You are on page 1of 1

#VALUE!

HUNGARY GLASSPACKAGING FACTORY

INSPECTION, CONTROL AND TEST PLAN (ITP)

Methot Of Statement Fire Installation Works MOS Document No BM-MOS-PLN-003

Document No HSCM-BRL-ITP-002 Rev.No

Date 3/1/2024 Rev.Date

ACTION GENARAL DOCUMENTS


TEST
S.No ACTİVİTY
FREQUENCY

RESPONSIBLE
S.C C CL REFERENCE DOCUMENT ACCEPTANCE CRİTERİA STATUS GENERAL NOTES
PARTY

1 DOCUMENTATION

1.1 Contractor drawings. 100% W Contract,PQP,Approved Drawing,Project Specification DIN Standards,NFPA,,Project specification,MOS QCI

1.2 Verify calibration of inspection, measuring and test equipment. 100% W Project Specification,Manufacturer Recommendation,PQP DIN Standards,NFPA,,Project specification,MOS QCI

2 MATERIALS
Approved Drawing,Manufacturer,Instruction,
DIN Standards,NFPA,,Project specification,MOS,Material
2.1 Control of pipes and insulation products to be used. 100% W Approved,Material Submittal,Purchase Order,Project QCI A
Submittal
Specification
Project Specification,Manufacturer DIN Standards,NFPA,,Project specification,MOS,Material
2.2 Pipe Fitting Equipment (Bolt, DObel, Rod, Profile, Clip). 100% W QCI A
Recommendation,Material Submittal Submittal

Project Specification,Manufacturer DIN Standards,NFPA,,Project specification,MOS,Material


2.3 Fire Equipments (Fire Pump, Fire Cabinet, Zone Valves, Compressor, Valves). 100% W QCI A
Recommendation,Material Submittal Submittal

3 INSTALLATİON

3.1 Pipe Installation as per approved drawings. 100% W DIN Standards,NFPA,,Approved Drawing DIN Standards,NFPA,,Project specification,MOS QCI

3.2 Valve and Accessory Assembly Control. 100% W Approved Drawing.PQP,DIN Standards,NFPA, DIN Standards,NFPA,,Project specification,MOS QCI

DIN Standards,NFPA,,Project specification,Approved


3.3 Hangers and support installation support spacing,ducting route,reinforcement & hangers. 100% S DIN Standards,NFPA,,Project specification,MOS QCI
Drawing.MOS

DIN Standards,NFPA,,Project specification.MOS,Material


3.4 Pipe Paint material are conforming to the project specification. 100% W DIN Standards,NFPA,,Project specification,MOS QCI A
Submittal

DIN Standards,NFPA,,Project specification.MOS,Material


3.5 Fittings, Threaded Branch and Clamp Compliance Control. 100% W DIN Standards,NFPA,,Project specification,MOS QCI A
Submittal

DIN Standards,NFPA,,Project specification.MOS,Material


3.6 Pipe Internal Cleanliness Control with Flushing Application. 100% W DIN Standards,NFPA,,Project specification,MOS QCI A
Submittal

DIN Standards,NFPA,,Project specification.MOS,Material


3.7 Sprinkler Installation Control Suitable for Intended Use. 100% W DIN Standards,NFPA,,Project specification,MOS QCI A
Submittal

4 EQUIPMENT INSTALLATİON

4.1 Fire Equipments (Fire Pump, Fire Cabinet, Zone Valves, Compressor, Valves) Check as per Approved Drawing. 100% W Approved Drawing.PQP,Project specification DIN Standards,NFPA,,Project specification,MOS QCI

4.2 Dilatation Expansion Joint Installation Control. 100% W Approved Drawing.PQP,Project specification DIN Standards,NFPA,,Project specification,MOS QCI

4.3 Equipment Foundation Location Check as per Approved Drawing. 100% W Approved Drawing.PQP,Project specification DIN Standards,NFPA,,Project specification,MOS QCI

4.4 Verify unit Installation is as per approved Drawing, Check Vibration pad Place Beneath the Package Equipment installation. 100% W Approved Drawing.PQP,Project specification DIN Standards,NFPA,,Project specification,MOS QCI

4.5 Fire Cabinet Model, Sheet Thickness, Lock, Paint Color etc. Compliance Check. 100% W Approved Drawing.PQP,Project specification DIN Standards,NFPA,,Project specification,MOS QCI

4.6 Fire Brigade Connection Nozzles, Cabinet Internal Sets (Tube and Hose) Assembly Control. 100% W Approved Drawing.PQP,Project specification DIN Standards,NFPA,,Project specification,MOS QCI

5 FINAL INSPECTION

5.1 Check Orientation & Level is per IFC Drawing.Check Condensate Drain System is as per approved drawing. 100% W Approved Drawing.PQP,Project specification DIN Standards,NFPA,,Project specification,MOS QCI

5.2 Check for leak test for pipe installation. 100% W Approved Drawing.PQP,Project specification DIN Standards,NFPA,,Project specification,MOS QCI

5.3 Control of Tightness Tests of Pipes (Hydrostatic Test, 1.5 times the operating pressure 24 hours). 100% W Approved Drawing.PQP,Project specification DIN Standards,NFPA,,Project specification,MOS QCI

5.3 Conducting Operational Tests, Complete Commissioning of the Entire System and Labeling. 100% W Approved Drawing.PQP,Project specification DIN Standards,NFPA,,Project specification,MOS QCI

S.No Action Definitions Codes GENERAL NOTES


1 Sub-Contractor S.C
2 Contractor C
3 Clıent CL
4 Inspectıon / Test I
5 Document Issued/Report Revıew R
6 Surveılance S
7 Hold Poınt (Notification Required And Presence Mandatory) H
8 Wıtness (Notification Required But Presence Not Mandatory) W

S.No Statüs Definitions Codes


1 Approved A
2 Awaiting Approval A.A
3 Verbal Approval V.A
4 No Presentation N.P
5 Rejected R

You might also like