Professional Documents
Culture Documents
2020.06.24 - Chronology of Break The PERTAMINA Cable - Rev
2020.06.24 - Chronology of Break The PERTAMINA Cable - Rev
June 11th,2020
15.00 PDP team prepare trench to reduce the vibration
that cause of piling SPSP.
For the location of the trench has been approved
by JO construction with the 50 – 80 centimeter
depth.
June 15th,2020
16.00 As the VMT result for the vibration test at the
CWI building. JO construction team ask PDP to
make additional depth of the trench (1-meter)
and maintain the trench.
June 24th,2020
06.45 Toolbox meeting
As follow JO construction comment, PDP
construction team ask excavator operator CAT
305E2 to maintain the depth of the trench as JO
construction comment.