REKAPITULASI LAPORAN PRODUKSI PROCESSING PLANT CP 7

PT. SEBUKU IRON LATERITIC ORES


PERIODE NOPEMBER 2023

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Produksi Rata - Rata


Tanggal Grand Total Produksi
Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Jumat Sabtu Minggu Senin Selasa Rabu Kamis Minimal Produksi
Maksimal
CP. 07 Line 1 3.5 2.0 0.5 3.2 9.2 0.5 3.5 2.3
Jam Produksi
CP CP. 07 Line 2 6.0 5.2 5.3 4.0 2.0 6.3 6.3 5.7 4.9 6.5 2.0 3.2 0.6 3.7 61.5 0.6 6.5 4.4

CP. 07 Line 3 - - -

CP. 07 Line 1 78.4 44.8 5.6 70.0 198.8 5.6 78.4 49.7
Input Raw
CP. 07 Line 2 151.2 100.8 106.4 61.6 22.4 168.0 173.6 134.4 100.8 128.8 28.0 84.0 16.8 77.0 1,353.8 16.8 173.6 96.7
Material CP
CP. 07 Line 3 - - -
Grand total Input Raw
- - - - - 151.2 100.8 106.4 61.6 - 100.8 - 168.0 173.6 134.4 100.8 - 128.8 72.8 84.0 - 22.4 - - 147.0 - - - - - 1,552.6 22.4 252.0 146.4
Material
CP. 07 Line 1 74.5 42.6 5.3 66.5 188.9 5.3 74.5 47.2
Output Product
(Primer+Sekun CP. 07 Line 2 143.6 95.8 101.1 58.5 21.3 159.6 164.9 127.7 95.8 122.4 26.6 79.8 16.0 73.1 1,286.1 16.0 164.9 91.9
der)
CP. 07 Line 3 - - -
Total Product (Primer +
- - - - - 143.6 95.8 101.1 58.5 - 95.8 - 159.6 164.9 127.7 95.8 - 122.4 69.2 79.8 - 21.3 - - 139.6 - - - - - 1,475.0 21.3 239.4 139.1
Sekunder)
CP. 07 Line 1 22.4 22.4 11.0 22.1 77.9 11.0 22.4 19.5
Tonase
CP. 07 Line 2 25.2 19.5 20.3 15.4 11.2 26.7 27.6 23.8 20.6 19.8 14.0 26.3 28.0 21.0 299.2 11.2 28.0 21.4
Input/Jam
CP. 07 Line 3 - - -

Total Tonase Input/Jam - - - - - 25.2 19.5 20.3 15.4 - 33.6 - 26.7 27.6 23.8 20.6 - 19.8 36.4 26.3 - 39.0 - - 43.1 - - - - - 377.1 22.2 50.4 40.8

CP. 07 Line 1 21.3 21.3 10.4 21.0 74.0 10.4 21.3 18.5
Tonase
CP. 07 Line 2 23.9 18.6 19.3 14.6 10.6 25.3 26.2 22.6 19.5 18.8 13.3 24.9 26.6 19.9 284.3 10.6 26.6 20.3
Output/Jam
CP. 07 Line 3 - - -

Total Tonase Output/Jam 23.9 18.6 19.3 14.6 - 31.9 - 25.3 26.2 22.6 19.5 - 18.8 34.6 24.9 - 37.0 - - 40.9 - - - - - 358.2 21.1 47.9 38.8
A. Daily Produksi Report : 25/11/2023
Crushing Plant CP. 07 Line 1 CP. 07 Line 2 CP. 07 Line 3 Total
Product Primer+Sekunder (Ton) 66.5 73.15 139.65

Note:
- Produksi hanya shift siang jam 07:00 s/d jam 15:00

A. Montly Report Produksi Update : 25/11/2023


Crushing Plant CP. 07 Line 1 CP. 07 Line 2 CP. 07 Line 3 Total
Product Primer+Sekunder (Ton) 188.86 1286.11 1474.97