PROJECT: PROPOSED 4 BEDROOM RESIDENCE AND OUTHOUSE DATE: 31/03/2022

CLIENT: MR. ANKOMAH

AMOUNT
ITEM DESCRIPTION QUANTITY UNIT RATE
(USD)

EXTERNAL WORKS
SWIMMING POOL CONCRETE WORKS

D: GROUND WORK

D20: EXCAVATING AND EARTHWORKS

EXCAVATING
Starting from ground or reduced level

A Excavate pits not exceeding; 1.50 metres deep commencing


at strip level. 50 M3 8.33 416.50

B Return, fill in and well ram selected excavated materials


around foundations. 3 M3 4.91 14.73

Working Space Allowance to Excavations


D Pits 55 M2 5.00 274.89

DISPOSAL
E Excavated materials; off site 47 M3 5.55 260.85

SURFACE TREATMENTS

F Spray site with "Aidrex 40" anti-termite


treatment to surfaces of excavations before concreting 55 M2 3.33 183.15

D: GROUND WORK 1,150.12


TO SUMMARY
AMOUNT
ITEM DESCRIPTION QUANTITY UNIT RATE
(USD)
E: IN-SITU CONCRETE / LARGE PRECAST CONCRETE

E10: IN-SITU CONCRETE

PLAIN IN-SITU CONCRETE


Plain In-situ Concrete (1:4:8-38mm aggregate)

B Blinding Beds; thickness not exceeding 150mm 2 M3 110.51 221.02

REINFORCED IN-SITU CONCRETE


Reinforced In-situ Vibrated Concrete (Grade 35)

G Swimming Pool Beds; thickness not exceeding 250mm 10 M3 125.36 1,253.60

E Ditto; Walls 10 M3 125.36 1,253.60

E20: FORMWORK

Sawn formwork as described to:

H Vertical sides of walls 92 M2 12.09 1,112.28

J Edge of beds; n.e height 250 28 M 12.09 338.52

K Edges of walls 7 M 6.05 42.35

E30: REINFORCEMENT

High yield bar to BS4466; cutting; bending and securing


with tying wire, distance blocks and ordinary spacers

A 12mm Diameter in Pool Base 1.15 T 1.16 1.33

B Ditto; in Walls 0.67 T 1.16 0.78

E: IN-SITU CONCRETE / LARGE PRECAST CONCRETE


TO SUMMARY 4,223.48
AMOUNT
ITEM DESCRIPTION QUANTITY UNIT RATE
(USD)
J: WATERPROOFING

J40: FLEXIBLE SHEET TANKING/DAMP PROOF


MEMBRANES

A Flexible sheet tanking; 500 micron damp proof membrane


to receive floor bed and walls 93 M2 3.42 318.06

B Liquid applied damproof membrane; two coats approved


Dura Proof Hydrokote pool water proofing compound; applied to 50 M2 30.04 1,502.00
slabs and walls or equal in impernuece primer with neuce seal
with fiber glass mesh 160 gr/m2

J:WATERPROOFING
TO SUMMARY 1,820.06
AMOUNT
ITEM DESCRIPTION QUANTITY UNIT RATE
(USD)

M: SURFACE FINISHING

M10: SAND CEMENT SCREEDS/FLOORING

A Cement and sand (1:4) beds and backings to block or


concrete base

41mm Screeded bed to receive Swimming Pool tiles 32 M2 8.72 279.04

M20: RENDERED COATINGS

20mm Cement and sand (1:4) rendering to block or


concrete base

Work to walls 59 M2 8.91 525.69

POOL SUNDRIES
Supply and Install plumbing fittings and accessories
Skimmers 2 nr 320.00 640.00

M: SURFACE FINISHING
TO SUMMARY 1,444.73
AMOUNT
ITEM DESCRIPTION QUANTITY UNIT RATE
(USD)

SUMMARY

PAGE

D: GROUND WORK 1,150.12

E: IN-SITU CONCRETE / LARGE PRECAST CONCRETE 4,223.48

J WATERPROOFING 1,820.06

M SURFACE FINISHING 1,444.73

BILL NO.2 - SWIMMING POOL WORKS $ 8,638.39


TOTAL FOR SWIMMING POOL WORKS

B2/5