Package: GS06 Balance Works as of 3/27/2024

STATUS
Item Description Done/Actual Balance Total Target completion date
1 Platform cutting (1400mm) 0 131 131
2 Drainage Gutter 0 126 126 type 1 30/5/24
3 Drip plate 0 126 0 Pending confirmation on the gap btwn t
4 Cover Plate (Chequered Plate) 0 131 131 Pending TWK gap filler
5 Evacuation Staircase 8 8 8
6 Pier Cleaning 10 131 131
7 Pier Marking 0 131 131
irmation on the gap btwn track plinth