Professional Documents
Culture Documents
Amount
Item No. Description Unit Qty. Unit Rate
SAR
A Division 1 ;Site Works
1 Earth Work
Excavation, Support and Protection for foundations, cleaning and top-soil
removal if any. commencing at reduced levels and depths as indicated on
drawings and soil investigation report recommendation. Removal of excess
material and allowing for any necessary Earth Work include. ( INCLUDING
DEWATERING )
Amount
Item No. Description Unit Qty. Unit Rate
SAR
Division 2-Skeleton Works
A Villa Footing- Supply & Install of Sub - Structure plain and Reinforced
Concrete having a minimum compressive strength of concrete at 28
days curing time using standard cylinder test and using type V
Including rebars, waterstop, formwork, curing, testing and all
accessories to complete .
1.1 Foundation
Foundation as per design & drawings (Concrete- C35 type 5), all
1.1.2
concrete works below or at backfilling level shall be water proof.
M³ 13.8 800.00 11,048.00
Supply & Install Steel Dowels within footing to install precast walls, as
1.2.2
per design & drawings
Pcs. 62.0 8.00 496.00
1.2 Villa Slab on Grade with wiremesh as per design & drawings M³ 13.00 470 6,110.00
1.3 5 cm Screed (C25 type 1) with out wiremesh (above Hollow core slab) M³ 12.92 300.00 3,876.00
1.5 Blinding Concrete 10 cm (C20 type 5) for Fence Footing M³ 1.54 250.00 385.00
1.4 Block wall ( Walk way edge ) as per design & drawings L.M 14.0 30.00 420.00
External Villa Yard Slab on Grade with wiremesh as per design &
1.5
drawings . ( REMEASURED )
M³ 6.71 470.00 3,153.70
1.6 Pergola Footing as per design & drawings M³ 1.2870 600.00 772.20
Total Estimated Contract Price for Pay
Item 2.00 ; TO BE CARRIED TO 29,050.90
COMPOSITE SUMMARY