Professional Documents
Culture Documents
Definitions
Acceptance Testing has the meaning as defined in the Agreement
Acceptance Tests has the meaning as defined in the Agreement
Agreement has the meaning as defined in the Agreement
CHAZOP Study Report has the meaning as defined in Schedule 2 Design and Construction Requirements
and Schedule 9 reporting and Review Requirements
has the meaning as defined in Schedule 3 Acceptance and Availability Tests
Commercial Operation Test Plan
Requirements
has the meaning as defined in Schedule 3 Acceptance and Availability Tests
Commercial Operation Test Report Requirements
Commercial Operation Testing has the meaning as defined in the Agreement
Commercial Operation Testing Plan has the meaning as defined in the Agreement
Commercial Operation Period has the meaning as defined in the Agreement
has the meaning as defined in Schedule 3 Acceptance and Availability Tests
Commissioning Requirements
has the meaning as defined in Schedule 3 Acceptance and Availability Tests
Commissioning Plan Requirements
has the meaning as defined in Schedule 3 Acceptance and Availability Tests
Commissioning Report Requirements
Construction Drawings has the meaning as defined in the Agreement
has the meaning as defined in Part 1, Project Overview and Design Requirements
Construction Plan
Schedule 2 Design and Construction Requirements
Construction Programme has the meaning as defined in the Agreement
means the reports prepared and submitted by Project Company pursuant to section
2.2.12 of Schedule 9 – Reporting and Submission Requirements, in accordance
with the requirements stipulated in section 4.14 of part 1, Project Overview and
Design Requirements, Schedule 2 Design and Construction Requirements and any
monthly updates of such reports and any other obligations set out elsewhere in the
Construction Reports Agreement.
has the meaning as defined in part 1, Project Overview and Design Requirements,
Contingency Event Schedule 2 Design and Construction Requirements and Schedule 4 Service
Requirements
Contingency Plan has the meaning as defined in Schedule 2 Design and Construction Requirements
CPL Corrosion Protection Lining
Daily Availability Reports has the meaning as defined in Schedule 7 Metering and Monitoring Requirements
Page 1
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Daily Operating Reports has the meaning as defined in Schedule 9 Repairing and Submission Requirements
has the meaning as defined in Part 1 Project Overview and Design Requirements,
Design Management Plan Schedule 2 Design and Construction Requirements
Detailed Project Report has the meaning as defined in the Agreement
Disposal Management Plan has the meaning as defined in Schedule 4 Service Requirements
Disposal Management Service has the meaning as defined in Schedule 4 Service Requirements
Environmental and Social Management Plan has the meaning as defined in Schedule 2 Design and Construction Requirements
and Schedule 9 Reporting and Submission Requirements
has the meaning as defined in Schedule 2 Design and Construction Requirements,
Schedule 4 Services Requirements and Schedule 9 reporting and Review
Environmental Management Plan Requirements
has the meaning as defined in Schedule 2 Design and Construction Requirements,
Environmental Management System Schedule 4 Services Requirements and Schedule 9 reporting and Review
Requirements
Expansion Phases has the meaning as defined in the Agreement
Final Handback Report has the meaning as defined in the Agreement
Good Utility Practice has the meaning as defined in the Agreement
GOPR Adherence Report has the meaning as defined in the Schedule 6 Guaranteed Output Performance
Requirements and Schedule 9 Review and Submission Requirements
Governing Laws has the meaning as defined in the Agreement
Competent Authorities has the meaning as defined in the Agreement
Guaranteed Output Performance
Requirements has the meaning as defined in the Agreement and Schedule 6 Guaranteed Output
Performance Requirements
Handback Testing Report has the meaning as defined in the Agreement
Handback Transition Plan has the meaning as defined in the Agreement
HAZOP Hazard and Operability Study
HAZOP Study Report has the meaning as defined in Schedule 2 Design and Construction Requirements
and Schedule 9 reporting and Review Requirements
Health and Safety Management Plan has the meaning as defined in Schedule 4 Service Requirements
Initial Handback Report has the meaning as defined in the Agreement
Inspection and Testing Plan has the meaning as defined in the Agreement
Kahramaa Facilities has the meaning as defined in the Agreement
Laws has the meaning as defined in the Agreement
Major Equipment has the meaning as defined in the Agreement
Metering and Monitoring System has the meaning as defined in the Agreement
Monthly Operating Reports
has the meaning as defined in the Agreement
Odour Management Plan has the meaning as defined in Schedule 4 Services Requirements
has the meaning as defined in Schedule 3 Acceptance and Availability Tests
Pre-Commissioning Plan Requirements
has the meaning as defined in Schedule 3 Acceptance and Availability Tests
Pre-Commissioning Report Requirements
Project Assets has the meaning as defined in the Agreement
Project Commercial Operation Date has the meaning as defined in the Agreement
Project Company has the meaning as defined in the Agreement
Project Site has the meaning as defined in the Agreement
QCS 2014 Qatar Construction Specification 2014
QSDDM Qatar Sewerage and Drainage Design Manual
Page 2 Rev 0
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Reviewable Data has the meaning as defined in section 2.1 and 3.1 of Schedule 9 Reporting and
Submission Requirements
Schedules has the meaning as defined in the Agreement
Service has the meaning as defined in Schedule 4 Service Requirements
Shared Facilities has the meaning as defined in the Agreement
Shared Facility Output Performance
requirements has the meaning as defined in Schedule 11 Payment Mechanism
Staffing Plan has the meaning as defined in Schedule 4 Service Requirements and Schedule 9
Review and Reporting Requirements
STW Facilities has the meaning as defined in the Agreement
Third Parties has the meaning as defined in the Agreement
TPS has the meaning as defined in the Agreement
has the meaning as defined in Part 1 Project Overview and Design Requirements,
Traffic Management Plan - construction
Schedule 2 Design and Construction Requirements
Traffic Management Plan - services has the meaning as defined in Schedule 4 Services Requirements
Page 3 Rev 0
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
1. General
The Project Company shall prepare and maintain records for the Project Assets and Kahramaa Facilities,
and shall supply information to Ashghal, at such a time and in a format specified by Ashghal. The
exhaustive list of required records and details shall be agreed with Ashghal.
The Ashghal to receive, review and approve the Reviewable Data defined in this Schedule 9 – Reporting
Requirements and any relevant explanatory documents.
In the event that Ashghal instructs the Project Company to undertake one or more Expansion Phases
pursuant to clause 7.2 of the Agreement, the Project Company shall comply with this Schedule 9 -
Reporting and Submission Requirements for each of the Expansion Phases as applicable.
Page 4 Rev 0
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Page 5 Rev 0
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Table 1 Reviewable Data Relating to the Project Assets and Kahramaa Facilities
Item of Submission Required date Latest time that Minimum frequency updates Recipient Purpose of
Reviewable Data Details of first specific Reviewable (in addition to when revised submission
(reference submission (no Data item must be at the initiation of the (information / No
in this later than) provided Project Company) Objection)
Schedule)
Design Management 2.2.1 60 days from 90 days from Effective N/A Ashghal No Objection
Plan Effective Date Date
Detailed Project Report 2.2.2 120 days from 180 days from Effective N/A Ashghal No Objection
Effective Date Date
Construction Plan 2.2.3 75 days from the 180 days from Effective On material changes and to maintain Ashghal No Objection
Effective Date Date consistency with the Construction
Programme
Contingency Plan for 2.2.5 N/A 180 days from Effective Annual until the Commercial Ashghal Information
Construction Period Date Operations Date
Quality Management 2.2.6 60 90 days from Effective Annual until the Commercial Ashghal Information
Plan – Construction Date Operations Date
(including certification
of the Quality
Management System)
Environmental 2.2.7 60 90 days from Effective Annual until the Commercial Ashghal Information
Management Plan - Date Operations Date
Construction (including
certification of the
Environmental
Management System)
Health and Safety 2.2.8 60 90 days from Effective Annual until the Commercial Ashghal Information
Management Plan - Date Operations Date
Construction (including
certification of the
Page 6 Rev 0
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Item of Submission Required date Latest time that Minimum frequency updates Recipient Purpose of
Reviewable Data Details of first specific Reviewable (in addition to when revised submission
(reference submission (no Data item must be at the initiation of the (information / No
in this later than) provided Project Company) Objection)
Schedule)
Traffic Management 2.2.9 60 90 days from Effective Annual until the Commercial Ashghal Information
Plan - Construction Date Operations Date
HAZOP and CHAZOP 2.2.10 N/A Prior to the construction N/A Ashghal Information
Study Reports commencement
Construction Drawings 2.2.11 N/A Prior to the construction N/A Ashghal No Objection
commencement
Construction Reports 2.2.12 End of the first 7 days after the last day of Monthly Ashghal Information
calendar month the period to which it
following the Works relates
Commencement
Date
Progress Meeting 2.2.13 N/A 7 days from the date of the Monthly Ashghal Information
Minutes meeting
Visual records of Works 2.2.14 One month after N/A Monthly Ashghal Information
progress Works
Commencement
Date
As-Built Drawings & As- 2.2.15 N/A Prior to the start of testing N/A Ashghal No Objection
Built Drawings Register and commissioning
Inspection and Testing 2.2.16 Three months before 10 Business Days prior to N/A Ashghal No Objection
Plan start of testing and the commencement of any
commissioning applicable testing
Page 7 Rev 0
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Item of Submission Required date Latest time that Minimum frequency updates Recipient Purpose of
Reviewable Data Details of first specific Reviewable (in addition to when revised submission
(reference submission (no Data item must be at the initiation of the (information / No
in this later than) provided Project Company) Objection)
Schedule)
Acceptance Testing 2.2.17 Within five (5) Ten (10) business days N/A Ashghal No Objection
Reports business days upon upon completion of the
completion of the tests
tests
Availability Testing 2.2.18 Within five (5) Ten (10) business days N/A Ashghal No Objection
Reports business days upon upon completion
completion
Page 8 Rev 0
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Page 9
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Page 10
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Page 11
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Project Commercial Operation Date for Project Assets and Kahramaa Facilities. The Contingency Plan
for construction period shall include a plan of how the Project Company shall inform Ashghal of
emergencies.
The Contingency Plan for construction period shall set out detailed procedures, allocation of resources
and personnel to manage such incidents or events that have or may present the potential to significantly
affect the activities or personnel of Ashghal or the Project Company, the public or the environment.
2.2.6 Quality Management Plan – Construction (including certification of the Quality
Management System)
The Quality Management Plan shall set out the policies, guidelines and procedures to be followed by the
Project Company in undertaking the Project and shall be in accordance with required Approvals, and
Good Utility Practices.
(i) mitigation measures preventing any accidents to personnel working on the Project Site
and any other persons that may be affected by construction activities,
Page 12
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
For the avoidance of doubt, the Project Company shall obtain any necessary approvals from relevant
authorities for road closures or diversions and provide appropriate traffic control or diversion signs if
needed.
2.2.10 HAZOP and CHAZOP Study Reports
2.2.10.1 HAZOP Study Report
The HAZOP study shall be carried out in accordance with the requirements set out in Schedule 2 design
and Construction Requirements and Good Utility Practice.
Project Company shall prepare and submit a HAZOP Study Report in the agreed format and content
with Ashghal. The Report shall minimum contain the study methodologies, recommendations suggested
by different parties and final list of recommendations that are implemented and considered for
implementation.
Project Company shall prepare and submit a CHAZOP Study Report in the agreed format and content
with Ashghal. The Report shall minimum contain the study methodologies, recommendations suggested
by different parties and final list of recommendations that are implemented and considered for
implementation.
2.2.11 Construction Drawings
The Construction Drawings shall include but not limited to the following:
site boundary and layout drawings;
general arrangement drawings;
hydraulic profiles;
process and instrumentation diagrams;
process flow diagrams and mass balance;
structural detail drawings;
architectural and building detail drawings;
mechanical and electrical equipment installation drawings;
piping drawings;
site services and ducting drawings;
electrical single line diagrams;
map of pipeline and approved traffic access; and
any other drawings or diagrams necessary for Construction.
The drawings shall be both digital and paper to suitable scales and shall include appropriate narrative
in accordance with international standards. All drawings shall follow the International System of units
(SI) with all measurements and dimensions quoted in SI units.
The Project Company shall keep a register of all construction drawings and shall ensure that the register
is complete and up-to-date at all times including the latest revision of all drawings. The drawings
register shall be laid out in a systematic and logical manner to facilitate the identification of drawings.
Page 13
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
The digital photographs shall be clear and shall not be retouched. The photographs shall not be supplied
to any third parties without the written permission of Ashghal.
The Project Company shall submit the photographs pursuant to requirements set out in section 5.16,
Part 1 Project Overview and Design Requirements, Schedule 2 Design and Constructions Requirements.
Page 14
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Inspections
Pre-Commissioning Plan
Commissioning Plan
Commercial Operation Testing Plan
The submission of the subsidiary plans shall comply with the requirements set out in Schedule 3 –
Testing and Commissioning Requirements and Schedule 7 – Metering and Monitoring Requirements.
The Inspection and Testing Plan shall provide a comprehensive explanation of how the Project Company
will organize the inspection, pre-commissioning, Commissioning and Commercial Operation Testing of
the Project Assets and Kahramaa Facilities in accordance with Schedule 3 - Availability and Acceptance
Tests Requirements and Schedule 7 – Metering and Monitoring Requirements.
In addition to the general requirements, the Inspection and Testing Plan shall include, as a minimum:
Inspection and Test Plan showing all work required under the dry tests and wet tests have been
completed and the associated results;
All non-complying points and limitations arising from inspections and tests;
All formal commitments that are required from the suppliers and subcontractor(s) to rectify faults
found during the pre-commissioning;
Proof of compliance with statutory and regulatory requirements; and
Page 15
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Step by step chronological findings and incidents from the commencement to end of
Commissioning
Inspection and Test Plan showing all work required under Commissioning has been completed and
the associated results, including flows, pollutant loads, chemical and power consumption;
All non-compliance events and limitations arising from Commissioning
Proof of compliance with statutory and regulatory requirements;
Calibration certificates for equipment or instruments used for testing
Plant operating peculiarities and observations and
All recorded data taken during each stage of Commissioning.
All relevant information and experiences gained during these tests, including readings such as flow,
effluent quality, noise, odour, vibration, power consumption, shall be integrated into project documents
including operation and maintenance manuals, As-built drawings, P&I Diagrams, etc.
Upon completion of the Commercial Operation Testing, the Project Company shall prepare separate
Commercial Operation Test Report for Project Assets and Kahramaa Facilities describing and
documenting each test.
The report shall include at a minimum the following but not limited to the information below:
A certification stating that Commercial Operation Testing was conducted in accordance with the
Commercial Operation Test Plan.
Results of each performance test including a determination of the extent to which the Project Assets
and Kahramaa Assets comply with the Commercial Operation Testing, the Guaranteed Output
Performance Requirements and all other requirements under the Agreement.
Summary of the performance of the Project Assets and Kahramaa Facilities clearly showing the
required Guaranteed Output Performance Requirements and actual performance flows, chemical
and power consumption history of the Commercial Operation Testing, i.e. chronological diary of
findings and incidents including:
o logs of alarms and operator attendance;
o operating peculiarities and observations;
o results of any statutory testing and inspection; and
o modifications to the process operation.
All required data measured and recorded during the Commercial Operation Testing including all
laboratory analyses, chemical consumption, instrument calibrations, pressures and other
measurements. Copies of data sheets, log sheets, calculations, laboratory reports and test sheets
shall be provided.
Page 16
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Summary of performance of each component under Kahramaa Facilities and their compliance with
agreed performance requirements along with evidence of acceptance of such tests from Kahramaa
personnel shall be performed.
All necessary certifications relating to testing, evaluation, analyses and performance.
Record of all equipment failures, repairs and preventative maintenance.
Summary of all data and calculations demonstrating the ability of the Shared Facilities and STW
Facilities to meet the Guaranteed Output Performance Requirements
Any additional data reasonably requested by Ashghal to be included in such report.
After completion of Asset Inspection Survey, the Project Company shall submit to Ashghal a report
summarising the observation and results of the Asset Inspection Survey, including all information
reasonably necessary to evaluate the applicable results pursuant to the requirements set out in section
6.4.1, Schedule 3 – Acceptance and Availability Test Requirements.
Page 17
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Page 18
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Operation & 3.2.1 Twelve months Prior to Project Annual Ashghal No Objection
Maintenance prior to Project Commercial Operations
Plan Commercial Date
Operations Date
Asset 3.2.2 Twelve months Prior to the Project Annual Ashghal No Objection
Management prior to Project Commercial Operations
Plan Commercial Date
Operations Date
Asset Register 3.2.3 Three months Prior to the Project Annual Ashghal Information
prior to Project Commercial Operations
Commercial Date
Operations Date
Disposal 3.2.4 Three months Prior to the Project Annual Ashghal No Objection
Management prior to Project Commercial Operations
Plan Commercial Date
Operations Date
Odour 3.2.5 Three months Prior to the Project Annual Ashghal No Objection
Management prior to Project Commercial Operations
Plan Commercial Date
Operations Date
Page 19 Rev 0
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Item of Submission Required date Latest time that Minimum frequency Recipient Purpose of
Reviewable Details of first specific Reviewable updates (in addition submission
Data (reference in submission Data item must be to when revised at (Information / No
this Schedule) (no later than) provided the initiation of the Objection)
Ashghal)
Availability 3.2.6 Three months One month prior to start Annual Ashghal No Objection
Testing Plan prior to start of of Availability Tests
Availability Tests
Operation & 3.2.7 Twelve months Prior to issue of Annual Ashghal Information
Maintenance prior to the Handback Certificate
Requirements commissioning of
and Manuals Project Assets
Scheduled 3.2.8 Three months Prior to the Project Annual Ashghal Information
Maintenance prior to Project Commercial Operations
Programme Commercial Date
Operations Date
Capital 3.2.9 Three months Prior to the Project Ashghal Information
Maintenance prior to Project Commercial Operations
Programme Commercial Date
Operations Date
Contingency 3.2.10 Three months Prior to the Project Annual Ashghal No Objection
Plan prior to Project Commercial Operations
Commercial Date
Operations Date
Staffing Plan 3.2.11 Three months Prior to the Project Annual Ashghal Information
prior to Project Commercial Operations
Commercial Date
Operations Date
Quality 3.2.12 Three months Prior to the Project Annual Ashghal Information
Management prior to Project Commercial Operations
Plan - Services Commercial Date
(including Operations Date
Page 20
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Item of Submission Required date Latest time that Minimum frequency Recipient Purpose of
Reviewable Details of first specific Reviewable updates (in addition submission
Data (reference in submission Data item must be to when revised at (Information / No
this Schedule) (no later than) provided the initiation of the Objection)
Ashghal)
certification of
the Quality
Management
System)
Environmental 3.2.13 Three months Prior to the Project Annual Ashghal Information
Management prior to Project Commercial Operations
Plan – Services Commercial Date
(including Operations Date
certification of
the
Environmental
Management
System and
OEMP)
Health & Safety 3.2.14 Three months Prior to the Project Annual Ashghal Information
Management prior to Project Commercial Operations
Plan -Services Commercial Date
(including Operations Date
certification of
the H&S
Management
System)
Traffic 3.2.15 Three months Prior to the Project Annual Ashghal Information
Management prior to Project Commercial Operations
Plan - Services Commercial Date
Operations Date
Page 21
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Item of Submission Required date Latest time that Minimum frequency Recipient Purpose of
Reviewable Details of first specific Reviewable updates (in addition submission
Data (reference in submission Data item must be to when revised at (Information / No
this Schedule) (no later than) provided the initiation of the Objection)
Ashghal)
Other documents
Public Health 3.2.18 N/A Prior to the Project Monthly Ashghal Information
Declarations & Commercial Operations
register Date
Procedure for 3.2.19 N/A Prior to the Project Annual Ashghal No Objection
Medical Commercial Operations
Safeguards Date
Results of each 3.2.20 One week of the In the case of initial Once every three months Ashghal No Objection
planned and inspection, calibration, prior to the after COD
unplanned calibration or test start of Acceptance Tests
inspection, of a monitoring
calibration or device
test of the
Monitoring
Device
Page 22
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Item of Submission Required date Latest time that Minimum frequency Recipient Purpose of
Reviewable Details of first specific Reviewable updates (in addition submission
Data (reference in submission Data item must be to when revised at (Information / No
this Schedule) (no later than) provided the initiation of the Objection)
Ashghal)
Results of on- 3.2.21 N/A Prior to the start of Continuous Ashghal Information
line and periodic Acceptance Tests
tests as per
Metering
Monitoring
Systems
Handback 3.2.22 N/A Prior to Handback Period N/A Ashghal No Objection
Transition Plan Commencement Date
Initial 3.2.23 N/A 11 months prior to N/A Project Information and action
Handback completion of Term Company
Report
Final Handback 3.2.24 N/A No later than 30 days after N/A Project Information and action
Report completion of the Final Company
Handback Inspection
Page 23
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Page 24
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Page 25
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Page 26
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
details of security work to be carried out on vital installations and protection and surveillance on other
installations or facilities; and
details of suitably equipped permanent or mobile accommodation to act as command and control
centres.
The Project Company shall review and update the Contingency Plan on an annual basis on the anniversary
of the Project Commercial Operation Date.
3.2.11 Staffing Plan
The Staffing Plan shall demonstrate that the operators and maintenance personnel for the Services are in
sufficient number and are appropriately qualified, skilled and experienced in their respective trades or
occupations to perform the Services and fulfil the requirements of Project Company’s staffing as set out in
section 2.9 of Schedule 4 - Services Requirements.
3.2.12 Quality Management Plan – Services (including certification of the Quality Management
System)
The Quality Management Plan shall set out the policies, guidelines and procedures to be followed by the
Project Company in undertaking the Project and shall be in accordance with the requirements of quality
management set out in section 2.10.2 of Schedule 4 - Services Requirements, applicable Laws, Approvals,
and Good Utility Practice.
The Quality Management Plan shall as a minimum:
be structured so as to address issues related to the Project Assets;
detail all activities in each of the stages of the O&M Period; and
identify the individuals responsible for these activities.
include a Certification of Quality Management System
3.2.13 Environmental Management Plan - Services (including certification of the Environmental
Management System)
The Environmental Management Plan shall set out the policies, guidelines and procedures to be followed by
the Project Company in undertaking the Project and shall be in accordance with the requirements of
Environmental Management set out in section 2.10.3 of Schedule 4 - Services Requirements, applicable
Laws, Approvals, and Good Utility Practices. The Environmental Management Plan shall as a minimum:
be structured so as to address issues related to the Project Assets;
detail all activities in each of the stages of the Commercial Operation Period;
identify the individuals responsible for these activities; and
preparation of operational Environmental Management Plan (OEMP) in line with the requirements set
out in Section 1.10, Part 5 Environmental Requirements, Schedule 2 Design and Construction
Requirements and also based on compliance with MME requirements
include a certification of Environmental Management System by a recognised organization
3.2.14 Health and Safety Management Plan - Services (including certification of the H&S
Management System)
The Health and Safety Management Plan shall set out the policies, guidelines and procedures to be followed
by the Project Company in undertaking the Project and shall be in accordance with the requirements of
Health and Safety Management set out in Schedule 4 - Services Requirements, applicable Laws, Approvals,
and Good Utility Practices. The Health and Safety Management Plan shall as a minimum:
Page 28
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
(i) mitigation measures preventing any accidents to personnel working in the Project and any
other persons that may be affected by operations and maintenance activities,
(ii) mitigation measures preventing disturbance to the following as a minimum: third parties, and
operation of any components of the Project Assets required to achieve Guaranteed Output
Performance Requirements during the Commercial Operation Period
For the avoidance of doubt, the Project Company shall obtain any necessary approvals from relevant
authorities for road closures or diversions and provide appropriate traffic control or diversion signs if needed.
3.2.16 GOPR Adherence Reports
The Guaranteed Output Performance Requirements (GOPR) Adherence Report shall detail measurement of
the Project Company’s performance within the corresponding reporting period against each requirement
defined in Schedule 6 - Guaranteed Output Performance Specification. The frequency, format and details
shall be agreed with Ashghal.
3.2.17 Daily, Monthly and Quarterly Reporting Requirements
3.2.17.1 Daily Operating Reports
The daily operating reports should include the results of the daily online metering, monitoring and testing
as per the requirements set out in Schedule 7 Metering and Monitoring Requirements and as set out in any
other Schedules.
Further the Daily Operating Reports shall also stipulate details related to failed output from any of the Project
Assets such as listed below;
the daily quantity and quality of TSE that does not comply with quality requirements stipulated
Schedule 6 - Guaranteed Output Performance Requirements,
the daily quantity and quality of by Products that does not comply with the requirements stipulated
Schedule 6 - Guaranteed Output Performance Requirements,
the daily quantity of Shared Facility Output that fails the Shared Facility Output performance
requirements
any other details required to be included as may be agreed with Ashghal
The Project Company shall also provide Daily Availability Reports on a Daily basis in accordance with
requirements stipulated in section 1.5, Schedule 7 Metering and Monitoring Requirements.
Page 29
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
Page 30
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
arbitration proceedings relating to the Project have been commenced during the preceding reporting period
against the Project Company by any third-party or government agency, that it is in compliance with the
Project Company Undertakings at Clause 21.3 of the Agreement that it is in compliance with all applicable
Legal Requirements in accordance with Clauses 13.5 and 13.6, and that all Approvals required for the
operation of the Project Assets are valid and in effect. Ashghal reserves the right to add additional Legal and
Financial Reporting requirements as may be reasonably necessary to ensure Project Company's compliance
with the Agreement.
3.2.18 Public Health Declarations
All personnel employed by the Project Company, or any of the Project Company’s contractors, working in
contact with the Project Assets shall complete a public health declaration certificate confirming appropriate
medical clearance before the work commences. The Project Company shall maintain an up to date register
of personnel who have completed this declaration. The Project Company shall submit the register in the
Monthly Operating Reports. No employee of the Project Company or any of its contractors shall be permitted
to work at the Project Assets unless they have completed this health declaration certificate.
3.2.19 Procedure for medical safeguards
The Project Company shall develop a procedure for medical safeguards in line with applicable Laws and Good
Utility Practice and shall submit in the Monthly Operating Reports.
3.2.20 Results of each planned and unplanned inspection, calibration or test of the Monitoring
Device
The submission shall comply with the requirements set out in Schedule 7 – Metering and Monitoring
Requirements.
3.2.21 Results of on-line and periodic tests as per the Metering and Monitoring Systems
The submission shall comply with the requirements set out in Schedule 7 – Metering and Monitoring
Requirements.
3.2.22 Handback Transition Plan
The Handback Transition Plan shall comply with the requirements set out in Schedule 8 – Handback
Requirements.
3.2.23 Initial Handback Report
The Initial Handback Report shall comply with the requirements set out in section 2.3 of Schedule 8 –
Handback Requirements.
3.2.24 Final Handback Report
The Final Handback Report, if required, shall comply with the requirements set out in section 2.4 of Schedule
8 – Handback Requirements.
3.2.25 Handback Testing Report
The Handback Testing Report shall comply with the requirements set out in section 3.1 of Schedule 8 –
Handback Requirements.
Page 31
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
4. Reviewable Procedures
The provisions of this section 4 (Review Procedure) (the "Review Procedure") shall apply whenever any
item, documents or course of action are required to be submitted to Ashghal for No Objection.
4.1 General
Each submission under the Review Procedure shall be accompanied by a copy of the document to be
reviewed (including, where applicable, any Reviewable Data) or a statement of the proposed course of
action (the entire contents of a submission being referred to in this section as a "Submitted Item").
4.1.1 as soon as possible, and in any event within ten (10) Business Days of the date of Ashghal's
receipt of a Submitted Item, Ashghal shall return one (1) copy of the relevant submitted item to
the Project Company endorsed "No Objection" or "comments" as appropriate (subject to and in
accordance with this Review Procedure);
4.1.2 if Ashghal fails to return a copy of any Submitted Item (including any re-submitted Submitted
Item) duly endorsed in accordance with this section 4.1 within the time period required therefor,
Ashghal shall be deemed to have returned the submitted item to the Project Company endorsed
"No Objection";
4.1.3 if Ashghal raises comments on any Submitted Item in accordance with this section 4.1, Ashghal
shall state the ground upon which such comments are based and reasonable evidence or other
information reasonably necessary to substantiate that ground.
Page 32
Public Private Partnership Agreement - Al Wakra & Al Wukair Sewage Treatment Plant
If Ashghal returns the Submitted Item to the Project Company endorsed "comments", the Project Company
shall comply with such Submitted Item after amendment in accordance with the comments unless the Project
Company disputes that any such comment is on grounds permitted by this Agreement. Any Dispute arising
with respect to any such Submitted Item that cannot be resolved pursuant to Clause 23.1 of the Agreement
shall be referred to the Independent Expert for resolution pursuant to Clause 23.2 of the Agreement.
Page 33