Professional Documents
Culture Documents
July 2022
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
RFP Documents
Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Table of Contents
Disclaimer ...........................................................................................................................1
Glossary ............................................................................................................................. 2
Definitions ......................................................................................................................... 3
1. General ................................................................................................................... 6
1.1 Introduction ........................................................................................................................................ 6
1.1.1 General requirements ................................................................................................................. 6
1.2 Scope of Acceptance Tests .................................................................................................................. 6
1.3 Right to Request Additional Testing .................................................................................................. 7
1.4 Inspections and Right to Witness Inspections and Tests ................................................................. 7
1.5 Taking of Samples and Laboratory Tests ..........................................................................................8
1.6 Odour Monitoring ...............................................................................................................................8
1.7 Noise Monitoring ................................................................................................................................ 9
2. Inspections ........................................................................................................... 10
2.1 Introduction to Inspections .............................................................................................................. 10
2.2 Site Inspections ................................................................................................................................. 10
2.3 Factory Acceptance Testing .............................................................................................................. 10
2.4 Site Acceptance Tests ........................................................................................................................ 10
3. Pre-Commissioning ............................................................................................... 11
3.1 Equipment Validation .......................................................................................................................11
3.2 Dry Testing .........................................................................................................................................11
3.3 Calibration of Metering and Monitoring Systems ...........................................................................11
3.4 Wet Testing ....................................................................................................................................... 12
3.4.1 Component Testing ................................................................................................................... 12
3.4.2 System Testing ........................................................................................................................... 12
3.4.3 Hydrostatic and Process Validation ......................................................................................... 12
3.5 Pre-Commissioning Report .............................................................................................................. 13
4. Commissioning ......................................................................................................14
4.1 Commissioning Plan ......................................................................................................................... 14
4.2 General Requirements: ..................................................................................................................... 14
4.3 Trial Operation .................................................................................................................................. 15
4.4 Commissioning Report ..................................................................................................................... 15
Page/Content/ii Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
5. Commercial Operation Testing ..............................................................................16
5.1 Commercial Operation Testing Plan................................................................................................ 16
5.2 Commercial Operation Testing ........................................................................................................ 17
5.2.1 Commercial Operation Testing – Project Assets ..................................................................... 17
5.2.2 Commercial Operation Testing – Kahramaa Facilities ...........................................................20
5.3 Commercial Operation Test Report – Project Assets .................................................................... 20
5.4 Commercial Operation Test Report – Kahramaa Facilities ........................................................... 21
5.5 Completion and Commercial Operation – Project Assets .............................................................. 21
6. Availability Testing ............................................................................................... 23
6.1 Asset Inspection Survey.................................................................................................................... 23
6.2 Availability Performance Tests ........................................................................................................ 23
6.3 Availability Testing Plan and Requirements ...................................................................................24
6.4 Availability Test Reports .................................................................................................................. 25
6.4.1 Asset Inspection Survey Report ................................................................................................ 25
6.4.2 Availability Performance Test Report ...................................................................................... 26
A. Appendix A: Project Assets Commercial Operation Testing – Secondary Treatment
Facilities ........................................................................................................................... 27
A.1 General .............................................................................................................................................. 27
A.2 Biological Treatment ........................................................................................................................ 27
A.2.1 Aeration Pattern test ................................................................................................................. 27
A.2.2 Standard Aeration Efficiency Testing ...................................................................................... 27
A.2.3 Mixing of non-aerated zones .................................................................................................... 27
B. Appendix B: Project Assets Commercial Operation Testing – Membrane Filtration
Requirements .................................................................................................................. 29
B.1 General ..............................................................................................................................................29
B.2 Functional Testing ............................................................................................................................29
B.3 Commercial Operation Testing of Membrane System....................................................................29
C. Appendix C: Project Assets Commercial Operation Testing – Odour Systems ...... 30
C.1 General ............................................................................................................................................. 30
C.2 Odour Control Commercial Operation Testing .............................................................................. 30
Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Disclaimer
All information contained in this RFP, including inter alia financial, geographical, commercial, legal and
technical information, has been included for illustrative and indicative purposes only to assist companies
and consortia in making their own evaluation of the Project. Each Respondent shall be solely responsible
for satisfying itself as to the information required to submit the bid for the Project.
Respondents should make their own investigations, projections, conclusions and consult their own
advisors to independently verify the information contained in this RFP and to obtain any additional
information they might require prior to submitting the Bid.
Whilst the information contained in this RFP has been prepared in good faith, it does not purport to be
comprehensive and it does not purport to have been independently verified. Neither Ashghal nor their
respective employees, agents or advisors make any representation or warranty, express or implied, with
respect to the veracity, adequacy, accuracy, reasonableness or completeness of the information contained
in this RFP or with respect to the information on which it is based or in respect to any written or oral
information or representation given or made, or to be given or made, by Ashghal or any of its advisors to
any company or Consortium or to its or their professional advisors, whether given or made prior to or after
the issue of this RFP (collectively, the “Information”).
Ashghal, its employees, agents and its advisors hereby expressly disclaim any and all liability arising out of
or in relation to the Information (including in relation to omissions therefrom) and in respect of the use of
and/or reliance on such Information by companies or consortia and/or its or their advisors.
This RFP does not purport to commit or bind Ashghal in any manner whatsoever to proceed to the RFP
stage or to the awarding of a contract. Ashghal reserves its absolute, complete and unfettered right to, at
any time and for any reason whatsoever, disregard all Bids and to terminate at will the competitive selection
process and may, at its discretion, proceed with the Project in some other manner, with no liability to any
party whatsoever.
Each Respondent is solely responsible for all costs it incurs in the preparation of its Bid, including without
limitation all costs of providing information requested by Ashghal, attending meetings and conducting any
due diligence. Under no circumstances will Ashghal or any of its advisors be liable for any costs or expenses
borne by the Respondent or any of its advisors in this process, nor shall they be liable for any damages or
consequential damages whatsoever, which may arise out of the process.
Ashghal reserves the right, in its absolute discretion, with no liability whatsoever to:
a. amend the scope of the Project, modify, cancel or suspend the RFP process or any or all stages of the
procurement process, at any time for any reason;
b. waive a defect or irregularity in the form or content of any RFP;
c. re-advertise for new responses, call for tenders, or enter into negotiations for this Project or for work
of a similar nature;
d. make any changes to the terms of business opportunity described in this RFP; and
e. extend, from time to time, any date, time period or deadline provided in this RFP.
All Bids submitted to Ashghal shall become the property of Ashghal immediately upon such submission.
Page 1 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Glossary
Term Abbreviation
ANSI
American national Standard Institute
ASCE American Society of Civil Engineers
ASTM American Society for Testing and Materials
HMI Human Machine Interface
MLSS
Mixed Liquor Suspended Solids
NOSP Notification of Safety Precautions
PLC Programable logical control
SAE supplier’s aeration efficiency
SCADA Supervisory Control and Data Acquisition
UF Ultra-Filtration
Page 2 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Definitions
Term Definition
Availability Testing or Availability Test (s) has the meaning as defined in the Agreement
Business Days has the meaning as defined in the Agreement
Commercial Operation Certificate has the meaning as defined in the Agreement
Commercial Operation Period has the meaning as defined in the Agreement
Commercial Operation Testing has the meaning as defined in the Agreement
Commercial Operation Testing Plan has the meaning as defined in the Agreement
Commercial Operation Tests has the meaning as defined in the Agreement
means the process of testing at the completion of construction of
the Project Assets and Kahramaa Facilities to ensure that the
Project Company met all of the preconditions necessary to
Commissioning commence Commercial Operation Tests, Commissioning shall be
undertaken in accordance with section 4, Schedule 3 (Acceptance
and Availability Test Requirements)
Page 3 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Day has the meaning as defined in the Agreement
Day(s) has the meaning as defined in the Agreement
Detailed Project Report has the meaning as defined in the Agreement
Dispute has the meaning as defined in the Agreement
Diversion Outflow has the meaning as defined in the Agreement
Failed Output Day has the meaning as defined in the Agreement
Fine Screenings has the meaning as defined in the Agreement
Good Utility Practice has the meaning as defined in the Agreement
Laws has the meaning as defined in the Agreement
Grit has the meaning as defined in the Agreement
Guaranteed Output Performance has the meaning as defined in the Agreement and Schedule 6
Requirements Guaranteed Output Performance Requirements
Improvement Notice has the meaning as defined in the Agreement
Independent Expert has the meaning as defined in the Agreement
Influent has the meaning as defined in the Agreement
Influent Excuse Event has the meaning as defined in the Agreement
Initial Availability Test has the meaning as defined in the Agreement
Inspection and Testing Plan has the meaning as defined in the Agreement
Kahramaa has the meaning as defined in the Agreement
Kahramaa Facilities has the meaning as defined in the Agreement
Kahramaa Facilities Provisional Acceptance
has the meaning as defined in the Agreement
Certificate
has the meaning as defined in the Part 1 – Project Overview and
Liquid Treatment Facilities Design Requirements, Schedule 2 Design and Construction
Requirements
Major Equipment has the meaning as defined in the Agreement
Metering and Monitoring System. has the meaning as defined in the Agreement
No Objection has the meaning as defined in the Agreement
Off Specification Influent has the meaning as defined in the Agreement
Off Specification TSE has the meaning as defined in the Agreement
Parties has the meaning as defined in the Agreement
Party has the meaning as defined in the Agreement
Page 4 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
means the facility that is part of STW Facilities designed and
constructed by the Project Company in accordance with Schedule 2
(Design and Construction Requirements) including biological
process, aeration system and post settlement tanks where the
Secondary Treatment Facilities
wastewater is treated to a certain degree of effluent quality by
using biological process to remove dissolved and suspended
organic compounds and provided with physical phase separation
to remove settleable solids.
Shared Facilities has the meaning as defined in the Agreement
Sludge has the meaning as defined in the Agreement
Sludge Treatment Facilities has the meaning as defined in the Agreement
Sulphur means a chemical element with the symbol S and atomic number
16.
Terminal Pumping Station has the meaning as defined in the Agreement
TSE has the meaning as defined in the Agreement
TSE Facilities has the meaning as defined in the Agreement
TSE Pump Station has the meaning as defined in the Agreement
Page 5 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
1. General
1.1 Introduction
This Schedule 3 (Acceptance and Availability Test Requirements) sets out the minimum requirements for
various Acceptance Tests to be carried out during testing and commissioning of the Project Assets and
Kahramaa Facilities. It also sets out the requirements for the Availability Testing of the Project Assets during
the Commercial Operation Period.
Page 6 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
All tests shall be conducted in accordance with internationally recognised standards and procedures agreed
with Ashghal.
In developing the Inspection and Testing Plan, the Project Company shall also take into account the testing
provisions described in Appendix A, Appendix B and Appendix C in relation to the relevant testing stages.
The tests for the Project Assets shall comprise tests of all structures, pipelines, equipment, systems and
processes under actual operating conditions, including operation of all equipment, systems and processes in
both manual and automated modes.
The Project Company shall submit the Inspection and Testing Plan for No Objection and agreement on the
requirements with Ashghal.
A final Inspection and Testing Plan shall be submitted at least three (3) months prior to commencement of
the Acceptance Tests.
Page 7 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Upon request of the Ashghal, factory inspection shall be arranged by the Project Company for Ashghal
personnel and Ashghal. The Project Company shall bear all associated costs for travelling, accommodation
and subsistence.
It shall be the sole discretion of Ashghal to nominate his inspection team of up to four (4) persons per factory
visit and it shall be the full responsibility of the Project Company to make all necessary logistic arrangements
for a factory inspection and to submit the detailed factory inspection programme at least ten (10) weeks
before the scheduled inspection with Ashghal.
Before dispatching to the Project Site and the commencement of the applicable factory acceptance test,
selected items of equipment identified jointly by the Project Company and Ashghal:
shall be inspected or tested at the manufacturer's factory on a test-rig set up to simulate the defined
operating parameters for such equipment (including major pumps, the aerators and other major
equipment between Project Company and Ashghal); or
shall be inspected at the manufacturer's factory in those cases where it is not possible to test operate at
the manufacturer's factory in order to ensure they confirm to the given specifications.
The results of the model shall comply with internationally recognized and best practice tools with the results
certified by an appropriately qualified person. The testing shall comprise comparison of monitored levels at
the key locations against the Guaranteed Output Performance Requirements in Schedule 6. Spot checks at
the boundary of the Project Site may also be carried out at the request of Ashghal.
The testing shall establish for each odour emission point agreed with compliance with the specifications
related to odour in the Guaranteed Output Performance Requirements in Schedule 6.
Page 8 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Page 9 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
2. Inspections
Page 10 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
3. Pre-Commissioning
Page 11 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Within five (5) Business Days following the delivery of such notice, the hydrostatic and process validation
tests shall be started. The testing shall be undertaken using potable water (or existing treated effluent with
appropriate standard) to ascertain the respective hydrostatic performance of the applicable equipment and
the reliability of all equipment, systems and facilities.
The Project Company shall comply with the following requirements in the performance of the hydraulic test:
testing water used during the test shall be re-circulated through the Project Assets via the multi-
purpose lagoons.
testing shall occur continuously at the design peak flow rate, including peak design recycle and
recirculation flow rates, for a duration of eight (8) hours to demonstrate that the Project Assets
performs at the hydraulic profile provided in the design.
the Project Company shall make up clean water lost to evaporation as necessary.
Page 12 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Hydrostatic tests shall be tested for all liquid retaining assets that form part of the Project Assets. If
necessary, the Project Company shall conduct two separate tests, each of at least eight (8) hours in
duration.
Page 13 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
4. Commissioning
Page 14 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Page 15 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Ashghal shall have five (5) Business Days to submit any comments on such plan and method. The Project
Company shall incorporate any such reasonable requests and re-issue the final Commercial Operation
Testing Plan. The Project Company shall implement and comply with such final Commercial Operation
Testing Plan in accordance with this Schedule 3 – Acceptance and Availability Test Requirements.
Page 16 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
A separate protocol for Commercial Operation Testing for Kahramaa Facilities shall be developed by the
Project Company as per the Kahramaa specifications, requirements and procedures. Project Company shall
carryout the necessary due diligence with Kahramaa prior to finalising such test requirements. Final agreed
Commercial Operation Testing procedure for Kahramaa Facilities shall be provided to Kahramaa and
Ashghal.
The Project Company shall not commence the Commercial Operation Testing until all treatment and
ancillary processes, including biological processes, reach stable operation conditions.
During the Commercial Operation Testing period, the instantaneous flow and the daily total flow for foul
sewage shall be continuously monitored by and recorded as per Schedule 7- Metering and Monitoring
Requirements.
Similarly Sludge quantities shall be monitored and recorded as per Schedule 7- Metering and Monitoring
Requirements.
Sampling shall be taken in accordance with Schedule 7- Metering and Monitoring Requirements) and tested
by institutions which are licensed to perform the particular tests and approved or agreed by Ashghal. All
instruments used during the Commercial Operation Testing shall be calibrated in accordance with
manufacturer’s requirements.
Page 17 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
The performance tests are carried out to demonstrate that the performance of the Shared Facilities and STW
Facilities meets or exceeds the Guaranteed Output Performance Requirements specified in Schedule 6 -
Guaranteed Output Performance Requirements.
During the Commercial Operation Testing, the Shared Facilities, Kahramaa Facilities and STW Facilities
shall operate as a complete unit and all equipment shall run under conditions as close as practicable to
specified load conditions.
No temporary equipment shall be allowed to operate during Commercial Operation Testing. The Commercial
Operation Testing shall be repeated in its entirety at the Project Company’s expense if the test fails or if the
Project Company is forced to use any temporary equipment to maintain operation.
If the Influent to the Project Assets is below the design capacity of the Project Assets, the Project Company
may, undertake the Commercial Operation Testing on a train/line-by-line basis, operating at one hundred
percent (100% of the proportionate capacity of each such line) in agreement with Ashghal.
If available and if Influent flow and load are below maximum design levels at the time of testing, selected
treatment process and ancillary systems shall be taken out of service during the Commercial Operation
Testing so that the treatment process and ancillary systems remaining in service are operated at maximum
design flow and loading conditions throughout the Commercial Operation Testing period.
All treatment process and ancillary systems within the Shared Facilities and STW Facilities shall be tested
during the Commercial Operation Testing.
Any systems taken out of service at the start of testing shall be put in service at some point during testing, for
a period of at least seven (7) days, while maintaining maximum design flow and loading conditions in all
operating systems.
After stable operation is reached, the Project Company shall perform the Commercial Operation Testing for
a continuous thirty (30) day Commercial Operation Testing period to demonstrate that the Shared Facilities,
and STW Facilities can meet the Guaranteed Performance Output Requirements set out in Schedule 6
without interruption over the full range of Influent flows and loads received at the STW Facilities, including
the flows from the MTS and tankered Influent.
The Commercial Operation Testing shall continue until such a time that the Guaranteed Performance Output
Requirements as set out in Schedule 6 are met continuously for the specified period. Failure to satisfy any
one of the requirements or test criteria will constitute failure of the entire test period. Minimum (not
exhaustive) success criteria for the Commercial Operation Testing, in addition to achieving the Guaranteed
Output Performance Requirements as set out in Schedule 6, for all the Project Assets and Kahramaa Facilities
are shown in Table 1 below.
Table 1: Minimum Success Criteria for the Commercial Operation Tests – Project Assets
Shared Facilities Criteria
Terminal Pumping Station Continuous operation of the Screen Shaft and Pump Shaft in automatic mode without
interruption in full design flow and load
i. Screen Shaft
ii. Pump Shaft Certain specified individual equipment items have been in continuous operation without
interruption
Automatic changeover of duty/standby units in the event of failure of the duty unit during
the continuous operation verified
Display of all the monitoring parameters at the plant console and SCADA verified
Ability of the TPS to react in the desired manner if Influent Excuse Event is detected
Ability to react in the desired manner when fault conditions are detected or reported is
verified
Page 18 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
TSE Pump Station Continuous operation of the TSE Pump Station in automatic mode without interruption in
full design flow and load capacity
Certain specified individual equipment items have been in continuous operation without
interruption
Automatic changeover of duty/standby units in the event of failure of the duty unit during
the continuous operation verified
Display of all the monitoring parameters at the plant console and SCADA verified
Ability to react in the desired manner when fault conditions are detected or reported is
verified
Liquid Treatment Facilities Continuous operation of the Liquid Treatment Facilities in automatic mode without
interruption in full design flow and load capacity
Certain specified individual equipment items have been in continuous operation without
interruption
Automatic changeover of duty/standby units in the event of failure of the duty unit during
the continuous operation verified
Display of all the monitoring parameters at the plant console and SCADA verified
Ability to react in the desired manner if Off Specification Influent or TSE that does not satisfy
the Influent Quantity and Quality Requirements is detected.
Ability to react in the desired manner if Off Specification TSE that does not satisfy the
Influent Quantity and Quality Requirements set out in Schedule 5 is detected
Ability to react in the desired manner when fault conditions are detected or reported is
verified
TSE quality is in accordance with the Guaranteed Output Performance Requirements set out
in Schedule 6
Sludge Treatment Facilities Continuous operation of the Sludge Treatment Facilities in automatic mode without
interruption in full design flow and load capacity
Certain specified individual equipment items have been in continuous operation without
interruption
Automatic changeover of duty/standby units in the event of failure of the duty unit during
the continuous operation verified
Display of all the monitoring parameters at the plant console and SCADA verified
Ability to react in the desired manner when fault conditions are detected or reported is
verified
Environmental Criteria
Requirements
Odour, Noise, Air Emissions Output compliance with the Guaranteed Output Performance Requirements set out at
and By-products Schedule 6.
Page 19 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Continuous operation of the facilities in automatic mode without interruption in full design
flow and load capacity
Certain specified individual equipment items have been in continuous operation without
interruption
Automatic changeover of duty/standby units in the event of failure of the duty unit during
the continuous operation verified
Display of all the monitoring parameters at the plant console and SCADA verified
Ability to react in the desired manner when fault conditions are detected or reported is
verified
Failure to meet any of the above criteria on any Day shall deem that particular Day to have "failed" (a Failed
Output Day). If more than two Failed Output Days occur during the Commercial Operation Testing period
shall be restarted.
The Project Company shall provide a daily report to Ashghal stating for such Day:
the daily total flow and instantaneous flow;
the results from the sampling and analysis of the output; and
the reasons for any output that does not comply with Guaranteed Output Performance Requirements
set out in Schedule 6 - Guaranteed Output Performance Requirements
Kahramaa Facilities Commercial Operation Testing for Kahramaa Facilities shall be as per Kahramaa
approved methodology and criteria.
All the electrical equipment and systems shall be installed and tested as per Good
Utility Practice and shall be fit for purpose.
Carryout all the necessary current and voltage measurements for the continuation
of energization of the substation to the satisfaction of Kahramaa.
Page 20 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Within ten (10) Business Days after the completion of any test, the Project Company shall compile and
provide to Ashghal a separate Commercial Operation Test Report for Project Assets describing the details,
as per the requirements in section 2.2.17.3 of Schedule 9 – Reporting and Submission Requirements. The
test report shall summarize the results of such test, including all information reasonably necessary to
evaluate the applicable results.
As far as applicable, Ashghal shall notify the Project Company within five (5) Business Days after receiving
each such test report whether it accepts or rejects that such test report is accurate, provided that if it rejects
such test report it shall provide detailed reasons therefore.
The failure of Ashghal to respond within such five (5) Business Days, unless extended by mutual agreement,
shall be deemed No-Objection to the test report.
If Ashghal rejects the test report submitted by the Project Company, Ashghal may request that the Project
Company repeat the relevant testing as soon as practicable thereafter. Failure to resolve such a dispute as to
the need to repeat the relevant Commercial Operation Test within thirty (30) Days of receipt of the test report
shall be referred to the Independent Expert for decision in accordance with clause 23.2 of the Agreement.
Upon the No-Objection of the test report for each of the Project Assets, Ashghal shall promptly issue an
Acceptance Certificate for that Project Asset.
Page 21 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
If Ashghal and the Project Company cannot agree on whether the Project Company has achieved Completion,
either Party may refer the dispute for decision by the Independent Expert in accordance with clause 23.2 of
the Agreement.
Upon receipt of the No-Objection, deemed No-Objection, or decision of the Independent Expert (whichever
is earliest) to the Completion Notice, Ashghal shall promptly issue a Commercial Operation Certificate to the
Project Company.
The Commercial Operation Period shall commence on the date immediately following such date of the
Commercial Operation Certificate, and this shall be known as the Project Commercial Operation Date.
Page 22 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
6. Availability Testing
Availability is the existence and availability of the designed capacity of the Project Assets to receive designed
flows and loads and carry out its intended functions in a safe and efficient manner to achieve its Guaranteed
Output Performance Requirements.
Availability Testing shall be scheduled to be carried out on all the Project Assets. Tests shall be conducted
on all assets at least one (1) time each Contract Year commencing from the Project Commercial Operation
Date.
In addition to the regularly scheduled annual Availability Tests, the Project Company shall be required to
conduct Availability Testing where more than two (2) discharges or Influent or TSE are made to a Diversion
Outflow within a Contract Year, other than as a result of an Influent Excuse Event, Ashghal Risk Event or
Force Majeure Event.
Availability Testing shall be conducted in accordance with this Schedule 3 (Availability and Acceptance Test
Requirements) and Schedule [7] (Metering and Monitoring Requirements) and to demonstrate that one or
all of the Project Assets;
(i) achieve the design data given in Schedule 2-(Design and Construction Requirements) and Schedule
5 (Influent Quantity and Quality Requirements)
(ii) are ready for use; and
(iii) are able to meet all applicable Guaranteed Output Performance Requirements set out in Schedule
6.
Availability Testing shall comprise the following.
1) Asset Inspection Survey, as defined below at section 6.1; and
2) Availability Performance Test, as defined below at section 6.2.
Following the successful completion of the condition assessment of the Project Assets, the Availability
Performance Test of the Project Assets shall be commenced.
The Availability Performance Tests shall be for the purpose of proving the operational performance of the
Project Assets under normal operating conditions in accordance with the Availability Testing procedures.
Page 23 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Item Capacity
design flows and loads The ability of all the Project Assets to receive the design flows
and loads and perform in the way it is intended to perform.
Guaranteed Output Performance Requirements The ability of the Project Assets to achieve the requirements
Guaranteed Output Performance Requirements set out in
Schedule 6
Page 24 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
If the inflow to the Project Assets as at the date of the relevant Availability Test is below the quantities and
qualities stipulated in Schedule 5 (Influent Quantity and Quality Parameters), the Project Company shall
agree with Ashghal and undertake the Availability Performance Test on a train/line-by-train/line basis,
operating at one hundred percent (100%) of the relevant capacity of each such train/line. If the Influent
quality parameters set out in Schedule 5 (Influent Quantity and Quality Parameters) are not met, the Project
Company shall provide correction curves to be non-objected by Ashghal.
During the testing period:
(a) the Project Asset being tested, and its related equipment and systems shall be operated
continuously and in accordance with the prevailing influent flow and load conditions and Good
Utility Practice;
(b) the Project Company shall monitor and check all equipment at regular intervals in accordance with
the checklists established in the Availability Testing procedures and record all operation data; and
(c) as required by the test program, and in agreement with Ashghal, the plants and equipment that are
part of the Project Assets may be stopped and the function may be taken over by stand-by plant or
equipment; such scheduled operation of stand-by units shall be strictly performed in compliance
with the operation manuals.
During the Availability Performance Test of the Project Assets, the instantaneous flows and the daily total
flows shall be continuously monitored and recorded by Metering and Monitoring System. Similarly sampling
and testing shall be taken in accordance with Technical Schedule 7 (Metering and Monitoring
Requirements) and tested by third party institutions which are licensed to perform the particular tests and
shall be approved by Ashghal.
For the avoidance of doubt, during the Availability Testing, samples shall be collected and tested in
accordance with Schedule 7 and the results of the Availability Tests shall demonstrate output compliance
with the Guaranteed Output Performance Requirements set out in Schedule 6. Otherwise, a failure of the
Availability Tests shall be recorded for the Project Asset being tested.
The costs of carrying out the Availability Testing including overheads related to staff, electricity, water, other
utilities and any chemicals and fuel required in the process shall be borne by the Project Company, except in
circumstances provided in the Agreement at clause 5.14(b)(ii).
Any Non – complaint TSE produced prior to PCOD shall also not be disposed outside the Project Site, TSE
Network and Deep Injection Wells. The Project Company shall also bear all the costs related to recirculating
and re treatment of the non-compliant TSE. The Project Co. shall also borne all the costs to related to cleaning
and reinstate the storage facilities if used for storage of non-complaint TSE prior to PCOD.
Page 25 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
defects observed during the inspection such that the safe operation of the equipment during Availability
Performance Tests would be adversely affected.
The Project Company shall agree with Ashghal a reasonable time and duration for rectifying the identified
defect and reschedule the Asset Inspection Survey.
If Ashghal and the Project Company cannot agree on whether the test report is accurate, either Party may
refer the dispute for decision by the Independent Expert in accordance with clause 23.2 of the Agreement.
Page 26 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
A.1 General
This section specifies the minimum requirements of tests that are to be considered by Project Company during
Commercial Operation Testing that is required for Secondary Treatment Facilities. However, the testing
requirements shall as per Commercial Operation Testing Plan agreed between the Parties.
Page 27 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Page 28 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
B.1 General
This section specifies the minimum requirements of functional testing and Commercial Operation Testing that
is required for membrane filtration technology be selected for tertiary treatment.
Page 29 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
C.1 General
This section specifies the minimum requirements of Commercial Operation Testing that is required for odor
systems.
Page 30 Rev 0