Dear Sir/Madam,
As well as known that, we had emergency case on 33/11/0.4kv
500kVA Earth transformer at sumbawanga Substation. Reported on
Saturday 06th November 2021 leakage of oil earth transformer. We
arrived at sumbawanga to attend emergency to maintain power
reliability to our customers. We achieved to stop leakage on time.
2
-We didn’t discover anything on power cable main transformer to bus
bar.
-We didn’t discover anything on Surge arrester installed on 33kv side
of main transformer.
- We observed damage on power cable from main transformer to earth
transformer.
- We observed the value of earthing resistance that, it is not good for
the substation
- 1500 Ohms measured value of earth resistance on the point whereby
neutral point connected.
On the side of heavy current we concluded that, the source of these
events were poor earth resistance at substation. These caused by
rehabilitation that going on at substation. Earthing system were
affected
In addition to, we did not have staffs from our side attached early on
construction going on now to safe guard our infrastructure.
(E).Recommendation:
Through these, in fact I would like to advice you that during
preventive maintenance we ought to have enough time for preventing.
If the time will be limited, we could not archive the meaning of
preventive maintenance
We could be having a lot of emergency unnecessary.
Written by:
Eng: Mkalawa Anselem
HCE-SWHZ: