Professional Documents
Culture Documents
RESPONSIBLE
S.C C CL REFERENCE DOCUMENT ACCEPTANCE CRİTERİA STATUS GENERAL NOTES
PARTY
1 DOCUMENTATION
1.1 Contractor drawings. 100% W Contract,PQP,Approved Drawing,Project Specification DIN Standards,NFPA,,Project specification,MOS QCI
1.2 Verify calibration of inspection, measuring and test equipment. 100% W Project Specification,Manufacturer Recommendation,PQP DIN Standards,NFPA,,Project specification,MOS QCI
2 MATERIALS
Approved Drawing,Manufacturer,Instruction,
DIN Standards,NFPA,,Project specification,MOS,Material
2.1 Control of pipes and insulation products to be used. 100% W Approved,Material Submittal,Purchase Order,Project QCI A
Submittal
Specification
Project Specification,Manufacturer DIN Standards,NFPA,,Project specification,MOS,Material
2.2 Pipe Fitting Equipment (Bolt, DObel, Rod, Profile, Clip). 100% W QCI A
Recommendation,Material Submittal Submittal
3 INSTALLATİON
3.1 Pipe Installation as per approved drawings. 100% W DIN Standards,NFPA,,Approved Drawing DIN Standards,NFPA,,Project specification,MOS QCI
3.2 Valve and Accessory Assembly Control. 100% W Approved Drawing.PQP,DIN Standards,NFPA, DIN Standards,NFPA,,Project specification,MOS QCI
4 EQUIPMENT INSTALLATİON
4.1 Fire Equipments (Fire Pump, Fire Cabinet, Zone Valves, Compressor, Valves) Check as per Approved Drawing. 100% W Approved Drawing.PQP,Project specification DIN Standards,NFPA,,Project specification,MOS QCI
4.2 Dilatation Expansion Joint Installation Control. 100% W Approved Drawing.PQP,Project specification DIN Standards,NFPA,,Project specification,MOS QCI
4.3 Equipment Foundation Location Check as per Approved Drawing. 100% W Approved Drawing.PQP,Project specification DIN Standards,NFPA,,Project specification,MOS QCI
4.4 Verify unit Installation is as per approved Drawing, Check Vibration pad Place Beneath the Package Equipment installation. 100% W Approved Drawing.PQP,Project specification DIN Standards,NFPA,,Project specification,MOS QCI
4.5 Fire Cabinet Model, Sheet Thickness, Lock, Paint Color etc. Compliance Check. 100% W Approved Drawing.PQP,Project specification DIN Standards,NFPA,,Project specification,MOS QCI
4.6 Fire Brigade Connection Nozzles, Cabinet Internal Sets (Tube and Hose) Assembly Control. 100% W Approved Drawing.PQP,Project specification DIN Standards,NFPA,,Project specification,MOS QCI
5 FINAL INSPECTION
5.1 Check Orientation & Level is per IFC Drawing.Check Condensate Drain System is as per approved drawing. 100% W Approved Drawing.PQP,Project specification DIN Standards,NFPA,,Project specification,MOS QCI
5.2 Check for leak test for pipe installation. 100% W Approved Drawing.PQP,Project specification DIN Standards,NFPA,,Project specification,MOS QCI
5.3 Control of Tightness Tests of Pipes (Hydrostatic Test, 1.5 times the operating pressure 24 hours). 100% W Approved Drawing.PQP,Project specification DIN Standards,NFPA,,Project specification,MOS QCI
5.3 Conducting Operational Tests, Complete Commissioning of the Entire System and Labeling. 100% W Approved Drawing.PQP,Project specification DIN Standards,NFPA,,Project specification,MOS QCI