
17 DGBR Dubai Green Building Regulations
18 DEWA Dubai Electricity and Water Authority
19 DM Dubai Municipality
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

20 SIRA Security Industry Regulatory Agency


21 EHS Environment Health & Safety
22 HVCA Heating & Ventilation Contractors Association
23 IEC The International Electro-technical Commission
24 IEEE Institute of Electrical and Electronic Engineers
25 IET Institution of Engineering and Technology
26 TIA Telecommunications Industry Association
27 IOP Institute of Plumbing
28 ISO International Organization for Standardization
29 LAN Local Area Network
30 LEED Leadership in Energy and Environmental Design
31 LV Low Voltage
32 MV Medium Voltage
33 NFPA National Fire Protection Association
34 O&M Operation and Maintenance
35 PDF Portable Document Format
36 SI International System of Units
37 UL Underwriters' Laboratories

02 | TENDER ACTIONS

2.1| REVIEW OF TENDER DRAWINGS


A The Tender / Issued for Construction drawings prepared by the Engineer primarily describe the design intent of the
Works, the working principles of the systems, general arrangements, and principles of services co-ordination and
the intended methods of installation.

B The Tender drawings are accordingly part diagrammatic with runs of piping, ducts, cable, conduit and the like being
shown to small scale and not necessarily indicating final exact installation positions.

1 The Tender drawings are intended to provide sufficient information:


a. to facilitate the preparation of an estimate and tender;
b. to enable all other participants to appreciate the inter-relation of the works with other trades and
disciplines;
c. When read in conjunction with the architectural and structural engineering drawings to enable the
preparation of the final builder's work information, co-ordination, installation and shop drawings
incorporating manufacturing drawings and final details of specified or selected plant and equipment.
d. The Tender drawings indicate equipment, pipework, ductwork, cable tray routes and trunking in
sufficient detail to show how all the engineering services can generally be accommodated and co-
ordinated with each other, the architecture and the structure. However, the Contractor shall be
responsible for the detailed coordination of all engineering services.
e. The Contractor shall be responsible for ensuring that the Design Intent indicated on the Tender
Drawings is in no way impaired due to additional pipe bends, deviations or changes in the service
routes and plant layout.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

f. Any dimensions are stated for elements that have a visual impact on the completed Works. The
drawings shall not necessarily show dimensions required to construct the Works nor shall they
accurately locate every item of equipment or plant ancillary which does not influence the visual
impact of the completed works. The decision of the CA as to what has a visual impact shall be final.
g. The Tender drawings are not intended to detail the building fabric or structure, nor are they based on
survey drawings or installation drawings of any other party or Consultant.
h. Plant and equipment shown on the Tender drawings is based upon the manufacturer‘s catalogue
information and is subject to verification by the Contractor.
i. Where sprinkler drawings are provided, the information shown on the tender drawings shall indicate
the design intent but this must be subject to verification by the approved installer who shall accept
full responsibility for the design in accordance with the local civil defense (Authority Having
Jurisdiction) and NFPA requirements.
j. Where it is necessary to survey an existing building or existing structure or services within that
building to prepare co-ordinated installation and shop drawings the contractor is to allow for this
within the contract price.
k. The Contractor shall interpret the design intent of the Tender drawings and reflect same in the co-
ordination and installation drawings subject to the comments of the CA.
1). Where differences occur between the Tender and the co-ordination and installation drawings
these differences shall be deemed to be included in the contract price for the Works and no
additional cost shall be allowed due to any variation in layout, arrangement or detail unless the
deviation is specifically covered by a CA Instruction before the production of the drawings.
2). The Contractor shall obtain all information required to produce the co-ordination and
installation drawings or requirements at no cost. Where it is necessary to survey an existing
building or existing structure or services within that building to prepare co-ordinated
installation and shop drawings the contractor shall undertake responsibility for obtaining that
information. The cost of obtaining that information must be included in the contract price.

2.2| DISCREPANCIES IN TENDER DOCUMENTS


A Any considered discrepancy or information which is incompatible or ambiguous between and within the tender
documentation shall be drawn to the attention of the Engineer during the tender period, allowing sufficient time for
a clarifying response and incorporation into the return tender or include for the most onerous option available. No
allowance shall be made for financial adjustment for discrepancies resolved following receipt of tenders.

B In the event of the discrepancies appearing in the drawings, or between the drawings and Specification, or drawings
and schedules, Tenderers shall refer the matter in writing to the CA for interpretation.

C The Contractor shall note that technical performance details, equipment schedules and/or equipment lists included
in (or referred to by) this specification or referred may not reflect the final requirement and are thus subject to
completion and/or revision or elaboration.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

D The Contractor shall not be entitled to any claim for extra monies, allowances or consideration (financial or other)
in respect of any differences between the equipment performance and/or selection schedules or lists given in the
project tender and construction documentation and the final selections procured by the contractor.

2.3| PRECEDENCE BETWEEN DRAWINGS, SPECIFICATION AND DOCUMENTS


A If changes occur to Regulations, Statutory Instruments or Standards etc., the Drawings and Specification shall take
precedence. The Contractor shall however, refer any such discrepancies to the Engineer before assuming a
particular interpretation, particularly in respect of Statutory Instruments, Regulations or Design Code.

2.4| INFORMATION TO BE SUBMITTED WITH TENDER


A The following information shall be provided by the Contractor in his Tender:

1 Details of any professional consultants employed to undertake required design services.


2 Technical proposal for the system(s) which shall be installed including method statement for the execution of
the works.
3 Schedules of proposed suppliers / manufacturers of products, equipment and plant, including all items for
which the choice of manufacture/supplier is at the discretion of the Contractor.
4 Method statements describing the organization and resources which the Contractor proposed and undertakes
to provide to control the quality of the contract works. The statement must include the number and type of
staff responsible for quality control, with details of their qualifications and duties.
5 Details of any proposed Sub-contractors or Specialist Installers.
B The Contractor shall provide the complete working details of all interfaces with other services that he has included
within his tender return. Failure to provide such details shall result in the tender being void.

C Only wholly compliant tender submissions shall be acceptable. Any exclusions must be priced out or clearly
identified to facilitate post tender analysis. The Contractor shall develop the concepts outlined in the tender
information, sufficiently to submit a fixed price tender for the works.

D Any comments by the Tenderer on the efficiency of the design, the availability of plant, materials and labour and
the time required for the completion of the work shall be made when the Tender is submitted.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

03 | TECHNICAL REQUIREMENTS

3.1| SUMMARY OF WORK


A The Contractor shall include for the design, supply, installation, testing and commissioning of all equipment and
ancillaries to form a complete and fit for purpose installation. This shall include delivery to site, offloading, storing,
protecting, putting into position, removal and disposal of waste materials, inspections, operating and maintenance
manuals, as fitted record drawings, staff instructions and handover to the Employer.

B The Contractor shall carry out the works as described herein and as shown on the Tender Drawings.

C The Contractor shall provide all necessary project management personnel, skilled labour and trained installation
technicians required to complete the works in accordance with the main Contract programme.

D The Contractor shall provide all necessary steelwork and structural support systems required to adequately support
the engineering systems and equipment.

E The Contractor shall make all necessary allowances to afford access for any tenant fit out and shall also undertake
the role as tenant liaison.

3.2| OPERATING CONDITIONS


A It is a requirement for all equipment, apparatus, materials and machines to be suitably rated for the adverse ambient
conditions in the UAE which are as follows:

1 Minimum ambient temperature: 8 degC (winter)


2 Maximum ambient temperature: 55 degC (summer)
3 Maximum relative humidity (RH): 100%
B All external equipment shall have a demonstrable ability (for the duration of its design life) to withstand abrasion
from sand and fine particles, intense sunlight with high infra-red and UV content, high ambient
temperature/humidity

C Precautions should also be taken to ensure the high saline content in both the ambient air and ground does not have
any adverse effect on the general operation of the plant, equipment or materials used on the project. No claims shall
be accepted where material enhancement is required to satisfy this clause to the Engineers satisfaction.

3.3| SPECIALIST INSTALLERS


A The Contractor shall include for specialist equipment and systems to be detailed, designed and commissioned by
relevant specialist vendors and suppliers. This shall include but not be limited to:

1 Audio Visual (AV) Systems


2 Fire and Voice Alarm Systems
3 Fire Protection Systems (Wet and Gaseous)
4 Automatic Controls / Building Management System
5 Emergency Lighting System
6 Public Address and Background Music System
7 Telecommunications Cabling
8 Telecommunications Networks and Systems Integration
9 Main Distribution Boards (Low Voltage)
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

10 Standby Power Generators


11 Medium Voltage Switchboards (Not Used)
12 Chilled Water Treatment
13 Pipework Stress and Expansion analyst
14 Diesel Fuel Pipe-work
15 CCTV survey of buried drainage pipes to ascertain the condition of pipes.
16 Earthing and Lightning Protection System
17 Clean Agent System
18 Acoustician
19 Pipework Stress and Expansion analyst
20 Water Features including pools, slides, splash pads and associated water treatment equipment
21 Vertical Transport manufacturer
22 Aviation Warning Lighting. (Not Used)
23 Security Systems – CCTV, Access Control etc.
24 Photo Voltaic System (Not Used)
B The Contractor shall ensure that all works carried out by Specialist Contractors are physically coordinated with each
other and that all Builders Work requirements are allowed for and coordinated.

3.4| CONTRACTORS DESIGN RESPONSIBILITY


A The Contractor shall be responsible for the detailed design of certain aspects of the mechanical, electrical and
plumbing systems on this project, where required and specified.

B The contractor is responsible for ensuring plant is installed such that sufficient space is allowed for access,
maintenance and operation in strict accordance with the manufacturers requirements.

C The Contractor shall be responsible for ensuring that the engineering services comply with all statutory
requirements, together with the requirements of all mechanical and electrical engineering specifications.

D The Contractor‘s Design obligations shall include but not be limited to provision of the following:

1 All MEPF plant and equipment supports, brackets and anchor points/thrust blocks, bases, builders’ work,
supplementary structures etc. as required;
2 The Contractor shall employ approved specialist to carry out stress and surge analysis on refrigerant systems.
The same specialist shall design the associated support systems. All forces applied by supports to the
structure shall be submitted to the Engineer for approval. The systems and supports shall be designed to
minimize loads imposed on the structure; for example where expansion bellows reduce the force on anchor
points connected to the structure, these should be applied. Similarly if increased number of anchor points can
lead to a necessary reduction in applied forces then this option shall be utilized. The Specialist shall also
design the seismic restraints as required for systems installed within the specified seismic zone of the project.
3 The Contractor shall design, supply and install all support systems required for the installation of MEPF
services. This shall include but not be limited to all necessary secondary support steelwork required to install
services from the main structure. Steel girder / clamp systems shall be provided to fix secondary steel work
to the main structural steelwork. No drilling or welding of structural steel shall be allowed without prior
approval of the structural engineer;).
4 Final fan, AHU, FAHU FCU, pump and valve sizing calculations i.e. system pressure drop calculations,
valve authorities, commissioning valve sizing, equipment selections etc. based on shop drawing general
arrangements. Equipment procured without supporting calculations shall be at the contractors own risk;
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

5 Valve, damper and the coordination of access locations including drains and vents as part of the working
drawings activities.
6 Drain and vent point locations and pipework gradients in accordance with current BSRIA Application
Guides for good practice i.e. Flushing and Cleaning of Water Systems.
7 Details of any equipment component design and selection necessary insofar as such items have been selected
by the Contractor for that item of equipment to meet the engineering specification and performance
indicated.
8 Automatic controls detailed design to meet the physical and operational requirements of the Mechanical
Services Specification. The Contractor shall be responsible for ensuring the satisfactory interfacing of the
controls installation and components within the plant and equipment to achieve the specified function.
Where interfaces such as relays or other devices or modifications to hardware or software are required, the
design and incorporation shall be the Contractor‘s responsibility.
9 Design of elements of the scheme provided by the Contractor for self-weight and other applied
forces/loadings in normal use. In particular any buried tanks or pipework that require design anchorage,
encasement or foundations together with thermal expansion accommodation and anchorage, including
provision of bellows or bends.
10 Acoustic design and selection of attenuation or noise reducing components to meet with the noise levels
specified within this specification based on actual equipment selection. All levels to be achieved with all
plant operating in normal mode. The Contractor shall ensure that all acoustic treatment is in line with the
projects acoustic design report.
11 Assessing system water capacities for the addition of chemical additives as specified. Ensuring that the
applications are in line with the BSRIA Application Guides (current) together with the overseeing of the pre-
commission and cleaning of water systems.
12 Selection of all anti-vibrating mountings to suit the particular application.
13 Final in site locations of control sensors, detectors and thermostat controls. Recommended locations shall be
included in the project specifications. Locations to be agreed with the Engineer.
14 Selection of regulation devices to comply with CIBSE Technical Memorandum TM8 and the particular
requirements of the specification and drawings including meeting the manufacturer‘s recommendations for
location.
15 Details of Electrical wiring diagrams of all equipment supplied by the Contractor showing all
interconnections between equipment to enable the necessary wiring to be undertaken, together with all
necessary wiring details to interface between systems where applicable.
16 In co-ordination with a specialist Switchgear supplier - develop the design, supply, install and commission a
switchgear System to comply with the description and details included within the contract documents and the
local Authority requirements.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

17 In co-ordination with a specialist Generator supplier - develop the design, supply, install and commission a
Diesel Generator System to comply with the description and details included within the contract documents
and the local Authority requirements.
18 In co-ordination with a specialist emergency lighting Central Battery System supplier - develop the design,
supply, install and commission a Central Battery System to comply with the description and details included
within the contract documents and the local Authority requirements.
19 In co-ordination with a specialist Security and CCTV System supplier - develop the design, supply, install
and commission a Security and CCTV System to comply with the description and details included within the
contract documents and the local Authority requirements.
20 In co-ordination with a specialist PV supplier - develop the design, supply, install and commission of a Photo
Voltaic system to comply with the description and details included within the contract documents and the
local Authority requirements.
21 In co-ordination with a specialist Lighting Controls supplier - develop the design, supply, install and
commission a Lighting Controls system to comply with the description and details included within the
contract documents.
22 In co-ordination with a specialist Fire Alarm supplier - develop the design, supply, install and commission a
Fire Alarm system to comply with the description and details included within the contract documents and the
local Authority requirements.
23 In co-ordination with a specialist Early Smoke Detection system supplier - develop the design, supply, install
and commission a Early Smoke Detection system to comply with the description and details included within
the contract documents and the local Authority requirements.
24 In co-ordination with a specialist Lightning Protection Specialist - develop the design, supply, install and
commission an earthing, Surge protection (SPD) and lightning protection system to comply with the
Standards, description and details included within the contract documents.
25 Dimensioning and final installation details of all electrical equipment, including the Automatic Control
panels to suit the detailed requirement of the particular agreed manufacturer‘s control equipment and cable
entry/exit accommodation such that:
a. Cable entry is possible in the selected location, with proposals for any necessary special cable
termination facilities.
b. Doors are not fouled by other plant, equipment, services or structural elements.
c. Safe operating and maintenance clearances are provided in all access points when installed on site.
26 Design Sizing, detailing and final routing of refrigerant pipework and link cabling/cable trays between items
of equipment provided under the contract works for variable refrigerant volume or split system air-
conditioning systems based on the final equipment selection and co-ordinated installation drawings.
27 Final location of all general equipment including exhaust, fuel lines/tanks, cooling systems and automatic
control panels and other essential components systems not mentioned here to ensure safe and reliable
operation of the complete system.
28 Design of adequate provision for movement of services and systems due to thermal expansion and
contraction, hydraulic pressures and building movement, including cold draw calculations and proving of
expansion loops in lieu of expansion equipment.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

29 Undertake the detailed design and location of expansion anchors and guide locations. (Details of all
expansion anchors and guides, including fixing details, load and thrust calculations shall be submitted to the
Contractor for comment prior to installation.)
30 Reconfirm final sub-circuit design including the sizing of all sub-circuit cables, circuit breakers and
distribution boards, in accordance with local authority requirements, based on procured equipment.
31 Detailed design of earthing and bonding requirements for electrical engineering services, mechanical
engineering services, architectural and structural elements requiring earthing and bonding
32 Design of fixing, connections and bonding details as required for final installation of lightning protection
systems.
33 Lighting control system design, including the assessment of circuit ratings and channel capacities of lighting
controllers. The Contractor shall also ensure that adequate ventilation is provided to all electronic equipment.
34 Security and CCTV Network design including Video Storage Systems and Control Room layouts. The
Contractor shall also ensure that all Security and CCTV Systems are designed and installed in accordance
with the Dubai Government Department of Protective Systems requirements. (Refer to Infosight Tender
Documentation for Requirements).Selection and configuration of all Local Area Network (LAN) switches
and routers including an assessment of the network traffic from the various ELV systems and
communications applications. (Refer to Infosight Tender Documentation for Requirements).
35 Acoustic calculations to determine the required quantity and capacity of all audio system speakers and
amplifiers for Public Address / Background Music and Voice Alarm / Occupant Warning Systems.
36 In coordination with a specialist design, supply, install and commission Building management system and
interface with guest room management and hotel property management system if applicable.
37 Detailed design of specialist fire protection/suppression systems such as Clean Agent Gas Suppression
System, Foam Systems, Pre-Action Sprinkler Systems in accordance with Authority Having Jurisdiction and
NFPA requirements.
38 Design all necessary facilities required for setting to work commissioning and testing of the completed
installations
39 Design and detailing works required by any Value Engineering proposals made and accepted by the CA
during the tender stage of the project and prior to Contract Award. Submit all shop drawings, material and
equipment submittals and calculations associated with the VE item to the CA for approval.
40 Contractor to include for coordination with relevant local Authorities for final connection to external utility
points for Drainage (Foul and Waste), TSE, ICT, Water ,Gas, Storm water and Electricity.

3.5| CONTRACTORS CALCULATIONS


A Calculations shall be issued to the Engineer for comment and shall be prepared in a recognised and agreed format,
complete with index. The Contractor shall readily make available to the Engineer any such Calculations requested
by him.

B Inspection or approval of any of the Contractor's calculations shall in no way alleviate the Contractor's
responsibility or obligations in ensuring the correct performance and safety aspects of the mechanical and services
installation. It shall not be deemed to affect the Contractor/Client design warranty.

C Calculations shall be clearly and concisely set out and shall be sub-headed to identify the exact section of the works
to which they refer.

D The use of computer programs in the preparation of designs shall be carefully controlled. All software programs
shall be verified and their use agreed with the CA prior to commencement of design tasks. Where unverified
software is used its use must be declared and the initial outputs justified by full and complete hand calculations.

3.6| SERVICES COORDINATION


18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

A The Contractor shall ensure that he has adequately coordinated and liaised with all individual work element
Contractors and shall ensure that he has included for all items necessary to provide a fully complete installation.

B The design drawings provided under the contract demonstrate only the design intent and the development of MEPF
services routes and co-ordination shall be considered as an integral element of the contract works and no additional
costs are applicable for running services in routes that differ from the design drawings, however all such deviations
are subject to approval by the Engineer

C Where separate work elements have been identified the Contractor who is appointed as the general mechanical,
electrical and plumbing installation Contractor shall be responsible for the co-ordination of the complete
engineering services‘ installation including the coordination and management of the testing and commissioning,
where interfacing is required, for all mechanical and electrical works element Contractors.

D All MEPF systems shall be designed and installed with adequate access and clearances to facilitate routine
maintenance and replacement of plant components.

E Any access hatches, platforms, gangways or step overs required to adequately access and maintain the MEPF
services are to be designed and coordinated by the contractor as part of the shop drawing process with approval
from the project structural engineer and architect prior to installation

F All aspects of the Works require detailed co-ordination to avoid any possible clash or conflict with other trades and
disciplines.

G Initiate co-ordination meetings with all other trades and disciplines and undertake all surveys that are necessary.
Minute these meetings and submit to the CA no longer than one week after the date of the meeting. The minutes
shall be suitably detailed to cover all matters raised and indicate which party requires to action matters.

H Identify at an early stage and report prior to commencement of the works, any conflict in the positioning between
engineering services, the structure or architectural elements. Ascertain if structural tolerances have been exceeded,
and service voids reduced, and take site on-site dimensions. Advise the CA of any proposed corrective action to
resolve any conflicts.

I When any new, revised or updated architectural, structural or services information is issued by the CA under the
authority of an Instruction, examine such information and if necessary modify the works accordingly to prevent any
clashes or abortive work due to such instruction.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

3.7| FINAL EQUIPMENT LOCATION


A The positions of all equipment, fittings, accessories etc., on the Tender drawings are approximate. Final positions
shall be established during the Engineers review of the Contractors’ Shop Drawings and subsequent Working
Drawings.

B The actual location of all earth electrodes, earth pits, etc., shall be reviewed by the Engineer before installation.

C The Contractor shall also refer to the Architectural and Interior Design drawings for the position and location of all
visible wall and ceiling mounted devices and equipment before any work is commenced. The Architectural
drawings shall generally take precedence. Report any discrepancies to the Engineer for resolution.

D The locations of switches, thermostats, outlets and control devices are shown diagrammatically only. Mount
switches, thermostats and other controls as close to door jambs and other openings as possible, maintaining a
minimum of 100mm from trims of doors except where installed in door frames of metal partitions. Ensure that these
locations meet with the approval of the Engineer. Check all doors swings and install switches on correct side of
doors as defined under Wiring Devices. The actual location of thermostats, switches, etc., shall be reviewed by the
Engineer before installation.

E The Engineer reserves the right to make reasonable changes required to accommodate conditions arising during the
progress of the work, at no extra cost to the Contract.

F The Contractor shall be deemed to have included within his tender submission for all services to move by up to 3
metres in any direction prior to installation at no extra cost to the contract.

G Particular care shall be taken to obtain uniform and tidy arrangements of wall and ceiling mounted equipment. The
precise position of a piece of equipment shall be determined as follows:

1 If available the setting out should be in line with the architectural setting out drawings. If not available, the
location of all visible components shall be submitted for approval prior to the commencement of installation
2 Single items of equipment, which are visually remote from other electrical or mechanical equipment, shall be
erected at the mounting heights stated in the Specification or on the drawings.
3 Two or more items of equipment whether electrical or mechanical or both, which are to be erected on the
same wall, or which shall be otherwise visually close to each other, shall be arranged in a neat and
symmetrical group. Symmetry of arrangement shall be obtained by horizontal and vertical alignment through
the center lines and not the edges of the equipment and for this purpose the mounting heights stated in the
Specification or on the drawings may be varied slightly.
H The proposed arrangements showing the outlines of all the electrical and mechanical equipment in each group shall
be marked on the wall and the approval of the Architect or his representative obtained before any holes or chases
are cut out.

I The location and size of existing services shown on the drawings are based on the best available information. The
actual location of existing services shall be verified in the field before work is commenced.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

J Changes and modifications necessary to ensure coordination and to avoid interference and conflicts with other
trades, or to accommodate existing conditions, shall be made at no extra cost to the Contract.

K The Contractor shall ensure that all plant to be supplied by him can be installed in the available space and that there
is adequate access to admit all plant to its position and enable maintenance and inspection to be carried out on the
plant without difficulty and without the need to remove or dismantle any building components.

L The Contractor shall carefully and thoroughly examine the drawings, specification and all other documentation
provided, and fully acquaints himself with the work to be done, as no allowance for claims shall be considered for
any alleged deficiency of work or materials. If any work or materials obviously necessary to complete the Works
have been omitted to be defined in the Specification, such work or materials shall be provided without any
additional payment.

M The Contractor shall take his own measurements for both the preparation of his tender and for the execution of the
work, and he alone shall be responsible for the accuracy of such dimensions and of drawings made there from. All
dimensions specially marked on the drawings shall be rigorously adhered to.

N All mounting heights shall be confirmed with the CA before commencing the work on site.

O Vent pipes, exhaust hoods or other mechanical equipment mounted on roof, or housing for such equipment, shall
not be close to the edge of the roof so that they cannot be seen visibly from the external landscaped areas and
adjacent roads.

3.8| BUILDERS WORK


A Allowances shall be included in the Main Contract for the provision of Builder‘s Work required for the MEPF Sub-
Contract Works including:

1 Formation of brick or concrete bases for engineering plant.


2 Casting-in conduits and pipe sleeves
3 Excavation and backfilling of trenches including the provision of sand/pea gravel both before and after the
laying of services.
4 Installation of cable tiles marker tapes and cable markers, supplied by the Sub-Contractors. Provision of
anchor thrust blocks. Formation of horizontal and vertical service ducts, covers and access panels as
appropriate. Cutting/forming of holes and wall chases, etc., and making good.
5 The Sub-Contractor shall be responsible for providing final Builder‘s Work details to the Main Contractor
based on authorised / certified installation and manufacturer's drawings to facilitate the installation of the
works.
6 The Sub-Contractor shall provide information at such time to enable Builder‘s Works provisions to be made
according to the main construction program.
7 The Sub-Contractor shall provide fully dimensioned drawings showing both size and position of Builder's
Work making due reference to the final Structural Engineering and Architectural dimensioned detailed
drawings.
8 The sub-contractor shall undertake the redesign of the associated builder's work associated with any for
approved alternative equipment or materials which subsequently vary the works in any way whatsoever.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

9 Provide final builders work details based on the installation, manufacturing and shop drawings to facilitate
the installation of the works;
a. (To include fully dimensioned drawings showing both size and position of builder's work making
due reference to the structural engineering and architectural final dimensioned detailed drawings.);
10 Detail all access requirements including access to false ceilings and ducts for maintenance. Provide fully
dimensioned and annotated drawings;
11 Undertake the redesign of the associated builder's work for approved alternative equipment or materials
which subsequently varies the works in any way whatsoever;

3.9| SUPPORTS AND SLEEVES


A Design, supply and install support systems for plant and services, including but not limited to steelwork, brackets,
hangers and clips, plinths, inertia bases, etc.

1 Submit details of all types of brackets and supports including fixing details,
2 Submit load and thrust calculations.
3 Provide fully dimensioned and annotated drawings.
B Design, supply and install sleeves, inserts, frames, fixing anchors etc., and any other items required to be cast or
built into the structures by others, including coordination of positions to such extent and accuracy to allow structural
construction to proceed.

C Undertake the detail design and co-ordination of all access platforms, access covers, gratings, ladders, stairs, rails
and protecting elements required for future maintenance and operation of plant/equipment. Provide fully
dimensioned and annotated drawings;

D Undertake and detail all fire stopping and sleeving systems for the Works where they pass through fire
compartments together with the installation of fire barriers where a fire rated partition is penetrated;

E Provide weather proofing of all services passing through external elements of the fabric.

F Provide approved fire barriers and fire stopping material where services pass through fire compartments and fire
rated partitions.

G Undertake and detail all acoustic stopping associated with the Works.

3.10| PLANT AND EQUIPMENT


A The Contractor shall ensure that the suppliers are provided with all performance data, specification and standards,
necessary for the provision of equipment for the specified duty and purpose.

B Where plant and equipment is pre-tendered, the Contractor shall ensure that his tender complies with all relevant
technical information contained in the specification irrespective of any pre-tender information suppliers provided to
the Engineer.

C The Contractor shall provide supervision, inspection, and testing reports during manufacture or fabrication at works
or on site.

D Ensure all plant, equipment and materials are protected against damage or adverse weather conditions until practical
completion. Any plant equipment or materials that have been subjected to damage, incorrect storage or incorrect
installation shall require to be replaced.

E Materials shall be of a consistent manufacturer and standard. Each type or range of material items shall therefore be
of a single manufacture.

3.11| PLANT WARRANTIES


18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

A The Contractor shall make due allowance within his Tender for all such costs necessary for extended plant
warranties as defined within this specification. The Contractor shall be fully aware of the Contract conditions and
milestones set by the principle Contractor.

B Where plant installed for main Contract works may be required for temporary service such as wild air for fit-out, air
handling equipment, domestic water distribution, switchgear, sprinkler pumps, car park fans, sewage/surface water
pumps, etc., the Contractor shall extend warranties to commence from the date of agreed project completion.

C All warranties, guarantees and software licences shall be provided in the name of the Client and not the Contractor.

D Contractor shall refer to Appendix D for list of warranties, guarantees and spares.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

04 | QUALITY REQUIREMENTS

4.1| STATUTORY REQUIREMENTS


A The whole of the work and materials to be supplied shall fully comply with the relevant Standards and Regulations
of the Local Authorities Having Jurisdiction, including but not limited to the following:

1 Dubai Municipality (DM)


2 Dubai Electricity and Water Authority (DEWA)
3 Dubai Civil Defence (DCD)
4 Dubai Green Building Regulations
B In the event of a contradiction between this Specification and any applicable Standards and Regulations, the most
stringent requirements shall be deemed to apply, and the Engineer shall be notified immediately.

4.2| GOVERNING STANDARDS


A The design and installation of all building services shall take account of the Standards and Code of Practices from
internationally recognized Organizations and Industry Associations including but not limited to the following:

1 American National Standards Institute (ANSI)


2 American Society of Plumbing Engineers (ASPE)
3 British (BS) and European (EN) Standards
4 Institute of Electrical and Electronic Engineers (IEEE)
5 Institute of Plumbing (IOP) Data Handbook
6 Institution of Engineering and Technology (IET) Wiring Regulations
7 International Electrotechnical Commission (IEC)
8 International Organization for Standardization (ISO)
9 National Fire Protection Association (NFPA)
10 Telecommunications Industry Association (TIA)
11 Uniform Plumbing code (UPC)
B A Certificate of Compliance with the relevant British Standard or EN Standard shall be provided to the Engineer at
his request.

C The Contractor shall be responsible for the detailed design of systems and details to the latest international
references, standards and codes of practices. Where no specific design, performance or installation standards are
quoted the following shall apply:

1 ASHRAE Guidelines
2 BSRIA Guidelines
3 CIBSE Guide Books
4 CIBSE Codes of Practice
5 CIBSE Technical Reports and Memoranda

4.3| ATLANTIS THE PALM GUIDELINES


A The Contractor shall take cognisance of the documentation available to them, specific to the Atlantis development
and shall ensure that all works comply with and follow these requirements.

1 Atlantis IT Infrastructure, Implementation Guidelines for Contractors, v.1


2 Atlantis, Design Standards, September 1st, 2013

4.4| APPROVALS PERMITS AND FEES


18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

A The Contractor shall obtain all necessary permits from the Local Authorities to complete the installation.
Submissions shall be lodged in a timely fashion with due regard for the Construction Programme.

B Payment procedure for all authorities permits and approvals shall be as defined in the Main Contract
documentation.

C Perform all tests required by the Authorities having jurisdiction and submit a copy of the final approved inspection
certificates. All costs for testing shall be borne by the Contractor.

D Where the requirements of any Authority call for the submission to them of any component of the works for
approval, testing, stamping or certifying, the Contractor shall, at their own expense, submit and deliver any such
component part to the place required by such Authority.

E After such component part has been satisfactorily approved, tested, stamped or certified, the Contractor shall return
it to the site for incorporation into the works. Any expense incurred shall be borne by the Contractor.

F The Contractor shall also be responsible for renewing all permits and NOCs obtained from Local Authorities during
the design period.

G The Contractor shall be responsible for the programming, submitting applications to and co-ordinating and
progressing the approvals or submissions required by any Authority.

4.5| QUALITY ASSURANCE


A All designers Contractors and suppliers are required where possible, to implement a management quality assurance
system in accordance with ISO 9001, ISO 9002, ISO 9003 (as relevant to the work involved).

B For the purposes of this project, the following categories shall apply:-

1 Registered Quality Assessed Companies


2 Non Registered Companies implementing documented Quality Assurance Practices
3 Non-Quality Assured Companies
C Where Contractors and suppliers are not registered Quality Assured Companies, they shall be required to submit
evidence of an implemented Quality Assurance management System to the Employer’s Agent. Such evidence could
be the Contractors Quality Assurance Manual.

D Contractors in this category may, at the discretion of the Employer’s Agent be required to submit to a quality
assurance assessment of their documented management system.

E Contractors and suppliers without any formal Quality Assurance System may, prior to appointment, be assessed by
a Quality Assurance Assessor appointed by the Employer’s Agent to determine the management control systems
operating within the Company that assess the contract requirements, provide contract control to attain specification
requirements.

F Quality Assurance Assessments shall be at the cost of the relevant Contractor or Specialist Contractor in advance
prior to the assessment.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

G Contractor’s Quality Control:

1 The Contractor shall have designated a single Quality Control (QC) Representative, not the Job
Superintendent or Job Project Manager, responsible for the overall quality of workmanship and compliance
with specifications.
a. The Contractor shall submit for approval a resume for the Quality Control Representative.
b. The QC Representative shall be responsible to observe and certify the performance of contractor tests
and pre-inspections identified on the Contractor’s Quality Control, Required Certification Log.
c. The QC Representative may elect to use an alternate expert to observe/certify performance.
d. The QC Representative shall be qualified to monitor construction quality by experience and training.
H The Contractor shall submit for approval a Quality Assurance Plan at the Pre-construction Meeting:

1 The plan shall include identification and resumes of the Quality Control Representative and any subordinate
experts to the QC Representative.
2 The plan shall also address the QC Representative’s on site presence and participation in pre-installation, and
subcontractor meetings.
3 The plan shall include a proposed bi-weekly Contractor’s Quality Control report.
4 This report shall include results of contractor certifications, Client's test results, post installation inspection
results, and updated Contractor’s Quality Control, Required Certification Log.
I The QC Representative shall have the authority to stop work at any time quality problems necessitate. This
authority shall be delineated in a letter of appointment from a company officer. The letter shall be included in the
Quality Assurance Plan.

J The Contractor shall employ and pay an independent agency, to perform all inspections, tests (included within this
specification), and similar quality control services which are designated in the technical specifications as a
Contractor requirement to provide.

K Failure and Re-testing:

1 Regardless of the original assignment of responsibility for inspection, testing or similar services, the
Contractor shall be responsible for re-testing where results of required inspections, tests or similar services
prove unsatisfactory and do not indicate compliance with Contract Document requirements. Removal and
replacement Work necessitated by such noncompliance shall be at the Contractor's expense the contractor
shall also meet the consultants costs for additional witnessing.
2 When inspections or tests cannot be performed after proper notification and at the fault of the Contractor,
rescheduling costs shall be the Contractor’s responsibility.

4.6| MANAGEMENT OF THE WORKS


A Management of the Works applies to the whole of the Works, including this Subcontract.

B Comply with the requirements specified therein in so far as they apply to the Subcontract Works, and co-operate
with and assist the Main Contractor in complying with them generally.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

C Co-operate with the Main Contractor, other subcontractors, suppliers, local authorities and statutory undertakings in
the execution of their work. In particular, the works carried out by others shall require close and careful liaison and
co-operation.

D Provide a detailed sub-program to assist the Main Contractor in producing a Master Program for the Contract
Works.

E Due allowance shall be made in the program(s) for the Works for, but not limited to, the following:

1 Ordering and installation periods.


2 The completion of drawing, etc. including the minimum working days for comment
3 Work resulting from instructions issued in respect to the expenditure of provisional sums.
4 Concurrent work by other trades.
5 Any temporary works necessary for the completion of the engineering services installations.
6 Pre-commissioning, commissioning and performance testing of the engineering services installations.
7 Preparation and provision of Record Drawings and Operating and Maintenance Manuals.
F Provide program information as:

1 Simple bar chart type.


2 Critical path network.
G Provide a separate and detailed commissioning program for agreement with the CA. Make due allowance for the
following:

1 Commissioning, demonstration and instruction procedures.


2 Provision of written notice before each (or series of) test, inspection, commissioning or demonstration
procedures are to be carried out, not less than
3 Demonstration to the CA that test instruments and equipment are accurate.

4.7| COMMISSIONING PROJECT MANAGEMENT


A Compile a detailed commissioning program and confirm/agree with the main contractor in accordance with the
main contract program.

B Establish a means of monitoring the progress of the commissioning, including checklists.

C Ensure that all parties involved in the commissioning process have documentation procedures for dealing with
Variations. Ensure that a control mechanism is set up which includes documentary back-up of what has been
changed, how and why.

D Establish a consistent numbering system to identify work items, components and devices.

E Ensure regular database and configuration back-ups are made throughout all stages of the commissioning process.

F Ensure attendance of all appropriate and responsible parties for interface pre-commissioning tests.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

05 | HEALTH, SAFETY AND ENVIRONMENT REQUIREMENTS

5.1| HEALTH AND SAFETY


A The Contractor and all persons (including Sub-contractors) employed by the Contractor on the work, shall comply
with all health, safety and environmental legislation, codes of practice/guidance from the Building Control and
regulations of the Authority Having Jurisdiction and with the provisions of any regulation, standards or working
roles of any industry associated with the contract works.

B The Contractor shall provide all necessary materials, goods, work and attendance required to ensure that safe
methods of working are followed when using any equipment or materials which may involve danger to life or
property.

C The Contractor shall particularly safeguard and take all necessary precautions against damage by fire or explosion
where the execution of the work may involve the presence of flame or sparks.

D Petroleum products and other inflammable or vaporising liquids, gases or solids shall only be used in accordance
with the regulations applicable to storage and use of these products. When equipment and vessels containing these
items are not in use they shall be removed, together with their contents, to a safe place of storage.

E The Contractor shall be satisfied and confirm that the whole of the installation is in accordance with the By-Laws,
Building Regulations, Building Control and regulations of the Authority Having Jurisdiction, all statutory authority
requirements and all interested parties.

F The Contractor shall provide all necessary general health, safety and welfare facilities and shall appoint a
“competent person” on the site to manage health and safety during construction.

G The Contractor shall ensure that all persons employed on, or visiting, the site are adequately informed, instructed,
trained, supervised and equipped such that they are able to carry out their duties without risk to safety or health and
take all necessary steps to ensure that only authorised persons are allowed into any construction area.

H The Contractor shall develop a project health and safety plan prior to the commencement of works on site, with
consideration of all reasonably foreseeable risks and shall include the arrangements for the management of the
construction works and for monitoring compliance with relevant statutory requirements.

I The Contractor shall supply any/all applicable method statements and comply with all procedures required by the
CA and the Principal Contractor. Health and safety method statements shall also be prepared for all work activities
and the contractor shall ensure that they adequately address compliance with relevant health and safety legislation
and coordination with any other relevant work activities.

J The Contractor shall ensure that all sub-contractors complete appropriate assessments of the risks to health and
safety in respect of their works as required by the relevant health and safety regulations of the Statutory Authorities.

K The Contractor shall prepare all necessary information for the production of a health and safety file for the works in
the format defined by, or agreed with the CA and ensure and coordinate the provision of information for the health
and safety file by all sub-contractors, specialists and suppliers. The health and safety file information shall be
prepared in adequate time to allow this to be co-ordinated and handed over to the Client at practical completion of
the works, unless otherwise agreed.

L The Contractor shall comply with latest edition of the Control of Substances Hazardous to Health (COSHH)
Regulations and undertake COSHH assessments for all activities and substances provided or used on site to assess
their potential health hazards. Copies of all relevant COSHH assessments must be issued to the operatives
concerned and strictly monitored. Particular attention must be given to the use of glues and sealants.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

M Labour saving lifting devices shall be used wherever possible and materials sized to allow easy manual lifting.

N The future replacement of plant and equipment shall be duly considered and the contractor shall ensure that no item
of plant or equipment is installed in such a manner that it cannot be routinely and regularly maintained in a safe
manner.

O The sub-contractor shall carry out risk assessments and ensure the safety of all persons and the Works comply with
the requirements of the Construction Design Management (CDM) Regulations by:-

1 Compiling risk assessments for the sub-contract works.


2 Providing information on the sub-contract works which might affect the health or safety of any person.

5.2| NOISE
A The Contractor is responsible for carrying out the work with as little noise as possible and with no nuisance. The
Contractor shall fully comply with the requirements of the Environment Protection requirements being enforced for
the intended site area.

B It shall be the responsibility of the Contractor to ascertain from the Authorities concerned prior to the submission of
his tender, whether the requirements and restrictions relate to hours of working permissible, maximum noise levels
not to be exceeded, methods of working and/or type of plant to be employed.

C The Contractor shall comply with all requirements and restrictions, which may be imposed and shall allow for the
cost of such compliance and all resultant programme requirements.

D The Contractor shall take all necessary precautions to prevent nuisance from smoke, rubbish and other causes. The
Contractor shall fit all compressors, percussion tools and vehicles with effective silencers of a type recommended
by manufacturers of the equipment.

5.3| FIRE PRECAUTIONS


A The contractor shall take all reasonable fire precautions in respect of stores, workshops and other installations.

B Where it is necessary to use any naked flame or welding equipment in executing the Works and where combustible
materials are in use, adequate protection shall be given to other adjacent materials and personnel.

C Permit to Works shall be obtained and suitable fire extinguishers shall be readily available at the position where
such work is proceeding.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

5.4| PROHIBITIED MATERIALS AND SUBSTANCES


A The Contractor shall not use materials which are “deleterious” or harmful to human health or the environment
during their installation or during long term disposal or degradation.

B The Contractor shall check with manufacturers and suppliers to confirm that products do not contain any such
“deleterious” materials, or materials that may become deleterious through a passage of time or when used in a
particular situation or in combination with other materials.

C For the purposes of this document, the word “deleterious” shall be deemed to include any use of materials or
combinations of materials that could reduce the normal life expectancy of:

1 Materials including plant, equipment and support systems.


2 Structural building elements in which they are incorporated or to which they are affixed.
D Without prejudice to the foregoing, the following materials shall, in any event, be deemed to be deleterious for the
purpose of this Contract:

1 High Alumina cement or concrete in structural elements


2 Woodwool slabs in permanent formwork to concrete or in structural elements
3 Calcium chloride in admixtures for use in reinforced concrete
4 Aggregates for use in reinforced concrete which does not comply with British Standard Specification 882,
1992 and aggregates for use in concrete which do not comply with the provisions of British Standard
Specification 8110, 1985.
5 Lead or any products containing lead in water piping and pipe fittings which do not comply with BS.869,
Part 2. Lead where the metal or its corrosion products may be directly ingested inhaled or absorbed. Lead-
based paints or primers
6 Products formed using urea formaldehyde
7 Products containing expanded polystyrene or other similar combustible materials
8 Products containing polyisocyanate foam
9 Materials containing fibers less than 3 microns diameter
10 Calcium silicate bricks and tiles
11 Slipbricks which do not conform to BS.5628, Part 3 and BS.3921
12 Tropical hardwoods from a non-renewable source
13 Products containing or manufactured using CFC’s (chloro-fluoro-carbons) hydro-chloro-fluoro-carbons
(HCFC) or HFA’s have been used as blowing agents (All refrigerants shall be zero ODP).
14 BCF (Halon) fire extinguishing systems
15 Solvents or adhesives that omit noxious vapours which in use and/or over an extended period of time,
following occupation of the buildings are detrimental to indoor air quality
16 Halon or any other substances causing ozone depletion.
17 Asbestos or products containing asbestos.
18 Materials comprised in whole or part of man-made and/or naturally occurring mineral fibers which have a
diameter of 3 microns or less and a length of 200 microns or less or which contain fibers not sealed or
otherwise not stabilised to ensure that fiber migration is prevented.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

19 Polyurethane or polyisocyanate foam


20 Polychlorinated biphenyls (PCBs) or similar compounds
21 Pentachlorophenol, lindane or tributyltin (TBT) oxide
22 Extruded polystyrene other than low ozone depletion materials
23 Materials manufactured with any form of animal hair.
24 Materials that support bacteria.
25 Substances publicized by the Health and Safety Executive, Building Research Establishment, British
Standards Institution or other relevant authorities or professional bodies having jurisdiction as being
deleterious to Health and Safety shall not be incorporated into any part of the Works.
26 All jointing materials shall be of a type approved by the respective authority.
E The Contractor shall certify that deleterious materials are not incorporated in the Works and provide a written
compliance statement to the CA prior to commencement of the Works.

5.5| ISOLATION OF POLLUTANT SOURCES


A Where activities produce hazardous fumes or chemicals, spaces must be provided with separate air extraction
systems to create negative pressure and exhaust the fumes or chemicals to ensure they do not enter adjacent rooms.

B Dangerous Goods must be stored in strict accordance with local authority Requirements.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

06 | ADMINISTRATIVE REQUIREMENTS

6.1| SUMMARY
A This Section specifies administrative and procedural requirements for MEPF quality control services.

B Quality control services include inspections and tests and related actions including reports required by Independent
Agencies, Governing Authorities, and the Contractor. These do not include Contract

C Inspection and testing services are required to verify compliance with requirements specified or indicated. These
services do not relieve the Contractor of responsibility for compliance with Contract Document requirements and
local authority requirements.

6.2| PROJECT QUALITY PLAN (PQP)


A The Contractor shall be required to produce a project quality plan for the building services works within four weeks
of contract appointment. The plan shall as a minimum contain the following information:

1 A statement on how the quality plan shall be controlled i.e. the revision and update mechanism.
2 Quality auditing procedures.
3 Key staff contact list. The names, addresses, telephones numbers and email addresses of the key staff
involved in carrying out the building services work including the Contractors staff, consultants, building
services Contractors staff and all the specialist suppliers and manufacturers staff.
4 A statement allocating responsibilities for the key staff involved in project work
5 Organograms of all the Contractors, consultants and specialist suppliers project structures. Organograms
shall extend from the person with project ownership in the company down to site staff.
6 A programme for the engineering works. The initial submission should contain a high level programme with
series of separate work activity programmes behind it that highlight the trade activities and milestones
associated with the system or area of work. The programme shall be integrated with the main contract
programme. The commissioning programme shall be prepared and agreed with The Main Contractors
commissioning specialist.
7 A method statement breakdown structure, e.g. general activities, pipework installation, insulation
installation, etc.
8 A schedule for all meetings associated with the engineering services works.
9 The design management procedures and description of the design development process.
10 A construction design information submission programme.
11 The engineering services work package break down structure.
12 A pack of standard forms, e.g. requests for information, test certificates, inspection certificates, etc.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

B Submit procedures for all the main construction activities including:

1 Procurement including a work package breakdown.


2 Offsite manufacturing, inspection and testing
3 Packaging, delivery and storage on site
4 Protection of the works
5 Requests for Information
6 Site supervision
7 Site inspection
8 Testing
9 Commissioning
10 Progress payments
11 Handover
C The project quality plan shall remain a “live” document throughout the construction period with

D all the Sub-Contractors and specialist suppliers adding to it.

E The document shall be “owned” by the Contractors work package Project Manager and it shall be that person’s
responsibility to update the document and ensure that all copies in circulation are current. Current copies of the
project quality plan shall be issued to The Main Contractor Engineering Services Manager and form part of the
project PQP.

6.3| CONSTRUCTION PROGRESS DOCUMENTATION


A The contractor shall ensure the Works programme is maintained up to date and redraft, without delay, in any
circumstance arise that affect the progress of the Works and submit to the CA. Progress reports shall be provided to
the CA every 4 weeks in addition to any other information required under the contract conditions.

B Progress reports shall include, but not limited to, the following information:

1 Date of order and delivery of all major plant and equipment.


2 Materials and equipment on site or installed.
3 Site labour employed.
4 Activity breakdown indicating target percent progress and actual percent progress for each activity
monitored against the contract programme.
5 Latest schedule of information required indicating required / received dates and highlighting critical path
items.
6 Status of utility services with connection dates for each service.
7 Latest progress indicated on a copy of the programme. The programme shall include a base line activity bar
for each activity and a separate progress bar to each activity bar
8 Any proposed alteration to the programme. Alterations shall be identified clearly prior to the activities being
undertaken and shall be in accordance with the contract.
9 Copies of snagging/defects lists verifying that inspections are being undertaken.
10 The contractor shall record progress of the Works weekly on a copy of the programme and maintain a set of
the latest drawings, which shall form the basis for the record drawings, marked up as the works progresses.
These shall be available for inspection by the CA at any time.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

11 If at any time the execution of the Works falls behind the contract programme, the contractor
12 shall formulate corrective measures and notify the CA of these intended measures prior to their being
adopted.

6.4| PHOTOGRAPHS
A The Contractor shall provide colour progress photographs in digital format (minimum of eight mega pixel) of the
Works taken at intervals to be agreed with the CA.

B Progress photographs shall be submitted to the CA within one week of being taken and shall have the date and time
when taken digitally displayed on the photograph. The photographs shall be submitted to the CA in the following
format:

C Five (5) Printed Sets: A4 size, one photograph per page

D Three (3) Digital Sets: JPEG type electronic format, issued on CD/DVD (all CD/DVDs shall be clearly labelled)

E Photographic details of all engineering services which are concealed within the building shall also be provided
before final concealment.

F No unauthorised photographs of the site or the Works or any part thereof shall be taken except with the permission
in writing of the CA and no such photographs shall be published or otherwise circulated without the like
permission.

6.5| MATERIAL AND DRAWING SUBMITTAL PROCEDURES


A All drawings, materials and manufacturers details must be approved by the CA prior to any orders being placed.

B Within one month of the contract appointment the contractor shall prepare and submit for CA’s approval a
Submittal Schedule for all proposed drawings and materials required for comment.

1 Material Submittals: the schedule shall indicate as a minimum the following information:
a. Material name and revision number
b. Latest date required on site for manufacturing purposes
c. Date required for final comment
d. Date for submission for comment
e. Date of delivery to site
2 Drawing Submittals: the schedule shall indicate as a minimum the following information:
a. Drawing number and revision number
b. Drawing title, service and scale
c. Date required for final comment
d. Date for submission for comment
e. Date of commencement of drawing production
C The Contractor shall revise and update the drawing and material Submittal Schedule as necessary on a regular basis
during the contract period. In planning the production of drawings and other submittals the Contractor shall take
into account the time required for:

1 Submission to the CA
2 Examination by the design team
3 Alterations and re-submission in the event of the initial submission not being
4 accepted
5 Final issue for approval purposes
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

D The full extent of all submittals required to be submitted for comment shall be indicated. The submittals shall be
grouped so as to support the construction programme for a particular part of the building or building engineering
service. Incomplete submittals shall not be examined until fully complete and /or re-submitted.

E All drawings shall be submitted sufficiently in advance of field requirements to allow ample time for checking and
re-submittal as may be required.

F Submittals shall be issued progressively as agreed in advance with the CA to facilitate examination. Adequate time
shall be allowed in the Contractor’s programme for submittals with due allowance for incorporation of comments
and resubmission in order not to cause delays.

G Each package shall contain all drawings, design calculations, support information, method statements,
manufacturer's literature, builder’s work information, etc. necessary to facilitate an independent review. All
documents (excluding drawings) submitted for review must be adequately bound. All documents shall be clearly
identified with a 'status' during the course of the project.

H A separate compliance statement shall be submitted for each item of plant or equipment with the specified technical
details and performance characteristics clearly shown in the English language.

I Calculations where applicable shall be submitted in a clear, definable and easily read format.

J All documentation submitted shall be accompanied by a certificate indicating that it has been checked and approved
by the installer's design manager.

K The following submittal categories shall be used:

1 Preliminary - Submittal presented for informal comment as appropriate. Any comment, or lack of comment,
is not to be construed or implied as giving approval.
2 Information - Submittal presented for information only and no comments required
3 For Review - To be reviewed and examined by the CA
4 Construction - For construction purposes
L All drawings shall require the approval of the installer's design manager to verify that the drawing has been
developed from an approved design and that the information does not conflict with the requirements of other design
disciplines.

M Unless stated otherwise elsewhere 15 working days from the date of receipt by the engineer shall be allowed for
review or comment or otherwise on all submittals.

N The number of copies and format of information to be provided shall be as follows:

1 2 No. Paper copies


2 2 No. Electronic Copies in either DWG, PDF or MS Word format
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

O Examination and Review of Material and Drawing Submittals:

1 The CA shall examine all submittals for compliance, in principle, with the design intent.
2 Such examination shall not relieve the Contractor of any duties, obligations or responsibilities under the
contract.
3 Examination of any drawing or material submittal by the Engineer shall not mean that the Engineer is
responsible for the correctness of the submittal or its suitability for purpose. These responsibilities shall
remain with the Contractor.
4 Only drawings that have been reviewed, and which incorporate the comments by the CA may be progressed
to 'Construction' status. Should it become necessary to revise the drawing its status must be changed to 'For
Review' and be re-submitted.
5 On receipt and examination of any material or drawing submittal, the following conditions shall apply:
a. Category 'A' – Approved
1). Installation, manufacture or construction may proceed in accordance with the drawings
submitted.
2). Unless indicated to the contrary on such drawings, the works shall comply with the Contract
Documents.
b. Category 'B' – Approved with Comments
1). Installation, manufacture or construction may proceed in accordance with the drawings
submitted subject to the Sub-Contractor taking necessary action based on the Supervising
Officer's comments and all annotations added to the returned drawings.
2). Unless indicated to the contrary on such drawings, the work shall comply with the Contract
Documents.
3). The required number of copies of the amended drawings shall be sent to the Supervising
Officer.
c. Category 'C' – Rejected
1). No work shall be installed, manufactured or constructed. The Sub-Contractor shall re-submit
new shop drawings to the Supervising Officer for review until re-submission is not required.
2). Submissions marked 'C' shall not be permitted on site.
P Revisions to Material and Drawing Submittals:

1 Where revisions take place either under the authority of a CA instruction, or by written agreement with the
CA or when revised architectural, structural or services information is issued, all drawings shall be modified
accordingly and shall be reissued for construction purposes subject to examination by the CA.
2 The Contractor shall be responsible for carrying out any alterations to his working drawings due to revisions
to the architectural and structural layouts.
3 The issue of revised drawings shall be in accordance with and with regard to the agreed programme for
construction and where time is available re-issues shall be grouped together, as agreed with the CA.
4 Providing all revisions are properly incorporated into the drawings and the final installation is correct
according to the drawings, then the final issue of these drawings may be used in conjunction with the draft
set of marked up prints kept on site, as the basis for the record drawings.
5 Revised items on drawings shall be indicated by 'clouds' around the changes and annotated with a revision
number/letter.
Q Acceptance of Material and Drawing Submittals:
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

1 Acceptance of any submitted data or Shop Drawings for material, equipment apparatus, devices,
arrangements, and layout shall not relieve Contractor from responsibility of furnishing same of proper
dimensions and weight, capacities, sizes, quantity, quality and installation details, to efficiently perform the
requirements and intent of the Contract.
2 Such acceptance shall not relieve Contractor from responsibility for errors, omissions, or inadequacies of any
sort on submitted data or Shop Drawings.

6.6| ALTERNATIVE MANUFACTURER’S EQUIPMENT


A Alternative manufacturers’ equipment and materials shall be equivalent in every respect to that specified. A
separate compliance statement for each such alternative shall be submitted to the CA and include:

1 Full company details


2 Country of manufacturer
3 Full technical data and performance characteristics
4 Specification compliance statement
5 Local authority compliance statement
6 Where a product is designed or manufactured to differing National or International design standards than
those outlined in the specification a complete comparative study shall be provided to demonstrate
equivalence of the codes
7 Certification attained
8 Details of any implications or consequential amendments to the design and/or construction/installation of
other parts of the works.
9 A complete and precise statement of the effects on cost. Relevant cost savings shall be deemed to have
allowed for all consequential costs associated with amendments of other parts of the Works. Additional costs
arising from necessary changes to the details of the installation shall be identified, including changes to the
design and drawings, as well as any associated ancillary equipment.
Effects on construction, programme, maintenance, cost in use or other differences
10 All necessary calculations supporting the proposed performance have been met.
B Where alternative equipment or materials offered have been accepted by the CA, either prior or post award of the
contract, the Contractor shall undertake and be responsible for the redesign of all services and builder's work
affected by these equipment changes.

C No additional costs or extension or delay to the programme in this respect shall be allowed.

D The acceptance of any alternatives shall be at the discretion of the CA, who is not bound to accept any alternatives.
Alternatives which would involve significant changes to other work shall not be considered.

6.7| MANUFACTURERS TECHNICAL DATA


A The Tender drawings have been prepared based on generic information of the equipment specified elsewhere.
Revisions or modifications of the physical characteristics of the equipment are likely between the generic
information and the final information issued on the manufacturing drawings for the selected products. When such
revisions or modification arise, these are to be incorporated and their effects on other parts of Works added to the
installation drawings and where necessary the final builder's work information.

B The Contractor shall review the manufacturer’s references at the earliest opportunity and bring any anomalies to the
attention of the CA in writing. No extra cost or claim or extension to the programme or delay shall be allowed for
such modifications to the drawings or the Works as a result of such changes.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

07 | DOCUMENTATION REQUIREMENTS

7.1| DOCUMENTS AND DRAWINGS ON SITE


A The Contractor shall ensure that one copy of the current work package Documents and Design Intent Drawings
prepared by the Engineer are kept in his office on site at all times and that his staff and operatives are fully
conversant with same.

B The Contractor shall also maintain on site a full set of up-to-date installation drawings to record the progress of the
works. These drawings shall form the basis of the ‘Record Drawings’ required upon completion of the works.

C The Installation Drawings shall be updated in line with all amendments issued by the Client's Agent within 10
working days.

D The drawings and documents on site shall be available for inspection by the Engineer at all times.

E All Services drawings shall be read in conjunction with the Architectural and Structural drawings, and it shall be the
Contractors responsibility to ensure that work is being carried out in accordance with the latest issue of the relevant
Architects, Structural and Engineers’ drawings.

7.2| CONTRACTORS WORKING DRAWINGS


A Contractors working drawings or Shop Drawings shall be defined as a drawing showing the inter-relationship of
two or more engineering services and their relation to the structure and building fabric and contain all the necessary
information required by tradesmen on site to install the works.

B The Contractor shall prepare and submit for approval of the Employers Agent all detailed working drawings of the
scheme, plant and any other details necessary for the instruction of their workmen. Should the Contractor fail to
comply with the requirements of this clause, they shall be responsible for any works of rectification including
associated builders work; mechanical or electrical work etc., at their own cost if instructed by the Clients Agent.

C The Contractor shall be responsible for dimensioning, setting out, detailed co-ordination of the services within the
scope of his Contract, the design intent drawings provided at tender are not suitable for this purpose.

D Coordination, installation and setting-out drawings dimensioned and to scale, shall be submitted for the Engineer's
review to make clear the work intended and to show its relation to adjacent work and to the work of other trades.
Three copies of such drawings shall be submitted for review, of which one shall be retained by the Engineer.

E The drawings must be comprehensive showing all details, dimensions, equipment, supports for services and
sections through critical areas to properly coordinate all services and work of other trades. Unless accepted by the
Engineer, all drawings must be to 1:50 scale.

F Site services drawing shall be prepared to show all existing services, modification to existing services and all new
services within the entire construction area. Drawings must show all connections of new or existing services to
Municipal services and must be approved by the relevant authorities. Location of all existing services shall be
carefully detailed and dimensioned on the drawings showing all sizes and invert elevations.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

G Drawings shall be prepared with due regard to the construction schedule and shall be submitted to the Engineer,
allowing reasonable time for examination and review.

H Work shall not proceed in areas involved until after final approval of all such drawings has been obtained. These
drawings shall include all existing information.

I Working Drawings shall indicate clearly all services and the materials and/or equipment actually being supplied, all
details of construction, accurate dimensions, capacity, operating characteristics and performance.

J Installation of any equipment shall not commence until after the Working Drawings have been reviewed and
approved by the Engineer.

K Working Drawings shall contain the following information:

1 Project title.
2 Reference to the applicable drawing and specification article.
3 Contractor and supplier identification, addresses and telephone numbers.
4 Certification that the contractor has reviewed the submittal.
5 References to individual specification sections for additional information requirements.
L Working drawing submittals shall be provided for each specific material, system, or equipment as identified herein.

M When requested, working drawings shall be supplemented by data explaining the theory of operation. The Engineer
may also request that this information be added to the maintenance and operating manual.

N Where plant or equipment is to be installed within or adjacent to any building or structure, the Contractor shall take
his own dimensions of the building or structure for the purpose of installing any plant and materials which are being
supplied and fixed under this contract and shall be responsible for the accuracy of such dimensions. These
dimensions shall be used in preference to any noted on the drawings.

O All dimensions shown on the Working Drawing shall be carefully checked and verified by the Contractor prior to
commencing the installation. Each Working Drawing shall include a Certification from the Contractor that all
related job conditions have been checked and that no conflict exists.

P Contractor’s Working Drawings shall be produced for all services described inclusive of, but not restricted to, the
following:

1 Layout of pipework and drainage sumps


2 Layout of earthing electrodes and earth pits
3 Builders-work drawings including details of plinths, bases, brackets, wall and floor openings, roof openings,
including fan curbs and trimmer requirements.
4 Details of access requirements throughout, suitable for testing, commissioning and maintenance.
5 Schedule of electrical requirements listing manufacturer’s specific data associated with all electrical plant
and equipment being provided by the Contractor.
6 Ductwork manufacturer’s drawings.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

7 Air handling unit manufacturers dimensioned arrangement drawings.


8 All packaged equipment certified drawings including fan coil units etc.
9 Fan manufacturers dimensioned arrangement drawings.
10 Specialist Automatic Controls Schematic and Wiring Diagrams
11 Working drawings of pipework general arrangement along with Plant Room layouts for boiler house,
ventilation plant rooms, etc. Pipework drawings to be 1:50 scale.
12 Plant room details 1:20 scale, accompanied by cross-sections and elevations to a scale of at least 1:20.
Drawings shall detail for each plant room the location of each unit, pipe routes and connections with valves
and fittings, duct routes and connection with accessories, drain connections, electrical connections and
controls. All drawings shall include explanatory notes and shall show the required sizes of pipes and ducts
with and without insulation as applicable.
13 The drawing should make allowances for installation working space and space to facilitate commissioning
and maintenance.
14 The drawing should be spatially co-ordinated i.e. there should be no physical clashes between the system
components when installed.
15 Critical dimensions, datum levels and invert levels should be provided together with dimensions in areas
where tolerances are minimal.
16 Spaces shown on the drawing should make allowance for the service at its widest point e.g. spaces between
pipe and duct runs. Allowances for insulation, standard fitting dimensions and joint widths should be
included on the drawing.
17 Make allowance for those plant items specified by the designer and identified in the design specification.
18 The drawing should indicate positions of main fixing points and supports where they have significance to the
structural design.
19 The drawing should demonstrate a feasible sequence of installation of the services.
20 The drawing shall show the interconnection of electric components, panels etc. in accordance with the design
and incorporating the details provided on manufacturer's drawings.
21 The information shall indicate maximum electrical loading for each supply cable; cable termination
facilities; and cable identification and all terminal numbers.
22 The working drawings shall include all information provided by a manufacturer, fabricator or supplier for a
particular project, and which is unique to that project and indicates a project specific representation of the
product, components or plant items to be supplied. Examples include ductwork, pre-fabricated pipework,
sprinkler systems, control and switchgear panels and associated internal wiring, pre-fabricated plant
customized plant and equipment etc.
23 Drawing provided by a manufacturer or supplier to indicate details of the product, components or plant items
and which the manufacturer or supplier guarantees the supplied equipment shall comply with.
24 The working drawings shall include all controls diagrams, drawings and/or schematic details of all control
components and instruments showing the layout with each item uniquely identified together with a
description of the controls operation and details of the associated interlocking.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Q The schematic and General Arrangement Drawings shall be prepared to describe the design of all engineering
services, the working principles of the systems and the intended methods of installation together with sizes and
capacities and rating of all components.

R Composite circuit and layout diagrams for electrical services shall detail not only all circuitry within main control
panels but also connection diagrams for all external equipment such as starters, all forms of control devices for
ventilation equipment, etc., together with all interconnecting wiring from the main point of supply onwards and all
termination markings. All circuit and layout diagrams shall include explanatory notes and shall show the required
sizes and type of all cables with the rating of such items on fuses, switches, etc.

S Individual circuit and layout drawings from the various component manufacturers shall not be accepted in lieu of
composite diagrams.

T Builder's work drawings shall show fully dimensioned, all foundations, bases plinths, sumps, holes and sleeves
details required and the overall size and weights of the plant concerned.

U All drawings shall include explanatory notes and shall show the required sizes of pipes and ducts with and without
insulation as applicable.

V If abbreviations are employed for the designation of components, an integral schedule shall be provided on the
drawings to explain the meanings of the abbreviations.

W Individual equipment drawings from the various manufacturers shall not be accepted in lieu of these composite
plant room drawings.

X Unless directed otherwise, drawings shall be prepared according to the Project’s CAD / BIM Standard Manual,
which shall be obtained at the time of tender for review and acceptance by the Contractor.

Y The Contractor shall allow for all necessary CAD / BIM resources for the production of drawings and make due
allowance in the programme to revise the drawing as necessary to take account of the design development.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

08 | EXECUTION AND CLOSE-OUT REQUIREMENTS

8.1| PROGRAM OF WORKS


A Within 2 weeks of the award of the contract, the contractor shall provide a detailed programme produced by means
of bar charts and full network analysis (if so requested), clearly illustrating how the overall programme shall be
achieved within the contract period stated elsewhere, in particular identifying and if necessary justifying the
following:

1 The latest dates for release of final information required from the CA.
2 The period required for the production, approval and issue of builder's work information, co-ordination, and
installation and shop drawings.
3 Allowance of adequate time for the production of drawings and builder's work information and for the
subsequent checking and approval of same by the CA. The actual activities of production, adjustment,
resubmission and review must be identified and a blanket time allowance shall not be acceptable.
4 The period required for the testing and commissioning of the services. Separate testing and commissioning
activities must be identified and a separate programme prepared.
5 The period required for operating the systems, load simulation tests, final adjustment and instructing the
Employer's staff.
6 The period required and latest dates for the production, approval and issue of record drawings and operating
and maintenance instruction manuals.
7 The periods required for each phase and engineering service on a floor by floor or zone by zone and plant
room by plant room basis.
8 The proposed order dates manufacturing period and proposed delivery to site for each item of major plant to
be clearly defined.
9 Any long delivery items shall be identified within one month of appointment and a detailed method
statement prepared to schedule the action to ensure the delivery to site in adequate time to meet the contract
requirements.
10 All information required above shall be agreed with the CA before inclusion in the proposed programme.
B The Mechanical and Electrical Work Package Services Installations shall be required to be integrated into the Main
Contractors or Construction Manager’s Programme of Works. The Contractor’s tender must include all necessary
shift working/overtime to comply with the required programme as detailed in the main project preliminaries
document.

C The Contractor shall allow in his Tender for the purchase of all materials and equipment from stockists and other
suppliers at such time, and in such a manner, as may be necessary to allow for the completion of the work in
accordance with the Contract Programme.

D The Contractor shall review the programme on a weekly basis and update the programme as necessary. If any
circumstances arise that affect the progress of the works the Contractor shall immediately notify The Main
Contractor and advise solutions to resolve the issues. Additional costs resulting from non-compliance with the
above shall be borne by the Contractor.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

8.2| WORKING HOURS


A The Contractor and all of his Sub Contractors/Specialist Suppliers shall be deemed to have included for working all
hours necessary to complete their works on programme.

B All weekend working and multiple shift working as necessary shall be deemed to be included within the returned
tender submissions to complete the project on programme.

8.3| SITE SUPERVISION


A The Contractor shall include in the Tender the provision of all necessary supervision during the execution of the
works. The Contractor shall employ constantly on site, a competent Foreman in charge to manage and direct the
execution of the works and he shall on behalf of the Contractor, receive and have charge of all drawings and
documents which may be delivered or given for use by the Contractor.

B The Contractor shall also include supervision, management and organisation by a competent engineer in addition to
his Foreman-in-Charge of the works, who shall be considered to be the duly accredited representative of the
Contractor, empowered to take instructions from the Client’s Agent and to execute same. This engineer must be in
attendance at the premises until the whole of the works have been completed and passed by the Client’s Agent and
shall instruct and give all information regarding the operation of the installation to the Employer’s representative.

C The Contractor shall ensure that supervision is of a high standard embracing quality of workmanship, interpretation
of and compliance with specification and current drawings, to ensure a satisfactory installation in all respects.

D The Contractor shall provide the necessary full and part time technical staff to ensure that the works are carried out
to meet the technical specifications and the project programme including all phasing requirements.

E The Contractor shall be responsible for ensuring that his specialist technical representatives are available to attend
meetings when required.

8.4| EXECUTION OF THE WORKS


A The Contractor shall allow in his Tender for all labour, materials, tools, plant and equipment required to supply,
deliver and erect all equipment, described in this Specification and indicated on the drawings to form a complete
working facility including tests and commissioning. This shall mean not only the main items of plant and equipment
but also all incidental sundry components with their labour charges necessary for the complete execution of the
works.

B The Contractor shall ensure that his work is installed in the correct sequence.

C The Contractor shall be responsible for ensuring that all sections of the work and all materials are compatible with
one another. The Contractor shall check and ensure that all of the equipment and works offered by him shall fit into
the space provided in the building(s) including the limited entry through doorways and into ducts.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

D The Contractor is responsible for the removal and disposal of all debris resulting from stripping out works. The
Contractor is to inspect the existing building structure and determine the work involved and the equipment and the
materials and equipment’s required for the stripping out of services.

E The Contractor shall at his own expense, make good any damage done to the property during strip out works.

8.5| INSPECTION BEFORE CONCEALMENT


A Ensure no section of the Works are covered, concealed or insulated until completion of a witnessed satisfactory test
(e.g. below ground, within trenches, ducts, ceiling voids, etc.)

B Give notice when Works which are to be covered or concealed are ready for examination and/or measurement, not
less than 10 working days. Give notice to the Clients Representative and the Consultant.

C Failure to give due notice may necessitate the uncovering of the work and reinstating it at no extra cost or claim or
extension to the programme or allowance for delay.

D Record drawings of any services to be concealed shall be issued to the CA at the time notice is given.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

09 | INSPECTION, TESTING AND COMMISSIONING

9.1| GENERAL
A All the works provided as part of this Contract shall be inspected, tested, set to work and commissioned in
accordance with the current Local Authority requirements, British Standards and as stipulated by equipment
suppliers.

B No inspection or testing by the Engineer nor the witnessing of satisfactory tests nor the authorising of despatch to
site shall in any way relieve the Contractor of any of his obligations under this Contract, nor shall it in any way limit
the right of the Engineer to reject such items after delivery to site if they subsequently prove to be defective or
unsatisfactory or unsuitable for their intended purpose.

C When the Contractor has ordered equipment from a manufacturer who, in turn, has bought-in major components
from a secondary supplier, the Engineer shall have the right to elect to inspect such components at the Works of the
secondary supplier, and the Contractor shall ensure, when placing his orders, that such rights are secured. For the
purpose of this clause, inter-departmental orders within the same organisation shall be treated in the same manner as
orders involving separate organisations.

D The Engineer shall have the right to waive, at his sole discretion, the requirements relating to his inspection of
materials, apparatus, and equipment at the makers' works. The exercise by the Engineer of this right shall not in any
way relieve the Contractor of his obligation to carry out the prescribed tests and to submit test certificates.

E No work shall be painted or otherwise prepared for despatch until it has been inspected by the Engineer, or
inspection has been waived and despatch has been authorised.

F When one or more of the Contractor’s purchase orders covers the supply of a number of like components or items
of equipment, the Engineer shall have the right to require that one item or component of each type and rating be
subjected to type tests as described in the relevant National Standard. Other similar items may then be subjected
only to routine tests.

9.2| MANUFACTURER TESTS


A Upon completion of manufacture, or before despatch in the case of stock items, all material, apparatus and
equipment intended for incorporation in the Works shall be subject to the tests specified in the relevant National
Standard or elsewhere in this Specification.

B Where specified, manufacturer’s tests shall be witnessed by the Client, CA, Mechanical and Electrical Consulting
Engineers and the manufacturer’s representative at the factory. The Engineer shall be given 14 days’ notice of any
works witness test.

C The Contractor shall allow for the provision of method statements, detailing the duration of the inspections and tests
on each item of equipment for the approval of the Engineer 14 days in advance of the tests. The Engineer's
comments shall be incorporated into such method statements.

D The Contractor shall provide such assistance, labour, materials, electricity, fuel, stores, apparatus and instruments as
may be requisite and as reasonably deemed necessary to carry out such tests efficiently.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

E All instruments used for the tests shall have a current Calibration Certificate available for inspection at works.

F If the Contractor fails to demonstrate the performance of the equipment offered he shall be requested to carry out
further tests until the Employer's Agent is fully satisfied that the equipment offered meets the requirements of the
specification at no extra cost to this contract.

1 Inspection and Testing During Manufacture:


2 The Engineer shall be entitled at all reasonable times during the manufacture to inspect examine and test on
the Contractor’s premises the materials and workmanship of all plant to be supplied under the contract and if
part of the said plant is manufactured on other premises.
3 The Contractor shall obtain for the Employer’s Agent’s permission to inspect, examine and test as if the said
plant were being manufactured on the Contractor’s premises. Such inspection, examination or testing, if
made, shall not relieve the Contractor from any obligation under the contract.
G The Contractor shall provide Business Class Travel and minimum 4-Star Accommodation for one of the Consulting
Engineers plus the Employer and the Employer’s Agent for the duration of all factory tests that are required to be
witnessed by the Engineer.

H Equipment to be factory tested and witnessed by the Engineer shall include:

1 Chilled Water Pumps


2 Chillers – NOT APPLICABLE
3 Ecology Units – NOT APPLICABLE
4 Air Handling Units
5 Fan Coil Units
6 Main Domestic Water Booster Pumps
7 Main and Sub-main Switchboards (Low Voltage)
8 Capacitor Panels MCC Panels
9 Emergency Power Generators
10 Uninterruptable Power Supplies
11 Transfer Switches (ATS)
12 Central Battery System – NOT APPLICABLE
13 Lighting Control System
14 PV System – NOT APPLICABLE
15 Heat Pumps

9.3| SITE TESTS


A A visual inspection shall be made of the installed equipment before any tests are carried out to confirm the
following:

1 Correct selection and erection of materials and workmanship.


2 Signs of damaged so as to impair safety.
B This inspection shall be completed with the part of the installation under inspection disconnected from the electrical
supply.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

C During construction of the works the Contractor shall undertake all necessary tests to ensure compliance with
regulations and the specifications relating to the works.

D Where any part of the installation is to be concealed within the building fabric tests shall be made to ensure that the
installation is satisfactory prior to concealment.

E The Contractor shall keep a record of the results of each test on site. Such records shall include details of sections
tested, remedial measures taken, sections of works replaced.

F Upon completion of the works the whole installation shall be subjected to the tests detailed within the relevant
specification for the item of works and as detailed on the Engineers Inspection sheets. Every defect shall be noted,
corrected and brought to the notice of the Employers Agent. Prior to final acceptance of the installation, all tests
shall be repeated either in whole or in part and witnessed by the Engineer to his full satisfaction.

G The Engineer shall be issued with detailed method statements for each test 14 days prior to carrying out the works.
The method statements shall detail the following:

1 Health and safety issues.


2 Instruments to be used and their calibration certificates.
3 Sequence of tests to be carried out.
4 Documentation, which shall be provided to record results. This documentation shall be fully completed with
all design information.
H All tests shall be executed within the programme of building works.

I All labour, communication two-way radios and test instruments shall be provided by the Contractor for carrying out
the tests. The instruments shall be correctly calibrated and certified for the limits of accuracy required and shall be
operated by competent persons, trained in the use of the instruments. Calibration certificates for the instruments
shall be attached to the test certificates. If in the Engineers opinion a particular instrument is not suitable then an
acceptable alternative shall be provided.

J The Engineer shall be at liberty to demand the use of any testing instrument or apparatus that he may reasonably
consider to be necessary in the execution of the testing.

K In the event of the works being incomplete and causing a postponement of the notified verification of test date or
the installation failing to pass the test the Employers Agent shall be at liberty to deduct from the contract price all
expenses incurred by him and the Engineer, in attending the repetition of the tests.

9.4| TEST NOTICES


A Provide all formalities in connection with Test Notices, Agreement and Application for Supply Forms etc. Ensure
all documents requiring the Employer's signature are forwarded to the CA in time to meet the building program in
order for the necessary test and supply arrangements to be made. No additional payments shall be made for
expenses incurred due to reconnections, re-visits etc., by Supply Authorities or any other officials.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

9.5| SAFETY PRACTICES FOR TESTING


A Safety practices while testing shall comply with applicable state and local safety orders including IEC, BS, NICEIC,
OSHA, NESC, NFPA 70E and the Accident Prevention Manual for Industrial Operations of the National Safety
Council shall be observed.

B Provide free of charge samples of material and workmanship proposed to be used in the Works. Samples shall
include all alternative finishes available as required. In the case of articles of special construction: drawings when
approved shall be retained until the articles concerned are supplied, as a sample.

C The samples submitted and approved, shall remain the property of the Employer until the completion of the
contract. Approval of the CA shall be obtained before equipment is placed on order The CA shall undertake to
approve samples within 4 weeks from receipt.

D No utility equipment shall be energized until all tests and adjustments have been made to the satisfaction of the
Local Electricity Authority.

9.6| COMMISSIONING
A The Contractor shall verify the correct operation of the whole installation including items of plant to ensure that it is
operating in accordance with the specified conditions and that the systems achieve the environmental conditions
required shall carry out commissioning.

B This shall include proving of equipment installed under full load conditions. Where heat loads or electrical loads are
not inherent in the installation temporary heat loads and electrical loads shall be provided.

C Upon completion of all testing and commissioning, the Contractor to show that the equipment, materials and
installations have been tested and commissioned shall provide two copies of the commissioning certificates. Each
certificate shall be signed by the Contractor and submitted to the Engineer within 14 days of the results being
obtained. Signed copies of certificate shall be included within the operating maintenance manuals.

D The Contractor shall provide, at his own cost, unless stated to the contrary, all water, power, fuel, labour etc.,
necessary for all testing and commissioning of the plant.

E Commissioning shall be undertaken in a progressive and logical manner in accordance with the recommendations of
the CIBSE Commissioning Codes and the requirements of the appointed commissioning agent, with pre-checks
undertaken on system cleanliness, static test completion, associated area readiness and the like, prior to the pre-
commissioning, testing, commissioning, witness testing and environmental performance testing of each of the
building services systems.

F A commissioning programme shall be produced by the commissioning contractor to highlight systems requiring
witnessing by the design team.

G Regardless of the original assignment of responsibility for inspection, testing or similar services, the Contractor
shall coordinate, with each agency engaged to perform inspections, tests and similar services, the sequence of
activities to accommodate required services with a minimum of delay.

H In addition the Contractor shall coordinate with each agency activities to avoid the necessity of removing and
replacing construction to accommodate inspections and tests.

1 The Contractor is responsible for scheduling times for inspections, tests, taking samples and similar
activities, notifying the Consultant and testing agency at least forty-eight (48) hours in advance of operations
requiring testing services. Providing incidental labor and facilities to facilitate inspections, tests, sample
taking and appropriate sample storage.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

2 All aspects of the works require detailed co-ordination to avoid any possible clash or conflict with other
trades and disciplines. Undertake such co-ordination in relation to the works.
3 No extra cost or claim shall be allowed due to conflict of works or installations, where full liaison with other
trades and disciplines would have prevented such an occurrence.
4 When any new, revised or updated architectural, structural or services information is issued by the CA under
the authority of an instruction, examine such information and if necessary modify the works accordingly to
prevent any clashes or abortive work due to such instruction.
5 No extra cost or claim shall be allowed to cover any clashes or abortive work that result from not requesting
an explanation or seeking clarification in respect of any such revision.
6 No extra cost or claim shall be allowed due to conflict of works or installations, where full liaison with other
trades and disciplines would have prevented such an occurrence.
I Protection and Repair

1 Regardless of the original assignment of responsibility for inspection, testing or similar services, repair and
protection are the Contractor’s responsibility.
2 Upon completion of inspection, testing, sample-taking and similar services, repair damaged construction and
restore substrates and finishes to eliminate deficiencies, including deficiencies in visual qualities of exposed
finishes.
3 Protect construction exposed by or for quality control service activities and protect repaired construction.
J Failure and Re-testing

1 Regardless of the original assignment of responsibility for inspection, testing or similar services, the
Contractor shall be responsible for re-testing where results of required inspections, tests or similar services
prove unsatisfactory and do not indicate compliance with Contract Document requirements. Removal and
replacement Work necessitated by such noncompliance shall be at the Contractor's expense the contractor
shall also meet the consultant’s costs for additional witnessing.
2 When inspections or tests cannot be performed after proper notification and at the fault of the Contractor,
rescheduling costs shall be the Contractor’s responsibility.
K The main contractor must employ an independent third party Commissioning Agent, Mechanical & Electrical
Commissioning Engineer for the duration of the Tests on Completion (commissioning) who shall affectively be
responsible for planning and executing the entire commissioning processes on behalf of the main contractor.

L Commissioning shall be in accordance with all local authority requirements

M The Contractor Commissioning Agent shall deliver to the Client’s appointed Commissioning Authority (CxA) and
the engineer one copy each of the following for review comment and approval:
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

1 Commissioning plan - The contractor is to provide a commissioning prior to the commencement of


commissioning, including the management strategy and list of all features and systems to be commissioned.
2 Shop drawings and product data relating to systems or equipment to be commissioned.
3 Start-up checklists along with the manufacturer’s start up procedures for installed equipment.
4 System test reports.
5 Completed equipment start up certification forms in addition to the manufacturer’s field or factory
performance and start up test documentation.
6 Completed test and balance reports.
7 Equipment and other warrantees.
8 Proposed training plans.
9 O&M information per the requirements of the commissioning plan.
10 Record drawings: The contractor is to maintain at the site an updated set of record or “as-built” documents
reflecting actual conditions of installed systems.
11 Functional performance test procedures and checklist. Develop functional performance test procedures or
performance criteria verification checklists for each of the elements identified in the commissioning plan.
12 Commissioning report - Complete a final commissioning report and submit it to the owner. The
commissioning report should summarize all the tasks, findings, and documentation of the commissioning
process and address the actual performance of the building systems in reference to the design documents.
The report should identify each component, equipment, system, or feature, including the results of
installation observation, start up and checkout, operation sampling, functional performance testing, and
performance criteria verification. All test reports by various subcontractors, manufacturers, and controlling
authorities shall be incorporated into the final report.
13 Training - Assemble written verification that training was conducted for appropriate personnel on all
commissioned features and systems.
14 Operation and maintenance manuals - Operation and maintenance manuals for completeness including
instructions for installation, maintenance, replacement, and start up; replacement sources; parts list; special
tools; performance data; and warranty details.
15 Recommissioning management manual - Develop an indexed recommissioning management manual with
components such as guidelines for establishing and tracking benchmarks for whole building energy use and
equipment efficiencies; recommendations for recalibration frequency of sensors; list of all user adjustable
set-points and reset schedules; and list of diagnostic tools.
16 Acceptance phase: For this phase, the facility and its systems and equipment are inspected, tested, and
verified, etc. It is during this phase that most of the formal training occurs, which is generally after the
construction phase is complete. A/E and contractor now finalize the as built or record documentation. The
end of this phase is marked by an approved functional completion.
N The Contractor and his independent third party Commissioning Agent, Mechanical & Electrical Commissioning
Engineer shall comply fully with the requirements of the tender documentation and the requirements of the Clients
appointed Commissioning Authority (CxA) as per the following:

1 Commissioning during construction shall begin with an initial commissioning meeting conducted by the
CxA where the commissioning process is reviewed with the commissioning team members.
2 Additional meetings shall be required throughout construction, scheduled by the CxA with necessary parties
attending, to plan, coordinate, schedule future activities, and resolve problems.
3 Equipment documentation shall be distributed by the Contractor to the CxA during the normal submittal
process, including detailed start-up procedures.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

4 The Contractor shall incorporate all CxA comments related to start-up plans and start-up documentation
formats and provide construction checklists for CxA and Engineers review and comment.
5 In general, the checkout and performance verification proceeds from simple to complex; from component
level to equipment to systems and intersystem levels, with construction checklists being completed before
functional testing occurs.
6 The contractors, under their own direction, shall execute and document the completion of approved
construction checklists and perform start-up and initial checkout. The CxA shall document that the checklists
and start-up were completed according to the approved plans. This may include the CxA witnessing start-up
of selected equipment.
7 The Contractors shall develop specific equipment and system functional performance test procedures for
comment and approval by the CxA and engineer.
8 The functional test procedures shall be reviewed with the Engineer and CxA.
9 The functional testing and procedures are executed by the contractors under the direction of, and documented
by, the CxA.
10 During initial functional tests and for critical equipment, the engineer or the CxA or the Engineer shall
witness the testing.
11 Items of non-compliance in material, installation, or setup shall be corrected at the contractor’s expense, and
the system is retested.
12 The CxA and Engineer shall review the O&M documentation for completeness.
13 All commissioning functional testing procedures as defined in the approved commissioning plan must be
completed by the Contractor.
14 All Operational training procedures and documentation shall be submitted to the CxA and Engineer for
review and comment.
O Compile and submit to the project supervisor the appropriate health and safety method

P statements and risk assessments.

Q Establish a means (such as checklists) of monitoring the progress of the commissioning.

R Ensure that all parties involved on the commissioning process have documentation procedures for dealing with
variations to contract. Ensure that a control mechanism is set up which includes documentary back-up of what has
been changed, how and why.

S Establish a consistent numbering system to identify work items.


18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

T Ensure regular database and configuration back-ups are made throughout all stages of the commissioning process.

U Ensure attendance of all appropriate and responsible parties for interface pre-commissioning tests (interface
between BMS and other plant items/systems).

V The Contractor shall submit notice of delay (if applicable) within 14 days (main contract preliminaries shall take
precedence if day quantity differs) in the event of a critical delay that may result in an entitlement to an extension of
time to completion. In the event that the contractor does not comply with this deadline, its entitlement and the
Employer’s liability shall be zero. This is to enable the Employer the opportunity to instruct mitigating actions to
avoid critical delay if deemed necessary and for the Engineer to scrutinize the main contractor’s programme to
mitigate any critical delay by re-sequencing the works and/or taking mitigating action. The submission of the notice
(within 14 days) by the Contractor shall be a condition precedent to any entitlement for an extension of time to
completion.

9.7| ENHANCED COMMISSIONING


A The CxA shall be involved in reviewing the operation of the building with operations and maintenance (O&M) staff
and occupants within 10 months after substantial completion. A plan outlining outstanding commissioning and
energy related defects shall be issued.

B The Contractor shall allow in costs for all necessary attendances and remedial re-commissioning works as required
to resolve the finding of the review.

1 Method Statements
C The Contractor shall provide the Engineer with full and detailed method statements for the pre commissioning,
setting to work, commissioning, and testing and handover procedures to be applied to the whole of the works.

D Where specialists are required to undertake the works, the Contractor shall obtain similar documents from them and
incorporate them into the Works Method Statement.

E Include within the method statement, the following:

1 Logic diagram of the process flow


2 Outline programme, detailed programme(s) to be added as the document develops
3 Copies of all check lists, record sheets, etc. proposed for use. Ensure all are clearly specific to the project and
complete with design information and schematic drawings
4 Permit to work systems and documentation
5 Details of works by others on which the Contractor depends on being complete and at what time to maintain
programme progress
6 Proposed off site testing
7 Proposed completion of work in zones
8 Proposals for quality control of the work prior to offering to the Employer’s Agent.
9 Handover, demonstration and training
F The Contractor shall submit the method statement for testing, commissioning and handover within one month of the
contract award and shall regularly update thereafter to incorporate the Engineers comments and/or on-going
developments.

G The commissioning method statements shall include procedures, logic diagrams and risk assessments for the pre-
commissioning checks, setting to work, commissioning, system proving and environmental testing of the Works.
They shall also include details of flushing, chemical cleaning and water treatment, logic diagrams and programme
for integration into the building sub-Contractor’s construction, commissioning and finishes programmes.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

H The Engineer reserves the right to request additional method statements from the Contractor for any other aspect of
the works, at his discretion at no additional cost.

9.8| SYSTEM DEMONSTRATION


A Subsequent to the completion of all testing and commissioning to the satisfaction of the CA, and when directed by
the CA, the contractor shall operate the plant and demonstrate that the overall systems function correctly in
accordance with the requirements of the specification.

B Full running and operation for a period of at least 72 hours shall be considered reasonable for this demonstration
and this period shall be allowed in the programme.

C During this period, the contractor shall be responsible for the recording of results and the operation and
maintenance of the plant. If appropriate, this time shall be used to instruct the Employer's staff in the operation and
maintenance of the systems.

D An operational report shall be provided of the demonstration and print out of the conditions maintained within the
space for the required demonstration period.

9.9| AUTHORITY AND SERVICE PROVIDER NOTICES


A Liaise with the Statutory Authorities and Utility Service Providers and provide any test notices required to ensure
final connections are made in accordance with the requirements of the testing and commissioning program.

B Documents requiring the Employer’s signature shall be forwarded to the CA in time to meet the contract
programme in order for the necessary test and supply arrangements to be made.

C No additional costs or extension to programme shall be allowed due to reconnections, revisits etc. by supply
authorities and service providers or failure to programme the works.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

010 | HANDOVER, OPERATION & MAINTENANCE

10.1| INSTRUCTION OF EMPLOYERS STAFF


A At a time to be agreed with the CA and prior to practical completion, the contractor shall instruct the Employer's
staff in the use, correct operation and general maintenance of the Works and be satisfied that such staff are
competent to take over the installation on completion.

B Adequate periods shall be allowed to instruct the Employer’s staff in the operating and maintenance of the Works
and the contractor shall submit to the CA for approval a detailed training programme and method statement for the
training of the Employer’s staff.

C During such periods of instruction the contractor shall undertake and be responsible for the correct operation and
maintenance of the installations.

D The contractor shall employ the services of all relevant specialists and suppliers necessary for this purpose and
provide each person with a comprehensive set of teaching notes and diagrams.

E All the associated training equipment required by the trainer(s) to enable the training to be demonstrated effectively
shall be provided.

F For all instruction periods the contractor shall maintain training records which shall be submitted to the CA on
completion. All attendee names shall be recorded and signatures obtained from all attendees confirming they have
understood the training given. A schedule of names shall be provided within the operating and maintenance
documentation.

G Any/all health and safety issues relating to the Works shall be brought to the attention of all attendees. All attendees
shall be provided with the appropriate Personal Protective Equipment (PPE).

H ‘Formal’ presentations shall be carried out over ‘half day’ periods. As an indication, the training for operating staff
should include, but not be limited to:

1 Building services system scope (demonstrated with the aid of schematics and/or other drawings/visual aids).
To include an overview of the purpose and normal operating functions of the Works and explaining the
philosophy and method of control used.
2 Demonstration and training (by controls Specialist) of the building control system.
3 An electronic projector style ‘walk through’ of the operation and maintenance manuals, highlighting
important areas of health and safety together with all other items of importance.
4 Highlighting, demonstrating and providing delegate experience in all maintenance procedures identified in
the O&M Manuals.
5 Physical tour(s) of inspection of the Works illustrating aspects covered in the ‘classroom’ and the location of
essential isolating points of all incoming services.
6 Explaining and illustrating all operator alarms, their possible causes and actions required.
7 Explaining all known and typical fault scenarios which are capable of being recognised and/ or rectified by
the operators.
8 Identifying and demonstrating all safety equipment and interlocks including all interlocks with other
suppliers’ systems /equipment.
9 Identifying the noise levels in the various areas and highlighting the need for any protection required.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

10 Specifying and illustrating any hazards associated with the Works and the methods employed to deal with
them.
11 Providing instruction on the correct operation of plant items and the safe limits of their operation.
12 Explaining the mode of operation and sequence of events resulting from both power failure and fire alarm
conditions.
13 Demonstrating any alarms and explaining they’re meaning and possible causes.
14 Highlighting any associated hazardous maintenance materials which may require special disposal
considerations.
15 Highlighting the signs, cause and effect of known/ possible breakdown or fault conditions.
16 Indicate and demonstrate (where practicable) arrangements made for access and removal of specific items of
equipment or key large or heavy subassemblies / components.
17 Demonstration of the safe day to day running and maintenance of all systems, plant and equipment.
18 Providing sufficient expertise to address delegate questions.
I The training for the operation of the controls, monitoring or BMS installations shall include as a minimum:

1 Initial training at the works of the controls supplier including hands on experience of equipment and software
similar to the installation.
2 Instruction on the procedures for testing and routine inspection of sensors and actuators to enable the
operator to assess the nature of faults and extent of remedial action required.
3 The provision of all appropriate reference and training manuals.
4 Complete initial instruction prior to commissioning of the installed system.
5 Site instruction on the installed system.
J Together with the controls and commissioning specialists, the contractor shall be available for an agreed period as
determined by the CA to assist the Employer's personnel in the operation of the various systems following practical
completion and occupation of the buildings.

K All costs associated with the instruction of the Employer’s staff and required attendance following practical
completion shall be included in the contract price.

10.2| RECORD DOCUMENTATION


A The Contractor shall provide the following Record Documents:

1 Record Drawings and Schedules


2 Operation and Maintenance (O&M) Manuals
3 Testing and Commissioning Sheets and Certificates
B The Contractor is advised that great importance shall be placed upon quality, accuracy, clarity and completeness of
the record documents and upon their being made available promptly.

C The Contractor shall demonstrate as required by the Employers Agent throughout the execution of the works, that
adequate and accurate records are being kept such as shall ensure the ultimate completeness and accuracy of the
record documents and that the records documents are themselves being progressively compiled as the work on site
proceeds.

D Draft copies of all Record Drawings and Operation and Maintenance Manuals shall be issued to the Engineer for
comment a minimum of six (6) weeks prior to Practical Completion, so that the Employers Agent has the
opportunity to comment and the corrections/amendments recorded, thereby allowing sufficient time for the approval
documents to be available at the time of issue of the Certificate of Practical Completion. Should these drawings not
be made available at this time, the Certificate of Practical Completion cannot be approved or shall be delay as 6
weeks shall be required for document review.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

E All record documents shall be provided in electronic form, i.e. CD, as well as the paper copies, compatible for the
Employer’s Agent’s retention. The number of copies required for all Record Documents shall be as follows:

1 Paper: 3 in English
2 CD / DVD / Portable Hard disk: 3 in English
F All CD / DVDs shall be labelled and DVD jewel cases shall be labelled identifying project title, issue date and
index of contents.

G All Record Documents shall be correlated so that the terminology and the numerical and/or other references used
therein are consistent with and similar to those used in the physical identification of component parts of the
Installation

10.3| RECORD DRAWINGS AND SCHEDULE


A The completed Record Drawings and Schedules shall be signed by the Contractor as record drawings and shall be
submitted to the Engineer at the same time as the Operating and Maintenance Manual is handed over for comment.

B Record drawings of the final "as installed" layouts shall be issued in draft form to the CA for examination 4 weeks
prior to the Testing and Commissioning period to allow checking for accuracy.

C Where portions of the work are to be concealed, draft copies of Record Drawings shall be supplied to the CA before
the work is concealed in order to facilitate checking and examination.

D Record drawings shall be international A1 or A0 size printed on to best quality paper.

E Record drawings shall also be reduced to international A3 size for inclusion in the O&M Manuals.

F Record drawings shall be prepared in AutoCAD 2004 or later format to an internationally recognised and agreed
project CAD layering convention. All services information shown shall be prominent and easily read when
compared to architectural backgrounds.

G A detailed list of CAD layers, external references or equivalent (if used) and list of files shall be provided with the
electronic copies. If the drawings were produced from CAD drawings provided by the CA, the same layering
system shall be used

H Record drawing title blocks shall contain the following information:

1 The project name and site address.


2 Name, address and contact telephone/fax number for each member of the Contractor and the Consulting
Engineer
3 Drawing title and building area that the drawing refers to.
4 Drawing number.
5 Drawing scales used.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

6 Date of drawing issue.


7 The name of the person who produced the drawing.
8 The name of the person who checked and approved the drawing.
I Each record drawing shall be endorsed with the words 'Record Drawing' in the bottom right hand corner adjacent to
the title blocks.

J Record Drawings shall show to the satisfaction of the Engineer the work as completed and shall record the
following:

1 The location, including level (if buried), of public service connections (if applicable) provided within the
contract, whether installed by the Contractor or the appropriate Authority, together with the points of origin
and termination, size and materials of pipes, line pressure, flow and other relevant information.
2 The layout, location and extent of all piped services showing pipe sizes, together with all valves for
regulation, isolation and other purposes, drain cocks, test points, gauges, flow or pressure switches and other
instruments.
3 Location, identity, size and details of all apparatus and controls equipment served by, or associated with,
each of the various services.
4 The layout, location and extent of all refrigerant pipe works, air ducts (if applicable), including those formed
in builders work or otherwise outside the contract, showing dampers and other equipment, acoustic silencers,
grilles, diffusers, other air terminals, balancing dampers, access panels, fire dampers, turning vanes, hand
holes, test holes, gauges and instruments. Each duct and terminal should be marked with its size and air
quantity flowing. Each terminal unit or grille shall have its duty clearly shown.
5 The location and identity of each room including spaces housing plant machinery or apparatus.
6 Detailed general arrangements of all machinery spaces, air handling plant rooms, tank rooms, electrical
switch rooms and other plant or apparatus, including the location, identity, manufacturer, size and rating of
each apparatus.
7 All necessary sections, elevations, isometrics and schematics of the plant spaces.
8 Control and wiring diagrams shall be provided incorporating details of each instrument and equipment item
and written description of the sequence of operation of each
K Floor layouts shall be to a scale of not less than 1:50.

L Plant areas and equipment rooms, sections, shall be to a scale of not less than 1:20.

M The drawings shall include symbols, valve charts, plans, sections, elevations and isometric interpretations to
provide a comprehensive record of the installations.

N Electrical drawings shall be in accordance with IET Regulations 514-09 and with this Specification.

10.4| PLANT ROOM DRAWINGS, SCHEMATICS AND INSTRUCTIONS


A In addition to Record Drawings, the following wall mounted glass covered drawings, schematics and instructions
shall be provided in plant rooms, switch rooms and any other appropriate locations:
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

1 Emergency operating procedures and telephone numbers for emergency call out service applicable to any
system or item of plant and equipment.
2 First aid instructions for treatment of persons after electrical shock
3 All information required under statutory or other regulations
4 Main Electrical Schematics
5 Controls schematics
6 Valve schedules showing reference, type, location, application/service and normal operating position
7 Schematic drawings of all systems and circuit layouts showing identification and duties of equipment,
numbers and locations, controls and circuits.
8 Valve schedules in the form of printed sheets showing the number, type, location, application/service and
symbol and normal operating position of each valve.
9 Location of all incoming service isolating valves and metering facilities.
10 Location of mechanical and electrical plant and equipment items.
11 Location of main incoming MV switchgear.
12 Location of sprinkler fire main control valve.
13 Prior to being fixed, plant and switch room schematics, schedules and instructions shall be submitted for
review by the CA. The review procedure shall be as for record drawings as stated elsewhere in this
specification and all items shall be fixed prior to practical completion.
14 Surfaces of such information shall be protected by pressure lamination and mounted using suitable fixings
and backboards if necessary.

10.5| OPERATION AND MAINTENANCE MANUALS


A The Contractor shall produce a comprehensive Operation and Maintenance Manual in line with the requirements of
BSRIA Application Guide BG/1 20078 Class D for the MEPF Services and shall make all necessary arrangements
to ensure that all required information is obtained from relevant plant and equipment manufacturers/suppliers.

B The Contractor shall include for all charges that may be required by manufacturers/suppliers for the provision of
information and literature.

C Copies of manufacturer’s data shall be supplied with respect of the nature, type and method of operation of
individual maintenance instructions. Such data, in the form of individual booklets and the like, shall be indexed and
cross referenced to the operating and maintenance instructions and presented suitably protected, in box files or
folders.

D Three (3) copies of complete operating and maintenance instructions for all MEPF systems and equipment, bound
in hard covered manuals, shall be supplied.

E The manual shall conform to the following minimum standards:

1 International A4 size and divided into volumes. Each volume shall consist of a washable four-hole ring
binder and internal section dividers complete with front pocket envelope and spine envelope, which shall
house front cove cards identifying the project title, volume number and the information contained in the
particular volume.
2 The text of the manual shall be “Arial” font size 11 printed on to best quality white paper. Tables and test
result sheets shall also be provided in this format.
3 Manufacturer’s literature shall be provided in each set of manuals as original documents. Photocopies shall
not be used.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

F The covers shall be substantial, of adequate size, distinctive and of sufficient strength to protect the contents for the
life of the installation. The method of binding shall give a permanent anchorage along the left-hand side whilst
allowing the text to be flat without damage to the spine.

G Dividers between sections shall be stepped, overlapping printed card. The divider shall be labelled to identify the
section of the manual that it precedes.

H All pages comprising the manual shall be subsequently numbered according to each section (i.e. section 1 pages
numbered 1/1, 1/2, etc., section pages numbered 2 2/1, 2/2etc.).

I The format of the manual shall be in accordance with the following sections:

1 Outline of Contents
2 Front Cover and Fly Sheet:
a. Document title - Operating and Maintenance Manual
b. Employer name and logo
c. Premises name
d. Services referred to in the manual
e. Volume reference where the manual runs to more than one volume
f. Description of contents (e.g. General Information and Design Details)
3 Spine details to be shown on all volumes:
a. Services referred to in the manual
b. Volume reference where the manual runs to more than one volume
c. Description of contents (e.g. General Information and Design Details)
4 Title Pages:
a. Premises name and address (authenticated postal address, phone, fax, e-mail etc.)
b. Services referred to in the manual
c. Full name and address of the Employer
d. Date of completion and date of handover of the services to the Employer
e. Date of issue
f. The author's reference number of the manual
g. Name and address of the author of the manual
5 Contents and Index:
a. Contents list for the whole manual. To comprise a master list of main headings of each section for
each volume of the manual, for cross reference.
b. Detailed contents for the particular volume. To include a structured contents list showing main
headings and details of contents of each section in that volume, with paragraph numbers and page
numbers.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

c. Detailed contents for each section. To be located at the front of each section of the manual, giving a
detailed, structured list of the contents of the respective section.
d. Index comprising a comprehensive alphabetical index for all sections of the manual
6 Section 1 – General information and introductory overview:
a. Full name, address, telephone and facsimile numbers, website address and email address of the
design team and all installing contractors, sub-contractors and specialists for the Works
b. Full name, address, telephone and facsimile numbers, website address and email address of all public
utilities and local authorities
c. Any limitations on the use of the manual
d. Record of amendments to manual schedule (including space for future records)
e. Description of how to use the manual
f. List of all supplementary documents
g. Distribution list and locations of all copies of the manual
h. Scope including a brief description of which systems and details are included in the manual
7 Section 2 – Contractual and Legal Information:
a. Details of ownership, leases etc. defining areas of responsibility for operation and maintenance
b. Construction / handover dates including installation start date(s), practical completion date and end of
defects liability date
c. Details and copies of all manufacturers’ guarantees or warranties together with maintenance
agreements offered by sub-contractors or manufacturers. Include expiry dates.
d. Insurance inspection reports. Documents pertinent to Employer’s / User's liability
e. Local and public authority consents. To include permissions required for access, alterations etc.
f. Safety and fire certificates. Certificates confirming that the premises and installed systems may be
safely utilised. These shall include examination certificates by competent persons for pressure
systems etc., together with written schemes of examination for pressure systems.
g. Software licence information.
8 Section 3 – Health and Safety:
a. Features or characteristics that may produce a hazard. Flammable, toxic or otherwise deleterious
substances necessary for the operation of systems; restricted access; pressure systems etc.
b. Known hazards against which protection can be provided
c. Mandatory requirements relating to safety. To include details of all systems and equipment requiring
periodic inspection/ examination/ testing to comply with relevant regulations, approved codes of
practice etc.
d. Relevant safety precautions. To include procedures to minimise the risk of damage or injury from
recognised hazards. Requirements for special manual procedures, permits to work etc.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

e. Details of recommended first aid equipment to be maintained on the premises.


9 Section 4 – Emergency Information:
a. Contact information for:
b. Utility supplier emergency services (gas, water, electricity)
c. Provider of emergency call out service
d. Installer’s emergency staff
e. Security/fire systems
f. Location of first aid equipment
g. Emergency control locations
h. Water main stopcock(s)
i. Gas shut –offs
j. Electricity isolation points
10 Section 5 – Description of Services and Design Intent:
a. A schedule of the floor areas of each of the building zones categorised by environmental servicing
type
b. Description of the whole building and intended use
c. Design philosophy including all design criteria
d. A full description of each of the installed systems and items of equipment. To include as a minimum
a written explanation of the following:
1). Scope
2). Intended purpose
3). Plant and distribution locations; divisions of main zones; etc., cross referenced to schematics
4). Function
5). General design parameters
6). Installed capacities
7). System capacities (based on commissioning results)
8). Restrictions of the systems
9). Planned operational efficiency and most economic mode of operation
10). Expected service life
11). Manufacturers information concerning correct operation
11 Section 6 – Equipment Schedules:
a. System by system schedules of all plant, equipment, valves, distribution boards etc.
b. stating as minimum:
1). Component type
2). Unique asset number
3). System
4). Location
5). Duty and size
6). Performance figures
7). Manufacturer and supplier
8). Manufacturer’s model and/or reference number
9). Manufacturer’s serial number and name plate details
10). Original order number for the particular plant/equipment item
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

11). Each item of plant/equipment must have a unique asset number cross-referenced to the record
drawings and schedules.
12 Section 7 – Systems Operation:
a. Descriptions of the operational and control strategies to include:
1). Control and operating strategy for each system
2). Outline of general operating mode including summer and winter operation
3). Start-up and shut down procedures. Description of procedures for whole system and
individual items of plant, from fully off to fully operational, including interlocks etc.
4). Interlocks and inter-dependencies between plant and systems.
5). Procedures for emergency shut down and operating procedures for standby plant.
6). Means of making safe potentially dangerous plant
7). Precautions necessary to overcome known hazards when operating each system, bringing into
operation all standby equipment included in each system
8). Instructions on fault finding and emergency in case of plant malfunction or equipment failure
control sequences for all systems installed
9). Details of all software provided and procedures for updating and/or modifying software
operating systems and control programs
10). Instructions for the creation of control procedure routines and graphic diagrams where
applicable.
13 Section 8 – Energy Management:
a. Energy management strategy to enable energy consumption to be monitored and controlled.
b. Metering philosophy. To include a schedule of the building’s energy supply meters and sub-meters,
indicating for each meter, the fuel type, its location, identification and description, and instructions
on their use.
c. Comparable performance benchmarks / target figures for energy consumption and energy costs.
d. The measured air permeability of the building
e. Forms for recording plant running hours, energy consumption and energy costs.
14 Section 9 – Maintenance:
a. Maintenance instructions for each item of plant, co-ordinated from manufacturer’s details and
recognised industry guidelines including:
1). frequency and recommended routine maintenance activities
2). dismantling and re-assembly
3). adjustment , calibration and testing
4). special tools needed for maintenance (cross referenced to the particular item)
5). test equipment and auxiliary services
6). reference to spare parts / replacements
b. Programme / frequencies for planned preventive maintenance.
c. Comprehensive schedules identifying:
d. Routine periodic checks on plant / system status and condition.
e. Periodic verification of accuracy of controls, instruments etc.
f. Routine visual and physical checks, measurements and certification of continuing fitness for purpose
and safety.
g. Routine checks / changes to plant / system components / settings to compensate for wear, operational
requirements, experience in use etc. so as to ensure continuing optimum performance.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

h. Recommended frequencies and procedures for routine lubrication of moving parts,


i. including generic specification for lubricants.
j. Procedures for fault finding and identifying causes of abnormal operation of plant / equipment.
15 Section 10 – Spares and Tools:
a. Schedule of types of replaceable assemblies, components etc. particular to specific plant.
b. Schedule of specialist tools / equipment particular for specific plant and necessary for undertaking
work at height etc.
c. Separate parts lists shall be provided for each item detailed in the equipment schedule.
d. Schedule of normal consumable items
e. Recommended stocking levels
f. Schedule of personal protective equipment necessary for operation / maintenance activities / tasks
16 Section 11 – Drawings:
a. A schedule of all engineering services record drawings for the Works. The information to include
drawing title, number, source, revision, date, system detail, file/storage location. The schedule to
include space to record future modifications and dates.
b. An A3 size reduced copy of all record drawings together with an index.
c. An A3 size reduced copy of all plant room and switch room drawings, schematics and schedules
d. Legend for all colour-coded services
e. Schematic drawings of each system, indicating principal items of plant, equipment, valves, etc.
f. A schedule of all manufacturers’ drawings for the Works. The information to include drawing title,
number, source, revision, date, system detail, file/storage location. Schedule to include space to
record future modifications and dates.
17 Section 12 – Testing and Commissioning Data:
a. Copy of report(s) confirming that the Works were satisfactorily commissioned signed by a competent
person(s)
b. Copies of all test certificates, records, commissioning and performance test records for the Works.
All certification shall be signed and witnessed.
c. Method statements for the testing and commissioning procedures undertaken
d. including description of equipment used.
e. Copies of calibration certificates for all test equipment.
f. Schedules of all fixed and variable equipment settings established during commissioning.
18 Section 13 – Manufacturers’ Data:
a. Schedule of all manufacturers and suppliers indicating company name, address, telephone and
facsimile numbers, email address(es), website address and equipment unique asset number. (Sorted in
company order alphabetically)
b. Product (manufacturer’s) data/ literature for all items of equipment and plant installed. The
information to be project specific and include detail drawings, circuit details and operating and
maintenance instructions.
19 Section 14 – Materials and Substances:
a. Register of harmful substances. Details of any materials that could be hazardous to health, used in
connection with or otherwise relevant to operational or maintenance activities.
b. COSHH details
c. Register of recyclable materials
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

d. Methods for safe disposal or destruction of any parts, materials or components. Provide a data sheet
for each material known to constitute a potential hazard, with detailed procedures for its safe,
authorized disposal.
20 Section 15 – Modification Information:
a. Details of allowances made by plant manufacturer or system designer for modifications
b. Provide space in manual to record future modifications.

10.6| ELECTRONIC OPERATING & MAINTENANCE MANUALS


A Electronic Operating & Maintenance Manuals shall be provided for the project in CD format. The documentation
shall be as that provided in hard copy format including data sheets, testing and commissioning results,
manufacturers' literature, wiring diagrams, and record drawings.

B The electronic manual shall be arranged with appropriate hyperlinks through a comprehensive and logical content
listings and cross-references to enable record information to be accessed by selection from the record drawings.
Graphics in the form of system schematics and building layouts shall be included on the system to enable this to be
done.

C All documentation shall be presented in one of the following formats:

1 Microsoft Word (latest version)


2 Microsoft Excel (latest version)
3 AutoCAD (latest version)
4 Revit Model (agreed version)
5 Adobe Acrobat (PDF) files
D In instances where documentation is not readily available in the above formats, such as manufacturers' Operating &
Maintenance instructions, the information shall be scanned. The scanned images shall be no less than 300 dpi and
24 bit colour and saved as JPEG files before being converted into Acrobat PDF files. Only good quality originals
shall be scanned ensuring that the images are straight and that all the information is clearly legible.

E All recorded test results and commissioning data shall be type written.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

10.7| CLOSE OUT PROCEDURES


A General:

1 Closeout procedures shall be sequenced properly so that work shall not be endangered or damaged, and so
that every required performance shall be fully tested and demonstrated.
B Final Operational Check:

1 A check of each item in each system shall be made to determine that it is set for proper operation.
2 With the Consultant present, the Contractor shall operate each system in a test run of appropriate duration to
demonstrate compliance with performance requirements.
3 During the following test runs, the Contractor shall make final corrections or adjustments of systems to
refine and improve performances where possible, including noise and vibration reductions, elimination of
hazards, better response of controls, signals and alarms, and similar system performance improvements.
4 The Contractor shall provide testing or inspection devices to permit observation of actual system
performances and shall demonstrate that controls and items requiring service or maintenance are accessible.
C Cleaning and Lubrication:

1 After final performance test run of each electrical system, the Contractor shall clean system both externally
and internally, shall comply with manufacturer’s instructions for lubrication of both power and hand
operated equipment, and shall remove excess lubrication, touch up minor damage to factory-painted finishes
and other painting specified as electrical work, and shall refinish work where damage is extensive.
D Operating Instructions:

1 General operating instructions are required.


2 In addition to specific training of the Client’s operating personnel specified in the individual sections, and in
addition to preparation of written operating instructions and complied maintenance manuals specified
elsewhere in these specifications, the Contractor shall provide general operating instructions for each
operational system and equipment item of electrical work, and coordinate instructions with instructions for
mechanical work, and other equipment where associated with electrical systems or equipment.
E System Description and Operation:

1 Shall be performed by the Contractor in the presence of the Client, the Client’s operating personnel and the
Consultant.
2 The Contractor shall describe each basic electrical system and shall explain identification system, displayed
diagrams, signals, alarms and audio visual provisions.
3 The Contractor shall describe interfaces with mechanical equipment, including interlocks, sequencing,
startup, shutdown, emergency, safety, system failure, security and similar provisions.

10.8| DEFECTS LIABILITY


A Liability for making good defects in the installations shall be for a period of twelve months from the date of issue of
the certificate of practical completion for the installations.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

B If as part of liability for defects, it is necessary to replace or renew any portion of the contract Works, the defects
liability period in respect of that portion of the contract Works shall be deemed to commence from the date of such
replacement or renewal.

C If the replacements or renewals are of such a character as may affect the efficiency of the contract Works or any
portions thereof, the CA may require that new tests be carried out to demonstrate that the plant is continuing to
work satisfactorily.

D The contractor shall take all precautions in the remedying of defects in the contract Works to minimise the risk of
damage to the buildings, the decorations, the fittings and the equipment. In the event of such damage occurring, the
contractor shall bear the cost of replacement or making good, subject to the proviso of being granted the benefit of
any settlement in respect of such damage accepted by the insurers under the insurance policies taken out in
accordance with the requirements of the contract.

E The contractor shall agree with the CA a programme for the carrying out and the completion of any work not finally
finished at the time of the contract Works being offered for acceptance and which does not prejudice the issue of a
practical completion certificate. This work may be requested to be executed out of normal hours and no additional
costs shall be accepted for this action.

F The contractor shall prepare and submit records of failures or malfunctions of any part of the Works during the
defects liability period, together with remedial action taken, subsequent re-testing and the results. The CA shall be
notified of damage, failures or malfunctions to the Works caused by incorrect operation of the installations,
vandalism or other actions by a third party.

G The contractor shall rectify all defects due to materials or workmanship or other faults that occur, including those
notified by the Employer or CA, during the defects liability period with the minimum of delay and at no additional
cost to the contract.

H Prior to practical completion a written statement shall be prepared for the approval of the CA that sets out the how
the defects which arise during the defects liability period shall be rectified to ensure that disruption to the
Employer's use of the building is kept to a practical minimum. This work may be required to be executed out of
normal hours and no additional costs shall be accepted for so doing. The CA shall be informed in writing when all
defects are finally rectified so that an inspection may be undertaken by the CA.

10.9| CONTINUED OPERATIONAL SUPPORT


A The Contractor shall provide skilled operating and maintenance personnel until the Client’s personnel takeover the
operation of entire mechanical and electrical plant.

B The Contractor shall respond promptly with continued consultation and services (beyond takeover date) on
electrical systems, matching required continued services on associated mechanical systems and equipment until the
end of the warranty period.

C The transfer of MEPF systems to the Client for operation shall not proceed until guarantees, warranties,
performance certifications, maintenance agreements and similar commitments have been executed, transmitted to
and accepted by the Consultant for placement in the Client’s records.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

011 | SUSTAINABILITY REQUIREMENTS

11.1| SCOPE OF WORKS


The Contractor shall supply, install, test and commission the complete MEP Services installation in relation to the
Trakhees EHS ‘Green Buildings’ Guidelines and any further project sustainability KPIs identified by the appointed
specialist Sustainability Consultant, some of which are addressed below.

11.2| SUSTAINABLE DESIGN


The design, construction and maintenance of buildings has a significant impact on our environment and natural
resources. Buildings typically annually consume more than 30% of the total energy and over 60% of the electricity used
in the developed world.

Green building practices can however substantially reduce or eliminate negative environmental impacts and improve
existing unsustainable design, construction and operational practices. As an added benefit, green design measures can
reduce operating costs, enhance building marketability, increase worker productivity and reduce potential liability
resulting from indoor air quality problems. In other words, green design has environmental, economic and social
elements that benefit all building stakeholders, including owners, occupants and the general public.

WME are fully committed to the principles of sustainable environmentally responsible building design and related
construction and will propose a high level of a sustainable design, although it is understood that the project budget must
be protected.

The Trakhees EHS Green Building Regulations will be used as a guideline, to inform our design, and a direction on
which or any other sustainable parameters being implemented, in coordination with the sustainability consultant.

11.2.1 SUSTAINABLE DESIGN INITIATIVES


 All HVAC systems will be efficiently sized based on heat load calculations for each of the spaces in each of the
building, for the basis of the selection of the equipment,
 The centralised HVAC systems for each building will be provided with heat recovery, based on the building
ventilation rates.
 Programmable thermostats linked to all air conditioning systems will be provided,
 All HVAC systems presently proposed, utilise chilled water and no ozone depleting refrigerants will be used.
 Interior lighting criteria will be achieved using LED lighting to minimise power density,
 Occupancy sensors will be provided for lighting control in relevant and appropriate spaces.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

012 | METERING STRATEGY


It is understood from ATP, that metering provisions within phase 3 of the water park, Aquaventure, will be for check
metering purposes only and not for billing.

12.1| CHILLED WATER METERING


The chilled water will be provided with a BTU meter located at the interface point to the site wide CHW network
typically served from the existing Empower District Cooling Plant connection via ETS 05.

All buildings will be sub metered at the tie in point to each building or plantroom, and the meters will be networked on a
dedicated system separate (MODBUS) from the BMS to allow real-time monitoring and data logging of the CHW
consumption of each building.

12.2| LOW TEMPERATURE HOT WATER (LTHW) METERING


The Low Temperature Hot Water will be provided with a BTU meter located at the interface point to the site wide
LTHW network served from the new Atlantis the Palm LTHW Plantroom (building B12) to be constructed as part of the
project scope of works.

All buildings will be sub metered at the tie in point to each building or plantroom, and the meters will be networked on a
dedicated system separate (MODBUS) from the BMS to allow real-time monitoring and data logging of the LTHW
consumption of each building.

12.3| ELECTRICITY METERING


All electrical meters will be located in a safe place like Main LV rooms and sub electrical rooms/cabinets, with only
access to authorized persons to avoid tampering and malfunctioning.

Final metering arrangements shall be developed and agreed with client according to DEWA regulations, and where
billing meters are required at the main distribution boards these will be provided in line with DEWA requirements.

All buildings will be provided with sub-metering for check metering only. Metering units will be kWhr meters with
power quality monitoring. Each meter will be linked on the site wide BMS system for monitoring only.

12.4| WATER METERING


The water supplies to each building will be sub-metered at metering locations within the associated buildings. In
addition, there shall be additional check meters for each tenant serving within the building.

All meters must be capable of remote data access and must have data logging capability and complying with DEWA
specifications.

12.5| GAS METERING


There will be a new gas supply required into the new LTHW plantroom, building B12. This will be provided with bulk
metering at the building location, for the authority metering requirement of Lootah gas.

There is no further gas distribution on the development, therefore no further metering requirements.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

013 | MECHANICAL SERVICES

13.1| SCOPE OF WORKS


A The Contractor shall supply, install, test and commission the complete Mechanical Services installation described
herein and indicated on the tender drawings and equipment schedules.

B The mechanical systems shall:

1 Distribute cooling energy and maintain a satisfactory thermal environment throughout the entire
development.
2 Produce and distribute Heat to maintain pool water temperatures during winter periods
3 Provide space cooling to limit the temperature of plant rooms.
4 Limit humidity and minimise the potential for condensation.
5 Provide fresh air ventilation to maintain a satisfactory internal environment throughout the entire
development.
6 Provide suitable extract ventilation where required to minimize odours and hazardous/noxious smells within
the buildings.
7 Provide smoke control/extract systems compliant with UAE Fire and Life Safety Code.
8 Provide plant room ventilation systems to maintain a satisfactory pollution level within the basement.
C The scope of work shall comprise, but is not limited to the following:

1 Chilled Water System and Reticulation:


a. Heat exchangers (within Triton tower basement plant room)
b. Chilled water piping
c. Pipeline Ancillaries
d. Valve packages
e. Water treatment
f. Flow Meters
g. Control Systems interface.
2 Low Temperature Hot Water (LTHW) System
a. Boilers
b. Flue Gas Chimneys
c. Fuel system
d. Filtrations Systems
e. Pressurisation Equipment
f. Expansion Tank
g. Degasser
h. Pumps
i. Pipelines
j. Pipeline Ancillaries
k. Valve packages
l. Water treatment
m. Flow Meters
n. Control Systems interface.
o. MCC panels
3 General Ventilation and Air-conditioning Systems:
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

a. Fresh Air Handling Units


b. HVAC Air Handling Units
c. Supply and Extract Fans
d. Fan Coil Units
e. Kitchen extract fans
f. Louvers and Diffusers/Grilles
g. Attenuation
h. Ductwork
i. Ductwork Ancillaries
j. Control Systems
k. DX Split Systems
l. Boiler Room Ventilation System
m. Transformer Room Ventilation
n. Generator Room Ventilation
o. Fire Pump Room Ventilation
4 Basement Pump Room Smoke Control Systems
5 Thermal insulation of MEPF services in line with local authority Regulations and Specifications
6 Seismic Restraints
7 Acoustic and Vibration Treatment (As per Acoustic consultant report)
8 Automatic controls and motor control centre’s
9 Building management system & automatic controls
10 Energy metering system
11 Generator make up air and exhaust system
12 Testing and commissioning of all systems
13 Demonstration and handover to the Employer
14 Provision of handover documentation including Operating and Maintenance manuals, provision of
warranties, service agreements and Planned Preventative Maintenance schedules
15 Training of Employer’s staff
16 Local Authority Approvals

13.2| THERMAL INSULATION


A The Contractor shall design, supply and install the complete thermal insulation installation requirements for all
pipes, valves, ducting and equipment. All external services shall be correctly treated in proprietary weatherproof
materials. The materials shall be suitable for their environment and not prone to deterioration where in performance
when subjected to the elements. Where insulation materials are supplied and installed within unconditioned areas
they shall be protected. The material shall be of rigid pre-formed construction such as aluminium cladding or
similar. Service bonding/classification shall be applied over the finish.

B All insulation shall be Dubai Central Laboratory approved

C Installations shall be thermally insulated in accordance with the specification to conserve energy or prevent surface
condensation. Services shall be colour banded/identified in accordance with the specification. Areas of thermal
insulation exposed to weather will be finished with aluminium cladding.

D The following mechanical services shall be thermally insulated in accordance with the relevant sections of this
specification:
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

1 External Louver plenums


2 Refrigeration systems
3 Air diffuser plenum boxes
4 Primary air supply ductwork from air handling units.
5 Primary air return ductwork back to air handling units which have heat recovery of the exhaust air
6 All CHW and LTHW pipe work and equipment in its entirety.
7 Secondary ductwork from FCUs/AHUs.
8 Full condensate system
9 Valves and accessories
E The contractor shall supply and install the following types of pipework insulation in accordance with specification
section 23 0719 – HVAC PIPING INSULATION

F Chilled water pipework (internal)

1 Foam type insulation (As per Section 23 07 00: HVAC Insulation), self-adhesive with aluminium covering
and aluminum cladding within plantrooms up to a height of 2.5m above the Finished Floor Level.
G Chilled water pipework in its entirety external (not buried)

1 Foam type insulation (As per Section 23 07 00: HVAC Insulation),, self-adhesive with aluminium covering
and 0.7mm aluminum cladding
H Chilled water pipework in its entirety external (buried)

1 HDPE pipe with HDPE jacket and polyurethane insulation.


I Low Temperature Hot Water pipework (internal)

1 Foam type insulation (As per Section 23 07 00: HVAC Insulation),, self-adhesive with aluminium covering
and aluminum cladding within plantrooms up to a height of 2.5m above the Finished Floor Level.
J Low Temperature Hot Water pipework in its entirety external (not buried)

1 Foam type insulation (As per Section 23 07 00: HVAC Insulation),, self-adhesive with aluminium covering
and 0.7mm aluminum cladding
K Low Temperature Hot water pipework in its entirety external (buried)

1 PB pipe with HDPE jacket and polyurethane insulation.


L Condensate Drainage

1 Closed cell elastomeric insulation with 0.7mm aluminium cladding where exposed to view (i.e. not within
false ceiling) or installed externally or in plant rooms.
2 Condensate receivers
a. 50mm Closed cell elastomeric insulation
M The contractor shall supply and install the following types of ductwork insulation in accordance with specification
section 23 0713 – DUCTWORK INSULATION

N Intake / Exhaust Ductwork (To / From FAHU to louvres)

1 No insulation required to Intake ductwork


2 Elastomeric Foam insulation to be provided if unit is located externally or in unconditioned space
O Supply Ductwork

1 Flexible Elastomeric foam or Cross linked Polyefolin insulation. Where ductworks routed through
plantrooms (below 2.5m above FFL) 0.7mm aluminium cladding to be provided
P Extract Ductwork
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

1 Flexible Elastomeric foam or Cross linked Polyefolin insulation where ductworks routed through external
environments no cladding required.
Q All insulation shall be provided with continuous vapour barrier if the material itself does not provide an intrinsic
vapour barrier.

R Flexible Elastomeric foam or Cross linked Polyefolin insulation applied externally shall be complete with
impregnated aluminium finish to protect it from UV during installation and before application of cladding.

13.3| CHILLED WATER SYSTEM


A The contractor shall install an operational and functional chilled water system to provide cooling requirements for
the project.

B The Contractor shall supply, install, test and commission a complete Chilled Water Distribution System, inclusive
of, but not limited to, builders work, BMS & controls, pipework, valves and chilled water accessories, all as
depicted on the drawings and described within the project specifications within the building to provide a source of
cooling for all air-conditioning, mechanical ventilation systems, swimming pool cooling and domestic water
cooling.

C The incoming Chilled water pipe shall be routed from the existing ETS-05 plant room to all buildings except
building B09 in the entire Aquaventure Extension Phase-3. The prayer room, building B09, is an extension of the
existing building (Dolphin Bay Village building) and the necessary chilled water connection for the HVAC
requirement within these new rooms will be tapped off from the existing building services in the building.

D It will be necessary for the contractor to liaise with the pump manufacturer to confirm the pump W24-10-HVACP-
05,0607 flow and head available via physical testing and make any modifications necessary to achieve the project
requirements.

E In addition, the PHEX capacities will need to be modified via the removal of plates to match the project loads and
to ensure laminar flow does not occur within the anticipated operating range.

F The external chilled water network from ETS-05 to every building shall be laid under the ground by infrastructure
contractor. The Contractor to coordinate services as per infrastructure tie-in connection.

G From this point the chilled water pipe enters the basement high level as per infrastructure tie-in point in buildings
B01 & B02. The CHW pipes enter into the buildings B03-B08, B10, B11a & B11b via mechanical services
cupboard provided at the perimeter of the buildings. In buildings B12-B14 & B21-23, it enters directly into the
plant spaces from underground and raises to high level to serve the equipment.

H The BTU meters and valve arrangements shall be installed at the entry point to the buildings, within the cupboards
or plant spaces. BTU meter should be IP65 rating.

I For the pool specialist requirements, Chilled Water pipes shall be routed and terminated in a PHEX within the
plantroom. The specialist contractor shall design and distribute from this point for all specialist plant requirements.
The main contractor shall supply, install these PHEXs within the plant room at Triton tower.

J PIPEWORK SUPPORTS AND ANCILLARIES

1 The Contractor shall supply and install two pipes, flow and return system of pipework to convey chilled
water throughout the entire chilled water system, which shall be suitably rated to cope with the pressures
associated with pumping to the building extremities.
2 Air vents shall be provided at all pipework high points, whilst dirt pockets and drain cocks shall be provided
at all pipework low points.
3 All pipework shall be thermally insulated, vapour sealed and clearly labelled throughout.
4 Pipework shall be black mild steel threaded 50mm and below, and flanged 65mm and above.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

5 Pipework support systems shall be designed in accordance with British Standard BS 3974: Part 1, Structural
calculations.
6 The Contractor shall design, supply and install all the necessary steel support structures including fixing to
the building structure with due cognizance to the existing structural design for all pipework.
7 The Contractor shall engage a specialist structural designer to carry out the necessary design work related to
supports and associated structural elements for all pipework and plant installations, including devices to
allow for expansion, contraction and seismic movement.
8 All structural calculations, details of supports and methods of fixing to the building structure shall be
submitted to the Project Structural Engineer for approval prior to installation. This shall include a stress and
surge analysis of all chilled water pipework systems.
K VALVING ARRANGEMENTS

1 The Contractor shall supply, install, test and commission the following valving arrangements to all air
handling units, fan coil units, and any other miscellaneous terminal units:
a. Equal percentage pressure independent control valves (PICV) with a flow limiting function and direct
flow measurement by KVs method
b. The Contractor shall supply and install isolation valves, strainers and a full bore flushing bypass with
lock-shield isolating valve in conjunction with manual air vents and drain cocks on the unit side of its
local flow mounted isolating valve and return mounted combined motorised valve for variable
volume only.
c. The Contractor shall supply and install fixed orifice metering station devices (including on main
branches to verify flushing velocities) to allow reading of chilled water flow rate at all air handling
units, fan coil units, domestic water and swimming pool PHEs plus any other miscellaneous terminal
units along with main branches to verify BSRIA flushing velocities,
2 The CHW connections to the Plate Heat Exchangers within the Triton Tower B01 shall be provided with
“Energy Valves” complete with modulating control, pressure independence, embedded temperature sensors
and ultra-sonic flow measurement to provide full Delta T control with in-built control algorithms and
historical data logging of flow rates, energy usage and Flow and Return Temperatures.

13.4| LTHW SYSTEM


A The Contractor shall supply, install, test, set to work and commission the Low Temperature Hot Water Supply
systems as described below and in the tender drawings and equipment schedules.

B LTHW system shall include but not limited to; LTHW Boilers, low temperature hot water supply and return system,
primary variable pumps, VFDs, buffer vessel, plate heat exchangers, pressure vessels, filtration systems, degasser,
relief valves, pressure independent control valves, isolation and non-return valves, three-way valves, temperature
and flow sensors, etc. Cold water supply to makeup water tank shall be softened using duplex ion exchange
softeners.

C The proposed new 4 number condensing boilers (3 duty + 1 standby) shall be located within boiler plant building,
B12. The capacity of each boiler is 2,377 kW. The boiler building is to include a dedicated make up air system for a
“room sealed” system configuration with hard-wired system interlocks to ensure safe operation and all associated
hydronic ancillaries.

D The LTHW shall be supplied to the specialist plant in Triton tower via variable primary pumping system. the
pumping system includes 4 number variable speed primary pumps (3duty + 1 standby) located within the boiler
plant. From the boiler plant, then the LTHW to be taken through buried pipes and terminated in PHEXs at the
Triton tower basement plant room.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

E From the PHEXs, the secondary side connections and further distribution shall be done by specialist contractor for
the specialist requirements.

F As common PHEXs are used for both cooling and heating purposes, the LTHW pipe shall be connected with chilled
water pipe with a motorized three-way valve at the immediate connection to PHEXs. This three-way valve will
switch the supply between CHW and LTHW as per cooling and heating requirement.

G LTHW DISTRIBUTION SYSTEM

1 The Contractor shall supply, install, test and commission a complete LTHW distribution system, inclusive of
but not limited to, builders work, pumps, Degasser, pressurisation units, expansion vessels, filters, de-
aerators, BMS & controls, pipework, valves and accessories, as depicted on the drawings and described
within the project specifications.
2 The LTHW reticulation system is constant temperature, variable primary flow distribution with Pressure
independent balancing & control valve.
3 The pipework material above ground shall be ERW Schedule 40 to ASTM A 53 as per Section 23 21 23
HYDRONIC PIPING
4 Each LTHW system to be equipped with a combined pressurization/auto-fill unit. The unit is a fully
automatic packaged set, with integral control panel to maintain system pressure and water top up when
necessary. A water meter is installed on the feed pipe to assist in identifying any system leaks.
H LTHW PUMPS

1 The Contractor shall supply, install, test and commission the complete LTHW Pump installations described
herein and indicated on the tender drawings and equipment schedules.
2 The Contractor shall supply, install, test and commission duty and standby (N+1), inline centrifugal pumps
as indicated on the tender drawings and equipment schedules. The pumps shall be provided with motors
compatible with variable frequency drives and shall operate at variable speed to meet heating demand. The
VFDs shall be IP54 rated and shall be equipped with radio frequency filters and a minimum of 3 integral
serial protocols for BMS interface.
3 Values of the resistance to fluid flow of items of equipment; pipe work and/or the total distribution system
indicated in the contract documents are approximate. It shall be the responsibility of the Contractor to verify
these values and provide pumps capable of delivering the required fluid volume (inclusive of selection
margins as noted in the contract documents) when operating against the actual total system resistance based
on actual procured equipment and pipe routing. All calculations prepared by the contractor shall submit to
the Engineer for approval prior to procurement of the pumps.
4 The variable primary pumping system shall under the dictates of speed control based on system differential
pressure monitored on the BMS. Pumps speed shall therefore be controlled to maintain a constant pressure
across the most remote pressure controlled sub-branch. This shall be achieved by using variable frequency
drives on the pump motors which shall vary the speed of the primary LTHW pumps via the BMS, under the
dictates of the differential pressure control. No variations or extensions of time resultant from a failure to
produce the relevant calculations in a timely manner will be considered.
5 All variable speed pumps shall be selected to the right of their Best Efficiency Point (BEP). Motor size shall
be selected so that the power curve does not cross the pump curve at any point (non-overloading).
6 The Contractor shall note that the building side system pumps are not to be used for flushing of the LTHW
system in order to eliminate of the risk of damage to the pump impellers. Temporary flushing pumps shall be
provided in place of the main LTHW pumps as part of the pre-commissioning cleaning process. Dirt pockets
shall also be provided at all system low points.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

7 The pumps shall be factory tested in the presence of the Engineer in accordance with the requirements of the
relevant British / European Standards and shall be selected to give the correct fluid flow rate and, unless
otherwise indicated, test certificates and performance curves shall be submitted.
I PIPEWORK SUPPORTS AND ANCILLARIES

1 The Contractor shall supply and install two pipes, flow and return system of pipework to convey LTHW
throughout the building, which shall be suitably rated to cope with the pressures associated with pumping to
the building extremities.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

2 Air vents shall be provided at all pipework high points, whilst dirt pockets and drain cocks shall be provided
at all pipework low points.
3 All pipework shall be thermally insulated, vapour sealed and clearly labelled throughout.
4 Pipework shall be ERW black mild steel threaded 50mm and below, and flanged 65mm and above.
5 Pipework support systems shall be designed in accordance with British Standard BS 3974: Part 1, Structural
calculations.
6 The Contractor shall design, supply and install all the necessary steel support structures including fixing to
the building structure with due cognizance to the existing structural design for all pipework.
7 The Contractor shall engage a specialist structural designer to carry out the necessary design work related to
supports and associated structural elements for all pipework and plant installations, including devices to
allow for expansion, contraction and seismic movement.
8 All structural calculations, details of supports and methods of fixing to the building
9 structure shall be submitted to the Project Structural Engineer for approval prior to installation. This shall
include a stress and surge analysis of all chilled water pipework systems.
J VALVING ARRANGEMENTS

1 The Contractor shall supply, install, test and commission the following valving arrangements to all water
cylinders.
a. Equal percentage pressure independent control valves (PICV) with a flow limiting function and direct
flow measurement by KVs method
b. The Contractor shall supply and install isolation valves, strainers and a full bore flushing bypass with
lock-shield isolating valve in conjunction with manual air vents and drain cocks on the unit side of its
local flow mounted isolating valve and return mounted combined motorised valve for variable
volume only.
c. The PICVs shall provide differential pressure control, flow regulation and two port open/close
modulation to vary the flow of water through terminal units in response to building demand/load.
Orifice plate flow measurement devices shall be provided when water flow measurement is not
integral to the PICV itself. The installation of these valves shall ensure that control valve authority is
maintained under varying differential pressures and over flow of LTHW that can lead to delta T
degradation is prohibited by a flow limiting function of the valve.
d. The PICV can also be configured with one integrated valve body to incorporate an adjustable CV
chamber and separate pressure regulating chamber to maintain a constant differential pressure across
the control surface.
e. The PICV shall consist of a Control Valve (CV) segment and Differential Pressure Control Valve
(DPCV) segment complete with sensing lines.
f. The Contractor shall supply and install variable orifice metering station devices (including on main
branches to verify flushing velocities) to allow reading of LTHW flow rate at swimming pool PHEs
plus any other miscellaneous terminal units along with main branches to verify BSRIA flushing
velocities.
g. During commissioning phase, the Contractor shall have a digital-measuring instrument furnished by
the valve manufacturer to translate quickly and accurately the valve pressure drop / metering station
into the corresponding LTHW flow. Post hand-over the ownership of this measuring instrument shall
pass to the client along with an in-date calibration certificate.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

2 The LTHW connections to the Plate Heat Exchangers within the Triton Tower B01 shall be provided with
“Energy Valves” complete with modulating control, pressure independence, embedded temperature sensors
and ultra-sonic flow measurement to provide full Delta T control with in-built control algorithms and
historical data logging of flow rates, energy usage and Flow and Return Temperatures.
K PRESSURISATION UNITS:

1 The Contractor shall supply, install, test and commission factory packaged, factory piped and factory wired
single point power connection, pressure fill system consisting of surge tank assembly, water feed make−up
assembly, pressurization tank with pump, control panel, pressure reducing valve assembly, pressure
indicator, level controller, flow balance valve, pressure switch, primary vessel with pumps and also a
secondary expansion vessel with fixed air cushion.
2 Each pressurisation unit shall be equipped with a microprocessor and fascia mounted display panel. The unit
shall be provided with volt free contacts for control, switching, monitoring and alarms to the BMS. The
following alarms shall be visually indicated on the display panel:
a. Power failure
b. Low water level
c. Pump running
d. Pump tripped
e. High/Low pressure cut-outs
f. Excessive pump operation
g. Current operating pressure
h. An audible alarm and muting facility shall be incorporated. The above alarms shall be available for
the BMS via volt-free contacts
L LTHW DOSING AND FILTRATION SYSTEM:

1 The Contractor shall implement an approved water treatment programme for the LTHW, to ensure freedom
from disposition (scale etc.) corrosion and microbiological activity, along with plant integrity and
operational efficiency.
2 The closed water systems shall incorporate facilities to enable flushing, cleaning and ongoing maintenance,
to prevent bacteriological contamination (subject to testing and ecessity), in accordance with the latest
BSRIA Guidance, and including ‗biocide treatment‘ of the incoming/fill water, provision of strainers,
bypasses, velocity measurements, flushing, chemical cleaning and regular bacteriological water quality
checks throughout the installation, flushing and commissioning phases.
3 Environmental considerations are paramount and only companies who can demonstrate environmental
excellence will be approved. The condenser water systems shall also be provided with permanent Disc
filtration system. The flushing, chemical pre-cleaning, passivation and maintenance treatment will be carried
out in accordance with the detailed Mechanical specifications.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

13.5| VENTILATION AND AIR CONDITIONING SYSTEM


A The Contractor shall supply, install, test, set to work and commission mechanical ventilation systems as described
below and indicated on the tender drawings and equipment schedules. The mechanical ventilation systems shall:

1 Provide a supply of fresh air for building occupants and dilute and remove internally generated
contaminants/pollutants.
2 Remove and replace foul air from toilets and refuse rooms.
3 Limit air infiltration by positively pressurising the entire building relative to the external ambient
environment.
B Air conditioning systems shall be installed to provide the building occupants with comfortable internal conditions
whilst consuming the least amount of energy possible via the use of intelligent building controls and the provision
of heat recovery.

C Mechanical ventilation systems shall be installed to provide fresh air for the building occupants, to dilute and
remove air contaminants generated internally within the building, to pressurise the building to reduce infiltration
and to dilute and remove polluted air and smoke (in the event of a fire) from the car park and residential corridors.

D All HVAC systems shall be fully controlled via the building management system, including switching, alarms,
control and monitoring as defined in the controls section of the specification, electrical specifications mechanical
specifications, equipment schedules and tender drawings. The plant shall be interlocked with the fire alarm system
to switch plant in the event of a fire condition, as defined elsewhere in this specification.

E Fan coil units shall be selected on their medium speed setting to meet the space cooling and acoustic requirements.

F Installations shall be thermally insulated in accordance with the specification to conserve energy or prevent surface
condensation. Services shall be colour banded/identified in accordance with the specification. Areas of thermal
insulation exposed to weather will be finished with aluminium cladding.

G Ductwork distribution systems shall be in accordance with Heating and Ventilating Contractor’s Association
(HVCA) Ductwork specification DW144, DW171, HVCA Ductwork Leakage testing guidance DW143 and HVCA
Good Practice Guide for Internal Cleanliness of New Ductwork Installations DW/TM2 where non-metallic
ductwork installations are specified for corrosive atmospheres, the systems shall be in accordance with HVCA
UPVC ductwork specification DW151 or HVCA GRP ductwork specification DW191 as applicable.

H Internal stiffening of the ductwork shall be as per ASHRAE SMACNA standards for the relevant pressure class in
line with the requirements of HVCA DW144 I. Seismic restraints shall be provided in strict accordance with
ASHRAE SMACNA classification 2A (in line with DM Guidance). All calculation, design and selection of the
support system shall be the contractor’s responsibility.

I Manually operated opposed blade volume control dampers shall be installed on every branch to affect proportional
and system balancing in accordance with Chartered Institution of Building Services Engineers (CIBSE)
Commissioning Code A. Plenum diffusers shall not be used for primary balancing of branches and up- stream
VCDs shall be provided

Ventilation system construction and installation shall be in accordance with the fire precautions requirements of the
Authority Having Jurisdiction (AHJ). Ductwork distribution systems shall be fire stopped and/or fitted with fire
dampers at penetrations of the fire compartments, as required to maintain the integrity of the building envelope and
its defined fire protection.

J Air handling and other plants at roof level (if any) shall be provided with lugs for connection to the lightning
protection installation.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

K The Contractor shall calculate the external static pressures for each air handling unit supply and return fan, extract
fans, ecology units, fan coil units etc. after finalising the shop drawings, and prior to selecting the related
equipment. The calculations shall be submitted and approved by the Engineer prior to the issue of the air handling
unit material submittals.

L The Contractor shall allow for one complete belt/pulley change for each air handling unit supply fan and extract fan,
ecology unit, extract fan etc. to be changed subject to the provision of satisfactory commissioning results (the
submitted commissioning figures shall demonstrate that measured air-flowrates are in accordance with the design
flow rates).

M The Contractor shall replace all air handling unit filters with new panel and bag filters in accordance with the
equipment schedules, supplied by the air handling unit manufacturer post commissioning and prior to handover.
Return air openings shall be protected during construction with F7 filters where systems are tested or operated.
Systems not operating shall be suitably sealed to prevent dust ingress.

N FCU’s shall be EC motors type and provided with Pressure independent control & Balancing valve (PICV) at each
terminal unit to ensure accurate flow control at all differential pressures.

O Ductwork distribution after the FCUs shall be via low pressure pre-insulated ductwork specified to comply with
latest DCD directives regarding acceptable insulation materials.

P Volume Control Dampers will be provided at each branch connection, as recommended by BSRIA and CIBSE
commissioning codes, with plenum boxes and final balancing dampers installed at each diffuser. Where necessary
to maintain an aesthetic affect dummy diffuser will be provided in addition to active diffusers.

Q For the plant room cooling in building B01, ceiling mounted air handling units (AHU) as proposed as an effective
cooling system based on the plant room size. The Ceiling mounted AHU’s shall have ductwork distribution via low
pressure ductwork and supply grilles in the ductwork of the respective unit.

R MECHANICAL VENTILATION – B04

1 The locker rooms in building B04 shall be supplied with fresh air from dedicated fresh air handling unit
located outside the building at ground level. The Fresh Air handling unit shall generally comprise of; supply
fan, return air fan, cooling coil, filters, heat recovery section (heat pipe heat recovery), horse shoe heat pipe,
attenuators (may be duct mounted), control devices such as sensors, switches, etc. and motorised dampers.
2 Horse shoe heat pipes utilising R134a are to be installed in the FAHUs as outlined in the schedules and on
the schematics to reduce the dehumidification load and provide “free” reheat to the supply such that it is
supplied at approximately neutral conditions
3 Fresh Air handling Units shall be located on concrete bases and shall utilise anti vibration mountings to
isolate noise and vibration from the structure. The support system shall be designed based on a seismic
restraint classification of 2B as defined by the Unified Building Code.
4 The treated fresh air is typically directly ducted to the FCUs serving to the locker rooms, showers and toilets
and extract air is taken from these areas. The systems shall be balanced to provide a slightly negative
pressure with respect to outdoors. The extracted air is passed through the heat recovery section in the FAHU
to provide heat recovery with a refrigerant (R134a) Horse Shoe Heat Pipe to increase dehumidification and
provide reheat to the supply air.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

5 The primary cooling medium for the roof top FAHUs is chilled water as described above. Each cooling coil
shall be provided with a Pressure Independent Control Valves (PICV) to match cooling output to actual
demand under all part loads and system differential pressures. Cooling coils shall be provided with
condensate drip trays. Condensate drains shall be provided with traps of sufficient depth of seal to match
internal operating static pressures. The air-handling units have been limited in size in an attempt to facilitate
the plant to be broken down into sections, which can be manoeuvred on to site and replaced in the future
more readily.
6 All ventilation air (Supply and Exhaust) ductwork will be insulated GI distributed from the units to the final
grilles.

13.6| TOILET VENTILATION


A The toilets and changing rooms shall be provided with extract ventilation. To maintain negative pressure within this
area, make up air, 85% of exhaust air shall be provided and to be connected in the return of the plenum box of the
FCU’s serving the toilets.

B The toilet extract fans shall be installed as per the tender drawings and specifications.

C All ventilation air (Supply and Exhaust) ductwork will be insulated GI distributed from the units to the final grilles
coordinated within the ceiling voids.

13.7| SMOKE VENTILATION – B01


A Smoke control system shall be provided for the basement plant room in Triton tower as the basement area exceeds
285 sqm. A ventilation rate of 3 air changes per hour shall be considered and ventilation system shall be provided
accordingly.

B The smoke extract fan shall be located in the basement high level and ductwork extended throughout the plant room
with exhaust grille in the ductwork. The smoke shall be discharged to outside via weather louvers at ground level as
coordinated with the architects.

C Whilst the makeup, which is 85% of the smoke exhaust, shall be drawn into the plant space via makeup air louver
with motorized damper. During smoke scenario only, the makeup air louver shall be open, and outside air shall be
pulled into the plant room based on the extract system.

D Smoke extract duct material shall be as per UAE fire code and specifications.

13.8| BUILDING MANAGEMENT SYSTEM


A The Contractor shall employ a BMS/controls specialist to design, supply, install and commission a complete and
fully operational automatic controls system as described below and indicated on the tender drawings and equipment
schedules.

B BMS works shall consist of the provision of all labour, materials, tools, equipment, software, software licenses,
software configurations and database entries, interfaces, wiring, tubing, installation, labelling, engineering,
calibration, documentation, samples, submittals, testing, commissioning, training services, permits and licenses,
transportation, shipping, handling, administration, supervision, management, insurance, temporary protection,
cleaning, cutting and patching, warranties, services, and items, even though these may not be specifically mentioned
in the documents which are required for the complete, fully functional and commissioned BMS.

C The Controls Specialist shall be responsible for:

1 The design and engineering of the complete automatic controls system including all necessary co-ordination
2 Providing all materials to form a complete and operational system as indicated
3 Off-loading, positioning and fixing of all control panels
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

4 Installation
5 Supervision of the installation
6 System calibration
7 Software programming
8 Testing and commissioning
9 Completed system demonstration to the Engineer and Employer
10 Employer training
11 Record documentation
D It is acknowledged that different systems offered by BMS specialists may vary in matters of system architecture,
software, integration and other details. It is the intention of this specification to outline the functional requirements
of the system, and it is expected that the final BMS providers shall base their proposals on their Open systems.
However, where any deviation from the specification is proposed, this must be analysed to ensure that the system
offered is fully compliant with the requirements of the final BMS specification and shall only be implemented upon
written approval from the Engineer.

E The contractor is to engage with Atlantis The Palm Facilities Management team to ensure that the proposed BMS
can be seamlessly integrated into existing site wide BMS with all set points adjustable and alarms reported at, the
existing head end software.

F The Contractor shall engage an Automation and Controls Specialist to design, supply, install, test and commission a
complete and functional Building Management System (BMS) to provide centralized monitoring and control of all
engineering services described within this specification, in particular:

1 Heating, Ventilation and Air-conditioning Equipment:


a. Fresh Air Handling Units and associated components
b. Fan coil units
c. Kitchen extract fans / ecology units
d. Air curtains
e. Chilled water pumps
f. LTHW pumps
g. Pressurisation units
h. Deaerators
i. Variable speed / variable frequency drives (VSDs / VFDs)
j.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

2 Smoke Control Fans and Equipment


a. Smoke/fire dampers
b. Pump room ventilation fans
3 Domestic Water and Public Health Systems:
a. Booster pump sets
b. Transfer pump sets
c. Water storage tanks
d. Water treatment systems
e. Sewage/waste water pumps
f. Sump pumps
g. Landlord grease traps
4 Lighting Controls:
a. Back-of-House and Car-park Lighting
b. External and Façade Lighting
5 Digital Metering Systems:
a. Chilled Water flow and BTU meters
b. NG meters
c. Domestic water meters
d. Electricity consumption (kWhr) and power demand (kVA) meters
6 Electrical Power Systems:
a. Automatic transfer switches (ATS)
b. Emergency power generator
c. Uninterruptible power supplies (UPS) and by-pass switches
G All plant and equipment listed above shall be monitored for fault and alarm conditions with status indication at the
head-end PC Workstations. In addition, the BMS shall be interfaced with the following specialist systems to
provide supervisory monitoring, status indication and annunciation of the critical alarms:

1 Electrical MDB / SMDB / MCC panels – Power Monitoring Units


2 Emergency Lighting Central Battery System
3 Lift Management System
4 Lift Pit water sensors
5 Disabled Persons Alarm System
6 Water (leak) Detection Systems
7 Gas (leak) Detection Systems
8 Fire Alarm System – including Sprinkler Control Valves and Fire Pumps
9 Gas Suppression Systems
10 Swimming Pool and Water Feature Plant and Equipment
11 Water Filtration and Chemical Dosing Systems
H The BMS shall be designed and configured to maximise energy efficiency by ensuring that plant does not run
unnecessarily and operates in accordance with the pre-defined control modes in response to control inputs.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

I The BMS shall comprise the following main components:

1 BMS Head-end and PC Workstations, complete with graphical user interface, keyboard and printer.
2 Plant-rooms: stand-alone outstations and Motor Control Centres (MCCs)
3 Field Devices: sensors, actuators and valves, complete with signal wiring.
J Communications Network and System Architecture:

1 BMS outstations shall be provided at strategic locations throughout the building with microprocessor-based
controllers providing monitoring, data collection and Direct Digital Control (DDC) of the MEP systems. All
BMS outstations shall be housed in lockable enclosures or MCCs, manufactured to Form 4 Type 2 standard
with separate power and controls sections to ensure safety and reliability.
2 The Contractor and his Controls Specialist shall provide all necessary power supplies for the BMS
outstations and MCCs, and all necessary hardware and software interfaces required to achieve a fully
independently wired BMS system
K Field Wiring and Secondary Communications Network: The BMS Sub-contractor shall provide all signal wiring
and secondary network cabling and equipment downstream from the BMS outstations and MCCs, for the inter-
connection of all system controllers, I/O, data gathering panels and field mounted devices including sensors,
motors, fan coil units, etc.

L Coordination with Electrical (Division 26) and Communications (Division 27) services trades:

1 Motor Control Centres (MCCs): all switchgear components and equipment including circuit breakers,
contactors, overload relays, motor starters and motor drives shall be procured from a single original product
manufacturer. The MCCs shall be supplied as complete functional units and designed in accordance with the
Division 26 – Electrical Services specification.
2 Power Supplies for Motors and Equipment: Liaise with the Division 26 Sub-contractor (Electrical) to ensure
that all circuit breakers, power wiring, motor starters and motor drives are properly coordinated with the
rated loads and starting characteristics of all motors and equipment being controlled.
3 Communications Outlets / Network Points: Liaise with the Division 27 Sub-contractor (Communications) to
ensure that sufficient data outlets are provided to support the BMS installation.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

014 | PLUMBING SERVICES

14.1| SCOPE OF WORKS


A The Contractor shall supply, install, test and commission the complete Plumbing Services installation described
herein and indicated on the tender drawings and equipment schedules.

B The scope of work shall comprise, but is not limited to the following:

1 Domestic Cooled Cold water supply system.


2 Domestic Cold Water supply system.
3 Domestic Hot Water systems
4 Foul and Waste Drainage system
5 Sanitary Wares
6 Condensate Drainage system
7 Roof Drainage system
8 Disposal of pool back wash from specialist
9 Testing and Commissioning of all system.
10 Demonstration and handover to the Client
11 Operating and Maintenance manuals, provision of warranties service agreements and planned maintenance
schedules
12 Training of Employer‘s staff
13 Local Authority Approvals

14.2| DOMESTIC COLD WATER SYSTEMS


A The Contractor shall supply, install, test, set to work and commission the Domestic Cold Water Supply systems as
described below and indicated on the tender drawings and equipment schedules. The Domestic Cold Water system
shall be provided for the project meeting the following.

B Potable Water Supply

1 Incoming and Storage


a. Phase 3 water park, Aquaventure will be serviced from the existing potable water tank, pump room
and pipework. Refer to infrastructure services section for the locations where tapping off from the
existing underground HDPE potable water main are made to serve the Phase 3 water park and
extension of these to each building and locations where each building shall be tied in.
b. Potable water from DEWA to each building shall be available from the above mentioned network at
an approximate distance of 1.0 metre around the building perimeter from the infrastructure services.
2 Distribution
a. From the above tie-in location, building services MEP Contractor shall extend the water supply pipe
within the building, raise to the high level and then reticulate to distribute potable water to the
various requiring sanitaryware appliances.
b. Prior to extending the water supply piping, each building is provided with one set of PRV, submeter
and IVs. The PRV station is used to reduce incoming pressure to the range of 2.5 to 3.5 bar. The
PRVs shall be set such that the pressure available at the hydraulically farthest appliance shall be
minimum 2.0 bar.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

c. The potable water supply system for the project mainly comprises of, but not limited to extension of
buried pipework to each building, provide PRV, meter, and isolation valves, cooled cold water heat
exchangers and pipework, extension of water supply pipework to external bib taps, external showers
etc.
d. The buried incoming potable water pipework shall be HDPE or uPVC Class E to PN20 rating. All
distribution domestic water pipework within the buildings shall be of high quality Polypropylene
PN20 random pipe (PPR) or approved equivalent. All pipework within wall chases shall be in PEX
system.
e. For Buildings B01,02 and 08 the incoming potable water supply shall be extended at the basement
high level with two branches.
f. Each branch is provided with one no. of PRV station after which one is capped off to serve
exclusively for the pool specialist while the other is extended to serve for the general building potable
water usages.
g. After the capped off connection, the pool specialist shall extend the pipework and reticulate to all his
equipment as part of his specialist design.
h. The Building services MEP Contractor shall coordinate with Pool specialist, for the required
pressure, flow and exact location of tie in etc.
i. The other general potable water supply serving for the building shall be extended by the MEP
Contractor to serve for bib taps, male and female toilets, etc as specifically applicable to the
respective building.
j. For buildings B03, 04, 13, 14 and 21, potable water is extended to serve for the toilets bib taps and
external showers as applicable.
k. The external showers shall be provided with 20mm diameter cooled cold water supply pipework with
cooled cold water supplied at 20 deg C. The buried cooled cold water pipework extended from the
adjacent building, shall be fully insulated and protected with external sleeve.
l. A stainless steel plate heat exchanger with all required ancillaries suitable for potable water
applications shall be installed for to generate the cooled cold water. The heat exchanger shall be
connected with chilled water supply and return pipes on the primary side.
m. Building B05 is an F&B building and shall be provided with full extent of potable cold, cooled cold
and hot water supply pipework to all requiring appliances.
n. Building B06 is an F&B building with an additional public toilet within and hence this building also
shall be provided with full extent of potable cold, cooled cold and hot water supply pipework to all
requiring appliances. However, there is no hot water supply required for the appliances in the toilet.
o. There is no water supply required for Buildings B07 A, B, C, B10, B11 A and B.
p. Building B09 is an extension from the existing building and hence potable water for this building
shall be extended from the existing water services from within.
q. Building B12 is a boiler building where in potable water shall be extended within the building and
provided with GRP water tank, water softeners, bib taps etc. Refer to HVAC sections for more detail
for this building.
r. Building B22 is a fire pump room building where in the incoming potable water from the
infrastructure shall be extended to supply to the fire water tank. In addition, the fire water room shall
also be provided with potable water for general purpose bib tap connection.
s. Building B23 is an irrigation water pump room building where in the incoming potable water from
the infrastructure shall be extended to supply to the irrigation water tank. In addition, the irrigation
water plant room shall also be provided with potable water for general purpose bib tap connection.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

3 The potable water distribution pipework to sanitary ware shall be provided with water hammer arrestors as
indicated I the drawings.
4 Pressurized potable water supplies shall run to each draw off point throughout the building. All branch
pipework supplies at each location shall be ensured for a consistent pressure at terminal plumbing fixture of
approximately 2 bar.
5 Hose bib taps and hand spray beside WC shall be provided with vacuum breakers to prevent potential
contamination from any back flow.
6 Pipework penetrating fire rated walls, partitions, floors or shaft enclosures shall be equally fire rated to suit
the requirements of the applicable Building Codes / Civil Defence.
7 The contractor shall provide additional pressure reducing valves sets in case these are required at site.
Backflow prevention devices shall also be installed as necessary to prevent cross-contamination and back-
siphonage of the water system.
8 Water efficient devices shall be installed in accordance with Authority guidelines and Green Building
Regulations to reduce total potable water consumption. This shall include;
a. Water conserving fixtures,
b. Dual flush toilets,
c. Cistern flush controls
d. Automatic proximity detection and water main isolation system
C All PVC/uPVC/CPVC material used in PH System must comply with ‘ECVM Industry Charter for the Production
of VCM and PVC’. The non-recycled content of PVC/uPVC must not contain lead, mercury, or cadmium stabilizers
and be produced using non-phthalate plasticizers. The contractor must use reasonable endeavours to procure PVC
with a recycled content of at least 30 percent.

D Carts

1 There are 6 nbr ‘carts’ located throughout the phase 3 water park, Aquaventure at the completion of technical
design, each of which will be provided with a potable water supply.
2 Refer to the Infrastructure package for further details.
E Bib Taps

1 There will be provided bib taps throughout the phase 3 water park, Aquaventure. WME have received a
proposed layout and number of bib taps from the landscape designer upon which the MEPF design is based.
2 Where these are shown on any of the buildings within the development which have a potable water supply,
they will be supplied from within the building.
3 Where these are shown on any of the buildings within the development which do not have a potable water
supply, they will be supplied from directly from the potable water infrastructure network.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

4 Where these are located with the landscape, they will be supplied directly from the potable water
infrastructure network.
5 Where bib taps are supplied from the potable water infrastructure network, they will be provided with a local
PRV.
F External Showers

1 There are external showers proposed at various locations across the phase 3 water park development,
Aquaventure based on the proposed layout received from the landscape designer.
2 The showers will be provided a cooled cold water supply from a suitable building in the vicinity of the
shower.

14.3| DOMESTIC HOT WATER SYSTEMS


A The Contractor shall supply, install, test, set to work and commission the Domestic Hot Water Supply systems as
described below and indicated on the tender drawings and equipment schedules.

B The Contractor shall supply, install and commission solar thermal hot water systems and all necessary ancillaries as
required in specific buildings (buildings B04, B05 and B06) for hot water generation within the development.

C Hot water system shall include but not limited to solar collectors, calorifier tanks, pumps, three-way valves, with
electric back up coils, circulation pump sets, relief valves, isolation and non-return valves, temperature and flow
sensors etc.

D One set of duty / standby forced circulation pump set shall circulate the hot water between the solar system and
calorifier that shall be controlled by a central control panel.

E The buildings shall be provided with solar hot water generation system backed up with electrical heating coil
integrally built within the calorifiers. The Hot water system shall be provided by an approved hot water system
specialist. The hot water system specialist shall be responsible for the detailed designing, procuring, installation and
commissioning of all components of hotel hot water system meeting the required sequence of operation of the
system.

F The entire operation of the system shall be sequenced by master control panel integrated with individual pump
control panels and BMS system. The master control panel shall be a central logic controller that shall integrate all
individual equipment related to hot water system to operate in unison to meet the intended demand.

G Hot water return shall be provided in the system to avoid dead legs and prevent legionella growth. A 2 hours
recovery rate shall be considered by the approved hot water system specialist.

H The Contractor shall ensure that all components of domestic hot water generation and all related other systems
including but not limited to, the calorifiers, solar collectors, hot water circulation pump sets, sensors, gauges, valves
and miscellaneous ancillaries etc - are so selected such that the systems to operate in unison and maintain a defined
sequence of operation upon demands. Contractor is responsible to offer the above as a complete all-inclusive one
working system offering all the main and ancillary components as part of the original contract.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

14.4| STORM WATER DRAINAGE


A The contractor shall supply, install, test, set to work and commission the storm drainage system as described below
and indicated on the detailed design drawings and equipment schedules.

B The Contractor shall select, supply, and install building rain water pipes that discharge freely in the building
perimeters.

C All rain water outlets and pipework routing shall be coordinated with architectural and structural services.

D The contractor shall ensure that all rain/storm water discharge is to be conveyed under gravity conditions to prevent
leakage and/or blockages occurring.

E The Building shall be with a complete above ground rain water drainage system which collects water from lower
and upper roofs via sufficiently sized, strategically located rain water outlets.

F The contractor to ensure that all rainwater outlets located on roofs shall be designed and located to suit roof falls
and gradients.

G The rain water pipes within the shafts shall be routed vertically and divert horizontally to reach the perimeter of the
building.

H Where rain water pipes are to pass through habitable spaces, these shall be acoustically treated to ensure that the
transmitted noise level does not exceed NR16 db.

I Where possible, all rainwater pipes shall be located in accessible positions to assist future maintenance.

14.5| IRRIGATION WATER SUPPLY


A The primary source of water for the irrigation water supply shall be potable water available from the infrastructure.

B The incoming potable water supply to the irrigation tanks shall be terminated with isolated valves and altitude float
valves.

C In addition, the irrigation water tank shall be provided with vents, overflows, warning pipes, access openings,
stainless steel ladders on either side of the tanks, equalization pipework, suction pipes, drain valves etc.

D Design of the irrigation pumpset shall be by the specialist irrigation designer and hence the sme is outside the scope
limit of MEP services.

E MEP Contractor shall coordinate with irrigation specialist for the required electrical load and type of connections
required from MEP.

F The Contractor shall cross-refer details described in the Specialist Irrigation package.

14.6| SOIL AND WASTE DRAINAGE


A The Contractor shall supply, install, test, set to work and commission the soil and waste Drainage systems as
described below and indicated on the tender drawings and equipment schedules.

B The sanitary drainage system for the building shall consist of three pipe system, one collecting foul, one collecting
waste from plumbing fixtures and the other, a vent pipe.

C Condensate from FAHU’s, AHU’s and FCUs shall be connected to the nearest drain available as indicated in the
drawings.

D All above ground drainage systems shall have separate foul, waste and vent pipes connecting to the drainage
systems below ground.

E In general, all buildings shall be provided with drainage services.


18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

F In addition, external showers shall be provided with floor drains and waste pipework connected with gully trap and
manhole provided by the infrastructure services.

G Buildings B05 and B06 shall be provided with fully automatic grease traps that shall be connected with gully traps
followed by manholes.

H Invert levels of the drainage pipework for buildings that are lower than the external manholes are provided with
waste water lifting stations / sump pits.

I Sump pumps shall be selected with N+1 redundancy with power from the building backup generators to protect the
network in the event of a power failure.

J The pumped connections shall be discharged to building manholes via pressure breaking manhole and gully trap.

K The sanitary drainage system shall be designed to have the following characteristics:

1 The drainage piping system inside the building shall be designed to carry away the discharge from the
sanitary fixtures and drain points quickly and quietly without risk of injury of health to the occupants of the
building. The drainage piping materials shall be as listed below:
a. Underground piping and fittings – uPVC
b. Above ground piping and fittings – uPVC
c. Commercial kitchens - HDPE
d. Condensate drain pipe and fittings – uPVC Class E
e. Pressurized line – uPVC Class E
f. Storm Water drainage - uPVC
2 Suitable accessibility via access covers, plugs and caps shall be provided to enable all traps, discharge pipes
and stacks to be tested, cleaned and cleared of any obstructions as and when necessary. Access point shall be
provided on all soil stacks above the spill-over level of the highest connection on the branch run, typically
1200mm above finished floor level.
3 All wet area shall be provided with floor drains with flush mounted removable gratings and frames recessed
and sealed into the floor. Floor drains subjected to infrequent flow are to be provided with a trap primer to
maintain water seal against odours and gases. Channel gratings shall be provided for areas such as garbage
rooms, MEP plant rooms etc.
4 Pipes penetrating fire rated walls, partitions, floors, floor/ceiling assemblies, or shaft enclosures shall be
protected with intumescent fire collars in accordance with the requirement of the applicable Building Codes.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

L The building drainage shall discharge into building’s first manhole and then finally connected with infrastructure
Sewerage connection.

M Waste water i.e. discharges from wash hand basins, sinks and floor drains shall be discharged to sewer with a gully
trap.

N Fully centralized automatic grease trap systems for kitchen waste drainage shall be provided.

O All horizontal drainage pipework that are installed within habitable spaces shall be acoustically treated as necessary
to ensure that the transmitted noise level does not exceed NR20 dB

P Provide Soil and waste drainage pipework from all sanitaryware.

Q Provide ventilating pipework that includes branch vents, cross vents, primary ventilating stacks, vents for manholes,
pressure break chambers, grease traps, drainage holding tanks etc

R The drainage pipework shall be installed to facilitate the testing, cleaning and future maintenance to be carried out
in a proper manner without causing nuisance. Roding access points shall be provided at each change of direction,
ground floor level and at the base of each stack prior to connection of the below ground drainage system. Sections
of horizontal pipe work on voids and false ceilings shall be kept to a minimum and installed to the shortest route
practical.

S Drainage below the building shall consist of pipework, manholes, gullies, cleanouts etc to suit the above ground
sanitary system and external drainage connections. Internal manholes shall be kept to a minimum and located to
minimize disruption during maintenance.

T The Contractor shall supply, install and fully coordinate all below ground drainage systems which includes – but are
limited to- sumps, interceptors and below ground drainage pipe work systems with the building structure,
foundations and all other ground services.

U On exiting the building any pumped drainage shall connect to the foul sewer infrastructure network via Pressure
Breaking Manhole in compliance with local authority regulations.

V The Contractor shall coordinate the building foul drainage manhole with infrastructure package as necessary. The
infrastructure foul main shall tie in with Authority’s foul water network as indicated in the drawings.

W The Contractor shall also coordinate for final approval by the Authorities.

X All drain water outlets such as floor drains etc shall be coordinated with ID, architectural and structural
requirements.

Y All soil and waste drainage pipework passing through habitable spaces such as lobbies, meeting spaces, etc shall be
acoustically lagged. All drainage pipework shall meet the noise criteria specified by the Acoustics specialist.

Z Routing of soil, waste and condensate drainage pipework through sensitive areas below or on top of an equipment is
not acceptable. In case of unavoidable circumstances, such installations shall be carried out only with the consent of
the Engineer and be with all precautionary measures. All such pipework shall be GRP layered after a thorough leak
testing certified by the QC, rigidly supported using non-slip clamps and additional channels, brackets etc, as a
minimum.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

AA The MEP contractor shall liaise with kitchen consultants, landscape specialist and other third parties as required &
detail the builder’s work requirement for water and drainage services on their shop drawings.

BB Planter drainage shall be fully detailed by the landscape specialist. MEP contractor shall coordinate with the
landscape specialist for the exact location and setting out of planter drains from planters etc.

CC Pipe identification shall be as per BS 1710:1984.

DD All PVC/uPVC/CPVC material used in PH System must comply with ‘ECVM Industry Charter for the Production
of VCM and PVC’. The non-recycled content of PVC/uPVC must not contain lead, mercury, or cadmium stabilizers
and be produced using non-phthalate plasticizers. The contractor must use reasonable endeavours to procure PVC
with a recycled content of at least 30 percent.

EE The Contractor shall supply and install all ancillaries required by the Commissioning Engineer to commission the
system. The installation shall be flushed and tested as required and on completion of all works. The Contractor shall
set to work the system after completion of all installation, testing and commissioning.

FF Workmanship

1 Install pipes, fittings and accessories in accordance with BS 8000-13, BS EN 12056-2 and manufacturer's
recommendations.
2 Obtain all components for each type of pipework from the same manufacturer, unless otherwise indicated.
3 Inspect components carefully before fixing and reject any which are defective.
4 Ensure cut ends of pipes to be clean and square with burrs removed.
5 Allow for thermal and building movement when jointing and fixing.
6 Form junctions using fittings intended for the purpose, ensuring that jointing material does not project into
bore of pipes, fittings and appliances.
7 Avoid contact between dissimilar metals and other materials which would result in electrolytic corrosion.
8 Provide access covers and cleaning eyes as necessary in convenient locations, to permit adequate testing and
cleaning of pipework.
9 Prevent entry of foreign matter into any part of system by sealing openings during construction. Fit all access
covers and cleaning eyes as work proceeds.
GG Traps

1 Pipework connections to WCs or similar soil appliance shall comprise a suitable rigid non-translucent
moulded white, e.g. push fit connector complete with synthetic sealing rings. Each connector shall be British
Board of Agreement Certified.
2 The use of helical or spiral flexible connectors will not be permitted.
3 All floor drains installed within the project shall be minimum with 75mm water seal in line with DM
requirements and shall be fully ventilated in order that the water seal shall be maintained at all times.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

4 Wash hand basins: 32mm diameter union outlet, 75mm seal, two piece white bottle trap with chrome plate
finish or as specified in Architect’s sanitary ware schedule.
5 Shower trays: minimum 50mm diameter, 75mm seal two piece ‘P’ traps, copper to BS 2871 or as indicated
on the Tender Drawings.
6 Sinks: 38mm diameter, 75mm seal two piece ‘P’ or ’S’ traps to suit installation, PVC.
7 Condense line connections: 50mm diameter, 75mm seal, two piece ‘P’ trap, uPVC to Class E.
HH Carts

1 Each of the 6 nbr ‘carts’ located throughout the phase 3 water park, Aquaventure, will be provided with a
connection to the below ground drainage system.
2 Refer to the Infrastructure design package for further information.
II External Shower

1 The external showers proposed at various locations across the phase 3 water park development, Aquaventure
based on the proposed layout received from the landscape designer, will be provided with a connection to the
below ground drainage system.
2 Refer to the Infrastructure design package for further information.

14.7| LEAK DETECTION SYSTEMS


A The Contractor shall supply, install, test and commission Leak detection on domestic water systems. The system
sha ll monitor the incoming mains water consumption against submeters around the building system. This shall
ascertain abnormal usages which indicate leaking pipework or appliances. The BMS (building management system)
shall monitor meters and raise alarms when required.

14.8| LIQUEFIED PETROLEUM GAS (LPG) SYSTEM


A. The Specialist Contractor approved by the Authority Having Jurisdiction shall design, supply, install, test,
commission and obtain all required approvals for the complete LPG Services as described herein as
performance specification and indicated on the design drawings.
B. The design and specification provided as part of the contract documentation is on a performance basis of the
purposes of coordination and costing. The system shall be designed and installed by a specialist contractor
appointed as part of the MEP contract and shall be approved by DCD and shall meet the following codes and
regulations:
1. Lootah Gas Design Guidelines
2. UAE Fire Life Safety Code of Practice
3. LPG infrastructure service provider (Lootah BCGas)
4. NFPA 58-2017
5. IGEUP/15
C. The system design conditions shall be as follows:-
1. There is one LPG tie that shall be extended from the infrastructure LPG network to serve for building
B12.
2. LPG gas shall be supplied to the boiler building with a minimum required supply pressure of
350mbar. There shall be first and second stage regulators installed in the incoming line.
3. LPG sub-metering shall be provided within the boiler room.
4. All signals from the gas panels /detectors shall be connected to the LPG control panel located within
the boiler room and shall be interfaced with fire alarm and BMS systems for monitoring.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

5. Contractor to install gas leak detectors, emergency solenoid switches etc within the building in line
with NFPA and DCD requirements
D. The following are the minimum control and monitoring requirements that shall be installed as part of the
installation. The specialist gas Contractor shall provide any other control and monitoring devices as required
by the local authorities’ requirements. All details shall be submitted to the Engineer for approvals.
1. Failsafe, electrical shut off valve at point of entry to building interfaced with building fire alarm
system and gas detection system.
2. Fail-safe electrical shut off valves at point of entry/gas meter to each boiler interfaced with local gas
detection, extinguishing and fire alarm systems.
E. A gas detection system shall be provided for the entire gas installation to monitor for any gas leak. The
system m shall be in accordance with the regulations and requirements of the local authority having
jurisdiction. Gas detectors shall be installed as identified on the drawings and described elsewhere in
specification. In the event of a leak being detected the system shall automatically shut the supply to the
distribution system. An alarm shall be raised on the gas detection and the building fire alarm systems. All gas
detectors should be sited at low level
F. Location of gas panel shall be to the approval of client and to the final approval of authorities
G. Pipe materials for LPG shall be,
1. All buried LPG piping shall be Poly Ethylene MDPE-80 SDR11, with nominal pressure rating
suitable for derated temperature and pressure conditions.
2. LPG pipe risers within the boiler room shall be Copper Table X to BS 2871.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

015 | FIRE PROTECTION SYSTEM

15.1| SCOPE OF WORKS


A The Contractor shall supply, install, test and commission the complete Fire Protection Services installation
described herein and indicated on the tender drawings and equipment schedules.

B The scope of work shall comprise, but is not limited to the following:

1 Sprinkler Systems
2 Breeching inlets for Stand-pipe and sprinkler systems
3 Class II Fire Hose Reel Cabinets
4 Portable Fire Extinguishers and Automatic Dry Powder Extinguishers
5 Gaseous Fire Suppression Systems
6 Clean Agent Extinguishing Systems
7 Testing and commissioning of all systems
8 Demonstration and handover to the Employer
9 Provision of handover documentation including Operating and Maintenance manuals, provision of
warranties, service agreements and Planned Preventative Maintenance schedules
10 Training of Employer‘s staff and
11 Local Authority Approvals

15.2| FIRE PROTECTION SYSTEM DETAILS


A The Contractor shall employ the services of an approved fire engineering specialist to design, supply, install, and
test and commission the complete firefighting installation.

B The mechanical firefighting systems for the development shall incorporate standpipes, sprinklers, clean agent, fixed
gas extinguishing systems and portable extinguishers, all in accordance with NFPA and Civil Defence requirements
/ regulations and the proposed fire strategy for the building.

C Breeching inlets shall be provided on the external perimeter of building B22 and B13 to serve the stand pipe and
sprinkler riser systems. Each breaching inlet shall comprise of a 4-way inlet breeching connection having a 150mm
dia. flanged outlet with 4no 65mm dia. instantaneous male coupling inlets etc. Contractor shall provide breeching
inlets as indicated in the drawings. In addition, Contractor shall liaise with Authorities for final number and
arrangement of the breeching inlets (if any) required for the project along with required pipework as part of the
original contract.

D All areas of the building shall be protected by the sprinkler system except for the areas listed below:

1 Electrical equipment areas and rooms, including telecom & network equipment rooms.
2 Areas protected by other special extinguishing systems using gaseous agents, water mist, water spray or
foam additives;
3 Bathrooms with no combustible fixtures and having a floor area of not more than 10m2;
4 Closets constructed entirely of non-combustible materials and having a floor area of not more than 2.2m2
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

E Fire Water Supply

1 Fire water for the project shall be supplied from site wide infrastructure potable water network. The
Contractor shall ensure the location of coordinates, flow and pressure requirements are fully coordinated
with infrastructure fire hydrant service provider.
2 After the tie in point, the incoming fire water pipework shall be provided with an isolation valve supervised
by the central fire alarm system and extended to supply the fire water tank sized for 227m3 of fire reserve.
3 Fire pumpsets Fire fighting systems shall be installed as a "dedicated system" in accordance with NFPA and
UAEFLS codes. The fire pumps (Electric Duty / Diesel Stand-by) selected for 1000GPM shall supply water
to the wet stand pipe, hose reels and sprinkler system for the building, in addition the site wide external fire
hydrants.
F The Specialist Contractor approved by DCD and shall include for the complete design, installation, testing and
commissioning of the fire protection equipment detailed on the drawings and in this specification. The Contractor
shall include for all labour, materials, complete with all supports and fixing back to approved building structure.
The contractor shall be responsible for producing a detailed hydraulic calculation to verify the actual pump head.
The systems associated with this package shall include but not be limited to the following systems.

1 The fire water line, then branched to sprinkler system and stand pipe system. The branch to Sprinkler system
shall be provided with one alarm check valve and extended to supply fire water to each zone control valves
served.
G Automatic Sprinkler System

1 The Contractor shall supply, install and commission automatic fire suppression systems for Buildings B01
and B22 as per NFPA Code and incorporate UAE Fire & Life Safety Code of Practice requirements as
required.
2 The systems shall be hydraulically designed and calculated to provide the required minimum discharge
density over the maximum area of operation for each of the Hazard Group Classifications.
3 The Contractor shall supply, install, & maintain the system in accordance to NFPA 13 standard & in
compliance to Local Civil Defence Authority. Each sprinkler zone (covering a maximum area of 4,831m2 as
per NFPA 13) shall be connected through Automatic Zone Control Valve (AZCV) assembly which normally
consists of supervised isolation gate valve, flow switch, check valve, &test & drain valve. The AZCV shall
be installed in an accessible area and shall be supplied from a dedicated sprinkler riser pipe (150mm Ø size)
to be in a designated pipe shaft / chase.
4 All supervised valves & switches shall have an interface to the fire alarm panel. The sprinkler system shall
be of heat actuated, normally closed sprinkler heads which controls the flow of water.
5 The sprinkler installation shall automatically operate on a fire condition to contain the spread of fire,
extinguish the outbreak via a matrix of sprinkler heads, and to provide an alarm signal to a central control
point within the building complex.
6 The entire sprinkler installation shall be a wet system and shall be served off a dedicated header distributed
through the development within the mechanical plant rooms.
7 The Contractor shall ensure that sprinkler system design, calculation, installation, testing and commissioning
shall be based on the appropriate NFPA13 standard (Standard for the Installation of Sprinkler Systems).
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

H Standpipe system with Class II Hose Stations

1 The Contractor shall supply, install and commission a standpipe system which provides a supply of water
through valves at each FHC stations as indicated in the drawings.
2 The standpipe installation shall be an NFPA Class II standpipe wet riser system. Fire hose cabinets shall
comprise of one no. of 40mm dia, 30m hose rack with one 5kg class ABC multipurpose extinguisher and one
5kg CO2 fire extinguisher.
3 The fire hose cabinets shall be located so that the combination of the hose position shall be able to reach all
areas of the floor served. Standpipes shall be at least 50mm diameter with branch pipes, a minimum of
40mm diameter, sized on the hydraulic criteria detailed in section 7.8 and 7.10 of NFPA 14.
I Gaseous Suppression Systems

1 The Contractor shall supply, install and commission a gaseous suppression where water systems are
undesirable due to potential of damage to equipment,
2 The system shall be of a Total Flooding system (Engineered) where the design & installation is accordance
with NFPA 2001 standard. A system comprises one or more containers connected to a system of piping and
nozzles. These gas containers shall be as close as possible to the rooms protected.
3 The clean agent gas shall be a clear, colourless, odourless, liquid that is super-pressurized with nitrogen and
stored in high-pressure cylinders. The clean agent shall leave no residue behind and shall not affect sensitive
equipment.
4 The Contractor shall supply, install and commission UL listed fire dampers and shutters for all rooms with
un-closable openings, louvers, etc. to ensure the integrity of the system in accordance with applicable NFPA
2001 standard & local authority requirements.
5 All system components such as storage cylinders, nozzles, fire alarm devices, etc. shall be from a listed &
approved manufacturer. All the cylinders & accessories shall be contained in a dedicated cylinder room
where installation, testing / commissioning & maintenance shall be conducted by the selected specialist
contractor approved by the Local Civil Defence Authority.
6 The Contractor shall ensure that the clean agent fire suppression system are being provided to, but are not
limited to the following areas
a. Electrical Rooms Above 10m2
b. Main Telecommunications rooms
c. ELV rooms.
J Areas where normal side wall sprinklers cannot meet the required coverage, side wall sprinklers with extended
coverage shall be provided.

K F&Bs shall be provided with fire blankets in addition to the fire extinguishers.

L The firefighting system shall deliver a minimum pressure of 4.5 bar(g) as required at each class II hose rack system;
Maximum pressure shall be limited to 10 bar(g).

M Gaseous fire protection systems shall be compliant to Trakhees EHS requirements.


18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

016 | ELECTRICAL SERVICES

16.1| SCOPE OF WORKS


A The Contractor shall supply, install, test and commission the complete Electrical Services installation described
herein and indicated on the tender drawings and equipment schedules.

B The scope of work shall comprise, but is not limited to the following:

1 MV Supply:
a. Coordinate and liaise with DEWA for the MV (11kV) supply into the development
b. All electrical services work within the DEWA MV rooms
2 LV Supply:
a. Coordinate and liaise with DEWA for the 400V supply feeders
3 LV Switchboards:
a. Main LV Switchboards (MDB)
b. Sub-main switchboards (SMDB)
c. Auto Mains Transfer Switches (ATS)
d. Motor Control Center (MCC)
e. Switchgear components
f. Final circuit distribution boards (DB)
4 LV Distribution System:
a. Mains power containment systems
b. Power cables
c. Power factor correction capacitors
d. Harmonic study and mitigation
e. Electronic surge protection
f. Cable tray, ladder rack, trunking and conduit installations
5 Earthing and Bonding:
a. Earthing and bonding systems
b. Functional earthing
6 Small Power distribution and provision of accessories:
a. Small power outlets
b. Cable wiring systems
c. Cast-in inserts
d. Fire barriers and fire transits
e. Supplies to AV system
f. Supply to Mechanical equipment and other miscellaneous systems
7 Standby Power system
8 Uninterruptible Power Supplies (Part of AV/IT package)
9 Emergency Lighting System
10 Lightning protection system
11 Cathodic Protection
12 Lighting and Controls:
a. Back of House Interior lighting
b. Front of House Interior lighting (Part of Specialist lighting package)
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

c. External feature lighting (Part of Specialist lighting package)


d. Automated lighting control systems (Part of Specialist lighting package)
13 Integrated Fire Detection and Voice Alarm System
14 Testing and commissioning of all systems
15 Demonstration and handover to the Employer
16 Provision of handover documentation including Operating and Maintenance manuals, provision of
warranties, service agreements and Planned Preventative Maintenance schedules
17 Training of Employer‘s staff
18 Local Authority Approvals.

16.2| MV SUPPLY
WME are advised that the required load for the phase 3 water park, Aquaventure will be made available for the
development within the existing allocated total connected load (TCL) for plot PJCRC19-27B. There are two proposals
in progress to provide this load, which WME is assisting ATP with as a separate work stream.

The provision of the load NOC for the required load remains the responsibility of ATP.

A new substation, LV room and Generator room is proposed as part of this expansion to be located on plot PJCRC19-
27B within the development boundary. This will be a split substation with the RMU room on the perimeter of the plot
and the transformer room, LV room and generator room within the development boundary.

An 11kV DEWA corridor and dedicated access route will be required from each RMU room to the transformer room
and is proposed along the plot boundary. The contractor shall be responsible for providing all necessary works to ensure
cable trenches are provided and backfilled with appropriate warning tape.

The new split substation will be sized for 4,500kW TCL capacity with 3nr 1500kVA DEWA transformers dedicated for
the electrical supply to phase 3 of the water park.

This new MV supply will be utilised for the electrical supply requirements of Aquaventure Waterpark phase 3
expansion, with the exception of buildings B04, B05, B09 and B10 which will be provided with an LV supply from the
existing electrical infrastructure at the existing Dolphin Experience Building, W25-14.

In addition, it is anticipated that the RMU building itself, building B24, will be provided with an LV supply from the
adjacent existing building, W25-10.

16.3| INCOMING LV SUPPLY


Aquaventure Waterpark phase 3 expansion will be provided with a new LV Supply by DEWA into a new LV room
within building B21 on the development.

The DEWA transformer room will be located within the same building, and immediately adjacent to the LV room. The
LV cabling will be routed in a trench from the transformer room into the LV room, for termination at the MDBs by the
contractor.

Contractor to coordinate and liaise with DEWA /external services Contractor for final location, arrangement of trench,
installation and termination etc.

The LV supply will be provided by DEWA, inclusive of all cabling up to the point of supply, being the MDB.
Termination of the LV cabling at the MDB will be by the main contractor.

The Contractor shall liaise with DEWA for the timely completion of the incoming LV cables, to suit the main Contract
program. Submit all necessary applications, obtain all necessary Authority Approvals and pay all fees associated with
application and approvals.

The Contractor shall assist to transport and install the LV cables etc. as deemed necessary.

The Contractor shall execute all necessary builders works, containment and earthing provisions required for the LV
installation. Accordingly, necessary cable shafts, cable trays/ladders, clamps, earth pits, earthing rods, earthing cables
etc. as required by DEWA shall be provided by the Contractor
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

The LV cables from the substation to the MDB shall be installed by the Contractor along with cable trench construction
and terminations, these cables shall be supplied by DEWA.

The incoming LV supply for buildings B04, B05 and B10 will be from the existing electrical infrastructure at the
existing Dolphin Experience Building, W25-14.

It is proposed to use the spare load for the electrical requirements of the buildings within ‘Dolphin Village’ and the
power requirements of the prayer rooms.

Based on our survey findings it appears that the non-essential load requirements can be met by utilizing the spare loads
in the SMDB panel ‘W2514NSB01’ (W2514-Dolphin Experience Electrical room).

The essential loads can be fed from the ESMDB panel ‘W2514ESB01’ (W2514-Dolphin Experience Electrical room).

Utilising these SMDBs requires modifications to be made in the associated boards and spare load utilization shall be
subjected to revised DEWA approval.

An LV supply for the RMU room, building B24, will be sourced from the adjacent building W25-10, within which a
panel board will be identified.

The contractor shall be required to submit a full method statement for approval, prior to undertaking any works to make
these new connections and associated reconfiguration of the LV Distribution in this area.

Following completion of all works on the exiting electrical infrastructure at W25-14, the contractor shall provide full
and updated record drawings of the LV distribution schematics and associated panel and board schedules in DEWA
format.

16.4| LOW VOLTAGE (LV) SWITCHGEAR


The Contractor shall supply, install, test, set to work and commission the LV Distribution system for the phase 3
expansion of the water park at Atlantis the Palm. The works are generally as described below and indicated on the
tender drawings and equipment schedules. LV Distribution system shall comprise of the following systems and
equipment:
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

A Main Low Voltage (LV) Distribution Boards (MDBs)

1 The main LV distribution boards shall be installed in the main Low Voltage electrical room located as part of
the new building, B21, at ground floor in accordance with DEWA regulations and requirements.
2 The LV room shall be provided with adequate cooling provisions by an HVAC system. No wet services are
allowed to run within or above this room.
3 The LV room layout, panel arrangement, trenches, panel clearance, earthing provisions etc. shall strictly
conform to DEWA requirements and approved drawings.
4 The main switch boards shall be free standing type factory-built assemblies assembled by the authorized
channel partners of the original switchgear manufacturer. The panels shall be type tested ‘design verified
assemblies’ strictly conforming to BS EN 61439. The type testing certificates shall be obtained from ASTA
or KEMA by the manufacturer and should be in Franchisee/Authorised Panel Builders name.
5 MDBs shall be constructed based on the requirements of IEC – 439 – 1. The panel construction shall be
designed to withstand a short circuit level of 50KA for 1 second, which is considered as a safe short circuit
protection level. Panel construction shall be form – 4b, type - 2 and ingress protection IP 42.
6 The panel shall fully comply with the DEWA requirements. The panels shall be cubicle type, modular and
readily expandable for future requirements.
7 The main electrical switchboards shall have front and rear access. The incoming cables shall be bottom entry
and outgoings shall be bottom or top as required.
8 Where switchboards stand over the trenches, include for all steelwork required to support the weight of the
panels and boards.
9 LV mains cables shall be procured by DEWA and installed by the Contractor between the substation and the
MDBs. The terminations at both ends shall be made by the contractor under the supervision of DEWA and is
subject to DEWA approval.
10 The contractor shall coordinate with structural engineer to ensure suitable plinths are provided to install the
main LV switchboards.
11 The Contractor shall provide kWh tariff meters for MDB in accordance with the DEWA requirements. The
Contractor shall liaise with DEWA for the calibration of CTs for the tariff meters.
12 An emergency power off (EPO) button shall be provided for each MDB to enable emergency tripping of all
incoming LV to the room. The EPO shall be located at the Security control room or at any readily accessible
place as per local authority requirement.
13 The Contractor along with the proposed switchgear manufacturer, shall verify all the electrical calculations
including short circuit study, discrimination analysis, cable and busbar calculations etc., and submit for
engineer’s review and approval.
14 The MDB shall be provided with the space for a spare breaker as indicated on the LV schematics to connect
the Active Harmonic Filter (AHF) equipment in future, if deemed necessary after the harmonic
measurements and analysis are carried out. However, the Contractor shall supply and install the necessary
CTs in the MDB to facilitate installation of the breaker at later stage without taking a shutdown on the MDB.
15 During the shop drawing and procurement phase the contractor is required to:
a. Check physical dimensions of main switchboards, capacitor panels, ATS, MCC panels, SMDBs etc.
prior to manufacture and carry out space and volume check.
b. Ensure the enclosures are adequately sized to fit inside the LV room in accordance to DEWA
approved LV room layout.
c. Provide check metering on all out goings of the main switchboards. Meters shall be electronic multi-
function type and shall report details onto the BMS.
16 For further details on the LV switchgear refer to detailed specification section and the LV schematics.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

B Sub-Main Switchboards (SMDBs)

1 The Contractor shall supply, install, test, set to work and commission the Sub-Main Switchboard systems as
described below and indicated on the tender drawings and equipment schedules.
2 The Contractor shall be aware that some SMDBs shall be located within electrical cupboards which will not
be provided with environmental conditioning for temperature or humidity. Natural ventilation will be
provided to these cupboards, with high and low level louvres in the access doors.
3 Where the SMDBs are located in electrical cupboards accessible externally, the full assembly including
accessories will be rated for this environment.
4 The submain switch boards shall be factory built assemblies assembled by the authorized channel partners of
the original switchgear manufacturer. The panels shall be type tested ‘design verified assemblies’ strictly
conforming to BS EN 61439. The type testing certificates shall be obtained from ASTA or KEMA by the
manufacturer & should be in Franchisee/Authorised Panel Builders name.
5 The submain switch boards shall fully comply with DEWA regulations. SMDB shall be constructed to IEC -
439-1 form - 2, and to a minimum protection of IP42. Short circuit rating shall be 35 KA minimum.
6 Where submain switch boards are located within plant areas with wet services for the supply of equipment
within this room, these shall be suitable uprated in ingress protection to IP54 as a minimum.
7 Sub-main switchboards shall be provided to serve defined areas and zones of the project as indicated on the
drawings.
8 Sub-main switchboards shall generally be floor or wall-mounted, front access type and cable entry from top
or bottom to suit the application.
9 Where sub-main switchboards are floor mounted, provide concrete plinth to mount the equipment upon.
10 When SMDBs and DBs are installed in the closets, the closets shall be suitably ventilated and fire rated to
the local Authority requirements.
11 During the shop drawing and procurement phase the contractor is required to:
a. Check physical dimensions of sub-main switchboard prior to manufacture, carry out space and
volume check to ensure the enclosures are adequately sized.
b. Provide check metering on all out goings of the sub-main switchboards. Meters shall be electronic
multi-function type and shall report details onto the BMS.
c. Life Safety switchboard enclosures shall be colour ‘RED’. Form of switchboard construction shall be
as indicated on design drawings.
d. Life Safety distribution boards shall have no automatic means of isolation and have a lockable cover
and be colour ‘RED’.
C Auto Mains Transfer Switch (ATS)

1 Design and manufacture Main Distribution Boards to allow automatic changeover from mains to standby
generator supply in accordance with local authority requirements. This shall be achieved through factory
built auto mains transfer switches (ATS).
2 At each changeover arrangement; provide a mains monitoring relay to allow automatic changeover in the
event of mains failure. Provide a phase failure signal to the Generator Control Panel to automatically start-up
the generator in the event of a mains failure at any of the main switchboard.
3 The ATS shall be factory built assemblies from the specialist manufacturer and confirming to UL 1008.
D Motor Control Center (MCC)

1 MCCs shall also be constructed to IEC – 439-1, form – 2, type – 2 requirements. Minimum protection shall
be IP42 and with a short circuit rating of 35KA. Local control panels for equipment shall be constructed to
from 2 requirements.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

2 Where MCCs are located within plant areas with wet services for the supply of equipment within this room,
these shall be suitable uprated in ingress protection to IP54 as a minimum.
3 There will be electrical supplies from the MDB to Mechanical Control Centres (MCCs) from which the
mechanical plant items will be supplied and linked to the BMS system as required.
4 The electrical contractor will provide the supply to the MCC, being the cabling, containment and termination
at the point of isolation. From this point, the mechanical contractor will complete the works up to the
mechanical plant, inclusive of cabling, controls and containment.
5 Control panel and soft starters (if required by mechanical design) shall be provided by mechanical contractor
when the mechanical equipment is supplied from SMDB or DB.
E Switchgear Components

1 The Contractor shall be aware that some electrical panels shall be located within electrical cupboards which
will not be provided with environmental conditioning for temperature or humidity. Natural ventilation will
be provided to these cupboards, with high and low level louvres in the access doors. All components will be
selected to suit the environmental conditions in which they will be located.
2 All Main Switchboards, Sub-Main Switchboards and Motor Control Centres shall be manufactured from the
same vendor, and complete with common components throughout. A mixture of breakers, contactors,
devices and components from more than one manufacturer shall not be acceptable.
3 All the enclosures shall be from the original switchgear manufacturer and type tested to BSEN 61439.
4 Provide all enclosures to manufacturer’s standard paint finish, unless not specified in the specifications.
5 All components shall be suitably rated and de-rated to operate in the adverse environmental conditions as
defined in the project Specification and the Local Authority Regulations. The contractor shall take note that
not all panels are located in electrical rooms which are provided with environmental conditioning, and where
panels are located in electrical cupboards accessible externally, the full assembly including accessories will
be rated for this environment.
6 Provide detailed co-ordination and discrimination study of all breakers used. This shall be carried out from
the point of incoming supply, down to the last socket and lighting point on the installation, including external
services. This shall be carried out for both normal supply conditions and under generator supply conditions.
7 Ensure all components comply with British Standards / European Norms/DEWA Standards requirements.
8 Provide the minimum spare capacity within all MDBs, SMDBs, MCCs, and DBs as follows;
a. MDB Panels 10%
b. SMDBs and MCCs 10%
c. Final DBs 10%
F Final Circuit Distribution Boards (DBs)

1 Provide final circuit distribution boards to all areas. Suitable locations for the distribution boards have been
provided in the design package, generally to limit the final circuit run to 70m. Provide distribution boards
from the same manufacturer as the main switchboards.
2 Provide distribution boards in compliance with the local power supply authority regulations.
3 Distribution boards shall be complete with miniature circuit breakers, earth leakage circuit breakers, under
voltage trip relays, main isolator and metal enclosure.
4 Provide all distribution boards with typewritten schedule with detailed information of all circuit loads.
5 Distribution boards shall be installed conceal from view in all public areas in line with authority regulations
and requirements. The distribution boards shall be accessible, but only by authorised personnel. Exposed
surface mounted boards shall only be provided within plant areas, switch rooms, and the like.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

6 When Distribution boards are installed in the closets, the closets shall be suitably ventilated and fire rated
and to the local Authority requirements. The contractor shall take note that not all distribution boards are
located in electrical rooms which are provided with environmental conditioning, and where boards are
located in electrical cupboards accessible externally, the full assembly including accessories will be rated for
this environment.

16.5| POWER FACTOR CORRECTION CAPACITORS


A Contractor shall design, supply, install, test and commission a power factor correction unit at each MDB as detailed
in the particular specifications as well as latest DEWA Regulations for Electrical Installations 2017 edition.

B The capacitor panels shall be factory built assemblies assembled by the authorized channel partners of the original
switchgear manufacturer. The panels shall be type tested ‘design verified assemblies’ strictly conforming to BS EN
61439. The type testing certificates shall be obtained from ASTA or KEMA by the manufacturer & should be in
Franchisee/Authorised Panel Builders name.

C Each main switchboard shall be provided with a free-standing Power Factor Correction cubicle to maintain the
overall Power Factor of the electrical installation between 0.90 (lagging) and unity (recommended value 0.95 lag) in
accordance with DEWA regulations.

D The PFC cubicle shall contain Automatic Regulating equipment to control the capacitor steps in accordance with
their requirement to compensate for the uncorrected power factor value within the distribution system.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

E Each PFC equipment cubicle shall utilise de-tuned capacitors. The capacitors shall be dry, encapsulated, and sealed
type conforming to IEC 61921. The capacitor units shall be rated temperature class D. The voltage rating of the
capacitors shall be 520V.

F Generally, all central air-conditioning plant shall incorporate integral means for power factor correction to achieve
and maintain a power factor between 0.90 (lagging) and unity throughout their normal working range.

G The capacitors shall be suitable for operation under harmonic current conditions. Contractor shall carryout
necessary network studies to ensure the correct rating of capacitors and their operation without causing resonance.
Suitable harmonic filters or reactors shall be installed to mitigate harmonics.

16.6| HARMONIC STUDY AND MITIGATION


A Harmonics of the power supply are caused mainly by non-linear loads connected to the supply system. These loads
shall not cause deviations of the voltage characteristics other than those allowed in European Standard EN 50160,
November 1994.

B Harmonic measurements shall be carried out by the Contractor after commissioning and when the building is
running on full load. If the harmonics (voltage & current) are exceeding the Authority limits necessary proposals to
install the filters to compensate the effects of the nonlinear loads. This shall be a provisional sum item and will
operated if required.

C The study can take place within 12 months of final acceptance by the Employer when the building is occupied and
fully operational with a written report and recommendations delivered to the engineer for review.

D The Contractor shall take full account of harmonics and voltage changes of the electrical systems and shall employ
a specialist vendor to carry out a full study. The specialist shall carryout the analysis and then design, supply,
install, test and commission all necessary equipment to mitigate the effects of harmonics. Subject to the approval of
the Engineer,

E The Contractor shall allow for necessary provision in each of the MDB to connect the Active Harmonic Filter
(AHF) if deemed necessary after carrying out the study. Space for a breaker shall be considered to connect the AHF
equipment. Necessary CTs shall be installed to avoid power interruption to the facility while installing the breaker
after the panel is commissioned. Space requirement for installing the AHC shall be considered in the LV room.

16.7| ELECTRONIC SURGE PROTECTION DEVICES (SPDS)


A Contractor shall develop, supply, install, test and commission a safe and efficient surge protection system to provide
protection against induced voltages in power distribution and low current networks arising from lightning strikes
and other electromagnetic discharges. Cables entering/leaving all the buildings and all externally mounted
equipment shall be suitably protected.

B The Contractor shall employ a system specialist to carry out the above performance objectives. The manufacturer
should be same as the specialist lightning protection and earthing system provider to cover the performance
indemnity.

C The surge protection throughout the electrical installation shall be in accordance with the recommendations of BS
EN 62305.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

D Surge protection shall comprise 3 main stages. Course protection shall be provided at all main switchboards.
Medium protection shall be provided at sub-main switchboards serving electronic equipment. Fine protection shall
be provided at distribution boards serving electronic equipment.

E All externally located electrical panels shall be provided suitably sized surge protection enclosed within IP rated
enclosures.

F Provide the surge protection equipment within switchgear enclosures. Locate behind removable covers complete
with vision window to read LED status indicators. The SPDs units shall be suitable for interfacing with the BMS to
indicate failure of the device.

16.8| LV DISTRIBUTION SYSTEM


The LV distribution will emanate from the main LV Room at building B21. From here, mains power cables will be
routed externally across the development to supply each of the new buildings.

The LV distribution in ground will be as per the infrastructure design and is a combination of LV power cables buried
direct and locations where UPVC cable ducts are utilized.

For the buildings within the Dolphin Village area, B04, B05 and B10, the LV distribution will be from the existing
electrical infrastructure at the existing Dolphin Experience Building, W25-14.

For the new RMU room, B24, the LV distribution will be fed from the existing electrical infrastructure within W25-10.

All mains incoming power cabling to each new building will be from the in-ground LV infrastructure rising via UPVC
ducts into electrical cupboards at each new buildings, where the LV supply will terminate in a panel for the supply of all
electrical services within that building.

Within buildings B01, B02 and B08 there are specialist equipment control panels for pool water filtration systems and
waterslide controls. The contractors shall allow for all the cabling, containment and terminations from the LV
distribution to an isolator local to each of these panels, and from the isolator to the specialist control panels, including all
required termination and glanding.

A Mains Power Containment Systems – External In-Ground

1 The mains power cables shall be in-ground as buried direct or within dedicated UPVC cable ducts as
required. Refer to the infrastructure package for details.
B Mains Power Containment Systems

1 The mains power cables within the buildings shall be distributed on cable ladder/trays from the main LV
rooms/electrical room. Cables shall be run in accessible places within services corridors, ceiling voids and
within riser space.
2 Riser systems within each building shall allow cables to rise to, generally stacked, electrical closets on each
level. These closets shall incorporate essential and non-essential boards, and lighting control panels etc.
C Power Cables

1 The Contractor shall design, supply, install, test and commission all main, sub-main and final distribution
cabling serving all main switchboards, sub-main switchboards, mechanical control panels, final distribution
boards, fixed items of plan, items of equipment, lighting points and outlet accessories.
2 All main and sub-main cables within the building shall be armoured, XLPE, halogen free, low smoke fume
(XLPE/SWA/LSF), rated as shown on the drawings and cable schedules.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

3 All main and sub-main cables shall be provided with separate earth protective conductors as shown on the
drawings and cable schedules, and in accordance with local authority requirements.
4 All final circuit cables shall be multi-stranded copper type, complete with LSF insulation.
5 All power cables installed throughout the project and within buildings shall be LSF (Low Smoke and Fume)
or LS0H (Low Smoke Zero Halogen) outer sheath type. This is necessary to minimise build-up of poisonous
fumes in the event of fire.
6 PVC cables shall not be used within buildings for the project without the written permission from the
Engineer.
7 Where cables feed to life safety equipment e.g. fire exhaust fans, fire pump sets etc. then these shall be
suitably fire retardant type cables with a fire retardant outer sheath that is also LSF / LS0H.
D Cable Wiring Systems

1 All power cables installed throughout the project shall be LSF (Low Smoke and Fume) or LSOH (Low
Smoke Zero Halogen) outer sheath type. This is necessary to minimise build-up of poisonous fumes in the
event of fire. PVC cables shall not be used for the project without the written permission from the Engineer.
2 All cables shall have LSF outer sheaths including data, telephone, fire alarms, emergency lighting, BMS
system, security, CCTV, intercom system, etc.
3 Sub-main cables shall be XLPE/SWA/LSF type whilst final circuits shall generally be LSF sheathed single
core trunking and conduit type cables.
4 Where cables feed to life safety equipment e.g. pressurization fans, fire exhaust fans etc. then these shall be
fire retardant type cables with a Fire Retardant outer sheath that is also LSF/LS0H.
5 The sizes of cables, wires, containment etc. shown on the drawings represent the design intent. The
contractors shall develop and submit shop drawings providing calculations for cables, wires and containment
sizes confirming it is sufficient in accordance with local authority regulations. Containment loads shall not
exceed the safe recommendation maximum load values and must include for any such external forces in
addition to the cable loads.
E Cast-In Inserts

1 Provide cast-in inserts within the electrical and communications risers for fixing and support of main vertical
and horizontal cable trays, ladder racks and trunking systems as well for supporting main wall mounted
equipment.
2 Inserts shall be spaced at regular intervals and installed complete with foam infill for easy removal and to
prevent the ingress of concrete during construction.
F Fire Barriers and Fire Transits

1 Provide fire barriers for all service penetrations to maintain the fire-rating of walls, floors, partitions, ceilings
etc. Close builders work openings to a 75mm perimeter around electrical service openings. The remaining
opening shall be fire-sealed using intumescent foam-type materials. Ensure that materials are installed
suitably for installation of same and co-ordinate accordingly.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

2 Floors shall be fire-sealed to provide two-hour fire ratings. Include for maintaining the fire resistance within
containment systems as described in the containment specifications e.g. within cable trunking systems.
G Cable Tray, Ladder Rack, Trunking and Conduit Installations

1 A cable containment system shall be provided for all electrical services, ELV services, AV/IT,
Telecommunication, GSM system, security system, Fire alarm system, BMS system etc.
2 The Contractor shall include for the design and provision of all cable containment systems required for the
project. The system shall allow for an additional 20% spare capacity.
3 All containment sizes indicated on the drawings are indicative and the contractors shall develop shop
drawings and submit calculations for containment sizes confirming it is sufficient in accordance with local
authority regulations.
4 Containment loads shall not exceed the safe recommendation maximum load values and must include for
any such external forces in addition to the cable loads.
5 All the primary containment distribution routes shall be earthed according to the manufacturer’s
requirements and in accordance with BS 7671 recommendations.
6 The containment system shall meet the seismic restraint requirements defined elsewhere in the project
specifications as well as the local Authority requirements as a minimum.
7 Generally all main and sub-main armoured and insulated cables shall be installed on cable trays. Provide
trays within the substation, cable trenches, main and sub-main LV rooms and for primary routes in ceiling
voids and risers.
8 Cables required to be installed on exposed support system shall be installed on trays complete with
protective cover on top.
9 All LV main and sub-main cables shall be supported throughout their entire length on ladder rack or cable
tray. Cables shall not be cleated or clipped direct to any surface.
10 Provide cable trays for all fire and alarm cables, emergency lighting cables, mains communications cables,
security systems cables, etc.
11 Provide vertical cable tray support systems within all risers to support cables as required.
12 Provide trunking systems to contain all single core cables, security/CCTV cables, incoming communications
cabling and intercom cabling. Proper segregation shall be achieved in accordance with DEWA requirements.
Dedicated containment shall be provided for the security system cables in accordance to DPS/SIERA
requirements.
13 Galvanised steel trunking shall be provided where there are a number of multiple circuit cables to be run.
Generally where four or more circuits are to be run in a common route, then a galvanized steel trunking
system shall be provided in place of conduit.
14 Ensure all cable trays and ladder racks are galvanised type. Cable tray shall be of the duty and type as
defined in the detailed specification section.
15 Define main containment systems and their routes on a set of detailed and coordinated shop drawings. These
shall be reviewed along with all necessary cable routes and add additional containment systems as necessary
to allow all cabling to be contained.
16 All secondary containment, being all containment not shown on drawing such as conduit system, are
considered a ‘Contractor’s Design Portion’ or CDP. The contractor shall be responsible for the design,
supply and installation of all secondary containment systems and conduits.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

17 Provide surface mounted or concealed GI conduits to contain cables from the main tray or trunking route to
the final accessory, outlet or fixed termination point.
18 PVC conduits shall only be permitted where these can be embedded in concrete walls or cast into the
concrete structure of the building.
19 Galvanised steel conduit shall be used where it is not possible to bury the conduits into the building.
20 All cable containment routed externally shall be installed complete with GI Cover Lids providing cables with
mechanical protection and external elements.
21 The contractor shall include for all external services containment as required. The contractor shall also
include for access manholes at each change of direction for buried below ground UPVC/RCC containment
and every 20m horizontal run distances.
H Carts

There are 6 nbr ‘carts’ located throughout the phase 3 water park, Aquaventure at the completion of technical design.

The allocation for each cart is 10kW and included with in the overall load calculation for the development. This will be
provided from the local infrastructure, sourced from panel boards located within local buildings.

The power will be presented as an IP67 BS4343 32A 400V socket outlet in an agreed location with the architect and / or
landscape designer. Refer to the infrastructure package for further details of the proposed connection.

16.9| EARTHING AND BONDING SYSTEMS


A Earthing and Bonding Systems

1 Provide earth pits, complete with earth electrode rods installed at grade level for earthing of the main LV
switchboards. The contractor shall coordinate with the earthing package for the specification of the earthing
pit requirements and drawings.
2 The earth pits shall be completely water tight and double seal type suitable for installation in the ground
floor. The earth rod seal shall provide an effective, reliable and water tight seal to both the earth rod
electrode and damp proof membrane. The earth pit and the earth rod seal shall meet the requirements of IEC
62561-5, and be capable of withstanding water pressure up to 5.5 Bar
3 The Contractor shall ensure that the earth pit locations are fully co-ordinated with the structural elements of
the building.
4 Provide duct pathways for connecting earth pits to LV rooms as required.
5 Provide earth electrode and earth mat configurations in accordance with local authority requirements and in
accordance with BS 7430.
6 Provide earth bars on isolated stand-offs within LV rooms for bonding of main and ancillary electrical
services components. Provide copper cable connection to earth pits and between adjacent earth bars.
7 Bond all exposed metallic parts of the building fabric and services installations to the various electrical earth
bars to maintain zero potential between metalwork components within the building i.e. the full earthing and
bonding installation shall be in accordance with local authority and the IET Wiring Regulations, with the
exception of the earth pits.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

8 Include for the full installation, commissioning and setting to work of the Earthing and Bonding Installations
in accordance with BS 7430 and BS 7671 and as indicated in the particular specification section for earthing.
9 Provide bonding to all ancillary equipment such as ceiling grids, metal wall partitions, fixed metal shelving,
building cladding, structural steelwork, movable wings, building hydraulics system and other metal elements
on the roof etc...
B Functional Earthing

1 Provide clean earth system for communications and IT systems. UPS-fed power supplies shall also be fed
from a separate clean earth.
2 Provide a separate earth pit connection for AV systems within this contract. Include for an earth bar within
the appropriate ELV Room connected to the electrode. All technical earths associated with the AV Systems
shall be connected at this point.
3 Provide a separate earthing system in each building for the Telecommunication rooms and for the server
room earthing.
4 Provide under floor exposed earthing tape installed on insulated stand-offs within the main IT /
communications server room. This shall be used for earthing the equipment server racks.

16.10| SMALL POWER DISTRIBUTION AND PROVISION OF ACCESSORIES


A Small Power outlets

1 The Contractor shall include for the design and installation of small power outlets and accessories. This shall
include, but not be limited to, general purpose outlets, socket outlets within common areas, outlets for
cleaners use, IP67 rated outlets for external use and IP 54 for use in plant rooms, fixed fused outlets for fan
coil units and the like.
2 Unless stated otherwise, all outlets and accessories shall be of the switched type.
3 All sockets, whether for general use or specific use, in front of house areas shall be located as per ID design.
4 All final sub-circuit wiring shall be concealed in trunking and conduit installation throughout. Allow for the
design and installation of all pathways as required.
5 All wiring for the small power installation shall be sized in accordance with the Local Authority Regulations;
using a minimum of 4.0mm2 LSF insulated copper conductors protected by 20A circuit breakers for radial
circuits and 32A circuit breakers for ring circuits.
6 All fixed equipment shall be wired through a suitably rated isolator mounted near the equipment. Isolators
feeding all the Life safety equipment shall be suitably fire rated.
7 Isolators installed in the wet areas shall be IP 65 rated. Isolators installed outdoors shall be IP 67 rated and
UV resistant.
8 All mechanical equipment, rotating machines, kitchen equipment etc. shall be provided with an emergency
push button (EPO) for emergency shutoff, anticipated to be integral to the machinery. Where this is not the
case, as separate EPO will be provided by the electrical contractor.
9 The final finishes of all the wiring accessories, isolators, floor boxes, exposed
DBs/SMDBs/panels/containments/equipment etc. shall be to Architect/ID’s requirement and final selection
is subject to Architect/ID approval.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

B Supplies Dampers

1 Provide essential power supplies to all ventilation dampers required for the project.
2 Coordinate the exact load requirements and ratings of circuit protective devices with the Mechanical
Installer.
C Supply to ICT and Security Equipment

1 The power and bulk load requirement for the following is considered in the LV schematic.
a. ICT Design
b. Security Design
2 ICT Design - The overall electrical load requirements are considered in the electrical design and the ICT
Rooms are provided with a dedicated electrical supply for the ICT Rack requirements as per the ICT
Consultant’s requirements.
3 Necessary SMDBs/DBs. power outlets, wiring, containment etc shall be considered by the Contractor. The
Contractor is fully responsible to ensure the power distribution is achieved to meet the design requirements
detailed in the ICT design package.
4 Within each buildings, small power supplies are provided to WAPs as required within the ICT design
package, and external WAP power requirements are also served from within buildings.
5 Security Design - The overall electrical load requirements are considered in the electrical design and the ICT
Rooms are provided with a dedicated electrical supply for the Security Rack requirements as per the Security
Consultant’s requirements.
D Supply to Mechanical and other Miscellaneous systems

1 The Contractor shall ensure adequate power supply in accordance to the local Authority requirements are
provided to every equipment and system defined in the project design documentation whether or not
explicitly indicated on the electrical design drawings.
2 The Contractor shall liaise with the other services Installer/equipment supplier and ensure that Panels/MCCs
feeding them include all necessary circuit protection devices, controls and starters/drives necessary for the
system operation. The details furnished on the drawings are indicative only and the Contractor shall develop
the designs of these panels as per the final equipment/system selection.
3 In general, the Contractor shall include the necessary power supplies and containment for, but not limited to,
the following systems:
a. All mechanical equipment and systems defined in the mechanical design package
b. All equipment and systems defined in the AV/IT and Security design packages
c. All equipment and systems defined in the Pool Specialist’s system design package
d. All equipment and systems defined in the slide designer’s system design package
e. All equipment and systems defined in the FLS system design package
f. All equipment and systems defined in the irrigation, Landscaping and Façade system design
packages
g. Power supply requirements for the DU/ETISALAT services and GSM network.
h. Power supply for the DDC panels, Lighting control panels, fire alarm panels, , rolling shutters,
display and sign boards, building maintenance units, etc.
i. Any other systems and equipment defined in the project design documentation.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

E External General Power

There will be provided general power outlets throughout the phase 3 water park, Aquaventure. which shall be single
socket outlets. The final locations shall be as defined by the landscape designer.

The power will be provided as IP56 BS1363 13A 230V socket outlets. Where these are located on any of the buildings
within the development, they will be supplied from a distribution board within the building.

In addition, all outlets located within the landscaped areas will be sourced from a local distribution board within an
electrical cupboard within the one of the standalone buildings.

16.11| STAND BY POWER SYSTEM


A Standby Diesel Generator Set

1 There will be a standby rated diesel generator provided on the Aquaventure phase 3 water park extension,
within building B21. This shall be provided for the backup of all life safety and essential power supply
requirements.
2 Contractor is responsible to install a complete generator set along with flues, ventilation, acoustic treatment,
fuel tank, fuel fill system and all cabling, controls and accessories as indicated on drawings and conforming
to tender specifications.
3 The Standby Generator, in line with DEWA requirements shall provide back-up power for all life safety,
20% public areas lighting and security related systems through an Automatic Transfer Switch (ATS)
connected between emergency and normal power. The proposed back-up system takes into consideration the
very high reliability of power supplied by DEWA. The back-up system shall feed all loads identified by Civil
Defence as essential in fire conditions.
4 From the generator, cabling systems will run to a panel integrated ATS located in the MDBs within the
adjacent LV room, from which supplies will be distributed to essential SMDBs and DBs within each of the
buildings across the waterpark phase 3 expansion development.
5 The ATS units should sense the power loss in any of the MDBs and should start the generator. Factory built
ATS switches shall be provided for switching over to essential supply in the event of normal supply failure.
Motorised breakers with interlocking facility shall not be used in lieu of the ATS.
6 Essential LV distribution will be separate from the non-essential LV distribution, and will be undertaken in
fire rated cabling systems if used for fire and life safety purpose.
7 Essential loads are not considered with fire rated cable requirement.
8 The Contractor shall design, supply, install, test, set to work and commission the essential Power systems as
described on the tender drawings, specifications and equipment schedules.
9 Provide all associated distribution network to serve the essential / life safety systems and the loads outlined
in the DEWA regulations/circulars, detailed specifications, schematics and load schedules.
10 The provided generator shall be designed, installed and commissioned strictly in compliance to the latest
UAE Fire Code, DEWA Regulations 2017 edition and other DEWA circulars issued in relation to essential
power supply requirements.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

11 The generator system shall be manufactured and assembled in the equipment manufacturer’s factory. Locally
assembled generators are not acceptable.
12 The generator shall be sized to support all life safety equipment including, but not limited to:
a. Fire alarms and voice evacuation system,
b. Emergency lighting,
c. Exhaust fans,
d. 20% lighting in the Public areas
e. Security systems,
f. BMS systems,
g. Stair way lighting, control rooms, plant rooms, electrical rooms etc.
h. IT room CCU units
i. Any other systems as per the local Authority requirements
13 In addition, the generator shall also support any loads identified on the schematic diagrams and generator
load schedules that are essential to the building operation.
14 The standby generator installation shall include for a total of 8 hours backup fuel storage stored in a day tank
(8 Hours) located under generator as base tank or separate within the generator room.
15 The generator shall be acoustically treated to meet the requirements detailed in the project specifications and
drawings. Provide noise pressure calculations in support of the final selected supply and exhaust air
attenuators to ensure noise breakout is in compliance of the particular specification section.
16 Provide acoustic treatment to the exhaust and attenuators to the air inlets and outlets and full acoustic
treatment inside enclosure to reduce noise levels to 70dBA @ 1m from all components of the generator set.
17 The contractor shall include for Full Factory Acceptance Test at the Factory complete with testing to various
loads for 20 Hours with a minimum of 4 hours running at full load. The total testing period shall be 24 Hour
Duration Period as per operator requirements prior to acceptance and delivery to site. The contractor shall
include for Business Class travel to and from destination including minimum 4 star hotel including meals
and other incidentals for approving engineer, project managers and a client representative at suitable times to
the relevant people. All tests shall be re-conducted on site upon complete installation with all components
connected and fully operational without any failures or trouble for a minimum period of 8 hours.
18 Include for start-up and initial commissioning of the generator with all associated switchgear, transfer
switches and distribution components by the manufacturer and under the supervision of the independent
testing and commissioning agency. Mechanical Services trade shall provide and install the bulk fuel storage
tanks and associated pumps and pipework.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

16.12| UNINTERRUPTED POWER SUPPLY (UPS) SYSTEM


A There shall be only rack mounted UPS systems for the requirements of the AV/IT and Security systems within the
phase 3 expansion of the water park. The contactor shall refer to the specific requirements as per the AV/IT and
Security tender documentation.

16.13| EMERGENCY LIGHTING SYSTEM


A The Contractor shall design, supply, install, and test and commission a centrally monitored self-contained
emergency lighting system throughout each of the buildings in accordance with NFPA-101 Life Safety Code and
the UAE Fire and Life Safety Code.

B The Contractor shall coordinate with the main Contractor/interior design Contractor for installing the emergency
light fixtures in the Front of House areas. The Contractor should carefully study the Architectural details of the
ceiling, walls etc. and develop proper installation drawings, fixing details etc. and submit to Engineer’s review and
approval.

C The final locations of the emergency lighting shall be agreed with the Engineer/Architect/ID. Selection of the light
fixture type is subject to Architect/ID approval. However, the Contractor is completely responsible to achieve the
emergency lighting in accordance to the local Authority requirements and Authority requirements shall supersede
Architect/ID requirement.

D The system shall include illuminated exit signs and emergency luminaires, each of which will have a dedicated
self-contained battery (AC/DC).

E Provide an emergency lighting monitoring and testing system to continually monitor the status of the emergency
luminaires and the individual batteries. Include all emergency sub-circuits and interface the system with the BMS to
enable remote monitoring from the Security Control Room.

F The central monitoring system shall:

1 Be complete with a digital display


2 Be complete with self-test capability
3 Be capable of automatic central testing
4 Be complete with fire alarm interface
5 Have volt free alarm relay contacts
6 Have remote alarm facility
7 Be interfaced to the BMS
G Provide generator backup to all emergency luminaires through the development.

H The emergency lighting system batteries shall be sized to provide a minimum of 3-hours of emergency illumination.
All emergency fittings shall be wired to operate as a non-maintained system and illuminate upon sensing a power
supply failure to the nearest normal lighting sub-circuit.

I All Emergency Exit Signs shall be wired to operate as a maintained system.

J All emergency lighting sub-mains and final sub-circuits shall utilise 3 hour fire-rated cables with LSF/LSOH outer
sheaths.

K All Emergency Luminaires and Exit Signs shall be identified by LED indicators (red indicating a system fault and
green indicating system healthy).

L Exit Signs shall incorporate pictograms in accordance with the European signs directive “Running Man symbols”.
The symbol orientation shall be selected to suit the direction of the escape route. At each final exit the Exit Sign
shall read ‘EXIT’, this shall be the final exit door for persons to egress to external area.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

M Provide an automated fault monitoring System to automatically monitor and test the emergency luminaires and the
batteries at regular intervals. The system shall include:

1 Monitoring panel located in Security Control Room.


2 A complete communications network including separate data cabling or mains signalling and fully
addressable network interfaces at all emergency light fittings.
N The contractor shall include for Full Factory Acceptance Test at the Factory complete with Full Load testing for the
required Duration Period as per Specification, NFPA regulations and operator requirements. The contractor shall
include for Business Class Flights to and from destination including minimum 4 star hotel for approving engineer,
project managers and a client representative.

O The specialist Contractor should maintain the system for one year from the date of handing over. The Contractor
should include for the two years AMC.

16.14| LIGHTNING PROTECTION SYSTEM


A The Contractor shall employ the services of an approved Lightning Protection Specialist Contractor to design,
supply, install, and test and commission the complete protection installation in line with the below.

1 The approved specialist shall design, provide and install a complete lightning protection system to the whole
development which makes up Aquaventure phase 3 expansion of the waterpark, building in accordance with
BS/EN 62305:2011.
2 Design calculations and risk assessments have been undertaken, and it has been identified that only building
B01, Triton Tower, will require lightning protection. However, the contractor is fully responsible for
employing a specialist to verify the design assessment and provide lightning protection for the full
development.
3 The principle of the system shall utilise a combination of the structural steel in the tower, and copper tape as
the main path to earth. The building risk analysis indicates that only building B01, Triton Tower, requires an
LPL-4 lighting protection system. The specialist contractor shall coordinate with the main contractor to
finalise earthing pit locations.
4 The system shall comprise the following main components:
a. Roof or membrane mounted strike plates or pads, PVC coated or coloured to match with membrane
colour.
b. Connections to structural steel using copper tails / cable
c. Connections to exposed steelwork and steel escape stairs
d. Bonding of building cladding and façade elements to the down conductors
e. Connection to dedicated earth pits on ground level.
f. Earth reference electrodes for testing
g. Test clamp devices on all down conductors.
5 Earth pits shall be as close as possible to the down conductor and shall be constructed to local Authority
standards. Minimum of 6 meter distance shall be maintained between any two earth pits.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

6 Include for the connection of steel from ground floor slab level to the earth pits using copper tape or cable to
match with building exterior.
7 The Contractor shall take special care to locate and ear mark the structural steel down conductors. The
continuity of the down conductors shall be ensured at each floor level before concreting. The required
resistance of under 0.2 ohms shall be demonstrated to the Engineer before pouring the concrete.
8 The earth pits shall be completely water tight and double seal type suitable for installation in the basement.
The earth rod seal shall provide an effective, reliable and water tight seal to both the earth rod electrode and
damp proof membrane. The earth pit and the earth rod seal shall meet the requirements of IEC 62561-5, and
be capable of withstanding water pressure up to 5.5 Bar
9 The striking pads on the roof cladding shall be of copper to prevent corrosion due to dissimilar metals. The
connectivity between the striking pad and the structural steel down conductor shall be achieved through
purpose made copper tail pieces. Bimetallic strips shall be employed where two dissimilar metals are bonded
together.
10 All exposed metallic parts of the building including façade cladding, framework, structural steelwork etc.
shall be bonded into the lightning protection system. This shall include the structure / sculpture / feature on
top of Triton Tower.
11 The external façade elements shall be bonded to roof network to maintain the same potential.
12 Strike pads on roof at different levels shall be bonded together to form an integrated lightning protection
system.
13 It is the complete responsibility of the Contractor to coordinate with structural, civil, and façade Contractors
to ensure a secured equi-potential bonding.
14 Employ a system specialist to carry out detailed design of the system including site tests ensuring correct
resistance is achieved.
15 The site location is thought to be highly corrosive. The contractor shall verify the conditions and consider
burying all earth rods in the ground surrounded in a conductive material mixture preventing corrosion of the
earth rods.
16 The Earth Rods installed shall be solid copper manufactured in accordance with BS EN 50164-2 and BS
7430.

16.15| LIGHTING AND CONTROLS


A Internal Lighting

1 The Contractor shall supply, install, test, set to work and commission the Internal Lighting systems as
described below and indicated on the tender drawings, specifications and equipment schedules.
2 The lighting to the FOH areas of each building and the building façade shall be based on layouts as prepared
by the Specialist Lighting Consultant and ID drawings. The contractors shall include for supply, installation
and commissioning of lighting and specialist lighting as indicated within the drawings and specifications.
3 The lighting for the remaining areas such as the back-of-house areas, non-public toilets, stair cores,
corridors, plant rooms, service / utility rooms, etc. shall be as per the electrical services drawings.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

4 All the lighting supplied shall have DALI Dimmable drivers for dimming and controlling purpose, as per the
Specialist Lighting Consultant’s design.
5 The Contractor shall coordinate with the main Contractor/interior design Contractor for installing the light
fixtures. The Contractor should carefully study the Architectural details of the ceiling, walls etc. and develop
proper installation drawings, fixing details etc. and submit to Engineer’s review and approval.
6 The final locations of the light fixtures shall be agreed with to Architect/ID. Selection of the light fixture
type is subject to Architect/ID approval. However, it is the responsibility of the Contractor to achieve the
required lux levels in accordance the standards.
7 The Contractor shall coordinate with the security system installer to ensure adequate lighting levels are
achieved for proper functioning of the CCTV cameras in accordance to DPS/SIRA requirements.
8 All the light fixtures shall be LED type. Fluorescent and other types of light fixtures shall not be used., The
lighting design shall utilise luminaires only from the approved list of manufacturers.
9 Wiring for the lighting shall be carried out using a minimum stranded 2.5mm2 LSF copper cables for live,
neutral and earth conductors installed in trunking and conduit.
10 Final connections to all ceiling mounted luminaires shall be via plug and socket type ceiling roses.
11 Where luminaires are installed within suspended ceilings they shall be individually supported unless the
ceiling support system is specifically designed to cater for the weight of the luminaires.
12 Submit technical details and samples of all luminaires for approval prior to any order of equipment. Use only
approved suppliers. Provide mock-up sample of the lighting for Engineer and Architect/ID review and
approval.
13 Within back of house areas and plant floors, lighting circuits shall be switched through conventional wall
switches. Lighting within corridors, lobbies and staircases shall be with presence detectors.
14 All surface trunking and conduit shall be galvanised steel (including ceiling voids). Conduits cast into the
structure shall be PVC type. The minimum size conduit for lighting circuits shall be 20mm.
15 LED luminaires shall be provided in all electrical rooms and plant rooms. Where rooms are double height,
U-channel support systems shall be provided within this contract to span from wall to wall within the room
or be suspended from the room soffit to fix the fittings to.
16 LED luminaires shall be provided to all back of house areas. In corridors, these shall be fixed to the common
service mounting arrangement as per the detailed section drawings through the corridor.
17 Where Back of House areas have suspended ceilings, these shall be provided with recessed LED luminaire
bodies that can accept a variety of different louvers and diffusers to suit the room requirements e.g. office
spaces (where louvers shall be installed), pantries (where prismatic controllers shall be provided) etc.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

16.16| INTERNAL LIGHTING CONTROL SYSTEMS


A The Contractor shall design, supply, install, test, set to work and commission the Internal Lighting control system as
per the Specialist Lighting Consultant ‘s specifications, lighting control schedules and luminaire schedules.

B The electrical supplies to all front of house lighting as per the lighting consultant’s specification, has been designed
on the understanding that the lighting control system will be DALI as per the lighting consultant’s technical design
submission.

C The contractor shall refer to Lighting Consultant/ID package for the FOH area switching strategy.

16.17| EXTERNAL LIGHTING AND CONTROL


A The supply and installation of light fixtures within the external and landscaped areas shall be carried out as part of
the electrical contractor’s scope of work. The Contractor shall refer to the Specialist Lighting Consultant ‘s
specifications, lighting control schedules and luminaire schedules to supplement this Specification.

B The Contractor shall provide associated lighting control systems, distribution boards and dimming systems. The
distribution boards and control equipment shall generally be located in electrical cupboards.

C The external lighting is fed from the lighting control panels located within local buildings throughout the
development. The Contractor shall route the necessary containment as per the site requirement. The Contractor shall
include all the containment (conduits, ducts, supports etc.) required to complete the installation as per the design
drawings.

D Each lighting control panel shall be provided with a supply from the local SMDB/DB within the electrical room or
closet.

E The Contractor shall be responsible for all final sub-circuit / channel design, including the sizing of all relay
modules, dimmer modules, sub-circuit cables, circuit breakers and distribution boards in accordance with their
preferred manufacturer as per the approved schedule of manufacturers.

16.18| FIRE DETECTION AND VOICE ALARM SYSTEM


A The Contractor shall employ the services of an approved Fire Alarm and Evacuation system specialist to design,
supply, install, and test and commission the complete protection installation.

1 The Contractor shall supply and install an extension to the existing integrated digital addressable fire alarm
system with automatic detection and alarm to all buildings of the waterpark phase 3 expansion in accordance
to UAE Fire Code as well as Dubai Civil Defense requirements.
2 The system shall be designed by a DCD approved specialist vendor and shall comply with the requirements
of NFPA-72 National Fire Alarm Code® and Local Authority Requirements.
3 The Fire Alarm system shall also be designed and installed in accordance with the Fire and Life Safety report
issued by the Fire and Life Consultant.
4 The Contractor is completely responsible for the design, install, commission and handover a fully functional
Fire Alarm and detection System in line with the DCD requirements.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

5 The Fire Detection and Alarm system shall be independent to the BGM system, however will be provided
with an interface to the BGM system to signal an alarm. The BGM system should be commissioned to turn
off all transmission on receipt of this signal.
6 The Contractor shall coordinate with the main Contractor/interior design Contractor for installing the Fire
alarm devices/panels in the FOH areas. The Contractor should carefully study the Architectural details of the
ceiling, walls etc. and develop proper installation drawings, fixing details etc. and submit to Engineer’s
review and approval.
7 The final locations of the Fire alarm devices/panels shall be agreed with the Architect/ID. However, the
Contractor is completely responsible to install and handover the Fire alarm and detection system in
accordance to the local Authority requirements. Authority requirements shall always supersede the
Architect/ID requirements.
8 The Fire Alarm system shall be fully integrated in accordance to local Authority requirements , including but
not limited to the following:
a. Integration to the existing fire detection and alarm system to operate seamlessly as a single system
for Aquaventure Waterpark,
b. The existing DCD’s 24x7 panel
c. The existing system at the Security Control Centre
d. BMS system
e. Emergency Lighting system
f. Background Music Systems
g. Security and Access control system
h. Fire suppression system
i. Mechanical Ventilation Plant
j. Dampers and Fans
k. Audio Visual Systems
9 The Fire Alarm and Voice Alarm system shall incorporate the following:
a. Re-commissioning of the existing Main fire alarm panels at Aquaventure, understood to be located at
the Ground floor Security Control Room.
b. The fire alarm panels at each of the new buildings.
c. The Fire Alarm system shall be configured to allow single stage evacuation from each building,
being the building of the alarm source.
d. Alarm Initiating Devices: fully addressable automatic fire, smoke and heat detectors, manual call
points, fire protection systems including hydrants, sprinklers and gas suppression system.
e. Supervisory Inputs: monitoring of sprinkler valves and other fire protection equipment to indicate
fault conditions and ensure they function as intended in the event of a fire.
f. System Interfaces: interface shall be achieved with systems which are required to shut-down or
activated in the event of a fire, as defined in the specifications, schematics and drawings.
g. Occupant Notification System: alarm sounders and beacons throughout all areas of the buildings,
with a network of audio amplifiers.
h. All notification devices shall be complete with strobes in high ambient noise areas
i. Local Civil Defence shall be automatically notified in the event of a fire alarm activation.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

j. The Fire Alarm system shall be backed up by an approved battery. The battery shall be supplied for
both of the following criteria along with 20% extra capacity:
1). Standby mode current – 24 hours
2). Alarm mode current – 1 hour
10 Where doors are provided with magnetic or similar door hold open devices, these shall release upon receipt
of a signal from the fire alarm system in order to maintain the required fire and smoke barriers.
11 Addressable interface units shall be provided in Motor Control Centres and Equipment Cabinets as required
to activate / control ventilation equipment and to mute local audio systems. The status of dampers shall be
monitored by the Main Fire Alarm Panel, i.e. open, closed, tamper, fault.
12 The contractor shall provide a full comprehensive Fire Alarm Cause and Effect Diagram of the complete
project including interfaces with all services connected to the fire alarm for approval by the engineer. An
initial Cause and Effect Diagram must be submitted with the initial Fire Alarm technical submittal for review
and comment by the engineer and Client. The final proposed Cause and Effect Diagram must be submitted
for approval a minimum of 3 months prior to commencing testing and commissioning of the system.
13 Where smoke detectors are required within the void spaces they shall be located such that head replacement
can be achieved through via the removal of visible ceiling components such as grilles, diffusers speakers etc.
Any proprietary tools required to facilitate the testing and replacement of the smoke heads shall be provided
as part of the contract.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

16.19| DISABLED TOILET ALARM SYSTEM.


A The contractor shall supply, install and commission fully functional disabled toilet alarm system in all the disabled
toilets in the development with alarming notification at the security control room.

B Each system shall comprise of an audible/ visual alarm unit, pull cord for raising the alarm, reassurance light and
reset unit. This shall be an integrated system and shall sound an alarm local to the toilet and at the main security
control room.

C The Disabled persons alarm system is defined in the ELV design package.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

017 | APPENDIX A: DESIGN CRITERIA AND PARAMETERS

17.1| BUILDING SERVICES MEP

17.1.1 GENERAL
A The project will be designed in accordance with all applicable local and international codes and standards as well as
general industry good practice and specific client requirements (where applicable).

B The contractor shall be aware and familiar with ‘Atlantis Design Standards’ and the Atlantis IT Infrastructure
Guidelines, and shall ensure that the installation is in compliance with these. Any deviations will be submitted for
approval prior to progressing with any installation works.

17.2| UTILITIES
A The infrastructure utilities scope of work includes the supply, installation, commissioning of new proposed utility
services up to the tie in points with the site wide infrastructure. The contractor shall ensure that the proposed
networks are in line with the authority requirements and fully coordinated with the external infrastructure
installed by others within the surrounding public realm and/ or adjacent plots. All infrastructure works carried
out within the plot shall comply with the authority standards and shall be tested in line with the
specifications.

B Utilities scope of work are listed below but not limited to:

1 Electrical Power supply


2 Chilled Water and Low Temperature Hot Water Systems
3 Potable Water
4 Sewerage
5 Stormwater drainage
6 Back wash from pools
7 Gas supply
C The contractor shall also refer to the infrastructure specifications and drawings.

D Electrical Power Supply

1 The power supply system for site shall be constructed in compliance with the most recent DEWA guidelines
and specifications. The power system shall be capable of supplying the electrical demand for the plot. The
scope for Electrical power network (0.4 kV LV network) includes the supply and installation of the electrical
cables in ducts/trenches from the tie-in point at plot boundary up to the proposed MDB in LV room inside
building.
2 Regulation, Codes, Standards and Guidelines
a. Dubai Electrical and Water Authority (DEWA), Regulations for Electrical Installations.
3 Standards
a. The electrical network will be designed in accordance with, Dubai Electricity and Water (DEWA)
Standards as well as relevant IEC and BS standards where applicable.
1). DEWA Infrastructure NOC Technical Manual 2014
2). Dubai Electricity and Water Authority (DEWA) - Power Supply Guidelines for Major Project
3). DEWA Regulations for Electrical Installations
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

4). DEWA Distribution Substation Guidelines


5). BS7671 Requirements for Electrical Installations, the IET Wiring Regulations 17th Edition.
6). IEC 60502 - Power cables with extruded insulation and their accessories for rated voltages
from 1 kV up to 30 kV
7). BS 77 Specification Voltages for A.C. transmission and distribution systems
8). IEC 60909-2 - Electrical Equipment - Data for Short Circuit Current Calculations in
Accordance with IEC 60909
9). IEC 60947 - Specification for Low Voltage Switchgear and Control Gear
E Potable Water

1 The potable water supply infrastructure for the project shall be capable of supplying sufficient volume of
water at adequate pressure to the proposed Aquaventure Waterpark Phase 3. Infrastructure scope is to
provide service connection for the potable water system from the tie in point available at the building
boundary.
a. Regulation, Codes, Standards and Guidelines
1). Dubai Electricity and Water Authority (DEWA)
2). Dubai Electricity and Water Authority (DEWA) Guidelines for New Development Projects -
Update 2011
b. Potable water Design Guidelines
1). The Design Criteria is based on the Dubai Electricity and Water Authority (DEWA)
Guidelines for New Development Projects - Update 2015.
2). The following system pressure requirements will be applied:
a). Distribution system pressure shall not exceed 6.9 Bars (100 psi).
b). The system shall maintain a minimum pressure of 1.4 Bars (20 psi) at ground level at
all points in the distribution system under all conditions of flow.
c). The water system shall deliver the peak hourly demand (PHD) at the required pressure
of 3 Bars (30 psi) at every existing and proposed service connection throughout the
distribution system.
d). Average day demand at a pressure shall not be less than 2.75 Bars (40 psi). Maximum
hourly demand shall not be less than 2.75 Bars (40 psi). Maximum residual pressure
shall not exceed 6.90 Bars (100 psi).
e). Minimum residual pressure shall not be below 2.75 Bars (40 psi).
F Sewerage

1 Proposed sewerage infrastructure shall be capable of collecting the sewage from proposed facilities within
the Plot and convey it to the External Infrastructure network by gravity. The network pipe material shall be
uPVC up to and including pipe sizes up to 315mm diameter and above 315mm shall be GRP. The design and
the construction of the conveyance system shall meet DM requirements.
2 Regulation, Codes, Standards and Guidelines
a. Dubai Municipality Drainage and Irrigation Department – Sewerage and Drainage Design
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Sanitary Sewer Design Guidelines

3 The Design is based on the Dubai Municipality Drainage and Irrigation Department Sewerage and Drainage
Design Criteria.
a. Minimum depth of the sewer pipe shall be 1.2 meter to the crown of the pipe. Concrete protection
will be provided for pipes with depth less than 1.2 meters under pavements.
b. Minimum vertical clearances between services shall be generally 0.30 m, and minimum horizontal
clearance between services shall be generally 3.0m.
c. The maximum spacing between manholes shall be 100 m.
d. Manholes shall be designed as stipulated in Tables 1.14.1 and 1.14.2 of Dubai Municipality Design
Criteria.
Ref No CRITERIA VALUE

1 Max Velocity (Forced Mains) 1.5 m/s

2 Min Velocity (Gravity Lines) 0.75 m/s

3 Minimum Pipe Size 200mm

4 Maximum Pipe Depth 9m


Proposed Pipe Work Material
5 uPVC
(<=315mm)
6 Proposed Pipe Work Material (> 315mm) GRP

Table 1.Design Criteria

G STORM WATER

1 Regulation, Codes, Standards and Guidelines


a. Dubai Municipality Drainage and Irrigation Department – Sewerage and Drainage Design
2 Stormwater Drainage – Design Criteria
a. The Design Criteria is based on the Dubai Municipality Drainage and Irrigation Department
Sewerage and Drainage Design Criteria. Summary of criteria is provided in table 1. There are two
major events that need to be considered during design development stages – the 5-years and 50-years
storm event (refer to Table 1)
b. Table 2 - Stormwater Design Criteria (DM)

Ref. No. Description Criteria Value

Rainfall 30 mm in 1.5 hr in 5 year return


1
period / I = 18.984 mm/hr
Design Storms /Rainfall
Intensity, (mm/hr)
116 mm in 24 hr in 50 year
2
return period / I = 4.932 mm/hr

Dubai Intensity-Duration-
Rainfall Intensity,
3 Frequency (IDF)Curves – refer
(mm/hr)
to Table 2 below

4 Minimum Inlet Time 15 min


18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Ref. No. Description Criteria Value

5 Maximum Clear Time 4 hr

6 Minimum Pipe Velocity 0.75 m/s

7 Manning’s Coefficient 0.012

Minimum Pipe
8 250 mm
Diameter
Pipes

Proposed Pipe Material


9 uPVC
(<= 315 mm )

Proposed Pipe Material


10 GRP
(>= 315 mm )

Curb Side Inlets, Catch Basins,


11 Inlet Type Catch Basins Manholes, Area
Drains
Inlets and
12 Manholes Inlet Spacing 25 m

Maximum Manhole
13 100 m
Spacing

14 SUDs Infiltration Rate Should be determined

Table 2.Design Criteria

H Back wash from pools

Same criteria for forced main as applicable to sewage/storm drainage shall be followed.

Gas

IGEM regulations, Lootah gas guidelines and UAEFLS 2018 code of practise shall be followed.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

17.2.2 MECHANICAL SERVICES


A Chilled water

1 The secondary side operating temperature of 7.2 +/- 0 .6 (Delta T 9 degree) for all the building to be
considered. Chilled water pipes shall be extended 1.0m from the building for infrastructure connection.

B External Design-Site Conditions

Weather station Dubai


Latitude 25° N

Longitude 55°E

Mean Daily Range 13.8 deg C

Summer Design Temperatures for space cooling 46 °CDB / 29 °CWB

Outdoor air condition for cooling coil sizing 34 °CDB / 32 °CWB


Winter Design Temperatures 11 °CDB

C Site Conditions

Building Thermal Performance

U-Value (W/m2K)
These values are given in Al saf’at code which are
followed in Dubai However, this needs to be confirmed
External Walls 0.57 by the Architect or green building consultant for actual
U – Values as the EHS guidelines doesn’t specify U
value for non-residential project.
These values are given in Al saf’at code which are
followed in Dubai However, this needs to be confirmed
Roofs 0.3 by the Architect or green building consultant for actual
U – Values as the EHS guidelines doesn’t specify U
value for non-residential project.
2.1 (SC - 0.40) glazing less than
40% These values are given in Al saf’at code which are
followed in Dubai However, this needs to be confirmed
Glazing 1.9 (SC – 0.32) glazing more than
by the Architect or green building consultant for actual
(Ground floor) 40%
U – Values as the EHS guidelines doesn’t specify U
1.9 (SC – 0.25) glazing more than value for non-residential project.
60%

Notes:
Glazing property stated is the overall performance of the glazing including mullions and frames.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

D Infiltration

An infiltration rate of 0.5 air changes / hour for perimeter spaces shall be used in the load calculation exercises to predict
the building cooling loads. This figure is based upon a good standard of façade design, detailing and construction. The
air leakage should not exceed 10m3/hr/m2 into or out of a building at an applied pressure of 50Pa. It is noted that this
represents a large element of the building cooling requirement and any success in reducing this figure will realise energy
consumption reductions. It is recommended to provide positive pressure within buildings to minimise infiltration and
poor indoor air quality.
E Internal Heat Gains

Lighting Load to be considered as per Lighting design consultant or as per ASHRAE if not provided by the Lighting
consultant.
Kitchen Equipment heat dissipation will be considered minimum 25% for gas equipment and 20% for electrical
equipment. However, this need to be confirmed by the kitchen consultant.
Safety Factor -10% sensible and latent 5 % as per Local Municipality.
People heat gain (sensible/Latent) should be considered as per ASHRAE for specified space set point temperature.
Duct heat gain to be considered as 2% and Duct leakage to be considered as 3 %. Infiltration as per ASHRAE standard.
F Internal Design Criteria

The following internal design conditions are proposed in accordance with industry best-practice recommendation (e.g.
ASHRAE / CIBSE Guide A) and are commonly adopted for building projects in UAE.
Summer Maximum
Areas Summer Maximum Humidity
Temperature (3)
Reception 24ºC ± 1ºC db, Uncontrolled (1)

Public Toilets 26ºC ± 1ºC db, Uncontrolled (1)

Meeting Rooms 24ºC ± 1ºC db, Uncontrolled (1)

Housekeeping 24ºC ± 1ºC db, Uncontrolled (1)

Lockers Room 24ºC ± 1ºC db, Uncontrolled (1)

Retail 24ºC ± 1ºC db, Uncontrolled (1)

Kitchen 26ºC ± 1ºC db, Uncontrolled (1)

Prayer Rooms 24ºC ± 1ºC db, Uncontrolled (1)

Main Server Room 20ºC ± 1ºC db, Uncontrolled

Grease Trap Room 24ºC ± 1ºC db, Uncontrolled (1)

Storage Room 26ºC ± 1ºC db, Uncontrolled


Manned Plant Room
24ºC ± 1ºC db, Uncontrolled
/Specialist Plant rooms
Electrical
24ºC ± 1ºC db Uncontrolled
Plant Room
Telecom/ELV Room 23ºC ± 3ºC db Uncontrolled

Garbage Room (dry) ** 18ºC ± 1ºC db (2) Uncontrolled

Unmanned Plant Room 26ºC ± 1ºC db Uncontrolled


18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Summer Maximum
Areas Summer Maximum Humidity
Temperature (3)

(1) Although no active humidity control is to be provided to these spaces the Air Conditioning and ventilation system
shall be designed to dehumidify the external air prior to supply (to approx. 12-13 ºC) to ensure the space humidity’s do
not rise above approximately 50% RH ± 10%.

(2) Summer temperature levels assume ‘dry’ waste only, with no specific food/organic waste present. Food waste may
require lower temperatures to slow down decomposition and prevent odours from emanating from garbage rooms.

(3) Whilst the internal dry resultant temperatures are for design calculations, actual room dry resultant temperatures will
be controlled to a bandwidth of +/- 2 °C.

(4) For occupant comfort, normal occupied spaces should have an average air velocity between (0.2 - 0.3) m/s.

G Mechanical Ventilation

Fresh air to be supplied to all zones. Fresh air requirement to be calculated based on the ASHRAE 62.1 latest version
accepted by local authorities. Ventilation Rates and Population Densities as per ASHRAE 62.1-2013.
H Mechanical Distribution Systems

1 Chilled water Pipework Systems


Pipe Sizing Source

Design pressure drop 300-400 Pa/m ASHRAE Fundamentals Pipe sizing

Maximum velocity 2-3 m/s ASHRAE Standard 90.1-2016

2 Duct Work Velocities & Noise Criteria

NC NC NC
Noise Criteria Ductwork 45 NC 35 NC 25
40 30
Distribution – Source
Rectangular Ductwork
Velocities (m/s)
ASHRAE Applications
Plant Rooms 17.8 12.7 8.6
2011
Main Duct Runs
Builders work masonry ASHRAE Applications
17.8 12.7 8.6
shaft 2011
Branch Runs (10-30% of
fan volume)
ASHRAE Applications
Above drywall ceiling 14.2 10.2 6.9
2011
ASHRAE Applications
Above acoustic ceiling 10.2 7.1 4.9
2011
ASHRAE Applications
Within occupied space 8.2 5.9 3.8
2011
Runouts (<5% of fan
volume)

Above drywall ceiling 4.0 3.3 2.75 2.5 <2.0

Above acoustic ceiling 4.0 3.3 2.75 2.5 <2.0

Within occupied space 4.0 3.3 2.75 2.5 <2.0


18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

NC NC NC
Noise Criteria Ductwork 45 NC 35 NC 25
40 30
Distribution – Source
Rectangular Ductwork
Velocities (m/s)

Return Air Openings 4.0 3.3 2.75 2.5 <2.0

Diffuser Connections 4.0 3.3 2.75 2.5 <2.0

Ductwork pressure drop


0.8 Pa/m max – typical values for constant
(within the above limiting Good Practice
pressure loss systems for low pressure ductwork
velocities)
Note: Noise Criteria being indicative with final values to be as pe Project acoustic requirement.

I FRESH AIR INTAKE SEPARATION DISTANCE

The following separation distances have been selected from ASHRAE 62.1 2007.

Object Minimum Separation Distance

Class 3 air exhaust/relief outlet 5.0m

Class 4 air exhaust/relief outlet 10.0m

Commercial Kitchen Exhaust (Grease Hoods) 10.0m

Commercial Kitchen without grease hoods 5.0m

Noxious or dangerous exhaust 10.0m


Garage entry, automobile loading area, or drive-in
5.0m
queue
Tuck loading area or dock, bus parking/idling area 7.5m

Driveway, street, or parking place 1.5m

Thoroughfare with high traffic volume 7.5m


Roof, landscape grade, or other surface directly below
0.3m
intake
Garbage storage/pick-up area, dumpsters 5.0m

Cooling tower intake or basin 5.0m


18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

J Building Management systems

1 As part of a strategy to provide excellent levels of monitoring, control and energy efficiency a Building
Energy Management System will be provided to meet the requirements of the Trakhees EHS Green Building
Regulations, CIBSE Guide H Building Control Systems and BS EN15232 Energy Performance of buildings.

17.2.3 PUBLIC HEALTH / WATER SYSTEMS


1 Water demand and Storage
a. Cold water storage requirements shall be calculated in accordance with DEWA guidelines for new
development projects (update 2015) and incorporate CIBSE Guide G demands where applicable.
However, Potable water tank is existing and is currently operational and serving for the existing other
phases of the project.
1). Notes:
a). Where water demand data is not available for specific usages to meet project
requirements in the DEWA guidelines then CIBSE Guide G shall be used.
b). It is to be noted that these occupancies for the PH design are not aligned with the
occupancies that have been agreed to utilise for the cooling and ventilation systems
design. This is so as not to oversize the storage tanks at this stage. Flow rates can be
increased, if necessary. This will be reviewed as part of the scheme design stage.

17.2.4 ELECTRICAL
A The Utility supply from the DEWA network will be as follows:

1 Primary incoming supplies are anticipated from DEWA at 11 kV primarily from the Crescent Road.
2 A DEWA RMU room will be provided as building B24, where the 11 kV intake position is proposed and
requires conformation with DEWA together with the routing of 11 kV supply.
3 A DEWA transformer room in building B21, will be provided where DEWA will run the 11kV supplies to
from B24,
4 400/230V LV supply cabling will be run from the transformer room to the main LV room in building B21.
B Life safety systems will be fully backed up with a standby diesel generator with 8hr fuel supply.

C Lightning Protection

1 A system consisting of a Faraday Cage is envisaged on Triton Tower with bonding making use of a
grounding pit or similar via exothermic welded connections.
D LightingThe lighting design is developed by the lighting consultant, and the contractor shall refer to the lighting
consultant’s documentation.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

1 Durability and Energy Consumption


a. In any case during its lifetime, the Waterpark will be used by thousands of people with long opening
times over nearly the whole area. Therefore, any lighting installation has to be designed with
durability and low energy consumption in mind.
b. Light fixtures will be embedded in the architecture or placed were no visitor can touch the fixture to
ensure that neither harm to the visitor nor damage to the fixture could occur.
c. The project requires high specifications in energy labels to ensure an exemplary low energy
consumption.
3. General
2 Lighting design will be guided by the following ideas:
a. considering the daylight appearance as a base for the artificial lighting concept
b. impressive appearance during the night
c. choreography of light with general lighting and feature lighting
d. high visual comfort
e. flexibility for the exhibition purpose and future development
f. appropriate light colours
g. easy maintainability
h. long lifetime
i. efficient luminaires
j. cost effectiveness
E Lighting Requirements

1 General Lighting Targets


a. Below table summarizes the targeted illumination levels and lighting power densities for the general
lighting.
b. Please note that the lighting has to be defined by the specialist lighting designer, so that the general
lighting is for circulation only.
Av.
Area Uniformity Glare Power density
Luminance

Circulation 100 lx 0.4 22 4.0 W/m²

Plantrooms 200 lux 0.4 22 TBD


Gift Shop TBD TBD TBD TBD
Restrooms 150 lx 0.4 25 5 W/m²
Landscape < 5 lx TBD - 2.0 W/m²

Table 3.Target values for lighting (based on CIBSE)


18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

c. General Remarks
1). The artificial lighting will be appropriate and functional ensuring a straight forward and
optimal lighting solution. All lighting fixtures will be placed in positions taking into account
the best angles, energy efficient illumination, visual comfort and easy maintenance.
2). The lighting layout for the general lighting will follow the main architectural structure in an
unobtrusive design. Special lighting features will be to highlight the architectural elements and
the overall appearance.
3). The outside appearance will be focused and since the landscaping has a clear way to the
building, an arcade lighting will create the sufficient vertical luminance to orientate safely in
the evening.
F Lighting Technology

1 Lighting Fixtures will be chosen complying with IEC 60598 and BS EN 55015.
2 Technical Strategy
a. The general artificial lighting will be based on LED technology.
b. Other lamp technologies such as fluorescent and high discharge lamps will not be recommended,
because the availability and the production of lamps and luminaires are not secured for the future.
The lighting market has matured already with LED technology and there is no sign of a future with
traditional technology.
c. The technical values of the latest LED technology will meet or outperform the values of the
fluorescent and discharge lamps in terms of efficiency, energy consumption, colour rendering,
lifetime and dimming capabilities.
d. The lifetime of the LED luminaire depends largely on the ambient temperature and the value of
current in mA with which the LED chip is driven. If this value is decreased, then there is a high
increase in lifetime. A balance of lumen output and long lifetime expectation has to be found to
optimize the luminaires. In any case, long and reliable operation is a key feature for the chosen light.
e. Technical data
1). Lumen output: 90 to 140 lm/W
2). Luminaire efficiency: > 0.85
3). General light colour: 4.000 K on black body line
4). Binning: 2 MacAdam Steps
5). Colour rendering: > 80
6). Life time: 60.000 h for every single component
7). Lumen maintenance: L 90, B 10 after 60.000 h (goal)
8). (Lumen depreciation up to 90 % of initial output with a maximum of 10 % failure)Design of
Outdoor SpacesThis section of the design criteria is explained in specialist’s documentation,
refer to Specialist Lighting Designer and Landscape Lighting documentation.

17.3| OPERATION AND MAINTENANCE


A Overview
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

1 The ability to successfully operate and maintain a building over time is significantly dependent upon
decisions that are made in the design process. Everything from building layout to finish materials will affect
building operation. To the extent possible, buildings can be designed to be ‘self-monitoring’ or at least
highly ‘transparent’ and ‘readable.’ Sensors and electronic systems that alert maintenance staff to potential
problems, or which regulate energy use can save cost over the lifetime of the building, both in operating and
replacement costs. The success of the operations and maintenance of any building depends largely on the
staff’s understands how the building works. Detailed operations and maintenance manuals will be developed
to assist in this effort. The manuals should include all details about any systems in the building that will
require maintenance or operation. Information on the manufacturer, vendor and installing contractor,
submittal data, operation and maintenance instructions, a parts list, replacement sources, tools needed for
maintenance, performance data and warranty information should all be listed in the O&M manuals. All
controls as well as equipment should be covered with instructions for operation, seasonal changeovers,
troubleshooting, alarms, system diagrams, control drawings, shutdown and unoccupied operation.

17.4| MAINTENANCE STRATEGY


A Maintenance activities are categorized depending on their timely repetition cycles and can be differentiated as
periodic maintenance, irregular maintenance and maintenance when necessary. They can generally be divided into
three categories, depending on the nature of the activity and their repetition cycles:

1 Inspection (periodic);
2 Cleaning and Servicing (irregular);
3 Replacement and repairs (when necessary).
B Inspection is a periodic maintenance activity. Periodic cycles shall be defined within the maintenance manual of the
final design. The inspection cycles range depending on the complexity of the building component. Critical
components will require inspection more often, while less critical elements can have a longer period of inspection.
It is anticipated that periodic activities will be conducted in an efficient manner, whereupon painting and repairs can
be conducted in a safe manner and on a larger scale when necessary.

C Cleaning can be a periodic or irregular maintenance activity, depending on the demands of the specific component.
Cycles shall be defined within the maintenance manual. Higher importance needs to be given to cleaning and
servicing necessary to maintaining functionality. Painting for select items can be considered as part of the general
cleaning and servicing of the building components, and shall be called out in the O&M manuals.

D Replacement and repair are maintenance activities to be conducted when deemed to be necessary after routine
inspections or when issues arise with respective components.

1 Design Criteria and Assumptions


a. The goals of the comprehensive Building and Operations and Maintenance Program for the new area
of the waterpark include, but are not limited to the following:
1). Reduce capital repairs;
2). Reduce unscheduled shutdowns and repairs;
3). Extend equipment life, thereby extending facility life;
4). Realize life cycle cost savings, and;
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

5). Provide safe, functional systems and facilities that meet the design intent and the Client’s
requirements.
b. A critical component of the O&M program is proper management. The management function must
integrate the full scope of the program into a coherent entity by facilitating proper department
interface.
c. Maintenance Scope – The following is a list of the primary building maintenance scope that need to
be inspected, cleaned and serviced and repaired and replaced in accordance with the manufacturers'
recommendations and building O&M manual.
1). Building Exterior
a). Roofing
b). Façade
c). Glazing
d). Lighting
e). Operable Components
2). Building Interiors;
a). Finishes
b). Lighting
3). Building Systems;
a). HVAC
b). Electrical;
c). Plumbing;
d). Drainage
e). Fire Alarm System;
f). Fire Suppression;
g). Gas systems
4). Landscaping/Grounds;
E Access and Equipment

1 The materials and machinery with which the building is constructed and with which the interior is fitted-out
should be durable as well as aesthetic. They should be easily cleaned and long lasting. Cleaning and
maintenance products should be low in toxicity and volatile organic compounds. It is important for the
building maintenance personnel to participate in further discussions relating to materials and cleaning
products so that they understand the importance of following the maintenance guidelines in regard to
environmental quality.
2 All areas of the building, including exterior spaces and the roof, will be designed with maintenance access
systems in mind in order to facilitate access for inspection, cleaning and servicing, and replacement and
repair. In the long-term, visual inspection is the most important part of all inspections. The following images
present three examples of common machinery that may be used to access all interior and exterior
components of the building during routine maintenance activities. The lifts can access the building through
the entry doors.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Figure 1. Scissor lift, Articulated Boom lift and Crawler Boom Lift

3 A more labour intensive alternative to provide access to the underside of the roof slabs would be to install
temporary scaffolding from the floor as shown in the following image.

Figure 2. Examples of temporary moveable scaffolding


18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

4 A fall arrest rail (which would need to be concealed) on the roof as shown in Figure 3, can be used for
abseiling in order to facilitate inspection and maintenance (debris clearing/painting) on top of the roof.
Possible details for a man-safe rail are shown in Figure 4.

Figure 3. Example of maintenance activities on top of the structure using a fall protection rail system

Figure 4. Example details of proposed Man-safe Rail

5 Computerized Maintenance Management Systems manage day-to-day operations and track the status of
maintenance work, and monitor the associated costs of that work. These systems are vital tools to not only
manage the day-to-day activities, but also to provide valuable information for preparing metrics to use in
evaluating the effectiveness of the current operations and to support organizational and personnel decisions.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

018 | APPENDIX B: SCHEDULE OF APPROVED MANUFACTURERS FOR


MECHANICAL

18.1| HVAC SERVICES


Acceptable Manufacturer’s /
SN Product / System Origin
Subcontractor
Grundfos
Armstrong
Europe / USA
1. Chilled water Pumps KSB
TACO
XYLEM Bell and Gosset
FlaktWoods
Carrier
Trane Europe / USA
2. Air Handling Units
Euroclima
York
Trosten UAE
Carrier
Flaktwoods
Euroclima Europe / USA
3. Fan Coil Units
Trane
York
Trosten UAE
Hiross
Computer Room Air-Conditioning / Airflow Company Europe / USA
4.
Close Control Units Liebert
Denco
Pullen Pumps Ltd
Armstrong
D.P. Pumps
5. Chilled Water Pressurization Units Europe / USA
Grundfos
IMI Hydronic Engineering
Lowara
Metito
Nalco
Corodex
6. HVAC Water Treatments-Chemical Europe / USA
Water bird
Culligan
VEOLIA
XYLEM Bell & Gosset
TACO
Air Separators
7. Aurora Europe / USA
Air / Dirt Separators
Crane
IMI Hydronic Engineering
IMI Hydronic Engineering Europe / USA
8. Vacuum De-Aerator
VEOLIA Europe
Galvanized Sheet Steel, Aluminum Nisshin Japan
9. & Nippon steel Japan
Stainless Steel Duct Work NKK Japan
Century Mechanical Systems UAE
10. Fabricated Duct Work Safid KSA
GMAMCO UAE

Duct Work Insulations (Closed Cell Armstrong USA


11.
Rubber ) Thermobreak UK
Kaimann Kaiflex Europe
Manson Insulation Inc. USA / Canada
12. Acoustic Lining (Sound Lining) Fiberglass Canada Inc. Canada
John Mansville USA
Interlock UK
13. Flexible Duct Work
Thermaflex Europe
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Acceptable Manufacturer’s /
SN Product / System Origin
Subcontractor
Trox
Balancing Volume Dampers
14. Waterloo Europe / USA
(Manual & Motorized)
Johnson Control
Trox
Europe / USA
15. Extractor Damper & Turning Vanes Waterloo
Johnson Control
Trox
16. Back Draft Dampers Waterloo Europe / USA
Johnson Control
Trox
17. Fire and Smoke Dampers Europe / USA
Ruskin Titus
Trox
Halton
18. Air Outlets (Diffusers & Grilles) Europe / USA
Waterloo
Krantz
Schneider
Honeywell
19. Building Management System Trane Europe / USA
Sauter
Siemens
Flakt Woods
Smoke Extract Fans, Chicago Blower
Centrifugal In line fans, Penn
20. Europe / USA
Twin Extract Fans Greenheck
Axial Inline Fans,
Nuaire LTD
Halton USA
Ecology Unit / Electro Static
21. EnviTec USA
Precipitators
Sirius USA
Nippon Steel Japan
Water Piping Sumitomo Japan
22.
Black Steel Seamless Kawasaki Japan
BSS UK
Grinnell-Gruvlok USA
Crane UK
23. Water Threaded Fittings
Aeroquip Corporation USA
Coupco Canada
Grinnell-Gruvlok USA
Crane UK
24. Pipe Butt Weld Fittings
Aeroquip Corporation USA
Coupco Canada
Kitz Japan
Econosto Europe
Hattersley UK
25. Gate Valve, Globe Valves , DFV's
Crane UK
Nibco UK
IMI Engineering UK
Douglas Italy
26. Strainers Armstrong Belgium
Spirax Sarco UK
Bell & Gossett USA
Automatic Flow Control Valves , Griswold Flowcon USA
27. Actuators & IMI(TA) Hydronics USA
Compression Tank Hattersley UK
Bellimo Actuators Switzerland
Victaulic USA
28. Water Grooved Pipe Couplers
Grinell USA
Thermobreak UK
Water Pipe Insulation
29. Kaimann Kaiflex Europe
(Closed Cell Rubber Insulations)
Armstrong USA
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Acceptable Manufacturer’s /
SN Product / System Origin
Subcontractor
Fosters USA
30. Insulation Vapor Barrier Ideal USA
Idenden USA
Fosters USA
Ideal USA
31. Adhesives and Sealant
Idenden USA
Armaflex USA
Weicco India
32. Hangers and Supports Mupro Germany
Flamco Holland
Kinetics Energy USA
Weicco India
33. Vibration Isolation Mason USA
Vibration Management Corp. USA
Vibro Limited Canada
Trox UK
34. Sound Attenuators Wildeboer Germany
Ruskin Titus USA
Econosto Holland
Weicco India
TACO USA
Amtrol Inc USA
35. Cast Iron Air Vents Bell & Gosset USA
Nibco UK

Flamco UK

Econosto Holland
Weksler Instruments USA
36. Meters and Gauges
Weiss USA
Dwyer instruments USA
Metraflex USA
37. Expansion Connections
Mason Industries USA
American Air Filters USA
38. Air Filter
Trox UK
Grinnell-Gruvlok USA
39. Anti-Corrosive Paint Aeroquip Corporation USA
Coupco Canada
Durodyne USA
40. Duct Accessories Aeroduct UAE
Airmaster UAE
Binder USA
41. Test Points
Sisco USA
ABB Italy
Starters, Contactors & Motor Siemens Germany
42.
Control Centers Schneider Germany
Eaton Muller Japan
Siemens Germany
Schneider Germany
43. Variable Speed Drives
Danfoss Denmark
ABB Germany
Colt UK
Nuaire UK
44. Car Park Ventilation fans
Flaktwoods Europe
Greenheck USA
KBE Lebanon
Trox USA
45. Sand Trap Louvres
Titus UK
Waterloo UK
Systemair Sweden
46. Air Curtains Airtecnics Europe
Berner International US
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Acceptable Manufacturer’s /
SN Product / System Origin
Subcontractor
Kamstrup Sweden
47. Chilled water meters / BTU Meters Siemens Germany
Hydrometer Germany
TA Hydronics (IMI Engineering) UK
Pressure Independent Control Valve Danfoss
48. Denmark
& Actuators
Hattersley UK
Bellimo Actuators Switzerland
GEA UK
49. Plate Heat Exchanger Alfalaval Europe
Sondex Denmark
Carrier USA
Trane USA
50. Air cooled & Water-cooled Chillers
York USA
Daikin Mcquay Europe
SPC UK
51. Heat pipes for dehumidification
HEATPIPE USA
Daikin Europe
52. Mini Split DX Units Carrier USA
Trane USA
Heat recovery wheels (Both
Eventus Austria
Sensible & Enthalpy)
53.
(70 % minimum sensible & Latent Gasonics USA
Effectiveness)
DRI India
Gasonics USA
54. CO monitoring systems
ACME USA
CML UK
Commissioning (Building Services
55. Suttons UK
& Life Safety)
I2I UAE
Naffco UAE
56. Fire Fighting Installation Juma Al Majid UAE
Suwaidi Engineering UAE
Lootah Gas UAE
57. LPG services Installation
Emirates Gas UAE
Royal Gas UAE
Integrated Gas UAE
Gulf Gas UAE
Daikin Europe
58. VRF Units Samsung Korea
LG Korea
GEA Europe
59. Cooling Towers Baltimore Air Coil (BAC) Europe
Marley US
Lakos US
60. Scrubber systems
Evapco US
Trox Germany / Malaysia
61. VAV Boxes Ruskin Titus Gulf USA
Barcol Europe

18.2| PUBLIC HEALTH

Item Product / System Acceptable Manufacturer’s / Subcontractor Origin

Terrain UK
Drainage Piping ( PVC, uPVC) and
1 Durapipe UK
Fittings
Marley UK
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Item Product / System Acceptable Manufacturer’s / Subcontractor Origin

Geberit Switzerland
Drainage Piping
2 Valsir Italy
(HDPE) & Fittings
Akatherm Netherlands
Polysystem Italy
3 (PP) polypropylene water supply Vialli Germany
Aquatherm Germany
George Fischer UK
4 (PB) Polybutylene Pipes and Fittings Durapipe UK
Polypipe UK
Polypipe UK
5 (CPVC) Chlorinated Polyvinyl Pipes
George Fischer UK
6 Copper Pipe & Fittings Yorkshire UK
Wednesbury UK
Pegler UK
Muller USA
7 PEX pipes & Fittings UPONOR UK
Henco Belgium
Geberit Switzerland
HENCO Belgium
8 Multilayered pipe and fittings Geberit Switzerland
Uponor UK
RSI India
Frederick Jones Canada
9 Manhole and Sumps Covers
Comap Italy
Pam (Stanton) USA
Veolia France
Nalco USA
10 Multi Media Filter, Terminal filters
Culligan UAE
Metito UAE
Crane UK
Hattersley UK
Kitz Japan
11 Plumbing Valves Nibco USA
Peglar UK
Toyo Japan
IMI Hydronics Europe
Wade Int.
UK
polypipe
USA
Zurn
USA
12 Drainage & Plumbing specialist Amtrol
USA
MIFAB
Germany
Kessel
Germany
Watts
13 Screen filter Yardney USA
XYLEM ( Bell & Gosset) USA
TACO USA
Aurora USA
14 Air Separator
Crane UK
Pneumatex ( IMI Hydronics) Europe
Econosto Holland
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Item Product / System Acceptable Manufacturer’s / Subcontractor Origin

Grinnel USA
Keystone USA
Kitz Japan
Pneumatex ( IMI Hydronics) Europe
15 Gate Valves, Globe Valves, DRVs Muller USA
PEGLAR UK
Hattersley Holland
Crane UK
Nibco USA
Douglas Italy
Armstrong Belgium
16 Strainers Spirex Sarco UK
Hattersley Holland
Mifab USA
Manson Insulation Inc. USA / Canada
Kimmco Kuwait
Water Pipe Mappy UK
17
Insulation (Fiber Glass) AFICO KSA
Knauf UAE
Armaflex USA
Armaflex UAE
Kiamanflex Italy
Water Pipe Insulation
18 Armstrong USA
(Closed Cell Rubber Insulations)
Aeroflex Korea
Rubatex Korea
Fosters USA
19 Insulation Vapour Barrier Ideal USA
Idenden USA
Fosters USA
Ideal USA
20 Adhesives and Sealant
Idenden USA
Armaflex USA
Kimmco Kuwait
21 Acoustic Lagging Material
Johns Manville USA
ITT Grinnel Corporation USA
Diamond India
Weicco India
22 Hangers and Supports
Mupro Germany
Hilti Germany
Flamco Holland
Kinetics Energy USA
Weicco India
23 Vibration Isolation Mason USA
Vibration Management Corp. USA
Vibro Limited Canada
Kessel Germany
24 Grease Interceptors
Aco Germany

Econosto Holland
Weksler Instruments USA
25 Meters and Gauges
Weiss USA
Dwyer instruments USA
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Item Product / System Acceptable Manufacturer’s / Subcontractor Origin

Metraflex USA
26 Expansion Connections
Manson Industries USA
American Air Filters USA
27 Air Filter Trox UK
Bin Air UAE
Grinnell-Gruvlok USA
28 Anti Corrosive Paint Aeroquip Corporation USA
Coupco Canada
Archon USA
29 Stainless steel Pipework & Accessories Alibaba UK
Victolic UK
Grundfos Europe
Flygt Sweden
30 Sanitary Sewerage Pumps KSB Germany
Armstrong USA
Wilo Europe
Grundfos Europe
Xylem USA
31 Domestic Water pumps KSB Germany
Aurora USA
Wilo Europe
ZURN USA
Geberit Switzerland
Roof Drain, Balcony Drain, Clean out,
32 ACO USA
Roof Vent cap etc.
WADE UK
DALLMER UK
ZURN USA
Geberit Switzerland
33 Floor drain covers/ gratings ACO USA
WADE UK
DALLMER UK
AO Smith USA
34 Electric Domestic Water Heaters Ariston Italy
Rheem USA
Zurn USA
Watts USA
35 Water Hammer Arrestor Jay R.Smith USA
Precision Plumbing products USA
Sioux Chief USA
Zurn Wilkins USA
36 Pressure reducing Valve Honey well USA
CLAVAL USA
Veolia Europe
37 Back filter Filter, Chlorination unit Culligan Europe
Metito Europe
RSI India
Frederick Jones Canada
38 Manhole and Sumps Covers
Comap Italy
Pam (Stanton) USA
ICI Caldaie
Viessmann
39 Gas Fired Boilers Cleaver Brooks Europe / USA
AO Smith
Byworth
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Item Product / System Acceptable Manufacturer’s / Subcontractor Origin

Pacetti Europe
40 Calorifiers Viessmann USA
Lochinvar Europe
ICI Caldaie
Viessmann
Centralized Boilers for LTHW
41 Cleaver Brooks Europe / USA
generation
AO Smith
Byworth
Alfalaval Europe
42 Plate heat Exchangers GEA Europe
Sondex Europe
Armtrol USA
43 Heat Exchanger Accessories AO Smith USA
TACO USA
Armstrong Europe
44 Thermostatic Mixing Valve Zurn Wilkins USA
Honeywell USA
Veolia Europe
Water treatment Units,
Culligan Europe
45 Grey water recovery units
Metito Europe
Water filtration and softening units
Waterbird Europe
Mitsubishi Japan
Bridgestone Japan
46 GRP Tanks
Balmoral UK
Sekuisi Japan
Solahart Europe
47 Solar Water heaters
Viessmann Europe
Armstrong Europe
48 Hot water digital Control Valve
RADA Europe
Climaventa Europe
49 Heat Pumps Mitsubishi Europe
Combitherm Europe
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

18.3| FIRE PROTECTION


FIRE PROTECTION
Acceptable Manufacturer’s Local
Item Product / System Origin
/ Subcontractor Agent
Nippon Steel
Sumitomo
Fire Suppression Piping
01 Kawasaki
Galvanized Sch. 40- Seamless
Surya
Shield
Grinnell
Central
Grooved Pipe Coupling Victaulic
02
UL/FM Approved
Viking
Shield
Grinnell
Threaded Fittings Crane
03
UL/FM Approved Aeroquip Corporation
Shield
Grinnell
Keystone
Victaulic
Hattersley
Nibco
Mueller
Valves Viking
04 UL/FM Approved Gate Valves,
Globe Valves & DFVs Naffco
Angus
Potter Roemer
Crane
Honeywell
Shield
Victaulic
Walker Fire
Grinnell
Fire Department Connections NAFFCO
05
(Breeching Inlet) Gem Sprinkler Corp
Croker
Angus
Walker Fire
Gem Sprinkler Corp-
Croker
Norsen
Fire Cabinets, Hose Reels, Fire
06 Angus
extinguishers
NAFFCO
Kidde Fenwal
Sffeco
Viking
Weir
Fire pump sets and control panels Peerless
07
UL and FM Approved Naffco
ITT/ XYLEM A-C
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

FIRE PROTECTION
Acceptable Manufacturer’s Local
Item Product / System Origin
/ Subcontractor Agent
Armstrong
Aurora
SPP
Patterson
Claval
Grinnell
Shield
Pressure Regulating and Pressure Gem Sprinkler Corp
08
Relief Valves Zurn-Wikins
Watts
Honey-well
Potter Roemer
Douglas
Armstrong
09 Strainers Crane
Zurn
Spirax Sarco
Grinnel
Diamond
Shield
Weicco
10 Hangers and Supports Mupro
Tolco
Hilti
Anvil
Flamco
Kinetics Energy
Weicco
11 Vibration Isolation Mason
Vibration Management Corp.
Vibro Limited
Econosto
Weicco
TACO
Elektrovent
Amtrol Inc
12 Air Vents Bell & Gosset
Nibco
Crane
Spirax Sarco
Honey-well
Flamco
Econosto
Weksler Instruments
13 Pressure Gauges
Weiss
Dwyer instruments
Sparling
Danfoss
13A Flow Meter
Smith Meter
Mueller
14 Anti Corrosive Paint Grinnell
Aeroquip Corporation
Carboline
Jotun
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

FIRE PROTECTION
Acceptable Manufacturer’s Local
Item Product / System Origin
/ Subcontractor Agent
National
Coupco
Shield
Central
15 Sprinkler Heads, Pre action systems Angus
Grinnell
Viking
NAFFCO
16 Tamper Switches
Tyco
NAFFCO
Tyco
Zone Control Valves
Angus
17 Supervising Valves
Viking
Sprinkler Alarm Valves
Reliable
Central
Angus
SFS
Elkhart
18 Landing Valves
Viking
Giacomini
NAFFCO
NAFFCO
Fike
Siemens
19 Clean Agent Fire Extinguishing Angus
Vilking
Kidde
Ansul
NAFFCO
Viking
Foam Sprinkler System
Tyco
Nozzles, Bladder Tanks, and Foam
20 Fike
Protection System Accessories,
kidde
Deluge System,
Fenwal
Grinnel
Shield
NAFFCO
Pressure Pipe – Above Ground &
21 Hepworth
Under Ground
Crane
Grinnell
NAFFCO
Fire Hydrant System
22 Mueller
(Hydrant, Piping, Valve)
Trumbull
Metito
Corodex
23 Disinfection System
Marlow
Kisco
Shelco Filters
24 Bag filter housing Rosedale
Pyramid Technologies
Crane
Kinetics
25 Expansion Joint
Bockington & Scott
Proco
26 HDPE pipe George Fisher
Gebrit
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

FIRE PROTECTION
Acceptable Manufacturer’s Local
Item Product / System Origin
/ Subcontractor Agent
Valsir
NOTE:

1 All Fire Protection system material shall be Local civil defense approved.
2 The inclusion of a make or item in the list above does not imply acceptance/approval for any particular
product or material. All specific equipment or material proposed for use on the project must comply with the
specification and must be approved in writing by the Engineers.
3 All First Aid Materials (Fire Extinguishers, Fire Hose Reel, Fire Hose Rack 1 1/2”, Fire Blanket) should
have at least been certified by two independent Certification Bodies as LPCB/BSI Kitemark/Vds and or
UL/FM.
4 For Clean agent fire suppression system Integrity test must be done by qualified, certified Engineer. The
installer must have UL approved filling station, for refilling and maintenance purpose.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

18.4| GAS SERVICES

Ite
Product / System Acceptable Manufacturer’s / Subcontractor Origin
m

Mannesmann Handel AG Germany


Siderca S.A.I.C. Argentina
Dalmine S.P.A. Italy
Corinth Pipeworks S.A. Greece
1 Pipes (Carbon Steel Pipelines) Umran Steel Pipes Inc. Turkey
Saudi Steel Pipe Company Ltd. K.S.A
Kobe Steel Group Japan
Rudolf Flender Gmbh Germany
Thyssen Krupp Germany

Raychem USA
Denso UK
2 Pipe Coating Materials
Long Products Ltd. UK
Canuse Canada

Wilson Walton USA/UAE


Carmon Ltd. UK
RCS USA
Caproco International Ltd. UK
Corrocean Italy
3 Cathodic Protection
HOckway UK
BAC Corrosion Control UK
Caproco Corrosion Prev. Canada
Vandervelde Protection NL
Emirates Techo Casting LLC UAE

Phoceenne France
BKL Fittings UK
TD Williamson Belgium Belgium
RMA Germany

Carbon Steel Pipe Butt-weld Trouvay & Gauvin France


4
Fittings/Flanges Korvers Piping Germany
Corus UK
Royal Econosto Group NI
Anson UK
Ulma Spain
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Ite
Product / System Acceptable Manufacturer’s / Subcontractor Origin
m

Korea Flange Co. Ltd. Korea


Raccortubi SRL Italy

Trouvay & Gauvin France


Korea Pillar Korea
Flexitallic UK
5 Gaskets LJC France
Royal Econosto NI
Alfa Laval Sweden
James Walkers & Co. Ltd. UK

Grove Italia Spa Italy


Perar Italy
Tyco Raimondi Italy
RMA Germany
Pietro Fiorentini Italy
Tormene S.P.A. Italy
Della Foglia Italy
Delta Valves Italy
6 Ball Valve OMB Italy
Serck Audco UK
Della Foglia Italy
RIV Italy
JC Fabrica Spain
Apollo USA
A+R Italy
Rego Italy
Bianchi

Galli & Cassina Italy


Serck Audco UK
Grove Italia Spa Italy
7 Plug Valves
Nordstrom USA
Delta Valves Italy
Halliburton Limited USA

8 Gate Valves Bryan Donkin UK


RMA Germany
Grove Italia S.P.A Italy
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Ite
Product / System Acceptable Manufacturer’s / Subcontractor Origin
m

OMB Italy
Tyco Raimondi Italy
Shipham UK
Tormene S.P.A Italy
Dresser Valves UK

Waga Germany
IGA UK
Dresser FLO Systems UK
Schlumberger Industries France
9 Pressure Regulating Skids Nuovo Pignone S.P.A Italy
Bayan Donkin UK
Petro Fiorentini Italy
Fisher Controls UK
Instromet Belgium

Nova Comet Italy


COMAP Italy/France
Clesse Italy/France
ESl ter-Amco Muller Germany
Bryan Donkin UK
Germany Fischer
Rego USA
Reca Italy
Pressure Regulators I Safety Relief &
10 Sperryn UK
Shut Off Valves
Gorter Nl
IGA UK
Mooney USA
Fisher Controls UK
Jeavons UK
Instromet Belgium
Tartarin Italy
Nuovo Pignone S.P.A Italy

11 Value Actuators Ledeen Dresser ltalia S.P.A Italy


Tyco Italy
Paladon UK
Rotork UK
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Ite
Product / System Acceptable Manufacturer’s / Subcontractor Origin
m

Shafer USA
Biffi Italy
Fisher Controls UK

Plenty UK
Peerless Europe Ltd UK
Vee Bee Filters UK
GO Engineering UK
12 Filters
Forain Italy
Peco USA
Pietro Fiorentini Italy
Bryan Donkin UK

Instromet Belgium
Daniel USA
13 Ultrasonic Meters
Krohne Germany
Schlumberger Industries France

Instromet Belgium
Dresser Roots UK
14 Turbine / RPD Meters Brayan Donkin UK
Schumberger Industries France
Daniel Flow Products Inc USA

Acataris China/
Germany
Toyo
China/Japan
Beta meter
Netherland
GMT
Germany
Samtech
15 Diaphragm Meters Italy
UGI
UK
Nuovo Pignone
Italy
Instromet
Belgium
Schlumberger Industries
France
Kalekalipe
Turkey

16 Meter Flow Computers Instromet Belgium


Daniel Flow Products lnc. USA
Schlumberger Industries France
Dresser Roots UK
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Ite
Product / System Acceptable Manufacturer’s / Subcontractor Origin
m

Fisher Rosemount USA


Bryan Donkin RMG UK
Pietro Fiorentini Italy
MECI France

Daniel UK
MECI France
17 Gas Chromatography
Rosemount USA
Elaster - Jnstromet Germany

KTICorporation USA
Borsig Gmbh Germany
18 Heaters
Foster Wheeler USA
M.B.H. Industrial Services UK

Paul & Loughtran Ltd UK


Foster Wheeler USA
19 Heat Exchangers
Babcock & Wilcox USA
Letter Germany

RMA Germany
20 Insulation Joint Zunt Italy
Alfa Engineering Italy

RMA Germany
Bryan Donkin UK
Nordstorm Valves USA
21 PE Ball Valves
Uponor UK
Fusion UK
George Rscher UK

Fusion UK
Durapipe UK
22 PE Fittings George Fischer UK
Upunor UK
Wask - RMF UK

Fusion UK
Durapipe UK
23 PE /PEX Pipes
Uponor UK
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Ite
Product / System Acceptable Manufacturer’s / Subcontractor Origin
m

Wavin Germany
Union Pipes Industry UAE
Hepworth UK
Cosmoplast UAE

Yokogawa Japan
Siemens Germany
Instromet Belgium
Cegelec France
AEG UK
24 Electrical & Instrumentation
ABB NO
Draka Nl
Schneider Electric France
Bristol Babcock Ltd USA

Chloride UK
Siemens Germany
Borri Italy
Enersys USA
Cegelec France
25 Batteries I UPS
Tungstone UK
Erskine UK
GE USA
Integrated Power Corporation USA
AEG UK

Asco USA
A+R Germany
26 Solenoid Valves
Zaksa Slovania
Madas Italy

EDS –Shield UK
Oldham Germany
27 Gas Detection Panel /Detectors
Sensitron Italy
Winter Germany

Yorkshire Mueller UK
28 Copper Pipe & Fittings
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Ite
Product / System Acceptable Manufacturer’s / Subcontractor Origin
m

Wensbury UK

Mueller USA

Cooker Connection kit including valve & Bowbros UK


29
Flexible hose CHUCHU France

30 Crimp /Transition fittings Crane Fludi UK

Steel Pipe – CS (Welded & Screwed) Nitrotube Ukraine


31
SCH40 & SCH80 Shootube Sumitomo Nippon Japan

West Space Trading (ASK Benkan LAME JD UAE


32 Steel Fittings Welded & Screwed
Technoforge MEGA)
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

019 | APPENDIX C: SCHEDULE OF APPROVED MANUFACTURERS FOR


ELECTRICAL SERVICES

19.1| ELECTRICAL

Item Product / System Acceptable Manufacturer’s / Subcontractor Origin

Telematics
1Aircraft Warning Lights Honeywell

Hughey & Phillips

Zenith/GE
2Automatic Transfer Switches
SOCOMEC
Schneider

C&D Technologies
3Batteries

4Busbar system NOT USED


Cosmoplast
Hepworth
5Cable Ducts (PVC)
Gulf Eternit
National Plastics

6Cable Lugs & Glands


Al Hathboor Electricals - BICC
Al Hathboor Electricals - Hawke
Critchley by Electromec

7Cable Markers Prysmian

Bandit-Idex
Tyrap Thomas & Betts
8Cable Ties and Clamps Critchley by Electromec
UAE and USA

Obo Bettermann
Wibe/Schneider
Swift/Legrand

9Cable Trays/Ladder Racks KSA/UAE


Index Industry Expert
TMI (Technical Metal Industrial Co.)
Delta Cable Management Systems
Everest Metal Industries LLC (EMI)
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Item Product / System Acceptable Manufacturer’s / Subcontractor Origin

Obo Bettermann

Swift/Legrand
KSA/UAE
10
Cable Trunking (Galvanised)
Index Industry Expert
TMI (Technical Metal Industrial Co.)
Delta Cable Management Systems
Everest Metal Industries LLC (EMI)
Marshall Tufflex
Decoduct
11
Cable Trunking (PVC)
Edgetube
MK & Egatube
Wiremold
12
Cable Trunking, skirting wall / dado (Steel)
Ackerman
OBO Bettermann

Marshall Tufflex
MK & Egatube
13
Cable Trunking, skirting wall / dado (uPVC)
OBO Bettermann

Protenax Europe, ME and Africa


14
Cable Cleats, Load Bearing and Trefoil

Adaptaflex

15
Conduits & Accessories (Flexible Metallic)
Burntube
Al Hathboor Electricals – Kopex
Rexton Technologies Middle East
16
Cast Resign MV/LV Transformers NOT USED

Marshall Tufflex
Burntube

Maruichi
17
Conduits & Accessories (Galvanised)
Index Industry Expert
TMI (Technical Metal Industrial Co.)
Delta Cable Management Systems
Everest Metal Industries LLC (EMI)
Al Hathboor Electricals – Barton
Rexton Technologies Middle East
Decoduct
18
Conduits & Accessories (PVC)
Marshall Tufflex
Rexton Technologies Middle East
19
Contactors, Motor starters and Controls Telemechaniqe
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Item Product / System Acceptable Manufacturer’s / Subcontractor Origin

Delta/Draka
20
Control Cables
Jeddah Cables

Rexton Technologies Middle East


Zeta Alarm Systems
21
Disabled Alarm Call Systems

Friedland
Aiphone
22
Doorbell System
Rexton Technologies Middle East
WJ Furse
AN Wallis
23
Earthing

Kingsmill Industries
24
Electric Vehicle Charging NOT USED

25
Emergency Lighting System
Teknoware
TM Technologie
Invensys (Schneider Electric)
26
Energy Meters (BMS)

Obo Bettermann
27
Fire Barriers and Fire Cable Transits

Dufaylite
Honeywell
Edwards
28
Fire Detection and Alarm system
Simplex by Tyco
Haven Fire and Safety
Bandit-Idex
UAE and USA
29
Fire Rated Cable Ties and Clamps
Tyrap Thomas & Betts

30
Fire Rated Isolators
Craig & Dericot

31
Fire Resistant Cables
Prysmian
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Item Product / System Acceptable Manufacturer’s / Subcontractor Origin

Delta / Draka
AEI Cables

32
Flexible Heat Resistant Cables for Lighting
Riyadh Cables

33
Floor Boxes NOT USED
Caterpillar
FG Wilson
34
Generators
Cummins Power Systems
Jengan LLC
Merlin Gerin

35
Harmonic Filtration Equipment

36 Obo Bettermann

Craig & Derricott

37
Isolators & Push Buttons
Merlin Gerin
Al Hathboor Electricals – ABB
Rexton Technologies Middle East Malaysia

38
Sylvania

Tridonic Atco

39
Lamps – HF and Controllable Ballasts
GE-Sylvania

Dynalite/Philips Australia

40
Lighting Control System
Cooper Controls
Ex-or -HoneyWell

41
Lightning Protection System WJ Furse
AN Wallis
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Item Product / System Acceptable Manufacturer’s / Subcontractor Origin

Kingsmill Industries

Whitecroft

42
Luminaires (general lighting)
Zumtobel

Prysmian
43
Power Cables & Wires (XLPE, LS0F)
Riyadh Cables
Jeddah Cables
Telemechaniqe

44
Programmable Logic Controllers (PLC)
Allen Bradley

45
Modular Wiring NOT USED
APC by Schneider Electric

Dorman Smith
46
Power Factor Correction
General Electric

Power to Desk NOT USED


47
(Workstation Solutions)
48
Raised Floor Power Distribution NOT USED
WJ Furse
AN Wallis
Dorman Smith
49
Surge Protection System

Schneider
Schneider

Dorman Smith
50
Switchgear
Eaton MEM

Liebert by Emerson
APC by Schneider Electric
Chloride
51
Uninterruptible Power Supply
General Electric

Al Hathboor Electricals - EPC


52
Variable frequency drives & Electronic starters
Telemechaniqe by Schneider Electric

Leroy Somer
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Item Product / System Acceptable Manufacturer’s / Subcontractor Origin

Allen Bradley

UK/ Europe
53
Wiring Accessories
Crabtree
Al Hathboor Electricals - Legrand
NOTE:

1 All Fire & Life Safety system material shall be UL listed and Local civil defense approved.
2 The inclusion of a make or item in the list above does not imply acceptance/approval for any particular
product or material. All specific equipment or material proposed for use on the project must comply with the
specification and must be approved in writing by the Engineer
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

020 | APPENDIX D: SCHEDULE OF GUARANTEES, WARRANTIES AND


SPARES

20.1| GENERAL
A. Where there are any discrepancies between the spare parts and warranties listed in the MEPF General
Requirements and Scope of Works / MEPF Standard Material and Workmanship Specifications and
the table below then the following table shall take precedence.
B. Where there is NO warrantee mentioned then a minimum 12 months warranty & Service to be provided for
all Plant & Equipment
C. In addition to the items identified in the table below the Contractor shall also provide a list of spares required
for ALL installed equipment as recommended by the manufacturer(s) and/or its authorized
installer/representative of the equipment. The contractor shall also deliver all spare parts to site in protective
containers where practicable.

20.2| SCHEDULE OF EXTRA MATERIALS

Note: This list is only for reference and assistance. The specifications sections prevail and should be considered
as the prevailing reference UNLESS INSTRUCTED OTHERWISE BY THE CLIENT

PERCENTAGE OF
Item Reference Item Description EXTRA MATERIALS / REMARKS
SPARES

HVAC

Spare parts shall be available for at least


Instrumentation and five years after completion of this
Section 230900 5%
Controls for HVAC contract. No warranty is required,
however replacement shall be provided.

Minimum 5 of each grille


Air Terminal Units Section 233600
size and type

Filters: Furnish one spare


filter for each filter
installed.
Fan Coil Unit Section 238219
Fan Belts: Furnish one
spare fan belts for each
unit installed.

Furnish extra materials described in


specification that match products
Mechanical installed and that are packaged with
Section 230553 10%
Identification protective covering for storage and
identified with labels describing
contents.

5 spares for each valve


Hydronic Piping Section 232113
size installed

1 mechanical seal for


Hydronic Pumps Section 232123
each pump
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Note: This list is only for reference and assistance. The specifications sections prevail and should be considered
as the prevailing reference UNLESS INSTRUCTED OTHERWISE BY THE CLIENT

PERCENTAGE OF
Item Reference Item Description EXTRA MATERIALS / REMARKS
SPARES

Air Duct Accessories Section 233300 3%

1 spare motor for each


fan type or capacity
Axial HVAC Fans Section 233413 provided.
1 set of belt for each belt
driven unit.

1 spare motor for each


fan type or capacity
HVAC Power
Section 233423 provided.
Ventilators
1 set of belt for each belt
driven unit.

1 complete set of filters


for each filter bank. If
system includes
Particulate Air prefilters, provide only
Section 234100
Filtration prefilters.
Provide 1 container of red
oil for inclined
manometer filter gauge.

Filters: One set for each


air-handling unit. Furnish extra materials that match
Gaskets: One set for each products installed and that are packaged
Fresh Air Handling
Section 237200 access door. with protective covering for storage and
Unit
Fan Belts: One set for identified with labels describing
each air-handling unit contents.
fan.

Furnish extra materials that match


Fan Belts: One set(s) for
products installed and that are packaged
each belt-driven fan.
Closed Control Unit Section 238123 with protective covering for storage and
Filters: One set(s) of
identified with labels describing
filters for each unit.
contents.

Furnish extra materials that match


Fan Belts: One sets for
products installed and that are packaged
each belt-driven fan.
Air Curtains Section 238124 with protective covering for storage and
Filters: One set of filters
identified with labels describing
for each unit.
contents.

FCU Fan Motors 5 Nos.

Thermostats 15 Nos.

Acoustic liner /
20 Mtr
insulation
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Note: This list is only for reference and assistance. The specifications sections prevail and should be considered
as the prevailing reference UNLESS INSTRUCTED OTHERWISE BY THE CLIENT

PERCENTAGE OF
Item Reference Item Description EXTRA MATERIALS / REMARKS
SPARES

5 spares for each valve


FCU control valve Nos.
size installed

Duct tape 10 Nos.

Flexible duct 5 Nos.

VCD 5% Per cent

CO monitoring sensor 3 Nos.

Bearing 10 Nos.

WATER SUPPLY

1 mechanical seal for


Hydronic Pumps Section 221123
each pump

DRAINAGE

FIRE FIGHTING

Provide1 spare Fire Blankets in


Fire Blankets Section 211200 Kitchens. It should have BS KITE mark
and should be LPCB approved

General spares as mandated by NFPA


and UAEFLS shall be complied with.As
a minimum,
2 Nos. sprinkler log books
2 Nos. sprinkler spanners of each type
6 Nos. conventional (68 deg. C)
sprinklers used in plant areas
6 Nos. spray (57 deg. C) concealed
Spare Sprinkler sprinkler used in corridors
Section 104400
Cabinets 6 Nos. spray (57 deg. C) recessed
pendent sprinkler used in areas with
ceiling
6 Nos. spray (57 deg. C) sidewall
sprinkler used in residential areas
6 nos. Spray (57 deg. C) (K=115)
extended coverage sidewall sprinkler
used in areas where room length is more
than 6.3 m

Spare Automatic General spares as mandated by NFPA


Section 211300 and UAEFLS shall be complied with.As
Sprinklers
a minimum,Provide no fewer than 2
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Note: This list is only for reference and assistance. The specifications sections prevail and should be considered
as the prevailing reference UNLESS INSTRUCTED OTHERWISE BY THE CLIENT

PERCENTAGE OF
Item Reference Item Description EXTRA MATERIALS / REMARKS
SPARES

special sprinkler head wrenches, or at


least 1 head wrench for each cabinet or
sprinkler type, whichever is greater.
House in a suitable lockable metal
cabinet.

General spares as mandated by NFPA


and UAEFLS shall be complied with.As
a minimum,
Sprinkler Cabinets: Finished, wall-
mounted, steel cabinet with hinged
cover, and with space and minimum of
six spare sprinklers plus sprinkler
Wet Pipe Fire wrench. Include number of sprinklers
Suppression Section 211313 required by NFPA 13 and sprinkler
Sprinklers wrench. Include separate cabinet with
sprinklers and wrench for each type of
sprinkler used on project.
Furnish extra materials that match
products installed and that are packaged
with protective covering for storage and
identified with labels describing
contents.

General spares as mandated by NFPA


and UAEFLS shall be complied with.As
a minimum,
2 Nos. sprinkler log books
2 Nos. sprinkler spanners of each type
6 Nos. conventional (68 deg. C)
sprinklers used in plant areas
6 Nos. spray (57 deg. C) concealed
Wet Pipe Fire
sprinkler used in corridors
Suppression Section 211313
6 Nos. spray (57 deg. C) recessed
Sprinklers
pendent sprinkler used in areas with
ceiling
6 Nos. spray (57 deg. C) sidewall
sprinkler used in residential areas
6 nos. Spray (57 deg. C) (K=115)
extended coverage sidewall sprinkler
used in areas where room length is more
than 6.3 m

General spares as mandated by NFPA


and UAEFLS shall be complied with.As
a minimum,
Foam Water System Section 211339 Discharge Devices: Not less than 20
percent of amount of each type installed.
Foam concentrate: Not less than 200
percent of amount installed.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Note: This list is only for reference and assistance. The specifications sections prevail and should be considered
as the prevailing reference UNLESS INSTRUCTED OTHERWISE BY THE CLIENT

PERCENTAGE OF
Item Reference Item Description EXTRA MATERIALS / REMARKS
SPARES

Furnish extra materials described below


that match products installed and that
are packaged with protective covering
for storage and identified with labels
describing contents.

Smoke Detectors 3%

Heat Detectors 3%

Sprinklers 2%

Hose reel parts 2%

GENERAL ITEMS

VOLUME 3 - PART F -ELECTRICAL

Spare parts lists from


original manufacturers to
General Spare parts lists
cover a period of two
years.

Spare parts lists from


Spare parts lists original manufacturers to
General
requirements cover a period of two
years.

LOW VOLTAGE
PANEL (MDB)

Provide spare breakers in MDBs as


Spare protective
noted in SLD drawings. Spare breakers
devices i.e.
Spare breaker As noted on drawings to be padlocked into 'OFF' position to
MCCBs, ACBs
ensure cannot be used unauthorised
etc.
bypassing authority metering.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Note: This list is only for reference and assistance. The specifications sections prevail and should be considered
as the prevailing reference UNLESS INSTRUCTED OTHERWISE BY THE CLIENT

PERCENTAGE OF
Item Reference Item Description EXTRA MATERIALS / REMARKS
SPARES

GENERATOR

Manufacturers
recommended
12 Month Service spare parts and First 12 Months service
Life Spares consumables for life
first 12 months of
service life.

Complete spare set of temperature


Complete spare set
Spare thermistors Complete spare set coefficient thermistors shall be
of thermistors
incorporated as per clause.

POWER FACTOR
REGULATING
EQUIPMENT

Provide schedule Facilities management will be able to


of recommended procure recommended spare parts in line
Spare parts schedule Spare parts schedule
spare parts from with manufacturers advice and allow for
manufacturer preventative maintenance scheduling.

TRANSFER
SWITCHES

Local
representative
must be able to
Local rep immediate supply spare parts Immediate availablilty
supply of spare parts to support day to from supplier
day and emergency
maintenance
requirements.

ISOLATORS AND
SWITCH FUSES

Spare wiring
Switches, Socket outlets, sensors,
devices not less
Wiring Devices 2% connection units, isolators, ceiling roses
than 2% for each
& 20A DP Switches
type

LIGHT FIXTURES
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Note: This list is only for reference and assistance. The specifications sections prevail and should be considered
as the prevailing reference UNLESS INSTRUCTED OTHERWISE BY THE CLIENT

PERCENTAGE OF
Item Reference Item Description EXTRA MATERIALS / REMARKS
SPARES

Lamps Luminaire lamps 5% Each type of lamp

Luminaire control
Control Gear 5% Each type of control gear
gear

Luminaire Louvers
Louvers & Lenses 5% Each louver and lens type
and lenses

Luminaire
Emergency emergency Each type of emergency conversion
5%
Conversion Modules conversion module
modules

UPS SYSTEM

Parts supplies shall be located in the


Spare parts support;
Parts availability 80% of all emergency field to provide 80% of all emergency
Manufacturers field
with 24 hours needs needs. Factory to serve as central
support
stocking facility.

CENTRAL
BATTERY SYSTEM

Each panel shall


have a spare fuse
carrier with at least 3 No. of each type in
Spare fuse carriers
three spare fuses each panel
for each size used
in the panel

Lamps, control gear,


conversion modules See Light Fixtures The lighting section requirements apply
As lighting section
and lenses and section to central battery luminaires also.
louvers

LIGHTING
CONTROL
SYSTEM

Make ordering of
new equipment for Ensuring lighting controls supplier will
Available from end user
expansions, provide equipments needed for
Spare parts not direct through
replacements, and expansions, replacements etc will
availability contractor. Licence
spare parts supply direct and not through the
required for mall systems.
available to end contractor.
user

Spare and Make ordering of Spares / replacement Ensuring Atlantis has future source of
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Note: This list is only for reference and assistance. The specifications sections prevail and should be considered
as the prevailing reference UNLESS INSTRUCTED OTHERWISE BY THE CLIENT

PERCENTAGE OF
Item Reference Item Description EXTRA MATERIALS / REMARKS
SPARES

new equipment for


expansions,
replacements, and
replacement parts parts available for at least compatible replacement parts etc and
spare parts
availability from 10 10 years from date of the installed system is relatively "future-
available to end
years minimum manufacture proof"
user for at least 10
years from date of
manufacture.

TELECOMMUNIC
ATIONS

Spare operator
console handsets
Operator Console
beyond those 5%
Handsets
required for fit-out
purposes

Licences on wifi
controllers to
accommodate
Wifi Licences 10%
additional % above
total of all installed
access points.

Spare speakers of
each type,
PA/VA/BGM System Controller and 5%
amplifier with
EOL

CCTV / ACCESS
CONTROL
SYSTEM

Spare accessories
of each type to be
Lock types, Door procided for
2 each 0
contacts replacement after
the warrenty
period.

Each camera types


CCTV Camera
with complete 1 each
types
accessories

Blank credential
Credential Cards cards; ready for 5%
printing
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Note: This list is only for reference and assistance. The specifications sections prevail and should be considered
as the prevailing reference UNLESS INSTRUCTED OTHERWISE BY THE CLIENT

PERCENTAGE OF
Item Reference Item Description EXTRA MATERIALS / REMARKS
SPARES

Fuses of all kinds, 10% but no fewer than 3


Fuses power and units of each type
electronic. installed

FIRE ALARM
SYSTEM

Provide 5% spare
Break Glass Units 3%
break glass units

Provide 5% spare
Heat Detectors 3%
heat detectors

Provide 5% spare
Smoke Detectors 3%
smoke detectors

Provide 5% spare
Duct Type smoke
duct type smoke
detectors with 3%
detectors with
sampling tubes
sampling tubes

Provide 5% spare
Ceiling speakers of
ceiling speakers of 3%
each type
each type

Provide 5% spare
Monitor module 3%
monitor module

Provide 5% spare
Control Module 3%
control module

Provide 5% spare
Supervisory
supervisory
receiving strip 3%
receiving strip
module
module

Provide 1no. spare


power supply unit
Power Supply Unit 1no
of each satellite
FA panel
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

20.3| SCHEDULE OF WARRANTIES

ATP AQUAVENTURE WATERPARK EXPANSION PHASE 3


SCHEDULE OF WARRANTIES/EXTENDED WARRANTIES - Revision 00 - 12/09/2019

Note: This list is only for reference and assistance. The specifications sections prevail and should be considered
as the prevailing reference.

SPECIFICAT SPECIFICATION
ION TITLE/DESCRIPT REMARKS
SECTION No. ION

Division 21 Fire Suppression

All fire fighting and sprinkler system including components furnished, and
installed under this contract, shall be guaranteed against defects in design,
Fire Fighting
104400 materials and workmanship for the full warranty period which is standard
Specialties
with the manufacturer, but in no case less than one (1) year from the date
of system acceptance.

All fire fighting and sprinkler system including components furnished, and
installed under this contract, shall be guaranteed against defects in design,
Fire Suppression
211200 materials and workmanship for the full warranty period which is standard
Standpipes
with the manufacturer, but in no case less than one (1) year from the date
of system acceptance.

All fire fighting and sprinkler system including components furnished and
Wet Pipe installed under this contract, shall be guaranteed against defects in design,
211313 Suppression materials and workmanship for the full warranty period which is standard
Sprinklers with manufacturer, but in no case less than one (1) year from date of
system acceptance.

All fire fighting and sprinkler system including components furnished, and
installed under this contract, shall be guaranteed against defects in design,
materials and
211339 Foam Water System
workmanship for the full warranty period which is standard with the
manufacturer, but in no
case less than one (1) year from the date of system acceptance.

All fire fighting and sprinkler system including pump set components
furnished, and installed
Clean Agent under this contract, shall be guaranteed against defects in design, materials
212200 Extinguishing and workmanship
System for the full warranty period which is standard with the manufacturer, but
in no case less than
one (1) year from the date of system acceptance.

Division 22 Plumbing

Domestic Water
221123.13 Packaged Booster One year from date of Substantial Completion
Pump Sets

221123 Domestic Water One year from date of Substantial Completion


18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

ATP AQUAVENTURE WATERPARK EXPANSION PHASE 3


SCHEDULE OF WARRANTIES/EXTENDED WARRANTIES - Revision 00 - 12/09/2019

Note: This list is only for reference and assistance. The specifications sections prevail and should be considered
as the prevailing reference.

SPECIFICAT SPECIFICATION
ION TITLE/DESCRIPT REMARKS
SECTION No. ION

Pumps

221419 Sump Pumps Five year from date of Substantial Completion

220519 Meters and Gauges One year from date of Substantial Completion

General Duty Valves


220523 One year from date of Substantial Completion
for Plumbing Piping

221319 Grease Interceptors One year from date of Substantial Completion

PH Approved
Appendix For warranty conditions & spares most stringent codes shall be applied
Manufacturer's List

Division 23 HVAC

Fresh Air Handling


237200 Five years from date of Substantial Completion
Units

Energy Recovery
237200 Five years from date of Substantial Completion
wheels

Pressurisation unit One year from date of Substantial Completion

232123 Hydronic Pumps One year from date of Substantial Completion

Leak detection &


231113 monitoring system One year from date of Substantial Completion
system

Mechanical
230553 1.6.1.2 Warranty Period: One year from date of Substantial Completion.
Identification

1.11.1.1.1 Warrant labor and materials for specified control system free
Instrumentation and
230900 from
Controls for HVAC
defects for a period of 12 months after final acceptance.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

ATP AQUAVENTURE WATERPARK EXPANSION PHASE 3


SCHEDULE OF WARRANTIES/EXTENDED WARRANTIES - Revision 00 - 12/09/2019

Note: This list is only for reference and assistance. The specifications sections prevail and should be considered
as the prevailing reference.

SPECIFICAT SPECIFICATION
ION TITLE/DESCRIPT REMARKS
SECTION No. ION

1.6.1 Special Warranty: Manufacturer's standard form in which


manufacturer agrees to repair or
replace components of venting system that fail in materials or
Breechings, workmanship within specified
235100
Chimneys & Stacks warranty period. Failures include, but are not limited to, structural failures
caused by
expansion and contraction.
1.6.2 Warranty Period: 10 years from date of Substantial Completion.

Special Warranty: Manufacturer's standard form in which manufacturer


agrees to repair or
replace components of computer-room air conditioners those fail in
materials or workmanship
within specified warranty period.
1.8.1.1 Warranty Period for Compressors: Manufacturer's standard, but
Computer Room Air not less than five
238123
Conditioners years from date of Substantial Completion.
1.8.1.2Warranty Period for Humidifiers: Manufacturer's standard, but not
less than three
years from date of Substantial Completion.
1.8.1.3 Warranty Period for Control Boards: Manufacturer's standard, but
not less than
three years from date of Substantial Completion.

1.8.1.1 Manufacturer's standard form in which manufacturer agrees to


repair or replace
components of computer-room air conditioners that fail in materials or
238124 Air Curtains
workmanship within specified warranty period.
1.8.2 Warranty Period
1.8.2.1 Five Years

238219 Fan Coil Units 1.6.1.1 Warranty Period: Five years from date of Substantial Completion.

1.7.1 Equipment, materials and workmanship incorporated into the work


Building Automation
250900 shall be warranted for a
System
period of one year from the time of system acceptance.

235600 Energy Meter Five years from date of Substantial Completion

Axial HVAC Fans


(Toilet Extract,
233413 Smoke Extract, Five years from date of Substantial Completion
Garbage Extract, S/S
ventilation,
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

ATP AQUAVENTURE WATERPARK EXPANSION PHASE 3


SCHEDULE OF WARRANTIES/EXTENDED WARRANTIES - Revision 00 - 12/09/2019

Note: This list is only for reference and assistance. The specifications sections prevail and should be considered
as the prevailing reference.

SPECIFICAT SPECIFICATION
ION TITLE/DESCRIPT REMARKS
SECTION No. ION

Generator Room
ventilation, Car park
Ventilation)

Pressure
230923 Independent Control Five years from date of Substantial Completion
Valve

230523 General Duty Valves One year from date of Substantial Completion

230519 Meters and Gauges One year from date of Substantial Completion

Air Duct
Accessories
233300 One year from date of Substantial Completion
(Damper &
Actuators)

TENDER VOLUME 3 - PART F

Division 26 Electrical Works

Unless otherwise specified in other sections, the contractor shall provide a


Particular
26 00 00 manufacturer's full warranty covering all products of this division, valid
Requirement
for one year from date of issue of Practical Completion Certificate.

1.6.1 A. Provide manufacturer’s warranty covering 5 years with factory


commissioning on all modules from date of purchase
Network Lighting 1.6.2 B. Provide manufacturer’s warranty covering one-year parts and
26 09 43
Control labor and ten year limited parts warranty to repair and replace defective
equipment applicable to daylight sensors, occupancy sensors, wall
stations, bus supply, and infrared receivers.

1.12.1 The Contractor shall provide a system warranty covering all parts,
labour and performance to all applied standards for a period of not less
than one (1) year from the date of acceptance by the Employer.
1.12.2 Manufacturer’s Warranty
Low Voltage 1.12.2.1 Provide all Manufacturer extended product, performance,
26 20 00 Electrical application, and labor warranties that apply to any system provided.
Distribution 1.12.3 Installation personnel shall meet manufacturer’s training and
education requirements for implementation of extended warranty program.
1.12.4 The contractor shall agree to repair or replace defective
components/materials and correct defective work when given notice by
the Employer during the warranty period.
1.12.5 Damage caused to completed work shall be replaced or repaired to
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

ATP AQUAVENTURE WATERPARK EXPANSION PHASE 3


SCHEDULE OF WARRANTIES/EXTENDED WARRANTIES - Revision 00 - 12/09/2019

Note: This list is only for reference and assistance. The specifications sections prevail and should be considered
as the prevailing reference.

SPECIFICAT SPECIFICATION
ION TITLE/DESCRIPT REMARKS
SECTION No. ION

the original condition or better by the contractor at no additional cost to


the Employer.
1.12.6 The warranty specified in this Article shall not deprive the
Employer of other rights the Employer may have under other provisions
of the Contract
1.12.7 Documents and shall be in addition to, and run concurrently with,
and not limiting, other rights and warranties the Employer may have under
provisions of the Contract Documents.
Extended warranty to cover routine and preventative maintenance,
periodic checks and replacement of defective parts for a period of not less
than two (2) years.

3.4 EQUIPMENT GUARANTEE


3.4.1 General
3.4.1.1 The Contractor shall provide a full one year guarantee covering
Motor Control the switchboards, to include routine and preventive maintenance, periodic
26 24 19 checks and replacement of defective parts.
Centers
Extended warranty to cover routine and preventative maintenance,
periodic checks and replacement of defective parts for a period of not less
than two (2) years.

3.4 WARRANTY
3.4.1 Warranty shall be for 12-months from the date of certified start-up.
Variable Frequency The warranty shall include all parts, labor, travel time, and expenses.
26 29 23
Motor Controllers Extended warranty to cover routine and preventative maintenance,
periodic checks and replacement of defective parts for a period of not less
than two (2) years.

1.2.4.7 Warranties on all equipment provided (Tenderers to provide


pricing for 12, 24 and 36 month options).
26 32 13 Engine Generators Extended warranty to cover routine and preventative maintenance,
periodic checks and replacement of defective parts for a period of not less
than two (2) years.

1.9 WARRANTY
1.9.1 UPS Module: The UPS module warranty & maintenance within the
UAE shall include:
Static 1.9.1.1 One Year 7 x 24 Corrective Maintenance
26 33 53 Uninterruptible 1.9.1.2 One 7 x 24 Annual Performance Check
Power Supply 1.9.1.3 7 x 24 Remote Monitoring Advance Response Service.
1.9.1.4 Monthly UPS Evaluation and performance Report when the UPS
is ordered with a modem and remote notify.
1.9.1.5 Web access to account information and site service activity.
1.9.1.6 One annual Power Protection Audit.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

ATP AQUAVENTURE WATERPARK EXPANSION PHASE 3


SCHEDULE OF WARRANTIES/EXTENDED WARRANTIES - Revision 00 - 12/09/2019

Note: This list is only for reference and assistance. The specifications sections prevail and should be considered
as the prevailing reference.

SPECIFICAT SPECIFICATION
ION TITLE/DESCRIPT REMARKS
SECTION No. ION

1.9.1.7 On-site service response time during first year shall be guaranteed
for 4 hour on-site response.
1.9.2 Battery: The UPS manufacturer shall warrant their battery cabinets
on a prorated basis for ten years to deliver no less than 80% of its rated
capacity, provided the prevailing ambient temperature of the battery area
does not exceed 25 deg C (77 deg F). For external battery systems, the
battery manufacturers’ warranty shall apply.

2.10.3.1 Emergency Luminaires:


2.10.3.1.1 Emergency luminaires shall:
a.
26 51 00 Lighting
vi. Minimum installation life of seven years and a guaranteed life of
three years when operated in accordance with manufacturer's
directions.

3.5 WARRANTY
3.5.1 All components, system software, parts and assemblies supplied
shall be guaranteed against defects in materials and workmanship for one
year from acceptance date.
26 51 00 Lighting 3.5.2 Labor to troubleshoot, repair, reprogram, or replace system
components at no extra charge to the employer during the warranty period.
3.5.3 All corrective software modifications made during warranty service
periods shall be updated on all user documentation and on user and
manufacturer archived software disks.

3.4 WARRANTY
3.4.1 All equipment furnished under this contract shall be warranted for a
period of twelve (12) months from the date of final Employer’s
26 52 00 Emergency Lighting
acceptance of the system.
3.4.1.1 Respond to service requests on-site, if required.
3.4.1.2 Replace or repair defective components as required.

1.5 WARRANTY
Surge Protection 1.5.1 The manufacturer shall provide a minimum of a five (5) year
Devices (SPD) for Limited Warranty from date of shipment against failure when installed in
26 90 00 compliance with applicable national/local electrical codes and the
Instrumentation and
Control Equip manufacturer’s installation, operation and maintenance instructions.
Extended warranty 10 years.

26 13 00 HV Panel As per DEWA regulations. DEWA owned, operated and maintained.

26 12 16 Transformers As per DEWA regulations. DEWA owned, operated and maintained.

26 05 26 Earthing System Standard supplier warranty (at least 12 months as per 26 00 00)
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

ATP AQUAVENTURE WATERPARK EXPANSION PHASE 3


SCHEDULE OF WARRANTIES/EXTENDED WARRANTIES - Revision 00 - 12/09/2019

Note: This list is only for reference and assistance. The specifications sections prevail and should be considered
as the prevailing reference.

SPECIFICAT SPECIFICATION
ION TITLE/DESCRIPT REMARKS
SECTION No. ION

Lightning Protection Standard supplier warranty (at least 12 months as per 26 00 00)
26 41 00
System Extended warranty 10 years

26 09 00 Energy Meter Five years from date of Substantial Completion

Standard supplier warranty (at least 12 months as per 26 00 00)


Power Factor
26 35 33 Generator Extended warranty to cover routine and preventative maintenance,
Equipment periodic checks and replacement of defective parts for a period of not less
than two (2) years.

Electronic Safety
Division 28
and Security

1.7 MAINTENANCE SERVICE


1.7.1 Maintenance Service Contract: As part of the product Warranty,
provide maintenance of Fire Alarm systems and equipment for a period of
12 months, using factory-authorized service representatives
1.7.2 Basic Services: Systematic, routine maintenance visits on a quarterly
basis at times scheduled with the Engineer. In addition, respond to service
calls within 24 hours of notification of system trouble. Adjust and replace
defective parts and components with original manufacturer's replacement
Fire Detection and parts, components, and supplies.
28 31 00
Alarm 1.7.3 Additional Services: Perform services within the above 12-month
period not classified as routine maintenance or as warranty work when
authorized in writing. Compensation for additional services must be
agreed upon in writing prior to performing services.
1.7.4 Renewal of Maintenance Service Contract: No later than 60 days
prior to the expiration of the maintenance services contract, deliver to the
Engineer a proposal to provide contract maintenance and repair services
for an additional one-year term. Employer will be under no obligation to
accept maintenance service contract renewal proposal.

2.2.2 The contractor shall utilize the modeling software to optimize the
Fire Detection and design of the pipe system and create custom reports for system installation
28 31 00
Alarm and commissioning. The detector chamber shall be LED based with 5
years warranty.
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

ATP AQUAVENTURE WATERPARK EXPANSION PHASE 3


SCHEDULE OF WARRANTIES/EXTENDED WARRANTIES - Revision 00 - 12/09/2019

Note: This list is only for reference and assistance. The specifications sections prevail and should be considered
as the prevailing reference.

SPECIFICAT SPECIFICATION
ION TITLE/DESCRIPT REMARKS
SECTION No. ION

SPECIAL TOOLS AND INSTRUMENTS


2.4.1 Turn over to the Employer prior to issue of Practical Completion
Fire Detection and
28 31 00 Certificate:
Alarm
2.4.1.5 Original licensed software packages complete with licensee
warranty and manuals.

3.3 TESTING AND GUARANTEE


3.3.1 The contractor shall guarantee all wiring and equipment free from
inherent mechanical and electrical defects for a period of 1 year from the
date of Substantial Completion.
3.3.2 Submit a written test report from an authorized representative of the
equipment manufacturer that the system has been 100% tested and
approved. Submit prior to request for final payment.
3.3.3 Provide instruction to the Employer with regard to proper use and
operation of the system.
Fire Detection and
28 31 00 3.3.4 Provide the Engineer with 2 complete operation and maintenance
Alarm
manuals for all systems and components.
3.3.5 Provide a complete set of record as-built drawings, indicating
system components and location, wiring, and conduit system, and
operation details.
3.3.6 Final testing shall be performed in the presence of the Local Fire
Department and the Engineer. The final test shall include a complete test
of all system devices and functions, and any additional testing requested
by the Local Fire Department. The Contractor shall provide all personnel
and equipment necessary to accomplish the test.

Carbon Monoxide 1.6 WARRANTY


28 31 01 1.6.1 Manufacturer shall provide a 1 year material warranty.
Detection Sensors
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

02 | APPENDIX E: DUCTWORK SPECIFICATION MATRIX

Ductwork Specification Matrix

Fire
Sl. Duct material and Insulation Cladding Extent of
Ductwork description Rated
No. thickness Material Material cladding
Duct

1 EXHAUST AIR DUCT No Galvanised sheet No insulation Aluminium - 1)Ducts are


(From FAHU to louver) steel required corrugated exposed to
Thickness as per ambient air
SMACNA and
2) requires
mechanical
protection.

2 OUTDOOR AIR DUCT No Galvanised sheet No insulation Not detailed


(From Louver to FAHU) steel required Not required
Thickness as per
SMACNA

3 GENERAL EXTRACT No Galvanised sheet Flexible Aluminium - 1)Ducts are


AIR DUCT steel Elastomeric corrugated exposed to
(From conditioned space Thickness as per ambient air
to FAHU) SMACNA and
2) requires
mechanical
protection.

4 GENERATOR Yes Duct Material & No insulation Not required Not detailed
EXHAUST AIR DUCT thickness shall be as required **
per SMACNA &
UAE Fire and Life
Safety Code
requirements.

5 SUPPLY / FRESH AIR No Galvanised sheet Flexible Aluminium - 1)Ducts are


DUCT steel * Elastomeric corrugated exposed to
(From AHU/FCU/FAHU Thickness as per ambient air
to conditioned space) SMACNA and
2)requires
mechanical
protection.

6 RETURN AIR DUCT No Galvanised sheet Flexible Aluminium - Ducts are


(From conditioned space steel Elastomeric corrugated exposed to
to AHU/FCU) Thickness as per ambient air
SMACNA and requires
mechanical
protection.

7 SMOKE EXTRACT AIR Yes Duct Material & No insulation Not required 1)Ducts are
DUCT thickness shall be as required ** exposed to
per SMACNA & ambient air
UAE Fire and Life and
Safety Code 2) requires
requirments. mechanical
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

Ductwork Specification Matrix

Fire
Sl. Duct material and Insulation Cladding Extent of
Ductwork description Rated
No. thickness Material Material cladding
Duct

protection.

8 TOILET EXTRACT AIR No Galvanised sheet Flexible Aluminium - 1)Ducts are


DUCT steel Elastomeric corrugated exposed to
Thickness as per ambient air
SMACNA and
2) requires
mechanical
protection.

9 GARBAGE EXHAUST No Galvanised sheet Flexible Aluminium - 1)Ducts are


AIR DUCT steel Elastomeric corrugated exposed to
Thickness as per ambient air
SMACNA and
2) requires
mechanical
protection.

11 GENERATOR Yes Duct Material & No insulation Not required Not detailed
MAKEUP AIR DUCT thickness shall be as required **
per SMACNA &
UAE Fire and Life
Safety Code
requirements.

13 BELOW SLAB No Galvanised sheet Flexible Not required Not required


CONCRETE ENCASED steel Elastomeric
SUPPLY DUCTWORK Thickness as per
SMACNA

14 BELOW SLAB Yes Duct Material & No insulation Not required Not required
CONCRETE ENCASED thickness shall be as required **
RETURN DUCTWORK per SMACNA &
UAE Fire and Life
Safety Code
requirements.

* Pre-Insuated ducts shall be used for Supply Air from FCU (BOH areas only)

** However fire rated insulation shall be provided when,


- there are combustible materials situated within close proximity (500mm) of a fire rated duct - to prevent the
materials being ignited by radiant heat in the event of a fire inside the duct (Type B test - inside to out)
-a fire rated duct pass through compartments and rooms contaning materials with a low ignition point - to reduce the
risk of a fire being ignited within the duct that could then travel to another compartment (Type A test - fire outside
to in)
-a fire rated duct passes through or above a protected corridor or stairway where the radiant hwat from a fire inside
the duct may affect the safety of the occupants trying to escape the building and/or the fire fighting services in
accessing the building.

*** Provision of proprietary Fire Rated Coating or Wrap will be considered subject to DCD approval of the system and
factory application of the product. On site protection shall not be allowed
18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

END OF SCOPE OF WORKS


18-176 ATLANTIS THE PALM, AQUAVENTURE EXPANSION PHASE III
PALM JUMEIRAH, DUBAI, UAE

CO N TACT
Kenneth Heney
Associate Director - Electrical
T: +971 (0)4 388 1616 | M: +971 (0)56 4164 041
E: k.heney@wmeglobal.com

www.wmeglobal.com

You might also like