HUNGARY GLASS PACKAGING FACTORY INVESTMENT VENTILATION INSTALLATION

WORKS
Scope Ventilation Installation Work Document no HSCM-QC-ITP-010
BOQ no 14.04.000.0000 Inspection and Test Plan for Ventilation Installation Work Revision 00
ITP No ITP-001 Submittal Date
Control Category
Activity Inspection
Description Inspection Method References Acceptance Criteria
no Frequency Sub- Project
Contractor Employer
Contractor Director
1 MATERIALS

Equipment/Material Receiving inspection for HVAC equipment,duct & accessories,hanger/supports, Insullation, air Approved Drawing,Manufacturer,Instruction,
1.1 terminal devices,Flexible Connection,volume/fire dampers,Electrical Instument Materials. 100% W S S R Certificate Check SMACNA,Project specification,MOS
Approved,Material Submittal,Purchase Order,Project
Specification
1.2 Storage,handling & Preservation of Above material/Equipment for HVAC System. 100% H S S R Visual Check Project Specification,Manufacturer Recommendation SMACNA,Project specification,MOS

2 INSTALLATION
HVAC Duct construction standards,SMACNA,Project
2.1 Duct material conforming to specification. 100% H Certificate Check specification SMACNA,Project specification,MOS

2.2 Duct layout and elevation. 100% W S S R Drawings Check SMACNA,Approved Drawing SMACNA,Project specification,MOS

2.3 Duct installation as per approved drawings. 100% H W S R Drawings Check Approved Drawing SMACNA,Project specification,MOS

2.4 Hangers and support installation support spacing,ducting route,reinforcement & hangers. 100% W S S R Visual Check-Drawings Check SMACNA,Project specification,Approved Drawing SMACNA,Project specification,MOS

2.5 Check joints & Application of duct sealant. 100% W S S R Visual Check Project specification, SMACNA,Project specification,MOS

SMACNA,Project specification,Approved
2.6 Visual check of connection tightness. Gaskets & seals. 100% W S S R Visual Check Drawing.MOS SMACNA,Project specification,MOS

2.7 Visual Inspection of duct & its accessories conforming to the project. 100% W S S R Visual Check Approved Drawing SMACNA,Project specification,MOS

2.8 Check accessories & duct free from damage. 100% W S S R Visual Check MOS,Project specification SMACNA,Project specification,MOS

2.9 Duct Insulation material are conforming to the project specification. 100% W S S R Certificate Check SMACNA,Project specification,MOS SMACNA,Project specification,MOS

2.10 Duct insulation installation as per drawing,check the insulation band spacing as per drawing. 100% W S S R Visual Check-Drawings Check SMACNA,Project specification,MOS SMACNA,Project specification,MOS

3 EQUIPMENT INSTALLATION
3.1 Duct accessories, duct heater, Volume Damper,sound alternator,Flow grid inspection,fire damper. 100% W W S R Visual Check-Drawings Check Approved Drawing SMACNA,Project specification,MOS

3.2 Installation of air terminal device, Flexible connections. 100% W W S R Visual Check-Drawings Check Approved Drawing,Project specification,MOS SMACNA,Project specification,MOS

3.3 Functional test of Fire Damper. 100% W W W R Visual Check SMACNA,Project specification.MOS SMACNA,Project specification,MOS

3.4 HVAC Electrical & Instrumentation Material Receving Visual Inspections. 100% W ELECTRICAL ITP ELECTRICAL ITP SMACNA,Project specification,MOS

3.5 Equipment Foundation Location Check as per Approved Drawing. 100% W R R R Survey check-Drawings Check Approved Drawing.,Project specification SMACNA,Project specification,MOS

4 FINAL INSPECTION
Calibration of test equipment 100% H R R R document review

4.1 Check Orientation, Approved drawing. 100% H W W R Visual Check-Drawings Check Approved Drawing SMACNA,Project specification,MOS

4.2 Check for leak test for duct installation. 10% H W W R Sealing Check SMACNA,Project specification.MOS,DW 144/DW 143 SMACNA,Project specification,MOS

4.3 Check for leak smoke test for duct installation. 10% H W W R Sealing Check SMACNA,Project specification.MOS,DW 144/DW 143 SMACNA,Project specification,MOS

Preparared by Reviewed by Approved by

H= Hold Point
W= Witness point
S= Surveillance Point
T= Test point
R= Review of Records