RENCANA KERJA HARIAN (RKH)

SHIFT REPORT

PT. Bakti Pertiwi Nusantara Site Sepo PT. Djava Berkah Mineral
SHIFT 2 (Night Shift) 12/10/2022
SHIFT 1 PRODUCTION REPORT HEAVY EQUIPMENT & MANPOWER
ACTIVITY PLAN EXISTING UNIT ACH. (%) Model EQ Class Populasi RFU BD MP Deviasi
OB Removal (Bcm) 2.882 1.267 44 Exca 300 Loader 5 3 2 2 -3
Ore Getting (Ton) 2.880 2.174 75 Exca 200 Loader 7 5 2 5 -2
Hauling ETO- EFO (Ton) 2.765 1.113 40 DT 20 Ton Hauler 26 26 0 18 -8
Barging (Ton) 7.875 7.875 100 Dozer 85 SS Unit Support 2 2 0 1 -1
Breaker Unit Support 1 1 0 1 0
REVIEW SHIFT 1 PRODUCTION REPORT Grader Unit Support 2 1 1 1 0
ACTIVITY PLAN ACTUAL ACH. (%) Vibro Case Unit Support 2 2 0 1 -1
OB Removal (Bcm) 2.882 550 19 Fuel Truck Unit Support 2 2 0 1 -1
Ore Getting (Ton) 2.880 901 31 Water Truck Unit Support 1 1 0 1 0
Hauling ETO- EFO (Ton) 2.765 715 0
Barging (Ton) 5.250 0 0
Remarks : Update 10 Oktober (Shift 1)

REVIEW MONTHLY 1 PRODUCTION REPORT RAIN & SLIPPERY


ACTIVITY PLAN MTD ACTUAL MTD ACH. (%) ACTIVITY SHIFT 1 SHIFT 2 REMARK
OB Removal (Bcm) 50.548 8676 17 RAIN
Ore Getting (Ton) 60.279 7614 13 SLIPPERY
Hauling ETO- EFO (Ton) 28.537 5567 20 LOST TIME 07.00 - 09.00 ; 11.00 - 13.15 Breakdown PC300 (11) ; Oil
Barging (Ton) 31.500 0 0 REFUELING
Remarks : Update 10 Oktober (Shift 1) Remarks : Update 10 Oktober (Shift 1)

SHIFT 2 (Night Shift) 12/10/2022


ACTIVITY PIT_ID FLEET PLAN LOADER HAULER SUPPORT Note :
OB Removal Pit1_Timur 1 1 DX300 3 DT BREAKER *OVERSHIFT
Ore Getting Pit1_Utara 1 1 DX300 5 DT 2 PC200 *Selective Ore, Production
Hauling ETO-EFO ETO 1 1 DX300 10 DT (42,43,44,45,11)
Barging * OB Removal Pit 1 Timur 3 DT (Fuso)
Supporting GRADER VIBRO WT * Optional Hauling Priority, 10 DT (8 Mercy dan 2 Quester)
Piling Waste Dump 1 PC200 Dozer * Maintanance Hauling Road
Piling ETO 1 PC200 * Pengawas (PIT : Iswan; ETO EFO : Inal)
Piling EFO
Prepare Barging
General Area #CONDITIONAL