4 Breakdown Control cable jointing for Raw mill water tank float
5 decided in meeting Bag filter Operation in DP mode
11 Project pending Job Power bus bar arrangement at LS crusher raw mill, coal mill,
12 Decided in meeting ZSS modification
14 HOD E&I control trial of Raw mill CA fan, classifier, tertiary crusher
17 HOD E&I Air Blaster trial after modification in contoller time setting as
18 HOD E&I Modification in water drain in compressure air receiver tank fo
19 decided in meeting Preheater Fresh air damper trial after modification for fire pro
24 HOD E&I LC1 MCC power bus bar and control tightness checking
25 HOD E&I CCR MCC power bus bar and control tightness checking
28 HOD E&I Packing Plant MCC bus bar, power, and control tightness
1.Wall cutting as per cable route & power socket & panel board
2.HDP pipe laying,
3.Metal box & panel board fixing. 02.01.2015 to
4.Mains input & power cable laying as per load, Mr. Manish HOD E&I
12.01.2016
5. MCB, Starter fixing, switches & power socket fixing. Cable
connection, testing of power to machine,
1.Wall cutting as per cable route & power socket & panel board
2.HDP pipe laying,
3.Metal box & panel board fixing subject to
4.Mains input & power cable laying as per load , Mr. Sathish material HOD E&I
5. MCB, fixing, switches & power socket fixing. Cable aviability
connection, testing of power to machine
1. cross checking first with variable drafts, then calibration at 30- start
40 mm wc draft condition 20.01.2016
Mr. Vikash Mishra HOD E&I
finishing at
25.01.2016
start
10.01.2016
Mr. R M kushwaha HOD E&I
finishing at
11.01.2016
start
12.01.2016
Mr. R M kushwaha HOD E&I
finishing at
13.01.2016
start
05.01.2016
Mr. Mustkin HOD E&I
finishing at
07.01.2016
start
10.01.2016
Mr. Suryabali HOD E&I
finishing at
15.01.2016
Completed
Completed
Completed
Completed
UNITED CEMENTS PVT. LTD.
NAUBISE-4, DHADING, NEPAL
Daily E&I HOD work book
Sl.no. Date Location Discription
04/01/2016
7 watts CFL light fixed for
16 Admin bulding staircase doom light and two wall
light removed in second floor and
04/01/2016
17 Admin bulding Three tube light fixed in terse and
connection was done.
Loose cable 3.5 core x 70 sq.mm
18 removed inbetween MRSS and Raw
mill hopper
Cable damaged at feeder side
19 900 FN 7 gland so cable cut and newly
glanded and termination work was
20 Badging plant control panel and
control cable shifted to LC2.
MCC bus bar tightness and
21 LC 2 blowering work was done and also
feeder tightness work completed.
Control transformer shifting work
22 LC 2 completed.
10/01/2016
Lighting switch board and power
58 New Lab switch and socket termination and
fixed. MCB fixed and termination
10/01/2016 was done for lighting and power
UPS power supply was given to
59 CCR Building CCR Conference hall PC from PLC
control desk VIA third floor power
Near Cement Welding JB connection work
60 mill weigh
feeder
11/01/2016
One extention box prepared and
72 CCR Building connection given in CCR MCC
11/01/2016 room for corpenter work.
73 Lab Switch boards are covered with
Carry bag for wall plastering work.
Cable laid inbetween compressor
74 Packing Plant air receiver tank and RIO panel for
solenoid valve. The termination
work is under progress.
75 Intend report preparation work.
After ZSS modification work trial
Raw mill was taken all are working properly
76
section
except 100 BC 1 and 23 due to
target problem. So informed to
600 RVF 1 and Trial were taken again after
77
500 DPC 2 change the timing setting of ZSS
controller. It is working properly.
DPC Pneumatic gates solenoid
78 checking one by one and trial from
CCR is Under progress.
New solenoid valve took from
79 store and checked for popet
damper purpose but this valve is
not proper fitting and holes are not
Neutral Earthing value checking
work when earthing rod inserted
LC 3 into ground and earthing
80
Transformer
chemicalwith water was added.
The individual earth pit values are
19.2 ohms, 29.8 ohms and in mesh
81 Cement mill area welding Panel
installation work was done.
82 Packing plant Auto drain valve was fixed for
packing plant air receiver tank 1
83 Packing plant Packer start at 2:10 pm and
stopped at 3:00 PM.
12/1/2016 Power and control cable laying
Damper for work was completed but cable
84
Kiln PA Fan
dressing work and LPBS Mounting
works are under progress.
Clincker silo top all 6 gates open
and close feed back are taken
85
inline with process team but Gate
number 4 is mechanically jam so it
is not operating full open and
86 500 CC 2 ZSS Trial taken now it is working
properly.
500 AR 1 and LPBS cable dressing was done.
87
1A
cable laying & cable dressing
Damper for PA completed from PA Fan to MCC 5
88
Fan
Pannel.but cable glanding work
under progress
Damper for PA damper LPBS mounting & fixining
89 work completed
Fan
14/01/2016
Another one body earthing rod
removed from the place so the soil
was digged by manually and filled
LC 3 the earthing chemical Powder with
98
Transformer water after that the earthing rod
14/01/2016 was fixed into the ground. The
earth value is 8.3 ohms. Yesterday
fixed earth pit value is 44 ohms.
The earth Value
transformer improving
neutral earthingProcess
resistance value checked by added
LC 3 earthing chemical powder .and its
99
Transformer
value checked in mesh mode.
Value is 3.24 ohms.so Earth
improving process is going on.
Kiln Tyre RTD Cable rerouting work is
100 Number underprogress.cable tray removed
9,10,11,12
and G.I pipe used for RTD cable.
Kiln auxilary Run for mechanical requirement.
101 and Thurester Thurester pressure is 50 Kg/Cm2.
pump
125 KVA DG, 380 KVA A and DG
synchronising panel and power
102
distribution panel cables were
disconnected and shifted from LT
DG room to HT DG.
60 Mtr Length 3.5C x 50 sqmm
103 Clinker silo cable laid and Dressing work
completed from LC5 welding
panel to clincker silo bottom.
3.5C x 120 sqmm Cable
104 LC 5 termination work was completed
PCC panel side with 250 A SFU
Unit and welding panel incomer
Near CCR building power
transformer(2.5 MVA, 6600/415V)
secondary side power cable (1C x
Near CCR 630 sqmm 25 Nos) redressing
105 power work started and the cable tray
transformer and L- channel was cut by use of
cutting machine. After that
disconnect the power cable
15/01/2016 (R,Y,B,N) in sequence and marked
with respective
15/01/2016
150 Watts Halogen Light 2
106 numbers fitted near CCR
transformer for night time
1.5 sqmm cable laid from 30 KVA
107 DG to CCR transformer for Power
transformer work.
108 75 x 75 mm L channel taken from
scrap yard for Power transformer
300 AD 1 Power contactor (3TF46) changed
109 Raw mill Aux. with new one, because its old
Drive
contactor moving and fixed
120 sqmm cable removed from HT
110 HT DG Room DG Auxilary panel and connected
in LT panel.
240 sqmm cable dismanteld cable
111 from 380 KVA DG shifted to LC 5
Cable cellar.
Near CCR Transformer secondary side
112 power cables disconnected and cable
transformer
tray mounting work.
1000 BC1, 2 ZSS target mounting work with
113
and 3 mechanical department.
100 DC 1, 200 DP switch setting was set 100 bar
114 16/01/2016 DC 1, 2 and as per the instruction of Mr. J.K
300 DC 1
singh sir.
115 Cooler Area One welding machine connection
was done.
one Grinding machine and drilling
116 machine connection was done in
coal mill and CCR transformer
TS PVT. LTD.
DING, NEPAL
OD work book
Manpower Pending
Remaks
Engaged status
Mr. Sathish,
Mr.Harendra, completed
Mr.Hari
Mr.Sathish completed
Mr. Raman,
Mr. Vishal, completed
Mr.Rajesh.
Mr.Manish Yadav,
Mr.Manish C, completed
Mr.Sanjeev
Mr. Faizan,
completed
Mr.Raman
Mr. Sathish
completed
Mr. Vishal
Mr. Ram mano
Mr. Sanjeev completed
Mr. Rajesh
Mr. Manish Yadav
Mr. Suriya bali completed
Mr. Mohit
Mr. Manish yadav
completed
Mr. Sanjeev
Mr. Mostkim
Mr. Raman & completed
1 Helper
Mr. Mostkim
Mr. Raman & completed
1 Helper
Mr. Sathish
completed
Mr. Marthand
Mr. Mostkim
completed
Mr. Manish Yadav
Mr. Mostkim
Mr. Raman
completed
Mr. Harendra
Mr. Gautham
Mr. Mostkim
completed
Mr. Harendra
Mr. Faizan
completed
Mr. Mohit
Mr. Sathish
Mr. Marthand completed
Mr. Vishal
Mr. Manish yadav
Mr. Sanjeev completed
Mr. Vishal
Mr. Sathish
completed
Mr. Vishal
Mr. Sathish
completed
Mr. Vishal
Mr. Faizan
completed
Mr. Rajesh
Under
Mr. Faizan
progress
Mr. Misra
completed
Mr. Faizan
Mr. Sathish
completed
Mr. Vishal
Mr. Mostkim
completed
Mr. Gautham
Mr. Mostkim
completed
Mr. Gautham
Mr. Mostkim Under
Mr. Minu Progress
Mr. Mostkim
completed
Mr. Raman
Mr. V Misra
completed
Mr. Raman
Mr. Sathish
completed
Mr. Harendra
Mr. V Misra
completed
Mr. Raman
Mr. Mostkim
Mr. Raman completed
Mr. Sanjeev
Mr. Sathish
completed
Mr. Sanjeev
Mr. Mostkim
Under
Mr. Suriya bali
Progress
Mr. Mohit
Mr Faizan
completed
Mr Raman
Mr Faizan Under
Mr Raman Progress
Mr Faizan
Mr. Mostkim
Under
Mr. Raman
progress
Mr. Harendra
Mr. Faizan
completed
Mr. Raman
Mr. Faizan
completed
Mr. Raman
Mr.Suryabali singh
Under
Mr.Mohit
Progress
Mr.Sanjeev
Mr. Mostkim,
completed
1 Helper
Mr. Mostkim,
completed
1 Helper
Mr. Raman
completed
Mr. Harendra
Under
Mr Faizan
progress
Mr Faizan
Mr Ram mano
Mr Manish C
completed
Mr Sanjeev
Mr Suriyabali
completed
Mr Mohit
Mr Suriyabali
Mr Mohit completed
Mr Sanjeev
Mr Sathish
Mr Vishal completed
Mr Minu
Mr Sathish
Mr Vishal
Mr Manish Yadav
completed
Mr Raman
Mr R M Kushwa
completed
Mr Harendra
Mr R M Kushwa
completed
Mr Harendra
Mr Mostkim
Under
Mr minu
Progress
Mr Gautham
Mr Suriyabali
completed
Mr Mostkim
Mr Mostkim
completed
Mr Gautham completed
Mr Gautham completed