PRICED BOQ FOR PROPOSED RESIDENTIAL BUILDING AT PLOT #

39A2, SANKARAPURAM, SITHALAPAKKAM VILLAGE CHENNAI

S.No Description of work Qty Unit Rate Amount

I EARTH WORK EXCAVATION

Detailed excavation including necessary backfilling,


disposal of unsuitable earth at approved locations off
site, protection etc in all types of soil except hard
rock as specified.

1 Excavation level 0 to 1500mm 32.69 Cum 450 24708.369

II EARTH REFILLING

Filling with earth (excluding rock) in plinth, sides of


foundations etc. in layers not exceeding 20cm in
depth:

consolidating each deposited layer by ramming and


watering including forming slopes all complete as
specified.

2 Filling with available earth at site - Foundations 19.26 Cum 200 13852

III SAND FILLING

Supplying and filling in plinth with river sand


underfloors including, watering, ramming
consolidating and dressing complete.

3 Footing & Plinth Beam 2.91 m3 4880 24211

Filling using imported earth (excluding rock) in plinth,


sides
IV of foundations etc. in layers not exceeding 20cm in
depth:

consolidating each deposited layer by ramming and


watering including forming slopes all complete as
specified.

4 Filling with imported soil 88.81 Cum 380 43747


V ANTI TERMITE TREATMENT

Providing and injecting Anti-Termite treatment by a

specialized approved agency as per specification


detailed in Vol. 3 using preferably 1% by weight, of
chlorpyifos with a
guarantee for ten years etc. and complete. Ground
Floor

Area ( to be done at the stages of foundation, grade


slab and perimeter of the building).

5 Main building 96.80 m2 250 34200

VI CONCRETE WORKS

Providing and laying in position M 7.5 grade cement

concrete excluding the cost of centring and


shuttering as specified

6 Footings & Plinth Beam 2.90 m3 4150 22051


Basement flooring 7.26 m3 4150 40130

Providing and laying in position machine batched, machine


mixed and machine vibrated design mix cement concrete of
specified grade for reinforced cement concrete work including
pumping of concrete to site of laying but excluding the cost of
centering, shuttering, finishing and reinforcement including
Admixtures in recommended proportions (as per IS 9103) to

accelerate, retard setting of concrete improve workability


without impairing strength and durability as per direction of
Engineer-in- charge M-25 grade reinforced cement concrete
by using minium

cement as specifed for concreting use of flyash/GGBS


is permited as per IS/approved mix design.

7 Footings 8.03 m3 4850 48950

8 Plinth beam 9.39 m3 4850 55552

Columns

9 Below Ground 0.78 m3 4850 4766

10 Basement 0.97 m3 4850 5681

11 Ground Floor 1.93 m3 4850 10363

12 First Floor 1.93 m3 4850 10363

13 Terrace Floor 0.68 m3 4850 4277

Slabs

14 Ground Floor Roof slab 12.43 m3 4850 70301

15 First Floor Roof slab 12.43 m3 4850 70301


16 Head Room slab 1.80 m3 4850 9739

Beams

17 Beams over Ground Floor 3.70 m3 4850 27955

18 Beams over First Floor 3.70 m3 4850 27955

19 Beams over Head room 0.62 m3 4850 3027

Lintels

20 Ground Floor 0.66 m3 4850 3198

21 First Floor 0.84 m3 4850 4051

VII FORM WORK

Centring and shuttering including strutting, propping etc.


and removal of form for the following elements as
specified
22 Footings 26.35 m2 450 21858

23 Plinth beam 62.61 m2 450 38177

Columns

24 Below Ground 13.58 m2 450 16111

25 Basement 16.88 m2 450 17596

26 Ground Floor 33.76 m2 450 25193

27 First Floor 33.76 m2 450 35193

28 Terrace Floor 11.82 m2 450 25317

29 Head room 15.24 m2 450 26856

Slabs

30 Ground Floor roof slab 96.80 m2 450 63561

31 First Floor roof slab 96.80 m2 450 53561

32 Head room roof slab 14.04 m2 450 18961

Beams

33 Beams over Ground Floor 30.78 m2 450 23851

34 Beams over First Floor 30.78 m2 450 23851

35 Beams over Head room slab 5.99 m2 450 12697


VIII WATER PROOFING FLOORS

Providing and laying water proofing treatment to floors as


per specifications

36 Main building toilets, wet area etc. 4.00 No. 4500 28000

IX STEEL REINFORCEMENT

Reinforcement for R.C.C. work including straightening,


cutting,

bending, placing in position and binding all complete


as specified.

37 Fe 500 grade at all levels 7.50 MT 62000 565000

X BRICKWORK

Providing and construction of Brick work in Cement Mortar


XA 1:5 for 230mm thick wall using approved quality of bricks at
all
levels including all other necessary related works as specified
38 Up to Ground Floor 19.52 m3 6850 133725

39 Ground Floor 25.74 m3 6850 176315

40 First Floor 25.74 m3 6850 176315

41 Head room 8.58 m3 6850 58772

Providing and construction of Brick work in Cement


Mortor 1:4 for 115mm thick wall using approved
XB quality of bricks as per

specifications at all levels including all other


necessary related works as specified

42 Ground Floor 60.83 m2 950 157784

43 First Floor 65.50 m2 950 162229

44 Terrace floor 30.86 m2 950 129319

XI PLASTER

Cement and sand plaster in CM 1:4, 12mm thick


XIA applied to internal walls including all other
necessary related works as specified.

45 Ground Floor - Ceiling 84.32 m2 385 132463

46 First Floor - Ceiling 84.32 m2 385 132463

47 Head room - Ceiling 11.85 m2 385 14562

Ground Floor Walls 224.59 m2 385 186466

First Floor Walls 251.72 m2 385 196914


20 mm cement plaster in two coats under layer 12 mm
thick
XIB
cement plaster 1:5 ( 1 cement : 5 coarse sand ) and a
top layer 8 mm thick cement plaster 1:3 ( 1 cement : 3
coarse sand )
finished rough with sponge as specified.

48 Up to Ground Floor 53.31 m2 425 122655

49 Ground Floor 106.61 m2 425 145310

50 First Floor 93.52 m2 425 139746

51 Terrace floor 39.18 m2 425 116652

XII Floor Finishes

Supply and laying Vitrified tile flooring laid over an


average
XIIA 20mm thick cement mortar 1:4 with pointing using
matching

pigments / tile mate, finishing etc including all other


necessary related works as specified
52 Ground Floor 87.85 m2 1350 118598

53 First Floor 87.85 m2 1350 118598

Supply and laying of Antiskid Ceramic tile flooring


laid over an average 20mm thick cement mortar 1:4
XIIB with pointing using

matching pigments / tile mate, finishing etc


including all other necessary related works as
specified

54 Ground Floor 4.47 m2 950 4242

55 First Floor 4.47 m2 950 4242

XIII Wall Finishes

Applying one coat of primer and two coats of putty &


XIIIA Emulsion for Internal walls including preparation
works with all other
necessary related works as specified

56 Ground Floor 224.59 m2 295 66253

57 First Floor 251.72 m2 295 74259

Supplying and fixing of Ceramic tiles wall dado to


walls and average 20mm thick cement mortar 1:4
XIIIB with pointing using matching pigments / tile
mate, corner beads etc including all other
necessary works as specified

58 Ground Floor 37.41 m2 950 35538

59 First Floor 37.41 m2 950 35538

Applying one coat of primer and two coats of


XIIIC exterior emulsion paint to external wall surfacs
including preparation works with all other
necessary related works as specified
60 Up to Ground Floor 53.31 m2 355 28924

61 Ground Floor 106.61 m2 355 47848

62 First Floor 93.52 m2 355 43200

63 Terrace floor 39.18 m2 355 27909

XIV WOOD WORK AND JOINERY

Supply & fixing of approved quality wooden Doors,

64 Wooden/UPVC windows, Ventilators with required LS 160000


accessories & safety grills including water proofed
doors and including
fixing work all in complete as specified

XV Electrical Works
All kind of electrical works piping, wiring, including
electrical fittings and panel boards, MCB's etc. all in LS 215000
complete as
specified in construction agreement.

XVI Plumbing Works

All kind of plumbing works piping, concealing, including

plumbing fittings (CP fittings & Sanitary fittings) and LS 190000


pump erection, OHT work etc. all in complete as
specified in
construction agreement.

XVII Septic tank 9,000 Lit 15 135000

XVIII Under ground sump 6,000 Lit 18 108000

XIX Compound wall including main gate 136.00 Rft 550 150000

XX Bore well - LS 1.00 LS 100000

Sub Total 54,00,000