DAILY INSPECTION SCHEDULE DATE: 5 December 2023

RESPECTIVE
PROJECT : WOODLANDS HEALTH CAMPUS SUBCON
MAIN CONTRACTOR : SDK CONSORTIUM
S/ INSPECTION FINALCAD
LOCATION DESCRIPTION OF WORK COMPANY TIME PIC RTO REMARKS SIGN
N NO. NO.

A EXTERNAL INSPECTION

B B4 INSPECTION

1st & 2nd fix Electrical service installation inspection at Riser lobby
1 B4 Zone 8 BK 2525 1434 11:00 am Hasan SDK/BK
(B4.4.423.CIR)

C B3 INSPECTION

SDK & ALL M&E 2:00PM -


1 B3 326 ROOM FUNCTION TEST STAIRCASE-26 326 7378 Jayson Mr. Chua Hian Loo
subcon 3:00PM
Stage-3 inspection for ESCS (System Functional Test ) -Smoke Zone-
2 B3 Zone 4 TAE 17448 4222 9:00 am Hasan/Kennedy Mr.Alfred Seah
1 GL:37-45/D-J
1st & 2nd fix Electrical service installation inspection at HS Server
3 B3 Zone 5 BK 2740 3462 11:00 am Hasan/Kennedy SDK/BK
room (B3.2.625.NE)
Stage-3 inspection for ESCS (System Functional Test ) -Smoke Zone-
4 B3 Zone 4 TAE 17449 4223 2:00 pm Hasan/Kennedy Mr.Alfred Seah
1 GL:36-48/H-T
Stage-3 inspection for ESCS (System Functional Test ) -Smoke Zone-
5 B3 Zone 4 TAE 17450 4224 4:00 pm Hasan/Kennedy Mr.Alfred Seah
1 GL:38-44/T-Y
326 Room function test inspection at Discussion room (B3.3.502.NE) SDK & ALL M&E
6 B3 Zone 8 326 4226 5:00 pm Hasan/Kennedy Mr.Alfred Seah
GL:38-40/L-N subcon
326 Room function test inspection at Discussion room (B3.3.503.NE) SDK & ALL M&E
7 B3 Zone 8 326 4227 5:50 pm Hasan/Kennedy Mr.Alfred Seah
GL:38-39/L-N subcon

D B2 INSPECTION

FM Defects closing inspection at Basement 2:


1917,1919,3825,4342,4360,4816,4137,4173,4178,4180,4181,4184,43
1 BASEMENT 2 SDK N/A NA 9:00 am Jayson A. Mr. Neo CS
66,4378,4380,4744,4820,4904,4981,4984,4990,4995,4999,5044,5047,
5131,5190,5297
2:00 pm - 3:30 Mr. Neo /
2 B2 Nurse Call System Stage-3 Inspection PT TBA TBA Yan / May
pm Mr. Aung

3 B2 Zone 3 1st & 2nd fix SPK service installation inspection at GL:31-34/B-C B-MECH 1988 6813 10:00 am Hasan/Bangwe SDK/BMECH
DAILY INSPECTION SCHEDULE DATE: 5 December 2023
RESPECTIVE
PROJECT : WOODLANDS HEALTH CAMPUS SUBCON
MAIN CONTRACTOR : SDK CONSORTIUM
S/ INSPECTION FINALCAD
LOCATION DESCRIPTION OF WORK COMPANY TIME PIC RTO REMARKS SIGN
N NO. NO.

E B1 INSPECTION

1 B1 FM Defects closing inspection at Basement 1 SDK N/A NA 2:00PM Jayson A. Mr. Jeffrey Tan

2 B1 Zone 3 B1 z3 1stFix SPK B1 NorthCourthyard GL28-34,E-K B-MECH 2588 7164 10:00 am Hasan/Seenu SDK/B-MECH

F LTC INSPECTION

1 LTC L1 FM DEFECTS CLOSING INSPECTION FOR LIFTS SLS (Schindler) NA NA 9:30 am Jayson P Mr. Albert

10:30am-
2 B1 LTC Continuation of Stage 3 testing inspection for Electrical system at Z-09 UG 5534 9659 Florence Mr. Albert
5:00pm
Green bar defects closing inspection for Electrical system and ELV
3 B1-RF Elec-Elv NA Refer to FC # 5:40 pm Florence Mr. Albert
system

4 B1 LTC Stage 4 testing inspection for KFAF-LTC-B1-01A TO F TAE 17274 9121 Florence Mr. Leong
1:30pm-
7:30pm
5 B1 LTC Stage 4 testing inspection for FAF-LTC-B1-07A TO C TAE 15401 8715 Florence Mr. Leong

G SOC INSPECTION

SDK & ALL M&E


1 SOC L6 327 M&E Above ceiling inspection L6.1.001.CIR 327 290 9:30 pm Sundar Mr. Tan Ming Lei
subcon
SDK & ALL M&E
2 SOC L6 327 M&E Above ceiling inspection L6.1.106. Male TLT 327 218 10:00 am Sundar Mr. Tan Ming Lei
subcon
SDK & ALL M&E
3 SOC L6 327 M&E Above ceiling inspection L6.1.105.Fem TLT 327 219 10:30 am Sundar Mr. Tan Ming Lei
subcon
SDK & ALL M&E
4 SOC L6 327 M&E Above ceiling inspection L6.1.349.ADM 327 190 11:00 am Sundar Mr. Tan Ming Lei
subcon
SDK & ALL M&E
5 SOC L6 327 M&E Above ceiling inspection L6.1.350.ADM 327 191 2:00 pm Sundar Mr. Tan Ming Lei
subcon
SDK & ALL M&E
6 SOC L6 327 M&E Above ceiling inspection L6.1.351.ADM 327 192 3:45 pm Sundar Mr. Tan Ming Lei
subcon
SDK & ALL M&E
7 SOC L6 327 M&E Above ceiling inspection L6.1.352.ADM 327 193 4:30 pm Sundar Mr. Tan Ming Lei
subcon
SDK & ALL M&E
8 SOC L6 327 M&E Above ceiling inspection L6.1.353.ADM 327 184 5:30 pm Sundar Mr. Tan Ming Lei
subcon
DAILY INSPECTION SCHEDULE DATE: 5 December 2023
RESPECTIVE
PROJECT : WOODLANDS HEALTH CAMPUS SUBCON
MAIN CONTRACTOR : SDK CONSORTIUM
S/ INSPECTION FINALCAD
LOCATION DESCRIPTION OF WORK COMPANY TIME PIC RTO REMARKS SIGN
N NO. NO.
SDK & ALL M&E
9 SOC L6 327 M&E Above ceiling inspection L6.1.358.ADM 327 207 5:45 pm Sundar Mr. Tan Ming Lei
subcon
09:30 AM TO
10 SOC L1 Electrical Stage-3 Testing L1 SOC UG 5596 9703 Sundar Mr Sara
11:30 AM
SDK & ALL M&E
11 SOC L7 327 M&E Above ceiling inspection L7.1.716.ADM 327 161 2:00 pm Sundar Mr Sara
subcon
SDK & ALL M&E
12 SOC L7 327 M&E Above ceiling inspection L7.1.717.ADM 327 167 3:00 pm Sundar Mr Sara
subcon
SDK & ALL M&E
13 SOC L7 327 M&E Above ceiling inspection L7.1.343.ADM 327 139 4:00 pm Sundar Mr Sara
subcon
SDK & ALL M&E
14 SOC L5 Lex Level test ZONE -A (GL-09-11/C-F) 5598 652 17:30 to 21:30 Sundar Mr Sara
subcon
3:30 pm - 5:30 Mr. Tan Ming Lei /
15 SOC L3 Nurse Call System Stage-3 Inspection PT TBA TBA Yan / May
pm Mr Aung

H TOWER INSPECTION

1 L4T5 SOI 167 DUCT 1F 2F NEP ROOMS (PANDEMIC CONVERSION) TAE 199 3553 Muthu/Vinod Mr. Yay Chan

2 L4T5 SOI 167 ELEC 1F 2F NEP ROOMS (PANDEMIC CONVERSION) TAE 16544 3554 Muthu/Vinod Mr. Yay Chan
9:30-11:30 am
3 L4T5 SOI 167 BMS 1F 2F NEP ROOMS (PANDEMIC CONVERSION) TAE 16545 3555 Muthu/Vinod Mr. Yay Chan

4 L4T56 SOI-305 PANEL RELOCATION AT AHCH UG 5595 3825 Muthu/Vinod Mr. Yay Chan

326 ROOM FUNCTION CHECK LINK BRIDGE CORRIDOR SDK & ALL M&E
5 L4 T34-T56 LINK BRIDGE 326 3826 1:30 pm Muthu/Vinod Mr. Yay Chan
L4.3.446.CIR subcon
SDK & ALL M&E
6 T7L2 326 -ROOM FUNCTION TEST FOR ICU DISP ROOM at L2.5.107-1 MIC 326 5576 Ramesh Mr. Yay Chan
subcon
SDK & ALL M&E
7 T7L2 326 -ROOM FUNCTION TEST FOR ICU CLEARNER ROOM at L2.5.10 326 5577 Ramesh Mr. Yay Chan
subcon
SDK & ALL M&E 2:00 pm-to-
8 T7L2 326 -ROOM FUNCTION TEST FOR ICU DU ROOM at L2.5.107 MICU. 326 5578 Ramesh Mr. Yay Chan
subcon 07:00pm

SDK & ALL M&E


9 T7L2 326 -ROOM FUNCTION TEST FOR CORRIDOR at L2.5.100 MICU. 326 5579 Ramesh Mr. Yay Chan
subcon
SDK & ALL M&E
10 T7L2 326 -ROOM FUNCTION TEST FOR SSL LOBBY at L2.5.100-1 MICU. 326 5558 Ramesh Mr. Yay Chan
subcon
SDK & ALL M&E
11 T7L2 326 -ROOM FUNCTION TEST FOR CORRIDOR at L2.5.100-2 MICU. 326 5559 Ramesh Mr. Yay Chan
subcon
DAILY INSPECTION SCHEDULE DATE: 5 December 2023
RESPECTIVE
PROJECT : WOODLANDS HEALTH CAMPUS SUBCON
MAIN CONTRACTOR : SDK CONSORTIUM
S/ INSPECTION FINALCAD
LOCATION DESCRIPTION OF WORK COMPANY TIME PIC RTO REMARKS SIGN
N NO. NO.
SDK & ALL M&E
12 T7L2 326 -ROOM FUNCTION TEST FOR ON CALL ROOM L2.5.109 at MICU 326 5555 Ramesh Mr. Yay Chan
subcon
SDK & ALL M&E
13 T7L2 326 -ROOM FUNCTION TEST FOR ON CALL ROOM STAFF TOILETS 326 5556 Ramesh Mr. Yay Chan
subcon
SDK & ALL M&E
14 T7L2 326 -ROOM FUNCTION TEST FOR ON CALL ROOM L2.5.111 at MICU 326 5557 Ramesh Mr. Yay Chan
subcon
SDK & ALL M&E
15 L2 T1 FORM-326 ROOM FUNCTION CHECK AT L2.2.132.EN ENDO 326 5575 DINESH Mr. Sim Tong Seng
subcon
SDK & ALL M&E
16 L2 T1 FORM-326 ROOM FUNCTION CHECK AT L2.2.111.EN ERCP 326 5570 DINESH Mr. Sim Tong Seng
subcon
SDK & ALL M&E
17 L2 T1 FORM-326 ROOM FUNCTION CHECK AT L2.2.112.EN ERCP 326 5571 9:30-11:30 am DINESH Mr. Sim Tong Seng
subcon
SDK & ALL M&E
18 L2 T1 FORM-326 ROOM FUNCTION CHECK AT L2.2.113.EN ERCP 326 5573 DINESH Mr. Sim Tong Seng
subcon
SDK & ALL M&E
19 L2 T1 FORM-326 ROOM FUNCTION CHECK AT L2.2.110.EN ERCP 326 5624 DINESH Mr. Sim Tong Seng
subcon
SDK & ALL M&E
20 L5 T5 326 ROOM FUNCTION CHECK CORRIDOR L5.4.445.CIR 326 868 9:30 am Muthu/Vinod Mr. Sim Hee Chuan
subcon
326 ROOM FUNCTION CHECK LINK BRIDGE CORRIDOR SDK & ALL M&E
21 L5 T34-T56 LINK BRIDGE 326 984 10:00 am Muthu/Vinod Mr. Sim Hee Chuan
L5.3.446.CIR subcon
SDK & ALL M&E
22 L6T6 326 ROOM FUNCTION CHECK TLT L6.4.569.AH & L6.4.570.ME 326 778 10:30 am Muthu/Vinod Mr. Sim Hee Chuan
subcon
SDK & ALL M&E
23 L6T6 326 ROOM FUNCTION CHECK TLT L6.4.562.AH 326 782 11:00 am Muthu/Vinod Mr. Sim Hee Chuan
subcon
SDK & ALL M&E
24 L6T6 326 ROOM FUNCTION CHECK TLT L6.4.551.AH & L6.4.552.ME 326 784 11:30 am Muthu/Vinod Mr. Sim Hee Chuan
subcon
SDK & ALL M&E
25 L6T6 326 ROOM FUNCTION CHECK TLT L6.4.543.AH 326 787 1:30 pm Muthu/Vinod Mr. Sim Hee Chuan
subcon
SDK & ALL M&E
26 L6T6 326 ROOM FUNCTION CHECK TLT L6.4.536.AH & L6.4.537.ME 326 790 2:00 pm Muthu/Vinod Mr. Sim Hee Chuan
subcon
SDK & ALL M&E
27 L6T6 326 ROOM FUNCTION CHECK TLT L6.4.531.AH & L6.4.528.ME 326 793 2:30 pm Muthu/Vinod Mr. Sim Hee Chuan
subcon
SDK & ALL M&E
28 L6T6 326 ROOM FUNCTION CHECK TLT L6.4.548.AH & L6.4.545.ME 326 805 3:00 pm Muthu/Vinod Mr. Sim Hee Chuan
subcon
SDK & ALL M&E
29 L6T6 326 ROOM FUNCTION CHECK TLT L6.4.556.AH & L6.4.557.ME 326 802 3:30 pm Muthu/Vinod Mr. Sim Hee Chuan
subcon
SDK & ALL M&E
30 L6T6 326 ROOM FUNCTION CHECK TLT L6.4.566.AH 326 799 4:00 pm Muthu/Vinod Mr. Sim Hee Chuan
subcon
SDK & ALL M&E
31 L6T6 326 ROOM FUNCTION CHECK TLT L6.4.574.AH & L6.4.575.ME 326 802 4:30 pm Muthu/Vinod Mr. Sim Hee Chuan
subcon
DAILY INSPECTION SCHEDULE DATE: 5 December 2023
RESPECTIVE
PROJECT : WOODLANDS HEALTH CAMPUS SUBCON
MAIN CONTRACTOR : SDK CONSORTIUM
S/ INSPECTION FINALCAD
LOCATION DESCRIPTION OF WORK COMPANY TIME PIC RTO REMARKS SIGN
N NO. NO.
SDK & ALL M&E
32 L6T6 326 ROOM FUNCTION CHECK ALC L6.4.577.AH 326 807 5:00 pm Muthu/Vinod Mr. Sim Hee Chuan
subcon
SDK & ALL M&E
33 L6T6 326 ROOM FUNCTION CHECK RESUS L6.4.576.AH 326 807 5:30 pm Muthu/Vinod Mr. Sim Hee Chuan
subcon
SDK & ALL M&E
34 L6T6 326 ROOM FUNCTION CHECK LINEN L6.4.544.AH 326 812 6:00 pm Muthu/Vinod Mr. Sim Hee Chuan
subcon
SDK & ALL M&E
35 L6T6 326 ROOM FUNCTION CHECK WCH L6.4.527.AH 326 813 6:30 pm Muthu/Vinod Mr. Sim Hee Chuan
subcon
SDK & ALL M&E
36 L6T6 326 ROOM FUNCTION CHECK EQUIP ALC L6.4.509.AH 326 824 7:00 pm Muthu/Vinod Mr. Sim Hee Chuan
subcon

GREEN / PINK BAR


I
INSPECTION
SDK & ALL M&E 9:30 AM - Refer to Refer to
1 TOWER5-6 ROOF HO WHC FM HANDOVER INSPECTION NA NA Arunpandi NOT REQUIRED
subcon 11:30AM Finalcad Finalcad
TOWER7-8 ROOF LDS SDK & ALL M&E 9:30 AM - Refer to Refer to
2 WHC FM HANDOVER INSPECTION NA NA Guru NOT REQUIRED
HO subcon 11:30AM Finalcad Finalcad
SDK & ALL M&E 9:30 AM - Refer to Refer to
3 TOWER7 L2 WHC FM GREEN BAR INSPECTION NA NA Myo NOT REQUIRED
subcon 11:30AM Finalcad Finalcad
SDK & ALL M&E 2:00PM - Refer to Refer to
4 TOWER L3 WHC FM GREEN BAR INSPECTION NA NA Myo NOT REQUIRED
subcon 5:30PM Finalcad Finalcad
SDK & ALL M&E 2:00PM - Refer to Refer to
5 TOWER2 L4 Zone 5 WHC FM GREEN BAR INSPECTION NA NA Arunpandi NOT REQUIRED
subcon 5:30PM Finalcad Finalcad
TOWER L1 ZONE 3 LDS SDK & ALL M&E 2:00PM - Refer to Refer to
6 WHC FM HANDOVER INSPECTION NA NA Guru NOT REQUIRED
HO subcon 5:30PM Finalcad Finalcad
SDK & ALL M&E 9:30 AM - Refer to Refer to
7 B1/B2M TOILET HO WHC FM HANDOVER INSPECTION NA NA Jayson/Thoga NOT REQUIRED
subcon 11:30AM Finalcad Finalcad
SDK & ALL M&E 2:00PM - Refer to Refer to
8 B4 INTER-DEPT/LL HO WHC FM HANDOVER INSPECTION NA NA Jayson/Thoga NOT REQUIRED
subcon 5:30PM Finalcad Finalcad

STAGE 4 -BLUE BAR


J
INSPECTION
2.00PM -
1 L7-T5/T6 WHC Stage 4; Alarm Panel testing AL (Air Liquide) NA NA ⛔ TBA Mr. Sim Hee Chuan
5.00PM
09:00 AM -
2 L2 T4 WHC STAGE-4 TCP T&C POD-2 OT-07 TO 09 KW (Kilowatts) TBA TBA ⛔ TBA Mr. Shek Kun Lee
11:00 AM
2:00 PM - 4:00
3 L2 T4 WHC STAGE-4 TCP T&C POD-1 OT-01 TO 06 KW (Kilowatts) TBA TBA ⛔ TBA Mr. Shek Kun Lee
PM
DAILY INSPECTION SCHEDULE DATE: 5 December 2023
RESPECTIVE
PROJECT : WOODLANDS HEALTH CAMPUS SUBCON
MAIN CONTRACTOR : SDK CONSORTIUM
S/ INSPECTION FINALCAD
LOCATION DESCRIPTION OF WORK COMPANY TIME PIC RTO REMARKS SIGN
N NO. NO.
WHC Stage 4 T&C: ACMV
17278 #1188
1.AHU-SOC-L2-01A/B 9.30AM -
4 LEVEL 2 (SOC) TAE 17352 #1187 ⛔ TBA Mr. Tan Ming Lei
2.AHU-SOC-L2-02 11.30AM
17391 #1203
3.TEF-SOC-L2-02
Postponed by
5 B3 CDS Foam system testing inspection B-MECH ? FC? Florence Mr.Aung/Mr. Alfred
B-MECH
WHC Stage 4 T&C: ACMV
17064 #9078
1.FCU-LTC-B1-18
6 BASEMENT 1 (LTC) TAE 17226 #9109 ⛔ TBA Mr. Leong
2.EAF-LTC-B1-10
17283 #9127
3.FAF-LTC-B1-12
WHC Stage 4 T&C: BMS 9.30AM -
1.LCP-FCU-LTC-L1-09 11.30AM
2.LCP-FCU-LTC-L1-11
7 L1 LTC TAE/QA 17303 #9833 ⛔ TBA Mr. Leong
3.LCP-FCU-LTC-L1-15A
4.LCP-FCU-LTC-L1-15B
5.PDV-LTC-01-A/B/C/D/E/F/G/H
WHC Stage 4 T&C: BMS
1.AHU-B2-10A/B
9.30AM -
8 BASEMENT 2 2.FAF-AHU-B2-11A/B/C TAE/QA 15596 #7150 ⛔ TBA Mr. Neo CS
11.30AM
3.KEF-T3-RF-02A/B/C
4.EAF-B2-43A/B
WHC Stage 4 T&C: ACMV
15846 #5549
1.EAF-L2-07 2.00PM -
9 LEVEL 2 (TOWER 5) TAE 15849 #5550 ⛔ TBA Mr. Yay Chan
2.EAF-L2-08 5.30PM
17039 #5548
3.TEF-L2-04
WHC Stage 4 T&C: ACMV
17270 #9822
1.AHU-LTC-B1-02
17271 #9823 2.00PM -
10 BASEMENT 1 (LTC) 2.AHU-LTC-B1-03 TAE ⛔ TBA Mr. Leong
17384 #9156 5.30PM
3.FAF-AHU-B1-12A/B
17360 #9149
4.PF-AHU-B1-09A/B