You are on page 1of 4

PROJECT TITLE:

ENGINEERING, PROCUREMENT AND CONSTRUCTION OF NEW SECURITY X-RAY BUILDING GATE NO.2

INSPECTION AND TEST PLAN ITP No. DATE: DISCIPLINE


ITP FOR INSTALLATION OF LIGHTING SYSTEM FITTINGS AND ACCESSORIES EL-ITP-0006 2/8/2021 ELECTRICAL
INSPECTION
RESPONSIBILITY
ITEM ACCEPTANCE Verifying ASSIGNMENTS
Quality Related Activity Reference
NO:
PROJECT PHASE CRITERIA Document &
& ACTIVITY CODE Form GAC MA'ADEN
1.0 DOCUMENT
REVIEW

Material Approved
1.1 Material approved Prior to Installation MD-101-SMEM-EG-EL-SPC-0001 Visual Check Document R R

1.2 Review of approved IFC drawings MD-101-SMEM-EG-EL-SPC-0001 Visual Check Approved Drawing R R
MATERIAL
RECEIVING
2.0 INSPECTION

Materaial Receiving Visual Inspection of


2.1 Lighting System Fittings and Accessories MD-101-SMEM-EG- EL-SPC-0001 Visual Inspection GAC-QVD-EL-001 H W/R
Visual check/Test
2.2 Handling Storage and Preservation) MD-101-SMEM-EG- EL-SPC-0001 Report GAC-QVD-EL-001 H W/R

3.0 INSTALLATION
Visual Inspection for lighting Pole
Plinth/Foundation,Location and Support of
3.1 Lighting Fixtures MD-101-SMEM-EG- EL-SPC-0001 Visual Check GAC-QVD-EL-016 H W

3.2 Lighting Fixtures Assembly and Installation MD-101-SMEM-EG- EL-SPC-0001 Visual Check GAC-QVD-EL-016 H W

GAC-QVD-EL-006
3.3 Conduit Installation MD-101-SMEM-EG- EL-SPC-0001 Visual Check GAC-QVD-EL-007 H W

GAC-QVD-EL-008
3.4 Cable Laying / Installation MD-101-SMEM-EG- EL-SPC-0001 Visual Check GAC-QVD-EL-009 H W
PROJECT TITLE:
ENGINEERING, PROCUREMENT AND CONSTRUCTION OF NEW SECURITY X-RAY BUILDING GATE NO.2

INSPECTION AND TEST PLAN ITP No. DATE: DISCIPLINE


ITP FOR INSTALLATION OF LIGHTING SYSTEM FITTINGS AND ACCESSORIES EL-ITP-0006 2/8/2021 ELECTRICAL
INSPECTION
RESPONSIBILITY
ITEM ACCEPTANCE Verifying ASSIGNMENTS
Quality Related Activity Reference
NO:
PROJECT PHASE CRITERIA Document &
& ACTIVITY CODE Form GAC MA'ADEN

Cable gland installation, Cable dressing,


3.5 identifaction, Termination Visual inspection MD-101-SMEM-EG- EL-SPC-0001 Visual Check GAC-QVD-EL-010 H W

4.0 TESTING
MD-101-SMEM-EG- EL-SPC-0001

Cable Continuity and Insulation Resistance Visual check/Test


4.1 Testing MD-101-SMEM-EG- EL-SPC-0001 Report GAC-QVD-EL-011 H W

Final Termination Bolt/ Screw Torque MD-101-SMEM-EG- EL-SPC-0001 Measure and Visual
4.2 Tightening Check GAC-QVD-EL-012 H W

4.3 Illumination Testing Visual Check GAC-QVD-EL-017 H W

Final inspection of
4.4 Final acceptance and punch list close Verify the rectification of Punch Items complete installation GAC-QVD-EL-099 H W/R
LEGEND
W-Witness Inspection/Test H-Hold Point for QC Inspection or Test R-Review of Documents RH-Review and Approval of Document
GENERAL NOTES
1 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
2 Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative i
3 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization attendance.representative in attend
GATE NO.2

DISCIPLINE
ELECTRICAL

REMARKS
GATE NO.2

DISCIPLINE
ELECTRICAL

REMARKS

anization representative i
representative in attend