Agenda
Page 3
Project System – Overview
• In SAP, Project System module provides necessary tools and structures for tracking entire
construction activity. As such a project can be initiated in SAP right at the stage of
conception of a new building complex.
Page 4
Agenda
Page 5
Project System – Project Lifecycle
• Concept • Define
• Project • Cost Planning Demand • Daily Progress
• Project
Structure • Budget • Project Monitoring
Closure
• WBS Hierarchy Planning Release • Reports
• Coding Mask • Budget
Changes
Page 6
Process Flowchart
Page 7
Agenda
Page 8
Project Organization Structure
Page 9
Project Organization Structure
Page 10
Project Organization Structure
PROJECT
PROFIT CENTER PROFIT CENTER
PROJECT
PROFIT CENTER PROFIT CENTER
CONTROLLING
PLANT AREA
1000
PROJECT PROJECT
PROFIT CENTER PROFIT CENTER
PLANT PLANT
Page 11
Agenda
Page 12
Project System – Project Structure & Process
Company Code,
Profit Center,
Project Definition Plant, Cost Center, • Project Definition
consists of WBS
Person Responsible
elements created in
Company Code, hierarchical way. Each
Profit Center, work breakdown
WBS Element structure is based on a
Plant, Cost Center, project definition that
Person Responsible serves as a framework
for the project.
• Contains parameters
Project that control the
Def. properties of the entire
project.
WBS
Element • Contains default values
that are passed on to
newly created WBS
elements.
Page 13
Page 14
Agenda
Page 15
Cost Planning
Start
Cost planning
(Create/Change)
Import
End
Page 16
Cost plan report after upload
Page 17
Agenda
Page 18
Budget Planning
Start
Budget planning
(Create/Change)
Import
End
Page 19
Budget report after upload
Page 20
Agenda
Page 21
Define Demand
In this activity, you define a demand which helps to plan, trigger and monitor
procurement and staffing out of enterprise projects. A demand represents a certain
need of a WBS element at a certain time and a certain location.
Assign
Define Request Time
Resource
Demand Demand Recording
(Optional)
Check and
Goods Issue Monitor
Close Demand Return Extra
from Project Demand
(Optional) Project Stock
Stock (Optional)
(Optional)
Page 22
Agenda
Page 23
Page 24
Page 25
Project Execution & Monitoring
Daily Progress Monitoring & Budget Changes
Budget Changes
o This notification will be displayed only in case there is a situation of actual postings
exceeding the budget threshold limit set in the AVC profile selected for the project.
o In this activity, you manage (transfer, return and supplement) the budget allocated to
WBS element.
Page 26
Agenda
Page 27
Project Closure
Page 28
Agenda
Page 29
Integration With Other SAP Modules
Financial
Accounting &
Sales &
Controlling (FICO)
Distribution (SD)
Plant & ▪ G/L Account
Machinery (PM) ▪ Revenue &
postings
Deduction
▪ Primary costs
▪ Maintenance reporting
Orders
Materials
Management (MM) SAP
▪ Purchases- Material
▪ Purchases- Services
Project Systems
▪ Goods receipt The integration between SAP Project System PS with application
modules allows you to design, plan, and execute the projects as
part of your normal project procedure. Hence, Project System
module has the constant data access to all the departments
involved in the project.
Page 30
Integration With Other SAP Modules
Materials Management (MM)
Based on Materials, PS helps in creating Purchase Requisitions and Purchase Orders. This
powerful integration makes PS a key player in the logistics cycle, including the ability to
handle Services via Service Masters.
Page 31
Agenda
Page 32
Project Monitoring – Standard Reports
Budget Updates
Budget Monitoring
Budget vs Actual vs Variance
Page 33