3.1.1. Project Development & Management Performance


A) Physical Performance
This month, various activities relating to project development and management have been
undertaken as detailed below:
 In relation to subcontractors, it was planned to employ and deploy 15 different subcontractors
and microenterprises in ECC projects at a fixed price and executed 20(133%).
 In relation to construction project management service:-
 It was planned to set cost estimates for 6 different projects and executed 14 (233%);
 Regarding projects’ procurement technical and financial evaluation, thirteen documents
have been evaluated;
 Concerning preparation of contract documents for internal and external customers, 11
contract document preparations have been undertaken.
 Regarding Preparing/updating the project contract documents for internal and external
customers, this month 18 contract documents were prepared.
 Regarding Inspection of project payment document, preparation and verification of
certificate, 1payment document of investment, and 3 payment documents of external
clients was done.
 4 building, 4 water, 6 transports, 4 central branch and 1 Housing Development projects,
a total of 19 projects were in the analysis up to May 30, by EVM.
 Regarding the quality assurance (QA) and quality control (QC) activities of construction
projects, 16 projects were analyzed.4 building, 3 water, 4 transport,4 central branch
project and 1 Housing Development
 In relation to Building design service: 2 architectural designs were planned and 2 prepared; 2
structural designs were planned and 2 prepared, 2 electrical designs were planned and two
design were executed, 2 sanitary designs were planned and two designs were executed, 3
BOQs were planned and 3 executed;
 In relation to Transport infrastructure design service, 2 road geometric designs have been
carried out. Eleven project survey works and 1 working drawing for road design projects have
been prepared.
 In relation to Water design service, two sanitary designs planned and executed.
B. Financial Performance
Company Name: Document No.:
የኢትዮጵያ ኮንስትራክሽን ሥራዎች ኮርፖሬሽን
ETHIOPIAN CONSTRUCTION WORKS CORPORATION OF/ECWC/SMPD/003
Document Title: Page No.:
Issue No: 2 Operational works report providing format Page 2 of 1

It was planned to make birr 6,460,000 revenue from project management, design, and training
services and birr 4,200,000.00 (65%) was executed.
Company Name: Document No.:
የኢትዮጵያ ኮንስትራክሽን ሥራዎች ኮርፖሬሽን
ETHIOPIAN CONSTRUCTION WORKS CORPORATION OF/ECWC/SMPD/003
Document Title: Page No.:
Issue No: 2 Operational works report providing format Page 3 of 1