Working Hour Calculation CT Jumlah Jarak Kapasitas Produktivity (WMT)

Unit Job Efficiency


Planned Working Hour/Day 24.0 (Menit) pengisian (Meter) (WMT) Hr Day Mth
Change Shift (S) - PC 200 4.00 10 - 2 33% 100.00 800.00 20,000.00
Meal and Rest (S) 1.00 DT 10 R 12.00 200 18 33% 30.00 240.00 6,000.00
Safety Talk (S) -
P2H (S) -
Produksi
Alat Produksi
Transport (S) 0.50
Ore Getting Waste Removal
Hujan and Slippery (S) 1.00 Exc ETO
Repair (R) 1.00
Target Okt WMT/Mth WMT/day Exc Orget DT DT Exc Removal
Cofee break (S) 0.50 Ore 40,000 1,600
Shift/day 2.00 Waste 10,000 400 2 6 2 1 1
Day Work/Month 25.00 Matmov 50,000 2,000
Month Work/Year 12.00
Effective WH/Day 8.00
Effective WH/Month 200.0
Mech. Availability (MA) 89%
Phisical Availability (PA) 46%
Use Of Availability. (UA) 73%
Effective Utilization (EU) 33%

Kebutuhan unit
Exc 200 : 3 Unit
DT 10 R : 8 unit

Unit Support :
Dozer, Grader,
Compactor.