Professional Documents
Culture Documents
ITP 1 OF 8
INDICATIVE INSPECTION TEST PLAN FOR MECHANICAL WORKS TAN GOPALPUR
ITP 2 OF 8
INDICATIVE INSPECTION TEST PLAN FOR MECHANICAL WORKS TAN GOPALPUR
ITP 3 OF 8
INDICATIVE INSPECTION TEST PLAN FOR MECHANICAL WORKS TAN GOPALPUR
ITP 4 OF 8
INDICATIVE INSPECTION TEST PLAN FOR MECHANICAL WORKS TAN GOPALPUR
ITP 5 OF 8
INDICATIVE INSPECTION TEST PLAN FOR MECHANICAL WORKS TAN GOPALPUR
ITP 6 OF 8
INDICATIVE INSPECTION TEST PLAN FOR MECHANICAL WORKS TAN GOPALPUR
Correct positioning
alignments / levels
Supporting - Primary / Secondary 1.Piping layout
Online fittings , valves, traps, filters, Physical/ Visual 100% 2.P&ID P W,RAN - RPT Statutory approval, wherever applicable
Safety valve, NRV, orifice plates etc. 3.isometric drawing
Flow direction
provision of platforms & Ladders
Provision for cold pull, if any
ITP 7 OF 8
INDICATIVE INSPECTION TEST PLAN FOR MECHANICAL WORKS TAN GOPALPUR
LEGENDS
H - HOLD POINT( Further steps shall commence only after clearance from STL/TCE- as applicable)
M - MONITOR
NR - RECORDS OPTIONAL
P - PERFORM
R - REVIEW & APPROVE
RAN - RANDOM
RPT - REPORT
S - SUBMIT
TC - TEST CERTIFICATE
W - WITNESS & APPROVE
TPI - THIRD PARTY INSPECTION AGENCY
ITP 8 OF 8