Rakam Karnali,Dailekh Karnali Province, Nepal Bill Of Quantity Name of the Scheme:-Saraswati Madhyamik Vidyalaya Gheraparkhal Yojana Location: Athabis Municipality 02 Dailekh, Chief Minister Employment Programmer Quantit S.N Description Of Work Unit Rate Total y Excavation in all types of soil as per drawing and technical A specification, including removal of stumps and other deleterious matter, with all lifts and lead as per (By Manual) I Excavation in Soft types of Soil 90% Cu.m 145.62 594.82 86617.69 II Excavation in Hard Rock 10% Cu.m 0.00 3196.88 0.00 Providing and laying of hand pack Stone in foundation on B Cu.m 6.47 3907.06 25286.49 prepared surface as per Drawing and Technical Specifications. Providing and laying of Plain Cement Concrete M 10 ( or C 1:2:4 for nominal mix) in Foundation complete as per Drawing Cu.m 6.05 17257.10 104396.83 and Technical Specifications. Random Rubble Masonry-Providing and laying of Stone D Masonry Work in Cement.Mortar 1:4 in Foundation complete Cu.m 100.86 12271.58 1237650.20 as per Drawing and. Technical Specifications Providing and Pointing with cement mortar on masonry work E Sq.m 105.17 319.36 33587.09 in structure as per Technical Specifications (mix Mortar 1:3) F Manually Breaking stones ( excluding Collection of Rubble) Cu.m 5.44 0.00 0.00 Haulage of Stone Boulder/ aggregates/ Sand/ excavated earth G etc. Unit = cum (For 50% by basket and 50% by wheel barrow Cu.m 63.00 0.00 0.00 for every additional 20 m haul. = 1 cum, 100 m) Collection of rubble of required size, hauling distance H Cu.m 123.75 0.00 0.00 10 m. and stacking. Total 1487538.30 I Purchase goods 1 Equipment Jobs 1.00 19791.00 19791.00 2 OPC Cement With 13% Vat (District Rate) Bags 306.09 1130.00 345882.06 5 Collection and transportation of sand( (District Rate) Cu.m 40.70 3000.00 122103.59 6 Stone Royalti Cu.m 123.75 150.00 18562.45 7 Sand Royalti Cu.m 40.70 150.00 6105.18 8 Transpot&loading/uploading for Stone Cu.m 123.75 0.00 0.00 9 Hoarding board (Iron Pole) No 1.00 7000.00 7000.00 Total Goods Purchase Amount 519444.28 Total amount held 2,006,982.58 Total Appropriation Amount 1,500,000.00 Contingency 2% 30,000.00 Total Contract Amount 1,470,000.00 To Be Reduced (Royalti Of Stone) 24,667.63 Total Amount To Be Paid In Full 1,982,314.95