You are on page 1of 2

ADANI TOTAL GAS -DRS NEW SITE QUANTITY

DATE-11/1/2024
SR
NO DESCRIPTION NO L W H QTY UNIT TOTAL QTY UNIT
1 EXCAVATION
SOUTH 1 19.95 1.695 0.8 27.0522 CUM
WEST 1 21.35 1.15 0.8 19.642 CUM
EAST 1 19.45 1.695 0.8 26.3742 CUM
NORTH 1 16.75 2.24 0.8 30.016 CUM
FOOTING 4 0.75 2.24 0.95 6.384 CUM
FOOTING 5 0.75 1.695 0.95 6.038438 CUM
FOOTING 5 0.75 1.695 0.95 6.038438 CUM
FOOTING 6 0.75 1.15 0.95 4.91625 CUM
126.461525 CUM

1 STONE MASONARY
1 20.5 0.6 0.1 1.23 CUM
2 19.3 0.6 0.1 2.316 CUM
1 16.25 0.6 0.1 0.975 CUM
4.521 CUM
FOOTING 19 0.75 0.75 0.1 1.06875 CUM
5.58975 CUM

2 PCC
1 20.5 0.6 0.1 1.23 CUM
2 19.3 0.6 0.1 2.316 CUM
1 16.25 0.6 0.1 0.975 CUM
4.521 CUM
FOOTING 19 0.75 0.75 0.1 1.06875 CUM
5.58975 CUM
3 STRAP BEAM AND FOOTING
5 4.1 0.35 0.3 2.1525 CUM
4 0.75 0.75 0.3 0.675 CUM
5 4.125 0.35 0.3 2.165625 CUM
4 0.75 0.75 0.3 0.675 CUM
1 5.48 0.35 0.3 0.5754 CUM
3 3.72 0.35 0.3 1.1718 CUM
3 0.75 0.75 0.3 0.50625 CUM
5 4.1 0.35 0.3 2.1525 CUM
8 0.75 0.75 0.3 1.35 CUM
11.424075 CUM

4 BEAM FOOTING STEEL AND COLUMN STEEL UPTO TOP LEVEL


AS PER CALUCLATION SHEET 215.68 KG
372.22 KG
109.07 KG
491.25 KG 1.55482 MT
366.6 KG

5 SHUTTERING WORK
10 4.1 0.3 1 12.3 SQ.M
10 4.1 0.3 1 12.3 SQ.M
10 4.1 0.3 1 12.3 SQ.M
2 5.78 0.3 1 3.468 SQ.M
6 3.72 0.3 1 6.696 SQ.M
4 2.3 0.3 1 2.76 SQ.M
30 1.05 0.3 1 9.45 SQ.M
59.274 SQM

5 BRICKWORK
(below the ground level)(upto lintel level) 5 4.65 0.35 2.1 17.08875 CUM
5 4.65 0.35 2.1 17.08875 CUM
1 6 0.35 2.1 4.41 CUM
3 4.14 0.35 2.1 9.1287 CUM
5 4.55 0.35 2.1 16.72125 CUM

64.43745 CUM 64.43745 CUM


6 LINTEL CONCRETE
1 23.2 0.35 0.15 1.218 CUM
1 22.5 0.35 0.15 1.18125 CUM
1 22.5 0.35 0.15 1.18125 CUM
1 18.5 0.35 0.15 0.97125 CUM
4.55175 CUM

7 LINTEL STEEL

AS PER CALCULATION SHEET 456.48 KG 0.45648 MT

8 LINTEL SHUTTERING
2 23.2 0.15 1 6.96 SQM
2 22.5 0.15 1 6.75 SQM
2 18.5 0.15 1 5.55 SQM
2 22.5 0.15 1 6.75 SQM
26.01 SQM

9 COLUMN SHUTTERING
(UPTO GROUND LEVEL) 19 4 0.3 1.8 41.04 SQM
19 2 0.3 0.3 3.42 SQM 44.46 SQM

10 COLUMN CONCRETE
19 0.3 0.3 2.1 3.591 3.591 CUM

11 BACK FILLING(EARTH WORK)


1 126.4615 87.04103 39.4205 CUM 39.4205 CUM

You might also like