Daily Report For Installation
Daily Report For Installation
PERIOD
ACTIVITY
DATE 7/10/2023
PERIOD
ACTIVITY
DATE 7/13/2023
PERIOD
ACTIVITY
7/6/2023 DATE 7/
TIME SUPPORTING REMARK PERIOD
ACTIVITY
FROM TO STAFF
1. Main Panel , Furnance Panel and MTC placed as
Rohit
11:00 per marking layout for DCM 200 .
2. Furnance Rail , fixed with DCM 200 and Furnanc
11:30 12:00 Rohit
placed on Furnance Rail .
FIRST 3. Furnance panel connection done and connection
HALF tightness checked for DCM 200 .
12:00 12:30 Rohit
4. Main Panel , Furnance Panel and MTC placed as
per marking layout for DCM 160 .
5. Furnance Rail , fixed with DCM 160 and Furnanc
12:30 13:00 Rohit
placed on Furnance Rail .
8. Furnance panel connection done and connection
13:10 14:00 Rohit , Hemkaran
tightness checked for DCM 160 .
Rohit , Sanjay & 8. Furnance heater cover fixed for both DCM 160 &
14:10 15:10
kartik 200 .
Rohit , Sanjay & SECOND 9 . Hydraulic Oil filling done in power pack of DCM
15:10 16:00
kartik HALF 200 .
16:10 16:40 Rohit 10. Hydraulic oil filling done in power pack of DCM
160 .
16:40 17:15 Rohit , Sanjay
Rohit & Bhanu 2. Hose pipe fixed in inlet and outlet Header in DCM
12:30 13:30
Pratap 200.
FIRST
Rohit & Bhanu HALF
14:30 15:30 3.Water supply turn on to check for any leakage .
Pratap
7/7/2023 DATE
TIME SUPPORTING REMARK PERIOD
ACTIVITY ACTIVI
FROM TO STAFF
ance Panel and MTC placed as
10:00 11:00 Rohit 1. Control wiring and basic w
or DCM 200 .
ed with DCM 200 and Furnance 2. Main panel to DCM cable c
11:10 11:50 Rohit
Rail . gland fixed for DCM 160 .
nnection done and connection FIRST
12:00 12:50 Rohit 3.Cable tray marking done fo
r DCM 200 . HALF
ance Panel and MTC placed as Rohit sanjay & 4. cable tray laying done and
13:00 13:30
or DCM 160 . bhanu Pratap & 200 .
ed with DCM 160 and Furnance
13:30 14:00 Rohit 5. DB fixed for both DCM 16
Rail .
nnection done and connection
13:10 14:00 Rohit 6. Control wiring and basic w
r DCM 160 .
over fixed for both DCM 160 & 7. Main panel to DCM cable c
14:10 15:10 Rohit
gland fixed for DCM 200 .
g done in power pack of DCM SECOND 8. Cable connection's tightnin
15:10 16:30 Rohit & kartik
HALF all the DB in both DCM 160 &
ng done in power pack of DCM 16:30 17:20 Rohit & kartik
7/11/2023 DATE
TIME SUPPORTING REMARK PERIOD
ACTIVITY ACTIVI
FROM TO STAFF
decided and distance measured Rohit & Mahapatra 1. DCM 160 Main Panel MCC
10:00 10:30
o DB for earthing . manpowers currrent checked found Heal
for Earthing Pit and Earthing Mahapatra
11:00 11:45 2. Basic operation checked fo
nd . manpowers
3 mm) laying done from earthing Mahapatra FIRST 3.Furnance started and put o
12:00 13:00
manpowers HALF 160 .
FIRST
HALF
Mahapatra
manpowers
Mahapatra
manpowers
on done for both DCM 160 and Mahapatra 4. DCM 200 Main Panel MCC
14:00 15:30
manpowers currrent checked found Heal
7/14/2023
TIME SUPPORTING REMARK
ACTIVITY
FROM TO STAFF
inlet and outlet header in DCM
10:00 10:30 Rahul & Plumber
1. Control wiring and basic wiring done for DCM 160. 9:30 10:30 Rohit
2. Main panel to DCM cable connections done and Rohit & Bhanu
10:30 11:20
gland fixed for DCM 160 . Pratap
Rohit & Mahapatra
3.Cable tray marking done for both DCM 160 & 200 . 11:30 12:10
manpowers
4. cable tray laying done and fixed for both DCM 160 Mahapatra
12:10 15:30
& 200 . manpowers
5. DB fixed for both DCM 160 and 200. 12:30 15:00 Mahapatra
manpowers
6. Control wiring and basic wiring done for DCM 160. 15:30 16:30 Rohit
7/12/2023
TIME SUPPORTING REMARK
ACTIVITY
FROM TO STAFF
1. DCM 160 Main Panel MCCB turn ON and voltage Rohit & Bhanu
10:00 10:30
currrent checked found Healthy . Pratap
Rohit & Bhanu
2. Basic operation checked for DCM 160. 11:00 11:45
Pratap
3.Furnance started and put on for charge for DCM Rohit & Bhanu
12:00 13:00
160 . Pratap
4. DCM 200 Main Panel MCCB turn ON and voltage Rohit & Bhanu
14:00 15:30
currrent checked found Healthy . Pratap
Rohit & Bhanu
5. Basic operation checked for DCM 200. 15:30 16:00
Pratap
6.Furnance started and put on for charge for DCM Rohit & Bhanu
16:20 16:50
200. Pratap