2 2 NOV 2011
-
DEPARTMENT ORDER ) SUBJECT: Cost Estimation Manual for Low
Rise Buildings
NO. 137 l
.)
Series of 201~ ~.""'"'7
In line with the Department's Quality Policy to implement projects at the right cost, all
Implementing Offices are hereby directed to adopt the herein Cost Estimation Manual
for Low Rise Buildings in the determination of unit cost of Pay Items of Work involved in
the construction and repair/retrofitting of low rise building projects.
This Manual aims to enhance the technical capability of DPWH engineers in the preparation
and review of Program of Works (POW) and Approved Budget for the Contract (ABC) and to
establish consistency in the format of preparation and serve as a uniform basis/reference in
the derivation of unit cost for each item of work. It shall be distributed to all concerned
offices of the Department and uploaded in the DPWH Intranet.
This Order shall be consistent with the implementation of D.O. No. 163, Series of 2015
"Standard Forms of Program of Works (POW) and Approved Budget for the Contract (ABC)"
with modification on its format and description of item numb8'r and scope of works (Annex
A) to conform with the DPWH Standard Specifications for Public Works Structures, Volume
III (Buildings, Ports and Harbors, Flood Control and Drainage Structures and Water Supply
Systems) and Standardized Pay Items of Work for Buildings as embodied in D.O. OS, Series
of 2017.
~~----
('
MARK A. VILLAR'
SecretarY
6.1.3 CSSD/BOC
Depa,trrent of Public Works and Highways
Office of the Secretary
1111111111111I11111111111111111111111
WIN7W02039
FOREWORD
Consistent with its commitment to excellence, the Department of Public Works and
Highways (DPWH) has continuously formulated and developed guides and techniques in
various fields of the construction process. This is to ensure the highest standards of outputs
at the right cost. The DPWH has always endeavored to standardize all its processes to
facilitate prompt and efficient response to the needs of the Filipino people.
This Cost Estimation Manual for Low Rise Buildings provides Standard Cost Sheets for
common pay items of work in building construction in accordance with the DPWH Standard
Specifications for Public Structures (Volume III). This manual was purposely developed to
provide uniform reference/basis in unit cost estimation and in the preparation of Program of
Works (POW) and Approved Budget of Contract (ABC) in tt1e implementation of various
DPWH infrastructure projects.
~~
MARK A. VILLAR
Secretary
Department of Public Works and Highways
Office of the Secretary
1111111111111111111111111111111111111
WIN7W02039
COST ESTIMATION MANUAL FOR LOW RISE BUILDINGS
TABLE OF CONTENTS
F()FlE:,",()Fl[) --------------------------------------------------------------------------------------------------
TABLE: ()F C() NTE:NTS- - - - ------ - - - ---------- - - ---- - ---- - - --- - - ------ - - - ----- - ---- - --- - ii
PFlE:FACE:------ - - - - - - - - - - - ------- - - - ---------- - - ---- - ---- - - ---- - - ----- - - - ----- - ---- ---- ----- - vii
INTFl()[)UCTI()N----------------------------------------------------------------------------. 1
G E:N E:FlAL N ()TE:S- - - - - - -------- - - - --------- - - - ---- - ---- - - ---- - - ----- - - ------ - --- ---- --- - - -- - - 2
C.1 Estimated travel speed, loading/unloading time & allowance for delay -------------------- 273
C.2 Formula for the calculation of dump truck travel time ----------------------------------------. 273
C.3 Computation of cycle time -------------------------------------------------------------------------. 273
ii
DEFINITION OF TERMS
_ - is the total estimated cost of the project which covers the Civil Works Cost,
Engineering Supervision and Administrative Overhead, Road Right-of-Way Acquisition Cost,
Construction Contingency, etc. The POW shall include information about the project location
and limits, quantity and unit cost for each item of work, construction duration, funding
source, equipment requirements, etc.
- is the total estimated agency estimate (direct cost, indirect cost and tax) for civil
works contract of infrastructure projects, wherein it is the ceiling of award of contract for
government locally-funded projects and reference for comparison of bid costs of contractors
for both locally-funded and foreign-assisted projects.
- is the determination of reasonable unit cost of each item of work which reflects the
breakdown showing the quantities of work items, unit prices of materials, equipment rental
rates, labor rates and DPWH-prescribed indirect costs including taxes.
iii
DPWH Standard Specifications for Public Works and Highways
iv
UNITS AND ABBREVIATIONS ACRONYMS
v
ACRONYMS
RC Reinforced Concrete
RCD Return Ceiling Diffuser
RCPC Reinforced Concrete Pipe Culvert
RLD Return Linear Diffuser
RO Regional Office
RPM Raised Pavement Markers
RSB Reinforcing Steel Bar
R_SC Rigid Steel Conduit
SCD Supply Ceiling Diffuser
SLD Supply Linear Diffuser
SPT Standard Penetration Test
SSS Social Security System
THHN Thermoplastic High Heat Nylon-coated
TW Thermoplastic Wire
TWHN Thermoplastic Water and Heat resitant
Nylon-coated
UPMO Unified Project Management Office
UPVC Unplasticized Polyvinyl Chloride
VO Variation Order
VRF Variable Refrigerant Flow
XLPE Cross-Linked Polyethylene
vi
PREFACE
Since the Department also implements the construction of vertical structures like
buildings, the Bureau of Construction sees the necessity of establishing guidelines in
estimating cost for buildings aligned with the Department's mantra of implementing projects
at the right cost. Generation of this manual aims to provide a uniform basis in the
preparation of reasonable cost estimates specifically for Low Rise Buildings (up to five
storeys) which the Department is more involved of. Likewise, this manual will aid in
facilitating a more efficient review and evaluation of Detailed Unit Price Analysis (DUPA) and
Program of Works (POW).
Guidelines presented in this manual are structured to be more applicable for building
projects implemented by the DPWH but may also be used in general building construction.
Sources in the formulation of this manual were collated data from previously implemented
projects of the Bureau, contributed by nonetheless, its experienced engineers who have long
years of involvement in project implementation.
vii
INTRODUCTION
The bulk of the involvement of the DPWH is in the construction of horizontal structures.
However, being one of the construction agencies of the government, it has been implementing
various vertical projects, specifically Low Rise Buildings (up to five (5) storey). It has also been
providing technical assistance on building construction to its own Implementing Offices and
other government agencies. Hence, as technical assistance and capacity building tool, this
cost estimation manual is formulated to establish a uniform basis or reference in the
preparation, review and evaluation of Detailed Unit Price Analysis (DUPA) and Approved
Budget for the Contract (ABC) particularly for government building projects. Further, this
manual aims to improve the accuracy of cost estimates and to facilitate a more efficient review
and evaluation of DUPA and Program of Works (POW) prepared by the Implementing Offices.
This manual covers only the common pay items of work in building construction with
details on the breakdown for costing of materials, labor, equipment including the overhead
cost and contingencies. Usage of this manual in the derivation of unit cost for DPWH projects
requires the user's input for unit rates of materials and labor based on the Department's
Construction Materials Price Data (CMPD) and Standard Labor Rates that are variable for
different locations (i.e. Regional and District Engineering Offices). This manual is limited only
to unit cost derivation, thus, methods and techniques in quantity take off are not discussed.
1
GENERAL NOTES
1. The capacity of equipment as presented in the standard cost sheet for each item of
work may be adjusted to a higher or lower capacity, provided the resulting unit cost is
more economical. Rental rates shall still be based on ACELGuidebook of 2014.
Example: In hauling of materials, use of Dump Truck with higher capacity of fifteen
(15) m3 instead of ten (10) m3 capacity as presented will result to a lower price, as the
capacity gets bigger, the lower the resulting cost of P45.46/m3 of hauling cost from
P54.10/m3• Furthermore, the utilization of a Payloaderwill be optimized.
2. The capacity of ten (10) m3 for the Dump Truck as presented, may be reduced in cases
of extraordinary conditions where the road has a very steep gradient, in a severely
deteriorated condition or in cases of bridges with load limitations. It is impractical
during the actual hauling to load the full capacity of the Dump Truck. A proper
explanation/justifications shall be made, however, in the preparation of estimate.
3. For items of work that involves hauling and disposal of materials where hauling distance
was indicated, in cases when actual hauling distance is shorter or longer than the
assumed hauling distance of 3 km in the standard cost sheets, corresponding
equipment hours for Dump Truck shall be adjusted based on the cycle time analysis.
The actual hauling distance should be the nearest possible disposal site determined by
the Implementing Office prior to the preparation of the ABC/POWand shall be indicated
in the DUPA.
4. For equipment utilization of less than one (1) day, the scheduled operating hours shall
be paid at operated cost per hour and the remaining hours of the minimum 8 hours a
day shall be considered for payment as bare rental rates.
5. The utilization of equipment other than the equipment model and capacity presented in
the standard cost sheets may be allowed, provided there is a corresponding justification
in the substitution. Rental rates of equipment should be based from ACELGuidebook or
the Bureau of Equipment Rental Ratesguidelines.
6. The presented DUPA is based on a one (1) gang of labor and equipment with the
specified output per unit. To increase the output, additional equipment and labor may
be added or an equipment with a higher capacity may be adopted.
7. The production outputs per item of work were established based on normal condition
and study conducted by the Bureau of Construction (BOC) field engineers during
construction of projects being implemented by the BOC.Any deviation to suit actual site
condition that tends to increase the total unit cost shall be subjected for approval by
the BOC.
2
8. The application of Mark-Up (OCM and Profit) shall be in accordance with the ranges of
the Total Estimated Direct Cost (EDe) of the project as prescribed under D.O. No. 197,
Series of 2016 or latest issuance.
9. The cost of materials component in the Standard Cost Sheets shall be based on the
latest Construction Materials Price Data submitted quarterly by the District Engineering
Offices, which includes payment of local taxes and hauling/delivery cost to site.
10. The cost of labor shall be based on the labor rates established for each District
Engineering Office, following the minimum labor wage as approved by the NWPC,
DOLE, plus monetary benefits calculated in accordance with D.O. No. 71, Series of 2012
or latest issuance.
,J
3
SECTION A
.J
4
A. COST ESTIMATION PROCESS
Consultant
UPMO
Assistant Secretary
BOD & BOC Undersecretary
Secretary
1. The Estimator shall determine the items of work involved based on the Approved Plans.
2. The Estimator shall prepare the DUPA, ABC & POW including its attachments applying
the items of work involved based on the latest standard labor rates & CMPD, standard
cost sheets and D.O. 22, Series of 2015 .
. ..0
3. The District Engineer shall approve the ABC & POW, if the project is within the Itmits of
authority delegated to him/her.
4. If beyond the authority of the DEO, forward the DUPA, ABC & POW and Approved
Construction Plans together with the required attachments to the Regional Office for
review/evaluation and approval, if the project is within the limits of the delegated
authority of the Regional Director.
5. If Planning and Design Division of the Regional Office will make an adjustment in the
quantities and delete/add pay item/s in the submitted construction plans, the ABC &
POW shall be adjusted accordingly by the District Engineering Office and resubmit the
same for approval.
1. The Estimator shall determine the items of work involved based on the Approved Plans.
2. The Estimator shall prepare the DUPA, ABC & POW including its attachments applying
the items of work involved based on the latest standard labor rates & CMPD, standard
cost sheets and D.O. 22, Series of 2015.
3. The Regional Director shall approve the ABC & POW, if the project is within the limits of
authority delegated to him/her.
5
4. If beyond the authority of the RO, forward the DUPA, ABC & POW and Approved
Construction Plans together with the required attachments to the Bureau of Construction
(BOC) and Bureau of Design (BOD) respectively, for review/evaluation for approval of
the Assistant Secretary for Technical Services, Undersecretary for Technical Services or
Secretary depending on the limits of authority.
5. If Bureau of Design shall make an adjustment in the quantities and delete/add pay
item/s in the submitted construction plans, the ABC & POW shall be adjusted accordingly
by the Regional Office and resubmit the same for approval.
1. The Consultant shall determine the items of work involved based on the Approved Plans.
2. The Consultant shall prepare the DUPA, ABC & POW including its attachments applying
the items of work involved.
3. The Project Director shall conduct review/evaluation of the proposed ABC & POW and
recommends its approval to the authorized approving official concerned.
4. Forward the ABC & POW and Approved Construction Plans together with the required
attachments to the Bureau of Construction (BOC) and Bureau of Design (BOD)
respectively, for review/evaluation to be approved by the Assistant Secretary for
Technical Services, Undersecretary for Technical Services or Secretary depending on the
limits of authority.
5. If the Bureau of Design shall make an adjustment in the quantities and delete/add pay
item/s in the submitted construction plans, the ABC & POW shall be adjusted accordingly
by the concerned UPMO and resubmit the same for approval.
Approval of the ABC 8r. POW shall be based on the following (or its latest
issuance):
1. Department Order No. 91, Series of 2012 - Authority of the Assistant Secretary for
Technical Services to Approve Plans, Program of Works and Approved Budget for the
Contract for DPWH Locally-Funded and Foreign-Assisted Civil Works Projects Costing
more than PhP50 Million up to PhP100 Million.
2. Department Order No. 95, Series of 2013 - Reissuance of D.O. No.9, S. 2011 Re:
Conduct of Pre-Procurement, Procurement, and Implementation Activities for DPWH
Foreign-Assisted Civil Works Projects.
3. Department Order No. 109, Series of 2014 - Approval of Plans, Program of Works
(POW) and Approved Budget for the Contract for DPWH Locally-Funded Projects
Costing PhP50 Million and below Implemented by Unified Project Management
Offices.
4. Department Order No. 140, Series of 2014 - Increased Limits of Delegated Authority
to Regional Directors to Approve Plans, Program of Work (POW) and Approved
Budget for the Contract (ABC) of Locally-Funded Projects.
5. Department Order No. 54, Series of 2011 - Revised Limits of Responsibilities and
Authorities of Concerned DPWH Offices and Officials in the Conduct of Pre-
Procurement, Procurement, and Implementation Activities for DPWH Locally-Funded
Civil Works Project.
6
PREPARATION OF DETAILED UNIT PRICE ANALYSIS
1. General
a. Determine the scope of works based on approved plans and specification including
other requirements adopting the standard pay items of works per Department Order
No. 96, Series of 2016.
b. Calculate the quantity and cost of material component of every item of work based
on plans and specifications and prevailing prices of construction materials in the
Construction Materials Price Data (CMPD) with consideration of allowance for waste
and/or losses not to exceed 5% of the material's requirement.
c. Determine the appropriate quantity based on best norms and practices in the
construction industry and cost for manpower and equipment requirement to be used
based on Standard Labor Rates per Region and latest ACEL rates.
d. Determine the unit cost per item of work as presented in Item 5.
Forema n------------------------------------1
Skilled Worker (Mason, carpenter)----- 2
Unskilled Labor---------------------------- 6
The production output per hour of an item of work should be derived based on the
number of days and appropriate manpower and equipment utilized to complete the work
in accordance with the right construction methodology. In this manual, the production
output was derived by the Bureau of Construction (BOC) Engineers based on actual study
and best practices during the construction of BOC implemented projects.
Number of hours to complete the work which includes setting of equipment and
accessories, batching, delivery and pouring of concrete= 6 hours and 21 minutes
(6.85 hr)
7
Type and number of equipment and tools including lightings utilized during pouring:
The percentages of OCM, Profit and VAT to be applied to the estimated direct cost (i.e.
cost of material, labor and equipment rental) should be based on Department Order
(DO) No. 197, Series of 2016 (Guidelines in the Preparation of Approved Budget for the
Contract) or latest issuance.
B. Equipment
8
6. Cost estimation techniques and best practices
.J
9
SECTION B
.J
10
B.1 SUMMARYTABLEOF ITEMSOFWORKAND DESCRIPTION
PART A EARTHWORKS
I-
800(2) Clearing and Grubbing (I.s.) 24
PART C FINISHING
4.5mm/ 6.0 mm Fiber Cement Board/ 4.5mm/ 6.0 mm 4' X 8' thk
fiber cement board/ 4.5mm Marine Plywood/ 6.0 mm Marine
1003(2) 90
Plywood/ 6.0 mm Ordinary Plywood on Metal Frame Double
Wall Partition
Hollow Steel Door/ Steel Flush Door/ Grille Door/ Steel Louver
1006 93
Door
1006(5) Fire Rated Fire Exit Steel Door 94
1052( 15)b Precast, Prestressed Concrete Piles, driven (hard strata) 170
1052( 16)a Test Piles, furnished and driven (type A, B, C or D), soft strata 171
1052( 16)b Test Piles, furnished and driven (type A, B, C or D), hard strata 172
1052(18)a Concrete Piles cast in Steel Shells, furnished and driven 179
1052(19)a Concrete Piles cast in Steel Pipes, furnished and driven 181
1052(22)b High Strain Dynamic Testing (PDA), ordinary soil condition 200
1052 (29) Micro Piles In Drilled Holes, 0.20m 0 (ordinary soil condition) 201
D. ELECTRICAL
1101 (2) 80.00 mm2 - 125 mm2 Electric Wire (TWITHHN/TWHN2) 215
•
Duplex Convenience Outlet/Receptacle, Grounding Type (GT) /
Weather Proof Duplex Convenience Outlet/Receptacle,
Grounding Type (GT)/ Special Purpose Convenience
1101 Outlet/Receptacle, Grounding Type for ACU, WH, etc/ 228
Explosion Proof Type Duplex Convenience Outlet/Receptacle,
- Grounding Type (GT)/ Duplex Convenience Outlet/Receptacle
with Ground Fault Circuit Interupter
Main Enclosed Automatic Circuit Breaker 100 AT, 125 AT, 205
1102 AT, 225 AT, 3P, 240V NEMA I, NEMA 3R, NEMA 4x Flushed/ 239
Surface Mounted
Main Enclosed Automatic Circuit Breaker 100 AT, 125 AT, 200
1102 AT , 2P, 225 AT, 2P, 240V NEMA I, NEMA 3R, NEMA 4x 240
Flushedf Surface Mounted
Low Voltage Switch Board Main 2500-4000 AT, 3P, 240V NEMA
1102 241
I with Breaker
PART E MECHANICAL
1202(2)a Fire Pump with complete control and standard accessories 255
1202(2)b Jockey Pump with complete control and standard accessories 256
A. Labor
a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District
b. Unskilled Laborer 2 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
3
a. Dumptruck (12 yd ) 2 1.00 See latest AGEL rental rates.
d
b. Payloader (1.50 m ) 1 1.00
c. Bulldozer (155 hp), D65A-8 1 1.00
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the time
of dump truck will be adjusted accordingly based on the
hauling cycle analysis.
.J
F. Materials
23 Part A - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. labor
B. Equipment
F. Materials
24 Part A - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
a. Construction Foreman 1 0.33 Labor Rates are variable per RegioniDistrict
b. Skilled Laborer 1 0.33 based on minimum wage as approved by
c. Unskilled Laborer 2 0.33 DOLE. Refer to the Schedule of Labor Rates.
Name and Capacity No of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
3
a. Backhoe (0.80 m ) 1 0.25 See latest ACEL rental rates.
b. Dumptruck (12 yd3) 1 0.17
c. Chain Saw 1 0.17
Minor Tools (5% of Labor Cost)
Note:
Add Boom Truck if necessary for trimming in urban
areas .
.J
F. Materials
a. Rope, 1" 0- 5 uses m 20.00 Prices of materials are variable per Regionl
District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
25 Part A - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.lDescription 800(3)b Individual Removal of Trees (Small b, above 300 mm 0 up to 500 mm 0)
Unit of Measurement ea
Output per hour 1.00 ea
A. Labor
a. Construction Foreman 1 0.67 Labor Rates are variable per RegionlDistrict
b. SkiUed Laborer 1 0.67 based on minimum wage as approved by
c. Unskilled Laborer 2 0.67 DOLE. Refer to the Schedule of Labor Rates.
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
Note:
Add Boom Truck if necessary for trimming in urban
areas .
.J
F. Materials
a. Rope, 1" 0- 5 uses m 20.00 Prices of materials are variable per Regionl
District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
26 Part A - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.lDescription 800(3)c Individual Removal of Trees (Small c, above 500 mm 0 up to 750 mm 0)
Unit of Measurement ea
Output per hour 1.00 ea
A. labor
a. Construction Foreman 1 3.33 Labor Rates are variable per RegionlDistrict
b. Skilled laborer 1 3.33 based on minimum wage as approved by
c. Unskilled laborer 2 3.33 DOLE. Refer to the Schedule of Labor Rates.
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
Note:
Add Boom Truck if necessary for trimming in urban
areas .
.J
F. Materials
a. Rope, 1" 0 -5 uses m 20.00 Prices of materials are variable per Regionl
District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
27 Part A - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description 800(3)d Individual Removal of Trees (Small d, above 750 mm 0 up to 900 mm 0).
Unit of Measurement ea
Output per hour 1.00 ea
A. Labor
a. Construction Foreman 1 6.67 Labor Rates are variable per Region/District
b. Skilled Laborer 1 6.67 based on minimum wage as approved by
c. Unskilled Laborer 2 6.67 DOLE. Refer to the Schedule of Labor Rates.
B. Equipment
Note:
Add Boom Truck if necessary for trimming in urban
areas.
F. Materials
.
a. Rope, 1" 0- 5 uses m 20.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
28 Part A - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description 800(4) Individual Removal ofTrees (large, above 900 mm (11)
Unit of Measurement ea
Output per hour 1.00 ea
A. Labor
a. Construction Foreman 1 8.33 Labor Rates are variable per Region/District
b. SkiUed Laborer 1 8.33 based on minimum wage as approved by
c. Unskilled Laborer 2 8.33 DOLE. Refer to the Schedule of Labor Rates.
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
3
a. Backhoe (0.80 m ) 1 6.25 See latest ACEL rental rates.
3
b. Dumptruck (12 yd ) 1 4.16
c. Chain Saw 1 4.16
Minor Tools (5% of Labor Cost)
Note:
Add Boom Truck if necessary for trimming in urban
areas .
.J
F. Materials
a. Rope, 1" (11- 5 uses m 20.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
29 Part A - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
B. Equipment
.J
F. Materials
30 Part A - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
3
a. Dump Truck (12 yd ) 2 1.00 See latest AGEL rental rates.
3
b. Backhoe (0.80 m ) 1 0.50
c. Backhoe with Breaker (0.80 m3) 1 0.50
Minor Tools (10% of Labor Cost)
.J
F. Materials
31 Part A - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
B. Equipment
a. Dump Truck (12 yd3) 2 1.00 See latest AGEL rental rates.
b. Backhoe (0.80 m3) 1 0.25
c. Backhoe with Breaker (0.80 m3) 1 0.75
Minor Tools (10% of Labor Cost)
.J
F. Materials
32 Part A - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
B. Equipment
.J
F. Materials
33 Part A - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
34 Part A - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
35 Part A - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
B. Equipment
F. Materials
Prices of materials are variable per Region!
a. Embankment Materials m3 1.25 District based on the prevailing unit prices in
(wI 25% Shrinkage Factor) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
36 Part A - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
37 Part A - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description 900 Structural Concrete (Ready Mix, Class AAlClass A/Class B/Class C/Class P/Seal Concrete,
7 days/14 days/28 days)
Unit of Measurement m3
3
Output per hour 3.72 m
A. labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Ready Mix, Class AAlClass B/Class C/Class P, 7 Prices of materials are variable per Regionl
3
days/14 daysl 28 days m 1.05 District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
Item No./Description 900( 1) Structural Concrete for Footing and Slab on Fill ( Ready Mix Concrete, Class A, 7 days/14 days)
Unit of Measurement m3
3
Output per hour 3.32 m
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.f
F. Materials
Sub - Total F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/12%/10%/8% of G
I. Contractor's Profit (CP) 10%/8% ofG
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: 1. This cost sheet shall be used for concreting footings and slab on fill by using ready mix concrete and manual pouring of
concrete applicable for Item Nos. 900(1 )b2 and 900(1 )c2.
Item No.lDescription 900(1) Structural Concrete for Footing Tie Beam, Column, Suspended Slab, Girder/Beam (Ready Mix
Concrete, Class A, 7 days/14 days)
Unit of Measurement m3
Output per hour 0.947 m3
Note:
Designation No. of Person/s No. of HourIs Hourly Rate Amount (PhP)
A. Labor
B. Equipment
,J
F. Materials
a. Ready Mix Concrete, 7 days/14 days m3 1.05 Prices of materials are variable per Regionl
District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
Sub - Total F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/12%/10%/8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: 1. This cost sheet shall be used for concreting footing tie beam, column, suspended slab, girderlbeam by using ready mix
concrete and manual pouring of concrete applicable for Item Nos. 900(1)a3, 900(1)a4, 900(1)a5, 900(1)a6, 900(1)b3,
900(1 )b4, 900(1 )b5, and 900(1)b6.
Item No./Description 900(1 )c2 Structural Concrete for Footing and Slab on Fill (Class A, 28 days)
Unit of Measurement m3
3
Output per hour 0.357 m
A. labor
Name and Capacity No of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Item No./Description 900(1) Structural Concrete for Footing Tie Beam, Column, Suspended Slab, Girder/Beam (Class A, 28 days)
Unit of Measurement
Output per hour
A. labor
- Labor Rates are variable per Region/District
a. Construction Foreman 1 1.00
based on minimum wage as approved by
b. Skilled laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
b. Unskilled laborer 4 1.00
Name and Capacity No of Unitls No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
C. Total (A + B)
D. Output per Hour = 0.270 m3
E. Direct Unit Cost (C + D)
F. Materials
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Item No./Description 902(1) Reinforcing Steel of Reinforced Concrete Structures for One-Storey, Grade 40/Grade 60
Unit of Measurement kg
Output per hour 143.438 kg
A. La bor
Name and Capacity No of Unit/s No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. Deformed Reinforcing Steel kg 1.00 Prices of materials are variable per Regionl
District based on the prevailing unit prices in
b. #16 Galvanized Iron Wire kg 0.015 the locality which include payment of local
c. Consumables (5% of Materials Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
Item No./Description 902( 1) Reinforcing Steel of Reinforced Concrete Structures for Two upto Five Storey
Unit of Measurement kg
Output per hour 129.094 kg
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
Item No./Description 903(2) Formworks and Falseworks (for two to five-storey building)
Unit of Measurement m2
Output per hour 4.5 m2
A. Labor
Installation
a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District
based on minimum wage as approved by
b. Skilled Laborer 4 1.00
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00
Stripping
a. Construction Foreman 1 0.56
b. Unskilled Laborer 6 0.56
Sub - Total for A
Name and Capacity Quantity No. of Dayls Daily Rental Rate Amount (PhP)
B. Equipment
=
Area 205.01 m2
a. H-Frame 1.7 m x 1.2m, set 40 14.00 Rental cost for scaffoldings may vary per
RegionlDistrict.
2 pes H-frames
4 pcs diagonal cross braces
4 pcs horizontal braces
8 pcs joint pins
b. Shoring Jack, 3.8 m full extension 62 14.00
c. Adjustable U-head Jack, 0.6m 80 14.00
d. Adjustable Base Jack, 0.6m 80 14.00
e. 1-1/2" GI Pipe x 6.0 m 62 14.00
f. 1-1/2" GI Pipe x 3.0 m 16 14.00
g. 1-1/2" GI Pipe x 4.0 m 32 14.00
h. 1-1/2" GI Pipe x 1.0 m 216 14.00
i. Tie Rod x 0.60m 278 14.00 .J
F. Materials
Prices of materials are variable per Regionl
District based on the prevailing unit prices in
a. Phenolic Board (0.019 x 1.2 x 2.4) - 5 uses pc 0.347 the locality which include payment of local
c. Good Lumber - 3 uses bd ft 4.727 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
b. Consumables (5% of Materials Cost)
established quarterly by Central Office Price
Monitoring Committee.
A. Labor -
Installation
a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District
b. Skilled Laborer based on minimum wage as approved by
2 1.00
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 4 1.00
Stripping
a. Construction Foreman 1 0.41
b. Unskilled Laborer 6 0.41
Sub - Total for A
Name and Capacity Quantity No. of Dayls Daily Rental Rate Amount (PhP)
B. Equipment
.J
F. Materials
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
49 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.lDescription 1001(1)a 50 mm ¢ -100 mm ¢ PVC Pipe, Series 6001 Series 1000
Unit of Measurement m
Output per hour 3.00 m
A. Labor
c. Unskilled Laborer
DOLE. Refer to the Schedule of Labor Rates.
2 1.00
Name and Capacity No of Unit/s No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
50 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description 1001(1)a 150 mm - 300 mm 0 PVC Pipe, Series 6001 Series 1000
Unit of Measurement m
Output per hour 4.00 m
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. 150 mm 0 PVC Pipe, Series 6001 Series 1000 m 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
51 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
-
a. Construction Foreman 1 0.98 Labor Rates are variable per Region/District
based on minimum wage as approved by
b. Skilled Laborer 2 0.98
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 4 0.98
Name and Capacity No of Unitls No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
52 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
53 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
54 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
55 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
56 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. 50 mm 0 High Density Polyethylene (HDPE) Pipe m 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
57 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.lDescription 1001 (1)c 150 mm ¢ - 300mm ¢High Density Polyethylene (HDPE) Pipe
Unit of Measurement m
Output per hour 4.00m
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
oJ
F. Materials
a. 150 mm 0 High Density Polyethylene (HDPE) Pipe m 1.00 Prices of materials are variable per Regionl
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
58 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
(Labor cost for these items are to be consideredl included in the installation of pipes.) Labor Rates are variable per Region/District
based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
Name and Capacity No of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. PVC/HDPE Fittings (Elbowl Clean Out! Couplingl Prices of materials are variable per Region/
ea 1.00
District based on the prevailing unit prices in
Wyel Teel Reducerl P-trapl Bushingl Plug) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
59 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
F. Materials
3
a. Item 900 - Reinforced Concrete m
b. Item 902 - Reinforcing Steel kg
a. Item 903 - Formworks and Falseworks m2
60 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
3
a. Item-803 - Structure Excavation m
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
61 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
62 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unit/s No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
63 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
See derivations for Item Nos. 1001(1)c, 1001(3), 1001(4), 1001(5), 1001(6) and 1001(7).
Name and Capacity No of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
.J
C. Total (A + B)
D. Output = 1.00I.s.
E. Direct Unit Cost (C + D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
See derivations for Item Nos. 1001(1)c, 1001(3), 1001(4), 1001(5), 1001(6) and 1001(7).
64 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS CDUPA)
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a.13 mm 0 - 50 mm 0 Galvanized Iron Pipe pc 1.00 Prices of materials are variable per Regionl
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
65 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. 65 mm 0 - 150 mm 0x 6 m Galvanized Iron Pipe pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
66 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A Labor
Name and Capacity No of Unit/s No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. Galvanized Iron Fittings (Elbowl Teel Reducer-Teel pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
Socket! Couplingl Reducer Coupling)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
67 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.lDescription 1002(3)a 13 mm 0 - 50 mm 0 Polyprophylene Random Copolymer (PPR-C) Pipe, PN 101 PN 161 PN 20
Unit of Measurement pc
Output 1 pc
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
68 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.lDescription 1002(3)a 63 mm ¢ -100 mm ¢ Polyprophylene Random Copolymer (PPR-C) Pipe PN 101 PN 161 PN 20
Unit of Measurement pc
Output 1 pc
A. Labor
Name and Capacity No of Unit/s No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
69 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. Polyprophylene Random Copolymer (PPR-C) pc 1.00 Prices of materials are variable per Regionl
District based on the prevailing unit prices in
Fittings (Elbowl Tee/ Female Threaded Tee/ Female
the locality which include payment of local
Elbow/ Female Threaded Adaptorl Male Threaded taxes and hauling cost to the project site.
Adaptorl End Cap) Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
70 Part C - Finishing
"
A. Labor
-
a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District
based on minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
71 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unit/s No. of Houris Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
72 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
(Labor-cost for these items are to be consideredlincluded in the installation of pipes.) Labor Rates are variable per RegionlDistrict
based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. Polyvinyl Chloride (PVC) Fittings, Blue (Elbowl pc 1.00 Prices of materials are variable per Regionl
District based on the prevailing unit prices in
Teel Tee-Reducerl Elbow Reducerl Socket! Couplingl
the locality which include payment of local
Reducerl Male Threaded Adaptorl Female Threaded taxes and hauling cost to the project site.
Adaptorl Cap) Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
73 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
74 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. Water Closet I Urinal with complete accessories set 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
75 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description 1002(5) Kitchen Sink/Scrub Up Sink/Slop Sink with Complete Accessories
Unit of Measurement set
Output 1 set
A. Labor
B. Equipment
F. Materials
a. Kitchen Sink/Scrub Up Sink/Slop Sink with Prices of materials are variable per Region/
set 1.00 District based on the prevailing unit prices in
complete accessories
the locality which include payment of local
b. Consumables (5% of Materials Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
76 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.lDescription 1002(5) Wall Hung/Countertop/Under Counter Lavatory with Complete Accessories
Unit of Measurement set
Output 1 set
A. Labor
Name and Capacity No of Unit/s No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. Lavatory (Wall Hung/Countertop/Under Counter) set 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
77 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. Floor Drain Plate set 1.00 Prices of materials are variable per Regionl
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
78 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A Labor
Name and Capacity No of Unit/s No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. Soap Holder (Toilet Soapl Liquid Soap) set 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
79 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Toilet Tissue Holder/Dispenser set 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
80 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. Bidet! Faucet! Hose Bibb set 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
81 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. 40 mm 1IlStainless Steel Grab Bar m 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
82 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
B. Equipment
.J
a. Shower headl Shower Valve set 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
83 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
F. Materials
84 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
85 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
F. Materials
86 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description 1003(1 ) 4.5mm Fiber Cement Board/ 4.5 mm Marine Plywood/ 6 mm Marine Plywood/ 6mm Ordinary Plywood
on Metal Frame Ceiling
Unit of Measurement m2
Output per hour 1.243 m2
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. 4.5mm Fiber Cement Board/ 4.5 mm Marine pc 0.365
Plywood/6 mm Marine Plywood/6mm Ordinary
Plywood
b.Metal Furring (size variable on plan and pc 1.131
and specifications ) 3m length
c. Carrying Channels (size variable depends on plans pc 0.357 Prices of materials are variable per Regionl
District based on the prevailing unit prices in
and specifications)
the locality which include payment of local
d. Hanger Bars/Rod (size variable depends on plans pc 1 taxes and hauling cost to the project site.
and specifications) Refer to the Construction Material Price Data
established quarterly by Central Office Price
e. Channel clip pc 6
Monitoring Committee.
f. Wall Angle pc 0.238
g. Rivets pc 14
h. 1" Metal Screw pc 4
Note:
Quantities were derived from plans and
specifications of a standard school building with carrying
channels spaced by 1.20 m and metal furring spaced by
0.40 m on center.
87 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description 1003(1)a 4.5mm Fiber Cement Board/ 4.5 mm Marine Plywood/ 6 mm Marine Plywood/ 6mm Ordinary Plywood
in Wood Framing Ceiling
Unit of Measurement m2
Output per hour 1.489 m2
A. Labor
-
a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District
b. Skilled Laborer 1 1.00 based on minimum wage as approved by
c. Unskilled Laborer 2 1.00 DOLE Refer to the Schedule of Labor Rates.
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. 4.5mm Fiber Cement Board/ 4.5 mm Marine
Plywood/6 mm Marine Plywoodl 6mm Ordinary Prices of materials are variable per Region!
pc 0.365
District based on the prevailing unit prices in
Plywood
the locality which include payment of local
b. Good Lumber bd.ft 9.257 taxes and hauling cost to the project site.
c. Assorted Nails kg 0.139 Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
Note:
Quantities are derived from a ceiling system with
ceiling nailers spaced at 0.40 m on centers.
88 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment .
.J
F. Materials
a. Gypsum Board pc 0.365
b.Metal Furring (size variable on plan and pc 1.13
c. Carrying Channels (size variable depends on plans Prices of materials are variable per Region!
pc 0.36 District based on the prevailing unit prices in
and specifications)
the locality which include payment of local
d. Hanger Bars/Rod «size variable depends on plans taxes and hauling cost to the project site.
pc 1.00
and specifications) Refer to the Construction Material Price Data
e. Channel clip pc 6 established quarterly by Central Office Price
Monitoring Committee
f. Wall Angle pc 0.238
g. Rivets pc 14
h. 1" metal screw pc 4
Note:
Quantities were derived from plans and
specifications of a standard school building with carrying
channels spaced by 1.20 m and metal furring spaced by
0.40 m on center.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/12%/10%/8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
89 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description 1003(2) 4.5mml 6.0 mm Fiber Cement Boardl 4.5mml 6.0 mm 4' X 8' thk fiber cement boardl 4.5mm Marine
Plywood/6.0 mm Marine Plywood/6.0 mm Ordinary Plywood on Metal Frame Double Wall Partition
Unit of Measurement
Output per hour
A. Labor -
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. 4.5mml 6.0 mm 4' X 8' thk fiber cement boardl Prices of materials are variable per Region/
4.5mm Marine Plywood/6.0 mm Marine Plywoodl 6.0 pc 0.730 District based on the prevailing unit prices in
mm Ordinary Plywood the locality which include payment of local
taxes and hauling cost to the project site.
b. Metal Studs (size variable depends on plan and Refer to the Construction Material Price Data
specs.) 3 m length pc 1.181
established quarterly by Central Office Price
c. Rivets Monitoring Committee.
pc 117.00
d. 1" Metal Screw pc 4.00
90 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A Labor
(Labor_ cost for these items are to be considered/included in the installation of doors, windows, and other fabricated materials.)
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
Prices of materials are variable per Region/
District based on the prevailing unit prices in
a. Finishing Hardwares (LocksetlLatches, Bolts, Door set 1.00 the locality which include payment of local
Closer, Knobs/Handles/ Hinges/ Ladderl Grab Bar) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
91 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.lDescription 1005 Residential Casement Steel Windowsl Heavy Duty Side-hinged Ventilatorl Projected Ventilatorl
Awning Ventilatorl Grille Window
Unit of Measurement m2
Output per hour 0.18m2
A. Labor
Name and Capacity No of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
Note:
It is assumed that fabrication of steel windows are
already completed. Thus, labor and equipment output
shall be based on installation time only.
F. Materials
m
2 Prices of materials are variable per Regionl
a. Residential Casement Steel Windowsl Heavy Duty 1.00
District based on the prevailing unit prices in
Side-hinged Ventilatorl Projected Ventilatorl Awning the locality which include payment of local
Ventilatorl Grille Window taxes and hauling cost to the project site.
b. Consumables (5% of Materials Cost) Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
92 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description 1006 Hollow Steel Door/ Steel Flush Door/ Grille Door/ Steel Louver Door
Unit of Measurement m2
Output per hour 0.26 m2
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
93 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
m
2 Prices of materials are variable per Region/
a. Fire rated Fire Exit Steel Door 1.00
District based on the prevailing unit prices in
b. Consumables (3% of Materials Cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
94 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
95 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description 1008 Aluminum Glass Window (Sliding/ Casement! Awning/ Fixed Type)
Unit of Measurement m2
Output per hour 0.36 m2
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Aluminum Glass Window (Sliding/ Casement! Prices of materials are variable per Region/
2 District based on the prevailing unit prices in
Awning/ Fixed Type) m 1.00
the locality which include payment of local
b. Consumables (3% of Materials Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
96 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
.J
97 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description 1010(1) Frames (Jambs, Sill, Head, Transoms and Mullions)
Unit of Measurement set
Output 1 set
A. Labor
Name and Capacity No of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. Jambs, Sill, Head, Transoms and Mullion set 1.00 Prices of materials are variable per Regionl
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
98 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
99 Part C - Finishing
DETAILED UNIT PRICE ANAlYSIS (DUPA)
A. Labor
Name and Capacity No of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A Labor
Name and Capacity No of Unit/s No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. Steell Aluminum Roll Up Door Set 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (3% of Materials Cost)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
A. Labor
B. Equipment
.J
F. Materials
A. Labor
-
a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District
b. Skilled Laborer 1 1.00 based on minimum wage as approved by
c. Unskilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
.
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Item No./Description 1013(2) Fabricated Metal Roofing Accessory (Ridge/Hip Rolls/Flashings/Counter FlashingNalley Roll)
Unit of Measurement m
Output per hour 10.00 m
A. Labor
B. Equipment
.J
F. Materials
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Gutter (0.6 mm) m 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. 12" x 1" Plain GI Strap pc 3.00 the locality which include payment of local
c. Blind Rivets pc 16.00 taxes and hauling cost to the project site.
d. Consumables (3% of Materials Cost) Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
Item No./Description 1014 Prepainted Metal Sheets (Corrugated, Short Spanl Long Span, below 0.427 thkl above 0.427 thk)
Unit of Measurement m2
2
Output per hour 2.076 m
A. Labor
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
Item No.lDescription 1014 Prepainted Metal Sheets (Rib Type, Short Spanl Long Span, below 0.427 thkl above 0.427 thk)
2
Unit of Measurement m
Output per hour 2.769 m2
A. Labor
B. Equipment
F. Materials
a. Prepainted Metal Sheets (Rib Type, Short Spanl Prices of materials are variable per Region!
District based on the prevailing unit prices in
Long Span, below 0.427mm thkl above 0.427mm m2 1.00
the locality which include payment of local
thk) taxes and hauling cost to the project site.
b. Tek screw/J-bolt with washers pc 10.00 Refer to the Construction Material Price Data
c. Consumables (3% of Materials Cost) established quarterly by Central Office Price
Monitoring Committee.
A. Labor-
B. Equipment
.J
F. Materials
A. labor-
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Primer Coat gal 0.04 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Liquid Waterproofing gal 0.03 the locality which include payment of local
c. Consumables (3% of Materials Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
A. Labor -
Labor Rates are variable per Region/District
a. Construction Foreman 1 1.00
based on minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 1.00
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
Item No./Description 1017 50mm (11 - lOOmm (11 Roof Drain/Canopy Drain/ Gutter Drain with Strainer
Unit of Measurement set
Output 1 set
A. Labor -
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. 50mm I1l - 100mm I1l Roof Drain/Canop Drain/ Prices of materials are variable per Region/
set 1.00 District based on the prevailing unit prices in
Gutter Drain with Strainer
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
Item No./Description 1018 Unglazed Tilesl Granite Tilesl Synthetic Granite Tiles
2
Unit of Measurement m
Output per hour 1.95 m2
A. labor-
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Unglazed Tilesl Granite Tilesl Synthetic Granite 2 Prices of materials are variable per Regionl
m 1.050
District based on the prevailing unit prices in
b. Cement bag 0.325 the locality which include payment of local
c. Sand 3
m 0.026 taxes and hauling cost to the project site.
d. Tile Grout Refer to the Construction Material Price Data
bag 0.125
established quarterly by Central Office Price
Monitoring Committee.
A. labor-
B. Equipment
.J
F. Materials
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate . Amount (PhP)
B. Equipment
.J
F. Materials
A. Labor -
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of UniUs No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
B. Equipment
.J
F. Materials
A. Labor
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
A. labor
Name and Capacity No. of UniUs No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
A. Labor
-
a. Construction Foreman 1 1.00 Labor Rates are variable per
b. Skilled Laborer 1 1.00 Region/District based on minimum wage as
c. Unskilled Laborer 2 1.00 approved by DOLE. Refer to the Schedule
of Labor Rates.
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
A. Labor-
B. Equipment
F. Materials
a. Concrete Neutralizer gal 0.02 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Concrete SealerlPrimer gal 0.04 the locality which include payment of local
c. Patching Compound gal 0.05 taxes and hauling cost to the project site.
d. Semi Gloss Latex (two coat only) gal 0.08 Refer to the Construction Material Price Data
e. Consumables (5% of Materials Cost) established quarterly by Central Office Price
Monitoring Committee.
B. Equipment
.f
F. Materials
a. Glazzing Putty gal 0.05 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Flat Wall Enamel gal 0.04 the locality which include payment of local
c. Enamel Quick Dry gal 0.04 taxes and hauling cost to the project site.
d. Paint Thinner I 0.25 Refer to the Construction Material Price Data
e. Tinting Color (Optional) pint 0.01 established quarterly by Central Office Price
Monitoring Committee.
f. Consumables (5% of Materials Cost)
A. Labor _
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. Red Oxide Primer gal 0.04 Prices of materials are variable per Regionl
District based on the prevailing unit prices in
b. Enamel Paint gal 0.10
the locality which include payment of local
c. Paint thinner L 0.25 taxes and hauling cost to the project site.
d. Tinting Color (Optional) pint 0.01 Refer to the Construction Material Price Data
e. Consumables (5% of Materials Cost) established quarterly by Central Office Price
Monitoring Committee.
A. Labor.
B. Equipment
F. Materials
A. Labor-
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Glazzing Putty gal 0.05 Prices of materials are variable per Region!
District based on the prevailing unit prices in
b. Flat Wall Enamel gal 0.04
the locality which include payment of local
c. Enamel Quick Dry gal 0.04 taxes and hauling cost to the project site.
d. Paint Thinner gal 0.01 Refer to the Construction Material Price Data
e. Tinting Color (Optional) pint 0.01 established quarterly by Central Office Price
Monitoring Committee.
f. Consumables (5% of Materials Cost)
B. Equipment
.J
F. Materials
A. Labor
-
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.f
F. Materials
a. Stainless Steel Doors and Frames 2 Prices of materials are variable per Region/
m 1.000
District based on the prevailing unit prices in
b. Consumables (3% of Materials Cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
A. Labor
-
a. Construction Foreman 1 1.00 Labor Rates are variable per RegionlDistrict
b. Skilled Laborer 1 1.00 based on minimum wage as approved by
c. Unskilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
Name and Capacity No. of UniUs No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. PVC Doors and Frames 2 Prices of materials are variable per Regionl
m 1.000
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
B. Equipment
.J
F. Materials
a. Perforated Aluminum Ceiling Pannel with frames Prices of materials are variable per Region/
m2 1.000
District based on the prevailing unit prices in
b. Consumables (3% of Materials Cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
Item No./Description 1046 100 mm CHB Non Load BearinglLoad Bearing (including Reinforcing Steel)
Unit of Measurement m2
2
Output per hour 3.825 m
A . Labor .
Labor Rates are variable per
a. Construction Foreman 1 1.00
Region/District based on minimum wage
b. Skilled Laborer 2 1.00 as approved by DOLE. Refer to the
c. Unskilled Laborer 3 1.00 Schedule of Labor Rates.
B. Equipment
.J
F. Materials
Item No./Description 1046 150mm CHB Non-LoadBearingl Load Bearing (including Reinforcing Steel)
Unit of Measurement m2
Output per hour 3.180 m2
A. Labor
-
a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District
b. Skilled Laborer 2 1.00 based on minimum wage as approved by
c. Unskilled Laborer 3 1.00 DOLE. Refer to the Schedule of Labor Rates.
B. Equipment
.J
F. Materials
a. 150 mm thk CHB (Load Bearing) pc 13.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Cement bag 1.500 the locality which include payment of local
c.Sand cU.m 0.04 taxes and hauling cost to the project site.
d. Reinforcing Steel kg 3.24* Refer to the Construction Material Price Data
e. #16 Tie wire kg 0.05 established quarterly by Central Office Price
Monitoring Committee.
A. Labor.
B. Equipment
.J
F. Materials
A. Labor·
Fabrication
a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District
based on minimum wage as approved by
b. Skilled Laborer 2 1.00
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00
Erection
a. Skilled Laborer 3 0.49
b. Unskilled Laborer 3 0.49
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. Structural Steel Framing including cross kg 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Acetylene kg 0.011 the locality which include payment of local
c. Oxygen kg 0.022 taxes and hauling cost to the project site.
d. Welding Rod kg 0.020 Refer to the Construction Material Price Data
e. Consumables (5% of Materials Cost) established quarterly by Central Office Price
Monitoring Committee.
A. labor
Fabrication
a. Construction Foreman Labor Rates are variable per Region/District
1 1.00
based on minimum wage as approved by
b. Skilled laborer 2 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled laborer 2 1.00
Erection
a. Skilled laborer 3 0.49
b. Unskilled laborer 3 0.49
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. Structural Steel Truss kg 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Acetylene kg 0.011
the locality which include payment of local
c. Oxygen kg 0.022 taxes and hauling cost to the project site.
d. Welding Rod kg 0.020 Refer to the Construction Material Price Data
e. Consumables (5% of Materials Cost) established quarterly by Central Office Price
Monitoring Committee.
A. Labor-
B. Equipment
.J
F. Materials
a. Structural Steel Purlins kg 1.05 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Welding Rod kg 0.020 the locality which include payment of local
c. Consumables (5% of Materials Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
A. Labor
-
a. Construction Foreman 1 0.10 Labor Rates are variable per Region/District
based on minimum wage as approved by
b. Skilled Laborer 1 0.10
DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 1 0.10 Rates.
Name and Capacity No. of UniUs No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
,J
F. Materials
a. Sagrod with nuts and bolts pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
A. Labor
-
Labor Rates are variable per Region/District
a. Construction Foreman 1 0.25 based on minimum wage as approved by
b. Skilled Laborer 1 0.25 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 0.25
B. Equipment
.J
F. Materials
A. Labor-
Name and Capacity No. of UniUs No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor -
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
A. labor
B. Equipment
Surface Preparation
a. Portable Grinder 2 0.40 See latest ACEL rental rates.
b. Jack Hammer 1 0.20
c. Air Compressor 1 0.40
c. Speed Ventilator 1 0.40
d. Electric Drill 1 0.20
e. Chipping Gun 1 0.10
f. Paddle Mixer 1 0.20
g. Generator Set (20KVA) 1 0.10
Application
a.Saturator Machine 1 0.10
b. Generator Set (20 KVA) 1 0.10 .J
F. Materials
A. Labor
B. Equipment
Surface Preparation
a. Portable Grinder 2 0.40 See latest ACEL rental rates.
b. Jack Hammer 1 0.20
c. Air Compressor 1 0.40
c. Speed Ventilator 1 0.40
d. Electric Drill 1 0.20
e. Chipping Gun 1 0.10
f. Paddle Mixer 1 0.20
g. Generator Set (20KVA) 1 0.10
Application
.J
a.Saturator Machine 1 0.10
b. Generator Set (20 KVA) 1 0.10
F. Materials
A. Labor
B. Equipment
.J
F. Materials
a. Portland Cement bags 14.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Additives L 3.50 the locality which include payment of local
c. Consumables (5% of Material Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
A. Labor -
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 1.00 See latest AGEL rental rates.
(Unloading and Stockpiling)
Minor Tools (10% of Labor Cost)
.J
F. Materials
a. Untreated Timber (375 mm (II average) bd-ft 48.30 Prices of materials are variable per Region/
b. Miscellaneous (5% of Materials Cost) District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Note: Monitoring Committee.
Assumed average minimum diameter is 375 mm
for less than 12 m length. For beyond 12 m length and
bigger diameter, adjust the quantity in bd-ft accordingly.
A. Labor
-
Labor Rates are variable per Region/District
a. Construction Foreman 1 1.00
based on minimum wage as approved by
b. Unskilled Laborer 4 1.00 DOLE. Refer to the Schedule of Labor Rates.
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 1.00 See latest ACEL rental rates.
(Unloading and Stockpiling)
Minor Tools (10% of labor cost)
F. Materials
a. Treated Timber (375 mm ¢ average) bd-ft 48.30 Prices of materials are variable per Region/
b. Miscellaneous (3% of Materials Cost) District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Note:
Monitoring Committee.
Assumed average minimum diameter is 375 mm
for less than 12 m length. For beyond 12 m length and
bigger diameter, adjust the quantity in bd-ft accordingly.
A. Labor
-
a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District
based on minimum wage as approved by
b. Skilled Laborer 2 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00
Name and Capacity No. of Unit/s No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 1.00 See latest ACEL rental rates.
(Unloading and Stockpiling)
Minor Tools (10% of Labor Cost)
.J
F. Materials
Item No./Description 1052(4)a.1 Precast Concrete Piles, furnished (400mm x 400mm - type A)
Unit of Measurement m
Output per hour 2.50m
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
2.50m
E. Direct Unit Cost (C + D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
cU.m 0.168
a. Ready Mix concrete, Class AA-27.60MPa @ 28Days* Prices of materials are variable per Regionl
b. Reinforced Steel Bar, Grade 60 kg 40.45 District based on the prevailing unit prices in
the locality which include payment of local
c. Tie Wire #16 (2% of RSB) kg 0.809
taxes and hauling cost to the project site.
d. Good Lumber - 4 uses bd-ft 15.333 Refer to the Construction Material Price Data
e. Marine Plywood, 1/2" x 4' x 8' - 4 uses pc 0.268 established quarterly by Central Office Price
f. Assorted CWN (1kg/100bd-ft of Lumber) kg 0.163 Monitoring Committee.
Casting Bed
a. Ready Mix Concrete, Class B cU.m 0.03
b. Good Lumber bd-ft 1.00
c. Base Course cU.m 0.06
Note:
*If no available Ready Mix Concrete at project site,
derive the cost of concrete using the Batching Plant or
One Bagger Mixer for small quantity.
Item No./Description 1052(4)a.2 Precast Concrete Piles, furnished (400mm x 400mm -type B)
Unit of Measurement m
Output per hour 2.50m
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 2.50m
E. Direct Unit Cost (C + D)
F. Materials
Prices of materials are variable per Regionl
cU.m 0.168
a. Ready Mix concrete, Glass AA-27.60MPa @ 28Days* District based on the prevailing unit prices in
the locality which include payment of local
b. Reinforced Steel Bar, Grade 60 kg 48.69
taxes and hauling cost to the project site.
c. Tie Wire #16 (2% of RSB) kg 0.974 Refer to the Construction Material Price Data
d. Good Lumber - 4 uses bd-ft 15.333 established quarterly by Central Office Price
e. Marine Plywood, 1/2" x 4' x 8' - 4 uses pc 0.268 Monitoring Committee.
f. Assorted CWN (1 kg/1 OObd-ft of Lumber) kg 0.163
Casting Bed
a. Ready Mix Concrete, Class B cU.m 0.03
b. Good Lumber bd-ft 1.00
c. Base Course cU.m 0.06
Note:
*If no available Ready Mix Concrete at Project Site,
derive the cost of concrete using the Batching Plant or
One Bagger Mixer for small quantity
Item No./Description 1052(4)b.1 Precast Concrete Piles, furnished (450mm x 450mm -type C)
Unit of Measurement m
Output per hour 2.30 m
A Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
J
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 2.30m
E. Direct Unit Cost (C + D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
Prices of materials are variable per Regionl
cU.m 0.213
a. Ready Mix concrete, Class AA-27.60MPa @ 28Days' District based on the prevailing unit prices in
the locality which include payment of local
b. Reinforced Steel Bar, Grade 60 kg 50.040
taxes and hauling cost to the project site.
c. Tie Wire #16 (2% of RSB) kg 1.001 Refer to the Construction Material Price Data
d. Good Lumber - 4 uses bd-ft 17.25 established quarterly by Central Office Price
e. Marine Plywood, 1/2" x 4' x 8' - 4 uses pc 0.30 Monitoring Committee.
f. Assorted CWN (1 kg/1 OObd.ft of Lumber) kg 0.183
Casting Bed
a. Ready Mix Concrete, Class B cU.m 0.033
b. Good Lumber bd-ft 1.00
c. Base Course cU.m 0.07
Note:
'If no available Ready Mix Concrete at Project Site,
derive the cost of concrete using the Batching Plant or
One Bagger Mixer for small quantity
Item No./Description 1052(4)b.2 Precast Concrete Piles, furnished (450mm x 450mm -type D)
Unit of Measurement m
Output per hour 2.30 m
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Payloader (1.50 m3), LX80-2C 1 0.05 See latest AGEL rental rates.
b. Concrete Vibrator 1 0.10
c. Plate Compactor (for Casting Bed) 1 0.27
d. Bar Bender 1 0.27
e. Bar Cutter 1 0.27
Minor Tools (10% of Labor Cost)
.J
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 2.30m
E. Direct Unit Cost (C + D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
Prices of materials are variable per Region!
cU.m 0.213 District based on the prevailing unit prices in
a. Ready Mix concrete, Class AA-27.60MPa @ 28Days*
the locality which include payment of local
b. Reinforced Steel Bar, Grade 60 kg 62.46
taxes and hauling cost to the project site.
c. Tie Wire #16 (2% of RSB) kg 1.249 Refer to the Construction Material Price Data
d. Good Lumber - 4 uses bd-ft 17.25 established quarterly by Central Office Price
e. Marine Plywood, 1/2" x 4' x 8' - 4 uses pc 0.30 Monitoring Committee.
Casting Bed
a. Ready Mix Concrete, Class B cU.m 0.033
b. Good Lumber bd-ft 1.00
c. Base Course cU.m 0.07
Note:
"If no available Ready Mix Concrete at Project Site,
derive the cost of concrete using the Batching Plant or
One Bagger Mixer for small quantity
Item No./Description 1052(5)a Precast, Prestressed Concrete Piles, furnished (400 mm x 400 mm)
Unit of Measurement m
Output per hour 48.00 m
A. Labor -
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 1.00 See latest ACEL rental rates.
Minor Tools (10% of Labor Cost)
.J
F. Materials
a. Precast, Prestressed Concrete Piles m 1.00 Prices of materials are variable per Region!
District based on the prevailing unit prices in
(delivered at site)
the locality which include payment of local
Miscellaneous (2% of Materials Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
Item No./Description 1052(5)b Precast, Prestressed Concrete Piles, furnished (450 mm x 450 mm)
Unit of Measurement m
Output per hour 48.00 m
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 1.00 See latest ACEL rental rates.
Minor Tools (10% of Labor Cost)
.J
F. Materials
a. Precast, Prestressed Concrete Piles m 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
(delivered at site)
the locality which include payment of local
Miscellaneous (2% of Materials Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 1.00 See latest ACEL rental rates.
Minor Tools (10% of Labor Cost)
F. Materials
a. Steel Sheet Pile KSP II (delivered at site) kg 48.00 Prices of materials are variable per Regionl
Miscellaneous (2% of Materials Cost) District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
Item No./Description 1052(7)a Precast Concrete Sheet Piles, furnished (0.50 m x 0.35 m)
Unit of Measurement m
Output per hour 1.90 m
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Payloader (1.50 m3), LX80-2C 1 0.03 See latest AGEL rental rates.
b. One Bagger Mixer 1 0.25
c. Concrete Vibrator 1 0.25
d. Water Truck/Pump (16000 L) 1 0.03
e. Bar Cutter 1 0.15
f. Bar Bender 1 0.15
g. Plate Compactor (5 hp), for Casting Bed 1 0.03
Minor Tools (10% of Labor Cost)
.J
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 1.90 m
E. Direct Unit Cost (C + D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
a. Reinforcing Steel Bar kg 41.64 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Cement bag 1.66
the locality which include payment of local
c.Sand m3 0.09 taxes and hauling cost to the project site.
d. Gravel m3 Refer to the Construction Material Price Data
0.18
established quarterly by Central Office Price
e. Plywood, 1/2" x 4' x 8' - 4 uses pc 0.24 Monitoring Committee.
f. Good Lumber - 4 uses bd-ft 12.40
g. #16 GI Tie Wire (2% of RSB) kg 0.83
h. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.12
Casting Bed
a. Cement bag 0.296
b.Sand m3 0.019
c. Gravel m3 0.037
d. Good Lumber - 4 uses bd.ft 1.00
e. Base Course m3 0.08
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Continoencies & Miscellaneous (OCM) Expenses 15%/12%/10%/8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No.lDescription 1052(7)b Precast Concrete Sheet Piles, furnished (0.50 m x 0.35 m), (Ready Mix Concrete)
Unit of Measurement m
Output per hour 2.30 m
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Reinforcing Steel Bar kg 41.64 Prices of materials are variable per Region!
District based on the prevailing unit prices in
b. Ready Mix Concrete, fc'=27.60 Mpa @28 days' m3 0.18
the locality which include payment of local
c. Plywood, 1/2" x 4' x 8' - 4 uses pc 0.24 taxes and hauling cost to the project site.
f. Good Lumber - 4 uses bd-ft 12.40 Refer to the Construction Material Price Data
g. #16 GI Tie Wire (2% of RSB) kg 0.83 established quarterly by Central Office Price
Monitoring Committee.
h. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.12
Casting Bed
a. Ready Mix Concrete, Class B m3 0.037
d. Good Lumber - 4 uses bd-ft 1.00
e. Base Course m3 0.08
Note:
'If no available Ready Mix Concrete at project site,
derive the cost of concrete using the Batching Plant or
One Bagger Mixer for small quantities.
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 0.58 See latest ACEL rental rates.
b. Drop Hammer 1 0.13
Minor Tools (10% of Labor Cost)
,J
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 3.00m
E. Direct Unit Cost (C + D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
a. Coco Log - 2 uses m 1.00 Prices of materials are variable per Regionl
District based on the prevailing unit prices in
b. Good Lumber (Falsework) - 4 uses bd-ft 16.00
the locality which include payment of local
c. NaillSpike (1 kg/100 bd-ft of Lumber) kg 0.16 taxes and hauling cost to the project site.
Miscellaneous (2% of Materials Cost) Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee,
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 0.58 See latest AGEL rental rates.
b. Drop Hammer 1 0.13
Minor Tools (10% of Labor Cost)
F. Materials
a. Coco Log - 2 uses m 1.00 Prices of materials are variable per Regionl
b. Good Lumber (Falsework) - 4 uses bd-ft 16.00 District based on the prevailing unit prices in
the locality which include payment of local
c. NaillSpike (1 kg/100 bd-ft of Lumber) kg 0.16
taxes and hauling cost to the project site.
Miscellaneous (2% of Materials Cost) Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
A. Labor
-
a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District
based on minimum wage as approved by
b. Skilled Laborer 6 1.00
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 1.00 See latest ACEL rental rates.
b. Diesel Hammer (K25 or equivalent) 1 0.25
c. Drop Hammer 1 0.40
d. Cutting Outfit 1 0.15
e. Welding Machine (500 A), Gas/Diesel Driven 1 0.10
Minor Tools (5% of Labor Cost)
.J
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 4.50m
E. Direct Unit Cost (C + D)
F. Materials
a. Coco Log - 2 uses m 1.00 Prices of materials are variable per Regionl
b. Good Lumber (Falsework) - 4 uses bd-ft 16.00 District based on the prevailing unit prices in
the locality which include payment of local
c. Nail/Spike (1 kg/100 bd-ft of Lumber) kg 0.16 taxes and hauling cost to the project site.
d. Oxygen/Acetylene (1 set/5000 kg of Steel) set 0.032 Refer to the Construction Material Price Data
e. Welding Rod (1 kg/2000 kg of Steel) kg 0.08 established quarterly by Central Office Price
Miscellaneous (2% of Materials Cost) Monitoring Committee.
Note:
Assumed weight of Steel H-Pile is 159 kglm
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 0.58 See latest AGEL rental rates.
b. Diesel Hammer (K25 or equivalent) 1 0.25
c. Drop Hammer 1 0.13
d. Welding Machine (500 A), Gas/Diesel Driven 1 0.08
e. Cutting Outfit 1 0.08
Minor Tools (5% of Labor Cost)
.J
F. Materials
a. Tubular Pile (0.40 m ¢ x 9.50 mm thk) m 1.00 Prices of materials are variable per Regionl
(delivered at site) District based on the prevailing unit prices in
the locality which include payment of local
b. Welding Rod (1 kg/2000 kg of Steel) kg 0.048 taxes and hauling cost to the project site.
c. Oxygen/Acetylene (1 set/5000 kg of Steel) set 0.019 Refer to the Construction Material Price Data
d. Coco Log - 2 uses m 1.00 established quarterly by Central Office Price
e. Good Lumber (Falsework) - 4 uses bd-ft 16.00 Monitoring Committee.
Note:
Assumed weight of Tubular Pipe Pile is 95.93
kglm
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 1.00 See latest AGEL rental rates.
b. Diesel Hammer (K25 or equivalent) 1 1.00
c. Drop Hammer 1 1.00
d. Welding Machine (500 A), Gas/Diesel Driven 1 1.00
e. Cutting Outfit 1 0.50
Minor Tools (5% of Labor Cost)
.f
F. Materials
a. Welding Rod (1 kg/2000 kg of Steel) kg 0.024 Prices of materials are variable per Region!
b. OxygenlAcetylene (1 set/5000 kg of Steel) District based on the prevailing unit prices in
set 0.0096
the locality which include payment of local
c. Coco Log - 2 uses m 0.18 taxes and hauling cost to the project site.
d. Good Lumber - 4 uses bd-ft 1.55 Refer to the Construction Material Price Data
e. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.02 established quarterly by Central Office Price
Monitoring Committee.
Miscellaneous (2% of Materials Cost)
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 0.56 See latest ACEL rental rates.
b. Diesel Hammer (K25 or equivalent) 1 0.31
c. Drop Hammer 1 0.31
d. Jack Hammer 2 0.19
e. Air Compressor (356 - 450 cfm) 1 0.19
Minor Tools (10% of Labor Cost)
.J
F. Materials
a. Coco Log - 2 uses m 0.71 Prices of materials are variable per Regionl
b. Good Lumber - 4 uses District based on the prevailing unit prices in
bd-ft 6.19
the locality which include payment of local
c. NaillSpike (1 kg/100 bd-ft of Lumber) kg 0.06 taxes and hauling cost to the project site.
d. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.06 Refer to the Construction Material Price Data
Miscellaneous (2% of Materials Cost) established quarterly by Central Office Price
Monitoring Committee.
A. Labor •
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 0.53 See latest AGEL rental rates.
b. Diesel Hammer (K25 or equivalent) 1 0.27
c. Drop Hammer 1 0.13
d. Cutting Outfit 1 0.20
e. Jack Hammer 2 0.20
f. Air Compressor (356 - 450 cfm) 1 0.20
Minor Tools (10% of Labor Cost)
.J
F. Materials
a. Coco Log - 2 uses m 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Good Lumber - 4 uses bd-ft 16.00
the locality which include payment of local
c. NaillSpike (1 kg/100 bd-ft of Lumber) kg 0.16 taxes and hauling cost to the project site.
d. OxygenlAcetylene kg 0.01 Refer to the Construction Material Price Data
Miscellaneous (2% of Materials Cost) established quarterly by Central Office Price
Monitoring Committee.
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 0.62 See latest AGEL rental rates.
b. Diesel Hammer (K25 or equivalent) 1 0.41
c. Drop Hammer 1 0.11
d. Cutting Outfit 1 0.16
e. Jack Hammer 2 0.16
f. Air Compressor (356 - 450 cfm) 1 0.16
Minor Tools (10% of Labor Gost)
F. Materials
a. Coco Log - 2 uses m 1.00 Prices of materials are variable per Region/
b. Good Lumber - 4 uses bd-ft District based on the prevailing unit prices in
16.00
the locality which include payment of local
c. Nail/Spike (1 kg/100 bd-ft of Lumber) kg 0.16 taxes and hauling cost to the project site.
d. Oxygen/Acetylene set 0.01 Refer to the Construction Material Price Data
Miscellaneous (2% of Materials Cost) established quarterly by Central Office Price
Monitoring Committee.
Item No./Description 1052( 15)a Precast, Prestressed Concrete Piles, driven (soft strata)
Unit of Measurement m
Output per hour 2.40 m
A. Labor .
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 0.53 See latest AGEL rental rates.
b. Diesel Hammer (K25 or equivalent) 1 0.27
c. Drop Hammer 1 0.13
d. Cutting Outfit 1 0.20
e. Jack Hammer 2 0.20
f. Air Compressor (356 - 450 cfm) 1 0.20
Minor Tools (10% of Labor Cost)
.J
F. Materials
a. Coco Log - 2 uses m 1.00 Prices of materials are variable per Region/
b. Good Lumber (Falsework) - 4 uses bd-ft 16.00 District based on the prevailing unit prices in
the locality which include payment of local
c. Nail/Spike (1 kg/100 bd-ft of Lumber) kg 0.16 taxes and hauling cost to the project site.
d. OxygenlAcetylene set 0.01 Refer to the Construction Material Price Data
Miscellaneous (2% of Materials Cost) established quarterly by Central Office Price
Monitoring Committee.
Item No.lDescription 1052(15)b Precast, Prestressed Concrete Piles, driven (hard strata)
Unit of Measurement m
Output per hour 1.95 m
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 0.62 See latest ACEL rental rates.
b. Diesel Hammer (K25 or equivalent) 1 0.41
c. Drop Hammer 1 0.11
d. Cutting Outfit 1 0.16
e. Jack Hammer 2 0.16
f. Air Compressor (356 - 450 cfm) 1 0.16
Minor Tools (10% of Labor Cost)
.J
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 1.95 m
E. Direct Unit Cost (C + D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
a. Coco Log - 2 uses m 1.00 Prices of materials are variable per Region/
b. Good Lumber (Falsework) - 4 uses bd-ft 16.00 District based on the prevailing unit prices in
the locality which include payment of local
c. NaillSpike (1 kg/100 bd-ft of Lumber) kg 0.16
taxes and hauling cost to the project site.
d. OxygenlAcetylene set 0.01 Refer to the Construction Material Price Data
Miscellaneous (2% of Materials Cost) established quarterly by Central Office Price
Monitoring Committee.
Item No./Description 1052(16)a Test Piles, furnished and driven (type A, B, C or D), soft strata
Unit of Measurement m
Output per hour 2.40 m
A. Labor .
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 0.53 See latest AGEL rental rates.
b. Diesel Hammer (K25 or equivalent) 1 0.27
c. Drop Hammer 1 0.13
d. Cutting Outfit 1 0.20
e. Jack Hammer 2 0.20
f. Air Compressor (356 - 450 cfm) 1 0.20
Minor Tools (10% of Labor Cost)
.f
F. Materials
a. Coco Log - 2 uses m 2.00 Prices of materials are variable per Region/
b. Good Lumber (Falsework) - 4 uses bd-ft 16.00 District based on the prevailing unit prices in
the locality which include payment of local
c. NaillSpike (1 kg/100 bd-ft of Lumber) kg 0.16
taxes and hauling cost to the project site.
d.Oxygen/Acetylene set 0.01 Refer to the Construction Material Price Data
e. Fabricated RC Pile (delivered at site) m 1.00 established quarterly by Central Office Price
Monitoring Committee.
Note:
The unit cost of Fabricated RC Pile is dependent
on its type.
Please refer to the Direct Cost of
Item 1052(7)a
Item No./Description 1052(16)b Test Piles, furnished and driven (type A, B, C or D), hard strata
Unit of Measurement m
Output per hour 1.95 m
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 0.62 See latest ACEL rental rates.
b. Diesel Hammer (K25 or equivalent) 1 0.41
c. Drop Hammer 1 0.11
d. Cutting Outfit 1 0.16
e. Jack Hammer 2 0.16
f. Air Compressor (356 - 450 cfm) 1 0.16
Minor Tools (10% of Labor Cost)
F. Materials
a. Coco Log - 2 uses m 2.00 Prices of materials are variable per Region!
b. Good Lumber (Falsework) - 4 uses bd-ft 16.00 District based on the prevailing unit prices in
the locality which include payment of local
c. NaillSpike (1 kg/100 bd-ft of Lumber) kg 0.16
taxes and hauling cost to the project site.
d. Oxygen/Acetylene set 0.01 Refer to the Construction Material Price Data
e. Fabricated RC Pile (delivered at site) m 1.00 established quarterly by Central Office Price
Monitoring Committee.
Note:
The unit cost of Fabricated RC Pile is dependent
on its type.
Please refer to the Direct Cost of
Item 1052(7)a
Item No.lDescription 1052(17)a Concrete Piles cast in Drilled Holes, 0.80 m 0, fc' = 28 MPa (ordinary soil condition)
Unit of Measurement m
Output per hour 1.58 m
A. Labor
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
a. Drilling Rig (300 hp) 1 0.26 See latest AGEL rental rates.
b. Crawler Crane (41 - 45 mt) 1 0.95
c. Crawler Crane (21 - 25 mt) 1 0.95
d. Dump Truck (12 yd3) 1 0.95
e. Payloader (1.50 m\ LX80-2C 1 0.95
f. Generator Set (300 kW) 1 0.95
g. Bentonite Bin 1 0.50
h. Bentonite Mixer 1 0.50
i . Water Pump, 100 mm suction !1l(7.5 hp) 1 0.74
j. Water Truck (16000 L) 1 0.74
k. Bar Cutter 1 0.50
I. Bar Bender 1 0.50
m. Welding Machine (500A), Electric Driven 1 0.71
n. Cutting Outfit 1 0.71
f
o. Tremie Pipe Set 1 0.24
p. SPT & Desanding Machine 1 0.24
q. Portable Breaker, BHF30S 2 0.05
r. Air Compressor, Portable (126 - 160 cfm) 1 0.05
s. Lighting System/Tower Lights 1 0.95
Minor Tools (10% of Labor Cost)
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 1.58 m
E. Direct Unit Cost (C + D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
a. Ready Mix Concrete, fc' = 28 MPa @ 28 Days cu.m 0.55 Prices of materials are variable per Region/
b. Reinforcing Steel Bar' kg 205.00 District based on the prevailing unit prices in
the locality which include payment of local
c. Tire Wire (2% of RSB) kg 4.10
taxes and hauling cost to the project site.
d. OxygenlAcetylene (1 set/5000 kg. of RSB) set 0.041 Refer to the Construction Material Price Data
e. Welding Rod (1 kg/2000 kg of RSB) kg 0.10 established quarterly by Central Office Price
Miscellaneous (3% of Materials, Bentonite and etc.) Monitoring Committee.
Item No.lDescription 1052(17)b Concrete Piles cast in Drilled Holes, 1.00 m 0, fc' = 28 MPa (ordinary soil condition)
Unit of Measurement m
Output per hour 1.33 m
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Drilling Rig (300 hp) 1 0.31 See latest AGEL rental rates.
b. Crawler Crane (41 - 45 mt) 1 0.96
c. Crawler Crane (21 - 25 mt) 1 0.96
d. Dump Truck (12 yd3) 1 0.96
e. Payloader (1.50 m3), LX80-2C 1 0.96
f. Generator Set (300 kW) 1 0.96
g. Bentonite Bin 1 0.53
h. Bentonite Mixer 1 0.53
i . Water Pump, 100 mm suction 11l (7.5 hp) 1 0.78
j. Water Truck (16000 L) 1 0.78
k. Bar Cutter 1 0.56
I. Bar Bender 1 0.56
m. Welding Machine (500A), Electric Driven 1 0.73
n. Cutting Outfit 1 0.73 .J
F. Materials
a. Ready Mix Concrete, fc' = 28 MPa @ 28 Days cU.m 0.86 Prices of materials are variable per Region/
b. Reinforcing Steel Bar * kg 253.59 District based on the prevailing unit prices in
the locality which include payment of local
c. Tire Wire (2% of RSB) kg 5.07 taxes and hauling cost to the project site.
d. OxygenlAcetylene (1 set/5000 kg. of RSB) set 0.051 Refer to the Construction Material Price Data
e. Welding Rod (1 kg/2000 kg of RSB) kg 0.13 established quarterly by Central Office Price
Miscellaneous (3% of Materials, Bentonite and etc.) Monitoring Committee.
Item No.lDescription 1052(17)c Concrete Piles cast in Drilled Holes, 1.20 m 0, fe' = 28 MPa (ordinary soil condition)
Unit of Measurement m
Output per hour 1.09 m
A. Labor
Name and Capacity No. of Unitls No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
a. Drilling Rig (300 hp) 1 0.35 See latest ACEL rental rates.
b. Crawler Crane (41 - 45 mt) 1 0.96
c. Crawler Crane (21 - 25 mt) 1 0.96
d. Dump Truck (12 yd3) 1 0.96
e. Payloader (1.50 m\ LX80-2C 1 0.96
f. Generator Set (300 kW) 1 0.96
g. Bentonite Bin 1 0.56
h. Bentonite Mixer 1 0.56
i . Water Pump, 100 mm suction (Il (7.5 hp) 1 0.82
j. Water Truck/Pump (16000 L) 1 0.82
k. Bar Cutter 1 0.60
I. Bar Bender 1 0.60
m. Welding Machine (500 A), Electric Driven 1 0.75
n. Cutting Outfit 1 0.75
.J
o. Tremie Pipe Set 1 0.22
p. SPT & Desanding Machine 1 0.25
q. Portable Breaker, BHF30S 2 0.04
r. Air Compressor, Portable (126- 160 cfm) 1 0.04
s. Lighting SystemfTower Lights 1 0.96
Minor Tools (10% of Labor Cost)
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 1.09 m
E. Direct Unit Cost (C + D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
a. Ready Mix Concrete, fe' = 28 MPa @ 28 Days cU.m 1.24 Prices of materials are variable per Region/
b. Reinforcing Steel Bar * kg 304.30 District based on the prevailing unit prices in
the locality which include payment of local
c. Tire Wire (2% of RSB) kg 6.09
taxes and hauling cost to the project site.
d. Oxygen/Acetylene (1 set/5000 kg. of RSB) set 0.06 Refer to the Construction Material Price Data
e. Welding Rod (1 kg/2000 kg of RSB) kg 0.15 established quarterly by Central Office Price
Miscellaneous (3% of Materials, Bentonite and etc.) Monitoring Committee.
Item No./Description 1052(17)d Concrete Piles cast in Drilled Holes, 1.50 m 0, fc' = 28 MPa (ordinary soil condition)
Unit of Measurement m
Output per hour 0.81 m
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Drilling Rig (300 hp) 1 0.39 See latest AGEL rental rates.
b. Crawler Crane (41 - 45 mt) 1 0.97
c. Crawler Crane (21 - 25 mt) 1 0.97
d. Dump Truck (12 yd3) 1 0.97
e. Payloader (1.50 m\ LX80-2C 1 0.97
f. Generator Set (300 kW) 1 0.97
g. Bentonite Bin 1 0.61
h. Bentonite Mixer 1 0.61
i . Water Pump, 100 mm suction ¢ (7.5 hp) 1 0.86
j. Water Truck/Pump (16000 L) 1 0.86
k. Bar Cutter 1 0.65
I. Bar Bender 1 0.65
m. Welding Machine (500 A), Electric Driven 1 0.76
n. Cutting Outfit 1 0.76 .J
o. Tremie Pipe Set 1 0.22
p. SPT & Desanding Machine 1 0.26
q. Portable Breaker, BHF30S 2 0.03
r. Air Compressor, Portable (126- 160 cfm) 1 0.03
s. Lighting SystemfTower Lights 1 0.97
Minor Tools (10% of Labor Cost)
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 0.81 m
E. Direct Unit Cost (C .;. D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
a. Ready Mix Concrete, fc' = 28 MPa @ 28 Days cU.m 1.94 Prices Df materials are variable per RegiDn/
District based Dn the prevailing unit prices in
b. Reinforcing Steel Bar' kg 387.77
the IDcality which include payment Df IDcal
c. Tire Wire (2% of RSB) kg 7.76 taxes and hauling CDSt tD the project site.
d. Oxygen/Acetylene (1 set/5000 kg of RSB) set 0.08 Refer tD the CDnstructiDn Material Price Data
e. Welding Rod (1 kg/2000 kg of RSB) kg 0.19 established quarterly by Central Office Price
MDnitDring CDmmittee.
Miscellaneous (3% of Materials, Bentonite and etc.)
Item No./Description 1052(17)e Concrete Piles cast in Drilled Holes, 1.80 m 0, fe' = 28 MPa (ordinary soil condition)
Unit of Measurement m
Output per hour 0.62 m
A. Labor
Name and Capacity No. of Unitls No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
a. Drilling Rig (300 hp) 1 0.42 See latest AGEL rental rates.
b. Crawler Crane (41 - 45 mt) 1 0.98
c. Crawler Crane (21 - 25 mt) 1 0.98
d. Dump Truck (12 yd3) 1 0.98
e. Payloader (1.50 m\ LX80-2C 1 0.98
f. Generator Set (300 kW) 1 0.98
g. Bentonite Bin 1 0.64
h. Bentonite Mixer 1 0.64
i . Water Pump, 100 mm suction 11l(7.5 hp) 1 0.90
j. Water Truck/Pump (16000 L) 1 0.90
k. Bar Cutter 1 0.68
I. Bar Bender 1 0.68
m. Welding Machine (500 A), Electric Driven 1 0.76
.J
n. Cutting Outfit 1 0.76
o. Tremie Pipe Set 1 0.22
p. SPT & Desanding Machine 1 0.26
q. Portable Breaker, BHF30S 2 0.02
r. Air Compressor, Portable (126-160 cfm) 1 0.02
s. Lighting System/Tower Lights 1 0.98
Minor Tools (10% of Labor Cost)
Sub - Total for B
C. Total (A + B)
D. Output per Hour - 0.62m
E. Direct Unit Cost (C + D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
a. Ready Mix Concrete, fe' = 28 Mpa @ 28 D cU.m 2.80 Prices of materials are variable per Regionl
District based on the prevailing unit prices in
b. Reinforcing Steel Bar' kg 451.98
the locality which include payment of local
c. Tire Wire (2% of RSB) kg 9.04 taxes and hauling cost to the project site.
d. Oxygen/Acetylene (1 set/5000 kg of RSB) set 0.09 Refer to the Construction Material Price Data
e. Welding Rod (1 kg/2000 kg of RSB) kg 0.23 established quarterly by Central Office Price
Monitoring Committee.
Miscellaneous (3% of Materials, Bentonite and etc.)
Item No./Description 1052(17)f Concrete Piles cast in Drilled Holes, 2.00 m 0, fc' = 28 MPa (ordinary soil condition)
Unit of Measurement m
Output per hour 0.53 m
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Drilling Rig (300 hp) 1 0.44 See latest AGEL rental rates.
b. Crawler Crane (41 - 45 mt) 1 0.98
c. Crawler Crane (21 - 25 mt) 1 0.98
d. Dump Truck (12 yd3) 1 0.98
e. Payloader (1.50 m\ LX80-2C 1 0.98
f. Generator Set (300 kW) 1 0.98
g. Bentonite Bin 1 0.65
h. Bentonite Mixer 1 0.65
i . Water Pump, 100 mm suction (1l (7.5 hp) 1 0.91
j. Water Truck/Pump (16000 L) 1 0.91
k. Bar Cutter 1 0.70
I. Bar Bender 1 0.70
m. Welding Machine (500 A), Electric Driven 1 0.77
n. Cutting Outfit 1 0.77 .J
F. Materials .
a. Ready Mix Concrete, fc' = 28 MPa @ 28 Days cU.m 3.46 Prices of materials are variable per Region/
b. Reinforcing Steel Bar' kg 490.33 District based on the prevailing unit prices in
the locality which include payment of local
c. Tire Wire (2% of RSB) kg 9.81
taxes and hauling cost to the project site.
d. OxygenlAcetylene (1 set/5000 kg of RSB) set 0.098 Refer to the Construction Material Price Data
e. Welding Rod (1 kg/2000 kg of RSB) kg 0.25 established quarterly by Central Office Price
Miscellaneous (3% of Materials, Bentonite and etc.) Monitoring Committee.
Item No./Description 1052(18)a Concrete Piles cast in Steel Shells, furnished and driven
Unit of Measurement m
Output per hour 1.80 m
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 0.39 See latest ACEL rental rates.
b. Diesel Hammer (K25 or equivalent) 1 0.15
c. Drop Hammer 1 0.07
d. Bar Cutter 1 0.12
e. Bar Bender 1 0.12
f. Welding Machine (500A), GaslDiesel Driven 1 0.05
g. Cutting Outfit 1 0.05
h. One Bagger Mixer 1 0.17
i. Water Truck/Pump (16000L) 1 0.04
j. Concrete Vibrator 1 0.04
k. Tremie Pipe Set 1 0.17
Minor Tools (10% of Labor Cost)
.J
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 1.80 m
E. Direct Unit Cost (C + D)
F. Materials
a. Tubular Pile (0.40 m ~ x 9.50 mm thk)* m 1.00 Prices of materials are variable per Regionl
b. Reinforcing Steel Bar kg 29.547 District based on the prevailing unit prices in
the locality which include payment of local
C. Cement bag 1.194
taxes and hauling cost to the project site.
d.Sand m' 0.063 Refer to the Construction Material Price Data
e. Gravel m' 0.126 established quarterly by Central Office Price
f. #16 Tie Wire (2% of RSB) kg 0.591 Monitoring Committee.
Note:
*Assumed weight of Tubular Pipe Pile is
95.93 kglm
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/12%/10%/8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description 1052(18)b Concrete Piles cast in Steel Shells, furnished and driven (Ready Mix Concrete)
Unit of Measurement m
Output per hour 2.00 m
A. Labor
Name and Capacity No. of Unitls No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 0.45 See latest ACEL rental rates.
b. Diesel Hammer (K25 or equivalent) 1 0.17
c. Drop Hammer 1 0.08
d. Bar Cutter 1 0.14
e. Bar Bender 1 0.14
f. Welding Machine (500A), Gas/Diesel Driven 1 0.06
g. Cutting Outfit 1 0.06
h. Concrete Vibrator 1 0.01
i. Tremie Pipe Set 1 0.05
Minor Tools (10% of Labor Cost)
F. Materials
a. Tubular Pile (0.40 m ¢ x 9.50 mm thk)* m 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Reinforcing Steel Bar kg 29.547
the locality which include payment of local
c. Ready Mix Concrete fc'=20.7 MPa m' 0.132 taxes and hauling cost to the project site.
d. #16 Tie Wire (2% of RSB) kg 0.591 Refer to the Construction Material Price Data
e. Welding Rod (1 kg/2000 kg of Steel) kg 0.063 established quarterly by Central Office Price
Monitoring Committee.
f. Oxy/Acetylene (1 kg/5000 kg of Steel) set 0.025
g. Coco Log- 2 uses m 1.00
h. Good Lumber (Falsework)- 4 uses bd-ft 16.00
i. Nail/Spike (1 kg/100 bd-ft of Lumber) kg 0.16
Miscellaneous (2% of Materials Cost)
Note:
'Assumed weight of Tubular Pipe Pile is
95.93 kglm.
If no available Ready Mix Concrete at project
site, derive the cost of concrete using the Batching
Plant or One Bagger Mixer for small quantity.
Item No.lDescription 1052(19)a Concrete Piles cast in Steel Pipes, furnished and driven
Unit of Measurement m
Output per hour 2.40 m
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 0.39 See latest ACEL rental rates.
b. Diesel Hammer (K25 or equivalent) 1 0.15
c. Drop Hammer 1 0.07
d. Bar Cutter 1 0.12
e. Bar Bender 1 0.12
f. Welding Machine (500A), GaslDiesel Driven 1 0.05
g. Cutting Outfit 1 0.05
h. One Bagger Mixer 1 0.17
i. Water Truck/Pump (16000L) 1 0.04
j. Concrete Vibrator 1 0.04
k. Tremie Pipe Set 1 0.17
Minor Tools (10% of Labor Cost)
F. Materials
a. Tubular Pile (0.40 m (Il x 9.50 mm thk)* m. 1.00 Prices of materials are variable per Regionl
b. Reinforcing Steel Bar kg. 29.547 District based on the prevailing unit prices in
the locality which include payment of local
c. Cement bag 1.194 taxes and hauling cost to the project site.
d. Sand m3 0.063 Refer to the Construction Material Price Data
e. Gravel m3 0.126 established quarterly by Central Office Price
Monitoring Committee.
1. #16 Tie Wire (2% of RSB) kg. 0.591
g. Welding Rod (1 kg/2000 kg of Steel) kg. 0.063
h. Oxy/Acetylene (1 kg/5000 kg of Steel) set 0.025
i. Coco Log- 2 uses m 1.00
j. Good Lumber (Falsework)- 4 uses bd-ft 16.00
k. NaillSpike (1 kg/100 bd-ft of Lumber) kg. 0.16
Miscellaneous (2% of Materials Cost)
Note:
*Assumed weight of Tubular Pipe Pile is
95.93 kglm.
Item No.lDescription 1052(19)b Concrete Piles cast in Steel Pipes, furnished and driven (Ready Mix Concrete)
Unit of Measurement m
Output per hour 2.00 m
A. Labor
Name and Capacity No. of Unitls No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41 - 45 mt) 1 0.45 See latest AGEL rental rates.
b. Diesel Hammer (K25 or equivalent) 1 0.17
c. Drop Hammer 1 0.08
d. Bar Cutter 1 0.14
e. Bar Bender 1 0.14
f. Welding Machine (500A), Gas/Diesel Driven 1 0.06
g. Cutting Outfit 1 0.06
h. Concrete Vibrator 1 0.01
i. Tremie Pipe Set 1 0.05
Minor Tools (10% of Labor Cost)
F. Materials
a. Tubular Pile (0.40 m ¢ x 9.50 mm thk)* m 1.00 Prices of materials are variable per Regionl
b. Reinforcing Steel Bar kg 29.547 District based on the prevailing unit prices in
the locality which include payment of local
c. Ready Mix Concrete fc'=20.7 MPa m' 0.132
taxes and hauling cost to the project site.
d. #16 Tie Wire (2% of RSB) kg 0.591 Refer to the Construction Material Price Data
e. Welding Rod (1 kg/2000 kg of Steel) kg 0.063 established quarterly by Central Office Price
f. Oxy/Acetylene (1 kg/5000 kg of Steel) set 0.025 Monitoring Committee.
A. Labor .
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Welding Machine (500A), Electric Driven 1 1.00 See latest AGEL rental rates.
b. Bar Cutter 1 0.25
c. Bar Bender 1 0.25
.J
F. Materials
a. Reinforcing Steel Bar, Grade 40 kg 23.86 Prices of materials are variable per Regionl
District based on the prevailing unit prices in
b. Steel Plate (100+100) x 300 mm, 12 mm thk kg 6.00
the locality which include payment of local
c. Welding Rod (1 kg/2000 kg of Steel) kg 0.015 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Drilling Rig (300 hp) 1 0.26 See latest AGEL rental rates.
b. Crawler Crane (41 - 45 mt) 1 0.95
c. Crawler Crane (21 - 25 mt) 1 0.95
d. Dump Truck (12 yd3) 1 0.95
e. Payloader (1.50 m3), LX80-2C 1 0.95
f. Generator Set (300 kW) 1 0.95
g. Bentonite Bin 1 0.50
h. Bentonite Mixer 1 0.50
i . Water Pump, 100 mm suction !2l (7.5 hp) 1 0.74
j. Water Truck (16000 L) 1 0.74
k. Bar Cutter 1 0.50
I. Bar Bender 1 0.50
m. Welding Machine (500A), Electric Driven 1 0.71
n. Cutting Outfit 1 0.71 J
o. Tremie Pipe Set 1 0.24
p. SPT & Desanding Machine 1 0.24
q. Portable Breaker, BHF30S 2 0.05
r. Air Compressor, Portable (126 - 160 cfm) 1 0.05 ,
s. Lighting SystemlTower Lights 1 0.95
Minor Tools (10% of Labor Cost)
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 1.58 m
E. Direct Unit Cost (C + D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
a. Ready Mix Concrete, fe' = 28 MPa @ 28 Days cU.m 0.55 Prices of materials are variable per Regionl
b. Reinforcing Steel Bar * kg 205.00 District based on the prevailing unit prices in
the locality which include payment of local
c. Tire Wire (2% of RSB) kg 4.10 taxes and hauling cost to the project site.
d. OxygenlAcetylene (1 set/5000 kg. of RSB) set 0.041 Refer to the Construction Material Price Data
e. Welding Rod (1 kg/2000 kg of RSB) kg 0.10 established quarterly by Central Office Price
Miscellaneous (3% of Materials, Bentonite and etc.) Monitoring Committee.
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Drilling Rig (300 hp) 1 0.31 See latest ACEL rental rates.
b. Crawler Crane (41- 45 mt) 1 0.96
c. Crawler Crane (21- 25 mt) 1 0.96
d. Dump Truck (12 yd3) 1 0.96
e. Payloader (1.50 m3), LX80-2C 1 0.96
f. Generator Set (300 kW) 1 0.96
g. Bentonite Bin 1 0.53
h. Bentonite Mixer 1 0.53
i . Water Pump, 100 mm suction 0 (7.5 hp) 1 0.78
j. Water Truck/Pump (16000L) 1 0.78
k. Bar Cutter 1 0.56
I. Bar Bender 1 0.56
m. Welding Machine (500 A), Electric Driven 1 0.73
n. Cutting Outfit 1 0.73
.J
o. Tremie Pipe Set 1 0.22
p. SPT & Desanding Machine 1 0.24
q. Portable Breaker, BHF30S 2 0.04
r. Air Compressor, Portable (126- 160 cfm) 1 0.04
s. Lighting SystemlTower Lights 1 0.96
Minor Tools (10% of Labor Cost)
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 1.33 m
E. Direct Unit Cost (C + D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
3
a. Ready Mix Concrete, fe' = 28 MPa m 0.86 Prices of materials are variable per Regionl
b. Reinforcing Steel Bar * District based on the prevailing unit prices in
kg 253.59
the locality which include payment of local
c. Tire Wire (2% of RSB) kg 5.07 taxes and hauling cost to the project site.
d. OxygenlAcetylene (1 set/5000 kg of RSB) set 0.051 Refer to the Construction Material Price Data
e. Welding Rod (1 kg/2000 kg of RSB) kg 0.13 established quarterly by Central Office Price
Monitoring Committee.
Miscellaneous (3% of Materials, Bentonite and etc.)
Item No.lDescription 1052(23)c Bored Piles, 1.20 m "" (ordinary soil condition)
Unit of Measurement m
Output per hour 1.09 m
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Drilling Rig (300 hp) 1 0.35 See latest AGEL rental rates.
b. Crawler Grane (41- 45 mt) 1 0.96
c. Crawler Crane (21- 25 mt) 1 0.96
d. Dump Truck (12 yd3) 1 0.96
e. Payloader (1.50 m3), LX80-2G 1 0.96
f. Generator Set (300 kW) 1 0.96
g. Bentonite Bin 1 0.56
h. Bentonite Mixer 1 0.56
i . Water Pump, 100 mm suction"" (7.5 hp) 1 0.82
j. Water Truck/Pump (16000L) 1 0.82
k. Bar Cutter 1 0.60
I. Bar Bender 1 0.60
m. Welding Machine (500 A), Electric Driven 1 0.75
n. Cutting Outfit 1 0.75
o. Tremie Pipe Set 1 0.22 .J
F. Materials
3
a. Ready Mix Concrete, fe' = 28 MPa m 1.24 Prices of materials are variable per Regionl
District based on the prevailing unit prices in
b. Reinforcing Steel Bar' kg 304.30
the locality which include payment of local
c. Tire Wire (2% of RSB) kg 6.09 taxes and hauling cost to the project site.
d. OxygenlAcetylene (1 set/5000 kg of RSB) set 0.061 Refer to the Construction Material Price Data
e. Welding Rod (1 kg/2000 kg of RSB) kg 0.15 established quarterly by Central Office Price
Monitoring Committee.
Miscellaneous (3% of Materials, Bentonite and etc.)
A. Labor
Name and Capacity No. of Unitls No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
a. Drilling Rig (300 hp) 1 0.39 See latest AGEL rental rates.
b. Crawler Crane (41- 45 mt) 1 0.97
c. Crawler Crane (21- 25 mt) 1 0.97
d. Dump Truck (12 yd3) 1 0.97
e. Payloader (1.50 m3), LX80-2C 1 0.97
f. Generator Set (300 kW) 1 0.97
g. Bentonite Bin 1 0.61
h. Bentonite Mixer 1 0.61
i . Water Pump, 100 mm suction 0 (7.5 hp) 1 0.86
j. Water Truck/Pump (16000L) 1 0.86
k. Bar Cutter 1 0.65
I. Bar Bender 1 0.65
m. Welding Machine (500 A), Electric Driven 1 0.76
n. Cutting Outfit 1 0.76 .J
F. Materials
3
a. Ready Mix Concrete, fc' = 28 MPa m 1.94 Prices of materials are variable per Regionl
District based on the prevailing unit prices in
b. Reinforcing Steel Bar' kg 387.77
the locality which include payment of local
c. Tire Wire (2% of RSB) kg 7.76 taxes and hauling cost to the project site.
d. Oxygen/Acetylene (1 set/5000 kg of RSB) set 0.078 Refer to the Construction Material Price Data
e. Welding Rod (1 kg/2000 kg of RSB) kg 0.19 established quarterly by Central Office Price
Monitoring Committee.
Miscellaneous (3% of Materials, Bentonite and etc.)
A. Labor
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
a. Drilling Rig (300 hp) 1 0.42 See latest AGEL rental rates.
b. Crawler Crane (41- 45 mt) 1 0.98
c. Crawler Crane (21- 25 mt) 1 0.98
d. Dump Truck (12 yd3) 1 0.98
e. Payloader (1.50 m\ LX80-2C 1 0.98
f. Generator Set (300 kW) 1 0.98
g. Bentonite Bin 1 0.64
h. Bentonite Mixer 1 0.64
i . Water Pump, 100 mm suction QJ (7.5 hp) 1 0.90
j. Water Truck/Pump (16000L) 1 0.90
k. Bar Cutter 1 0.68
I. Bar Bender 1 0.68
m. Welding Machine (500 A), Electric Driven 1 0.76
n. Gutting Outfit 1 0.76
o. Tremie Pipe Set 1 0.22 .J
F. Malerials
a. Ready Mix Concrete, fe' = 28 MPa m3 2.80 Prices of materials are variable per Regionl
District based on the prevailing unit prices in
b. Reinforcing Steel Bar * kg 451.98
the locality which include payment of local
c. Tire Wire (2% of RSB) kg 9.04 taxes and hauling cost to the project site.
d. Oxygen/Acetylene (1 set/5000 kg of RSB) set 0.090 Refer to the Construction Material Price Data
e. Welding Rod (1 kg/2000 kg of RSB) kg established quarterly by Central Office Price
0.23
Monitoring Committee.
Miscellaneous (3% of Materials, Bentonite and etc.)
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Drilling Rig (300 hp) 1 0.44 See latest AGEL rental rates.
b. Crawler Crane (41- 45 mt) 1 0.98
c. Crawler Crane (21- 25 mt) 1 0.98
d. Dump Truck (12 yd3) 1 0.98
e. Payloader (1.50 m3), LX80-2C 1 0.98
f. Generator Set (300 kW) 1 0.98
g. Bentonite Bin 1 0.65
h. Bentonite Mixer 1 0.65
i . Water Pump, 100 mm suction 0 (7.5 hp) 1 0.91
j. Water Truck/Pump (16000L) 1 0.91
k. Bar Cutter 1 0.70
I. Bar Bender 1 0.70
m. Welding Machine (500 A), Electric Driven 1 0.77
n. Cutting Outfit 1 0.77
o. Tremie Pipe Set 1 0.21 .J
F. Materials
3
a. Ready Mix Concrete, fc' = 28 MPa m 3.46 Prices of materials are variable per Region!
b. Reinforcing Steel Bar * kg 490.33 District based on the prevailing unit prices in
the locality which include payment of local
c. Tire Wire (2% of RSB) kg 9.81
taxes and hauling cost to the project site.
d. Oxygen/Acetylene (1 set/5000 kg of RSB) set 0.098 Refer to the Construction Material Price Data
e. Welding Rod (1 kg/2000 kg of RSB) kg 0.25 established quarterly by Central Office Price
Miscellaneous (3% of Materials, Bentonite and etc.) Monitoring Committee.
A Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41- 45 mt) 1 1.00 See latest AGEL rental rates.
b. Vibro Hammer wI Hydraulic Power Pack 1 0.50
c. Welding Machine (500 A), Gas/Diesel Driven 1 0.50
d. Cutting Outfit 1 0.50
Minor Tools (10% ofLabor Cost)
F. Materials
a. Steel Casing, 10 mm thk m 1.025 Prices of materials are variable per Region!
District based on the prevailing unit prices in
b. Oxy/Acetylene (1 set/2500 kg of Steel) set 0.082 the locality which include payment of local
c. Welding Rod (1 kgl500 kg of Steel) kg 0.409 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Note:
Monitoring Committee.
Assumed length of Steel Casing without splicing
but with full weld = 12.00 meter, 2.50% additional quantity
of Steel Casing represents the collar of O.30 m for 12 m.
A. Labor •
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41- 45 mt) 1 1.00 See latest AGEL rental rates.
b. Vibro Hammer w/ Hydraulic Power Pack 1 0.50
c. Welding Machine (500 A), Gas/Diesel Driven 1 0.50
d. Cutting Outfit 1 0.50
Minor Tools (10% of Labor Cost)
.J
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 2.40 m
E. Direct Unit Cost (C + D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
a. Steel Casing, 10 mm thk m 1.025 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Oxy/Acetylene (1 seU2500 kg of Steel) set 0.102
the locality which include payment of local
c. Welding Rod (1 kg/500 kg of Steel) kg 0.511 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Note:
Monitoring Committee.
Assumed length of Steel Casing without splicing
but with full weld = 12.00 meter, 2.50% additional quantity
of Steel Casing represents the collar of O.30 m for 12 m.
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41- 45 mt) 1 1.00 See latest ACEL rental rates.
b. Vibro Hammer wI Hydraulic Power Pack 1 0.50
c. Welding Machine (500 A), Gas/Diesel Driven 1 0.50
d. Cutting Outfit 1 0.50
Minor Tools (10% of Labor Cost)
F. Materials
a. Steel Casing, 10 mm thk m 1.025 Prices of materials are variable per Regionl
b. Oxy/Acetylene (1 set/2500 kg of Steel) District based on the prevailing unit prices in
set 0.122
the locality which include payment of local
c. Welding Rod (1 kg/500 kg of Steel) kg 0.612 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
Note: established quarterly by Central Office Price
Assumed length of Steel Casing without splicing Monitoring Committee.
but with full weld= 12.00 meter, 2.50% additional quantity
of Steel Casing represents the collar of O.30 m for 12 m.
A Labor_
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41- 45 mt) 1 1.00 See latest ACEL rental rates.
b. Vibro Hammer wI Hydraulic Power Pack 1 0.50
c. Welding Machine (500 A), Gas/Diesel Driven 1 0.50
d. Cutting Outfit 1 0.50
Minor Tools (10% of Labor Cost)
C. Total (A + B)
D. Output per Hour = 1.60 m
E. Direct Unit Cost (C .;-D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
a. Steel Casing, 10 mm thk m 1.025 Prices of materials are variable per Region/
b. Oxy/Acetylene (1 set/2500 kg of Steel) set 0.153 District based on the prevailing unit prices in
the locality which include payment of local
c. Welding Rod (1 kg/500 kg of Steel) kg 0.763 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
Note: established quarterly by Central Office Price
Assumed length of Steel Casing without splicing Monitoring Committee.
but with full weld = 12.00 meter, 2.50% additional quantity
of Steel Casing represents the collar of O.30 m for 12 m.
A. Labor
Name and Capacity No. of Unitls No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41- 45 mt) 1 1.00 See latest AGEL rental rates.
b. Vibro Hammer w/ Hydraulic Power Pack 1 0.50
c. Welding Machine (500 A), Gas/Diesel Driven 1 0.50
d. Cutting Outfit 1 0.50
Minor Tools (10% of Labor Cost)
C. Total (A + B)
D. Output per Hour = 1.33 m
E. Direct Unit Cost (C + D)
F. Materials
A. Labor -
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41- 45 mt) 1 1.00 See latest ACEL rental rates.
b. Vibro Hammer w/ Hydraulic Power Pack 1 0.50
c. Welding Machine (500 A), Gas/Diesel Driven 1 0.50
d. Cutting Outfit 1 0.50
Minor Tools (10% ofLabor Cost)
.J
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 1.20 m
E. Direct Unit Cost (C + D)
F. Materials
a. Steel Casing, 10 mm thk m 1.03 Prices of materials are variable per Region!
District based on the prevailing unit prices in
b. Oxy/Acetylene (1 set/2500 kg of Steel) set 0.203
the locality which include payment of local
c. Welding Rod (1 kg/500 kg of Steel) kg 1.016 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Note:
Monitoring Committee.
Assumed length of Steel Casing without splicing
but with full weld= 12.00 meter, 2.50% additional quantity
of Steel Casing represents the collar of O.30 m for 12 m.
Item No./Description 1052(25) Splicing of RC Piles with Epoxy (400 mm x 400 mm)
Unit of Measurement ea
Output per hour 0.50 ea
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41-45 mt) 1 1.00 See latest ACEL rental rates.
Minor Tools (10% of Labor Cost)
F. Materials
a. Reinforcing Steel Bar (36 mm ¢ x 1.50 m)* kg. 51.83 Prices of materials are variable per Region/
b. Concrete Epoxy for RC Piles (Part A & B) set 0.70 District based on the prevailing unit prices in
the locality which include payment of local
c. Silica Sand gal 1.40 taxes and hauling cost to the project site.
d. Pipe Sleeve, 50 mm 0 GI m 3.00 Refer to the Construction Material Price Data
Miscellaneous (2% of Materials Cost) established quarterly by Central Office Price
Monitoring Committee.
Item No./Description 1052(26) Splicing of RC Piles with Epoxy (450 mm x 450 mm)
Unit of Measurement ea
Output per hour 0.50 ea
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted Crane (41-45 mt) 1 1.00 See latest ACEL rental rates.
Minor Tools (10% of Labor Cost)
F. Materials
a. Reinforcing Steel Bar (36 mm 11l x 1.50 m)* kg 51.83 Prices of materials are variable per Region/
b. Concrete Epoxy for RC Piles (Part A & B) District based on the prevailing unit prices in
set 0.80
the locality which include payment of local
c. Silica Sand gal 1.60 taxes and hauling cost to the project site.
d. Pipe Sleeve, 50 mm 0 GI m 3.00 Refer to the Construction Material Price Data
Miscellaneous (2% of Materials Cost) established quarterly by Central Office Price
Monitoring Committee .
Item No.lDescription 1052(27)a Pile Integrity Testing (Sonic), ordinary soil condition
Unit of Measurement ea
Output per hour 1.00 ea (assumed pile length = 30 m)
A. Labor
Name and Capacity No. of Unit/s No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Pile Integrity Testing (Sonic) and accessories 1 lot See latest AGEL rental rates.
(includes professional fee of Structural Engineer
and reports)
b. Welding Machine (500A), Electric Driven 1 4.00
Minor Tools (10% of Labor Cost)
F. Materials
a. Black/GI Pipe & accessories 2"1Il x 6 m, Schedule 20 m 120.00 Prices of materials are variable per Region!
District based on the prevailing unit prices in
b. Welding Rod kg 0.10
the locality which include payment of local
Miscellaneous (2% of Materials Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Note: Monitoring Committee.
Materials quantity component, equipment and
labor output may vary proportionately depending on
the pile length.
Item No.lDescription 1052(27)b Pile Integrity Testing (PIT), ordinary soil condition
Unit of Measurement ea
Output per hour 1.00 ea
A. Labor
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
a.Pile Integrity Testing and accessories 1 lot See latest ACEL rental rates.
(includes professional fee of Structural Engineer
and reports)
b. Grinding Machine and accessories 1 2.00
.J
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 1.00 ea
E. Direct Unit Cost (C + D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
Item No./Description 1052(22)b High Strain Dynamic Testing (PDA), ordinary soil condition
Unit of Measurement ea
Output per hour 1.00 ea (assumed pile 0= 1.50 m)
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
J
Sub - Total for B
C. Total (A + B)
D. Output per Hour - 1.00 ea
E. Direct Unit Cost (C + D)
F. Materials
Note:
Materials quantity component, equipment and
labor output may vary proportionately depending on
the pile length.
Item No./Description 1052 (29) Micro Piles In Drilled Holes, 0.20m 12' (ordinary soil condition)
Unit of Measurement m
Output per hour 3.00 m
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Drill Rig, Mechanical Rotary 1 0.74 See latest ACEL rental rates.
b. Truck Mounted Crane (25T) 1 0.95
c. Bar Bender 1 0.04
d. Bar Cutter 1 0.04
e. Bentonite Mixer 1 0.50
f. Bentonite Bin 1 0.50
g. Water Pump 1 0.50
h.Water Truck 1 0.50
i. Welding Machine 1 0.50
j. Tremie Pipe Set 1 0.24
k. SPT & Desanding Machine 1 0.24
I. Tower Light 1 0.50
m. Minor Tools (10% of Labor Cost)
.J
F. Materials
a. Ready Mix 0.033 cU.m Prices of materials are variable per Region/
b. Reinforced Steel Bar' 12.626 kg District based on the prevailing unit prices in
the locality which include payment of local
c. Welding Rod (1kg/2000kg of RSB) 0.006 kg taxes and hauling cost to the project site.
d. Miscellaneous (3% of Materials, Bentonite & etc.) Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
Item No.lDescription 1100(1) 15 mm 0 - 25 mm 0 Rigid Steel Conduit (RSC)/lntermediate metal Conduit (IMC)I
Electrical Metal Tubing (EMT)
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
C. Total (A + B)
D. Output per Hour = 1.333 lenqth
E. Direct Unit Cost (C + D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
a. 15 mm 0 - 25 mm 0 x 3.00 m Rigid Steel Conduit Prices of materials are variable per Regionl
(RSC)I Intermediate metal Conduit (IMC)I Electrical length 1.00 District based on the prevailing unit prices in the
Metal Tubing (EMT) locality which include payment of local taxes
and hauling cost to theproject site. Refer to the
b. Consumables (5% of Materials Cost) Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
Item No.lDescription 1100(1) 32 mm 13- 40 mm 0 Rigid Steel Conduit (RSC)I Intermediate metal Conduit (IMC)I
Electrical Metal Tubing (EMT)
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. 32 mm 0 - 40 mm 0 x 3.00 m Rigid Steel Conduit Prices of materials are variable per Region/
(RSC)I Intermediate metal Conduit (IMC)I Electrical length 1.00 District based on the prevailing unit prices in the
Metal Tubing (EMT) locality which include payment of local taxes
and hauling cost to the project site. Refer to the
b. Consumables (5% of Materials Cost) Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
Item No./Description 1100(1) 50 mm 0 - 65 mm 0 Rigid Steel ConduiU Intermediate metal Conduit (IMC)/
Electrical Metal Tubing (EMT)
A. Labor
B. Equipment
"
F. Materials
a. 50 mm 0 - 65 mm 0 x 3.00 m Rigid Steel ConduiU Prices of materials are variable per Region/
Intermediate metal Conduit (IMC)/ Electrical Metal District based on the prevailing unit prices in the
length 1.00
Tubing (EMT) locality which include payment of local taxes
and hauling cost to the project site. Refer to the
b. Consumables (5% of Materials Cost) Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
Item No./Description 1100(1) 80 mm 12)- 100 mm 0 Rigid Steel Conduit (RSC)I Intermediate metal Conduit (IMC)I
Electrical Metal Tubing (EMT)
A. Labor
Name and Capacity No. of UniUs No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
,J
F. Materials
a. 80 mm 0 x 3 m Rigid Steel Conduit (RSC) length 1.00 Prices of materials are variable per Region/
b. Consumables (5% of Materials Cost) District based on the prevailing unit prices in the
locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
A. Labor
Name and Capacity No. of Unit/s No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
'.
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 2.00 m
E. Direct Unit Cost (C + D)
F. Materials
a. 15 mm 0 - 25 mm 0 Flexible Metal Conduit m 1.00 Prices of materials are variable per Region/
b. Consumables (5% of Materials Cost) District based on the prevailing unit prices in the
locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
A. Labor
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
.
B. Equipment
"
F. Materials
a. 15 mm fZJ- 32 mm fZJx 3.00 mm Polyvinyl Chloride Prices of materials are variable per Region!
length 1.05 District based on the prevailing unit prices in the
(PVC) Pipes
locality which include payment of local taxes
b. Consumables (5% of Materials Cost)
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
A. Labor
(Labor cost for these items shall be considered/included in the installation of conduits.)
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
"-
F. Materials
a. Coupling/Elbow/End Bell/Clamp or others pc 1.00 Prices of materials are variable per Region!
District based on the prevailing unit prices in the
locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
".
Sub - Total for B
C. Total (A + B)
D. Output - 1.00 pc
E. Direct Unit Cost (C + D)
F. Materials
a. Junctionl Utilityl Pulll Square Box pc 1.00 Prices of materials are variable per Region/
b. Consumables (3% of Materials Cost) District based on the prevailing unit prices in the
locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
"-
F. Materials
Item No.lDescription 1101(2) 1.6 mm2 - 5.5 mm2 Electric Wire (TWITHHNITWHN2)
Unit of Measurement m
Output per hour 25m
A. Labor
Name and Capacity No. of Unit/s No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
"
F. Materials
a. 1.6 mm2 - 5.5 mm2 Electric Wire Prices of materials are variable per Region/
m 1.00 District based on the prevailing unit prices in the
(TWITHHNITWHN2)
locality which include payment of local taxes
b. Consumables (3% of Materials Cost) and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee,
A. Labor
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
"
F. Materials
A. Labor
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
"-
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 5.714 m
E. Direct Unit Cost (C + D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
a. 30.00 mm2 - 38 mm2 Electric Wire Prices of materials are variable per Region/
m 1.00 District based on the prevailing unit prices in the
(TW/THHN/TWHN2)
locality which include payment of local taxes
b. Consumables (3% of Materials Cost) and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
A. Labor
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
"
F. Materials
a. 50.00 mm2 - 60mm2 Electric Wire Prices of materials are variable per Region!
m 1.00 District based on the prevailing unit prices in the
(TWITHHNITWHN2)
locality which include payment of local taxes
b. Consumables (3% of Materials Cost) and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
Item No./Description 1101(2) 80.00 mm2 - 125 mm2 Electric Wire (TW/THHN/TWHN2)
Unit of Measurement m
Output per hour 2.857 m
A. Labor
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
.
B. Equipment
"
F. Materials
a. 80.00 mm2 - 125 mm2 Electric Wire Prices of materials are variable per Region/
m 1.00 District based on the prevailing unit prices in the
(TW/THHN/TWHN2)
locality which include payment of local taxes
b. Consumables (3% of Materials Cost) and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
Item No.lDescription 1101(2) 150.00 mm2 - 250 mm2 Electric Wire (TW/THHN/TWHN2)
Unit of Measurement m
Output per hour 1.875 m
A. Labor
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
"-
F. Materials
a.150.00 mm2 -250 mm2 Electric Wire m 1.00 Prices of materials are variable per Regionl
District based on the prevailing unit prices in the
(TW/THHN/TWHN2)
locality which include payment of local taxes
b. Consumables (3% of Materials Cost) and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
(G + H + I + J)
Note 1. Use this cost sheet for Item Nos. 1101 (2)a18, 1101 (2)a19 and 1101 (2)a20.
Item No.lDescription 1101(2) 325.00 mm2 - 400 mm2 Electric Wire (TWITHHNITWHN2)
Unit of Measurement m
Output per hour 1.60 m
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
-,
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 1.60 m
E. Direct Unit Cost (C + D)
F. Materials
a. 325.00 mm2 - 400 mm2 Electric Wire m 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in the
(TWITHHNITWHN2)
locality which include payment of local taxes
b. Consumables (3% of Materials Cost) and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
A. Labor
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
..
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 1.333 m
E. Direct Unit Cost (C + D)
F. Materials
a. 500.00 mm2 Electric Wire (TW/THHN/TWHN2) m 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in the
b. Consumables (3% of Materials Cost) locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
A. Labor
(Labor cost shall be included in the Power Contract with MERALCO or Local Power Cooperative.)
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 0
E. Direct Unit Cost (C + D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
a. XLPE, Creosoted pole, anchor Rod, anchor log, (Materials cost included in the Power Contract with MERALCO
power load studs, pad mounted transformer, pole-type or Local Power Cooperative.)
transformer, transformer bracket, Aluminum
Conductor Steel-Reinforced (ACSR) powerfuse,
concrete pole, power transmission pole, pin insulator,
pole top pin, machine bolts and washers
Item No./Description 1101 (7) 2.00 mm2 - 5.5 mm2 Bare Copper Wire
Unit of Measurement m
Output per hour 20.00 m
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
"
F. Materials
a. 2.00 mm2 - 5.00 mm2 Bare Copper Wire m 1.00 Prices of materials are variable per Region!
b. Consumables (3% of Materials Cost) District based on the prevailing unit prices in the
locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
Item No.lDescription 1101 (7) 8.00 mm2 - 22.00 mm2 Bare Copper Wire
Unit of Measurement m
Output per hour 10.00 m
A. Labor
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
.
B. Equipment
"
F. Materials
a. 8.00 mm2 - 22.00 mm2 Bare Copper Wire m 1.00 Prices of materials are variable per Region/
b. Consumables (3% of Materials Cost) District based on the prevailing unit prices in the
locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
Item No./Description 1101(7) 30.00 mm2 - 38.00 mm2 Bare Copper Wire
Unit of Measurement m
Output per hour 12.00 m
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
"
F. Materials
a. 30.00 mm2 - 38.00 mm2 Bare Copper Wire m 1.00 Prices of materials are variable per Regionl
b. Consumables (3% of Materials Cost) District based on the prevailing unit prices in the
locality which include payment of local taxes
and hauling cost to the project site, Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
Item No./Description 1101 (7) 50.00 mm2 - 60.00 mm2 Bare Copper Wire
Unit of Measurement m
Output per hour 10.00 m
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
".
F. Materials
a. 50.00 mm2 - 60.00 mm2 Bare Copper Wire m 1.00 Prices of materials are variable per Region!
b. Consumables (3% of Materials Cost) District based on the prevailing unit prices in the
locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
Item No.lDescription 1101 (7) 80.00 mm2 - 125.00 mm2 Bare Copper Wire
Unit of Measurement m
Output per hour 6.00 m
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
'.
F. Materials
a. 80.00 mm2 - 125.00 mm2 Bare Copper Wire m 1.00 Prices of materials are variable per Region/
b. Consumables (5% of Materials Cost) District based on the prevailing unit prices in the
locality which include payment of local taxes
and hauling cost to the project site, Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee,
Item No./Description 1101(7) 200.00 mm2 - 250.00 mm2 Bare Copper Wire
Unit of Measurement m
Output per hour 6.667 m
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
"
F. Materials
a. 200.00 mm2 - 250.00 mm2 Bare Copper Wire m 1.00 Prices of materials are variable per Region!
b. Consumables (5% of Materials Cost) District based on the prevailing unit prices in the
locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
A. Labor
Name and Capacity No. of Unit/s No. of Houris Hourly Rate Amount (PhP)
B. Equipment
..
Sub - Total for 8
C. Total (A + B)
D. Output - 1 set
E. Direct Unit Cost (C + D)
F. Materials
Item No.lDescription 1101 Single Convenience Outlet/Receptacle, Grounding Type (GT)I Heavy Duty Convenience
Outlet/Receptacle, Grounding Type (GT)I Weather Proof Single Convenience Outlet/Receptacle,
Grounding Type (GT)I Pop-up Type/Floor Triplex Convenience Outlet/Receptacle, Grounding Type (GT)
A. Labor-
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Item No./Description 1101 Duplex Convenience Outlet/Receptacle, Grounding Type (GT) I Weather Proof Duplex Convenience
Outlet/Receptacle, Grounding Type (GT)I Special Purpose Convenience Outlet/Receptacle, Grounding
Type for ACU, WH, etcl Explosion Proof Type Duplex Convenience Outlet/Receptacle, Grounding Type
(GT)I Duplex Convenience Outlet/Receptacle with Ground Fault Circuit Interupter
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Duplex Convenience Outlet/Receptacle, Grounding Prices of materials are variable per Region!
Type (GT) I Weather Proof Duplex Convenience District based on the prevailing unit prices in the
Outlet/Receptacle, Grounding Type (GT)I Special locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Purpose Convenience Outlet/Receptacle, Grounding
Construction Material Price Data established
Type for ACU, WH, ete! Explosion ProofType Duplex quarterly by Central Office Price Monitoring
Convenience Outlet/Receptacle, Grounding Type set 1.00 Committee.
(GT)I Duplex Convenience Outlet/Receptacle with
Ground Fault Circuit Interupter
Item No./Description 1101 Pop-up Type/Floor Single Convenience Outlet/Receptacle, Grounding Type (GT)/ Pop-up Type/Floor
Duplex Convenience Outlet/Receptacle, Grounding Type (GT)/ Explosion Proof Type Single
Convenience Outlet/Receptacle, Grounding Type (GT)/ Single Convenience Outlet/Receptacle with
Ground Fault Circuit Interrupter
A. Labor-
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Pop-up Type/Floor Single Convenience Prices of materials are variable per Region!
Outlet/Receptacle, Grounding Type (GT)/ Pop-up District based on the prevailing unit prices in the
Type/Floor Duplex Convenience Outlet/Receptacle, locality which include payment of local taxes
and hauling cost to the project site_ Refer to the
Grounding Type (GT)/ Explosion Proof Type Single
Construction Material Price Data established
Convenience Outlet/Receptacle, Grounding Type set 1.00
quarterly by Central Offiice Price Monitoring
(GT)/ Single Convenience Outlet/Receptacle with Committee
Ground Fault Circuit Interupter
A. Labor
Name and Capacity No. of Unit/s No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
"-
F. Materials
Item No./Description 1102 Panel Board with Main Breaker/Branches, 3 wires, 1 neutral, 250 Amp - 400 Amp
Unit of Measurement set
Output 1 set
A. Labor
Note:
Labor includes disassembling of Panel Board
component, fabrication of hole (conduit for main breaker
and branches), installation of fitting, alignment of panel
board enclosure, re-installation of circuit breaker
component and accessories, termination of wire, testing
and commissioning.
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
"
F. Materials
a. Panel Board with Main Breaker and 8 Branches Prices of materials are variable per Region!
set 1.00 District based on the prevailing unit prices in the
250 amp - 400 amp
locality which include payment of local taxes
b. Consumables (3% of Materials Cost)
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
Item No./Description 1102 Panel Board with Main Breaker/Branches, 3 wires, 1 neutral, 50 Amp - 200 Amp
Unit of Measurement set
Output 1 set
A. Labor
Note:
Labor includes disassembling of Panel Board
component, fabrication of hole (conduit for main breaker
and branches), installation of fitting, alignment of panel
board enclosure, re-installation of circuit breaker
component and accessories, termination of wire, testing
and commissioning.
Name and Capacity No. of Unitls No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Panel Board with Main Breaker and 8 Branches 50 Prices of materials are variable per Region/
amp - 200 amp set 1.00 District based on the prevaifing unit prices in the
locality which include payment of local taxes
and hauling cost to the project site. Refer to the
b. Consumables (3% of Materials Cost)
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
Item No./Description 1102 NEMA I (Enclosed Circuit Breaker) Single Phase or Three Phase Commercial/lndustrial Type
Unit of Measurement set
Output per hour 1 set
A. Labor
Note:
Labor Includes removal of circuit breaker,
Alignment, mounting and removal of hub/hole, installation of
pipe/fittings, re-installation of circuit breaker, termination of
wires, testing and commisioning.
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
",
F. Materials
a. NEMA I Enclosed Circuit Breaker, plug-in or bolt Prices of materials are variable per Region!
set 1.00 District based on the prevailing unit prices in the
type 15A T-70A T Flushed Mounted
locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
Item No./Description 1102 NEMA 3R (Enclosed Circuit Breaker) Single Phase or Three Phase Commercial/Industrial Type
Unit of Measurement set
Output per hour 1 set
A. Labor
Note:
Labor Includes removal of circuit breaker,
Alignment, mounting and removal of hub/hole, installation of
pipe/fittings, re-installation of circuit breaker, termination of
wires, testing and commisioning.
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
"
F. Materials
a. NEMA 3R Enclosed Circuit Breaker, plug-in or bolt set 1.00 Prices of materials are variable per Region/
type 15AT-70AT Flushed Mounted District based on the prevailing unit prices in the
locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
Item No./Description 1102 Motor Control Center with main, branch breaker and motor starter (NEMA 1, NEMA 3R and 4X) Flush or
Surface Mounted
Unit of Measurement set
Output per hour 1 set
A. Labor
Note:
Labor Includes removal of circuit breaker,
Alignment, mounting and removal of hub/hole, installation of
pipe/fittings, re-installation of circuit breaker, .termination of
wires, testing and commisioning.
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
"
F. Materials
a. Motor Control Center with main, branch breaker and Prices of materials are variable per Region/
set 1.00
motor starter (NEMA 1, NEMA 3R and 4X) Flush or District based on the prevailing unit prices in the
Surface Mounted locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
Item No.lDescription 1102(8) Generator (Stand by and Continuous), Synchonizing Panel for Generator, High Voltage Switch Gear
A. Labor
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Generator (Stand by and Continuous), Synchonizing Materials Cost by Specialty Works or Manufacturer'sJSupplier's
Panel for Generator, High Voltage Switch Gear Quotation (attach at least 3 quotations)
Item No./Description 1102 Main Enclosed Automatic Circuit Breaker 50 AT, 60 AT, 70 AT, 3P, 240V: NEMA I, NEMA 3R, NEMA 4x
Flushedl Surface Mounted
Unit of Measurement set
Output per hour 1 set
A. Labor
Note:
Labor Includes removal of circuit breaker,
Alignment, mounting and removal of hub/hole, installation of
pipe/fittings, re-installation of circuit breaker, termination of
wires, testing and commisioning.
B. Equipment
'.
F. Materials
Main Enclosed Automatic Circuit Breaker 50 AT, 60 set 1.00 Prices of materials are variable per Region/
AT, 70 AT , 3P, 240x: NEMA I, NEMA 3R, NEMA 4x District based on the prevailing unit prices in the
Flushedl Surface Mounted locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
Item No./Description 1102 Main Enclosed Automatic Circuit Breaker 50 AT, 60 AT, 70 AT, 2P, 240V NEMA I, NEMA 3R, NEMA 4x
Unit of Measurement set
Output 1 set
A. Labor
Note:
Labor Includes removal of circuit breaker,
Alignment, mounting and removal of hub/hole, installation of
pipe/fittings, re-installation of circuit breaker, termination of
wires, testing and commisioning.
B. Equipment
"
F. Materials
a. Main Enclosed Automatic Circuit Breaker 50 AT, 60 set 1.00 Prices of materials are variable per Region!
AT, 70 AT, 2P, 240V NEMA I, NEMA 3R, NEMA 4x District based on the prevailing unit prices in the
Flushedl Surface Mounted locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
Item No./Description 1102 Main Enclosed Automatic Circuit Breaker 100 AT, 125 AT, 205 AT, 225 AT, 3P; 240V NEMA I, NEMA
3R, NEMA 4x Flushed/ Surface Mounted
Unit of Measurement set
Output per hour 1 set
A. Labor
Note:
Labor Includes removal of circuit breaker,
Alignment, mounting and removal of hub/hole, installation of
pipe/fittings, re-installation of circuit breaker, termination of
wires, testing and commisioning.
B. Equipment
"
F. Materials
a. Main Enclosed Automatic Circuit Breaker 100 AT, set 1.00 Prices of materials are variable per Region/
125 AT, 205 AT, 225 AT, 3P, 240V NEMA I, NEMA District based on the prevailing unit prices in the
3R, NEMA 4x Flushed/ Surface Mounted locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee
Item No./Description 1102 Main Enclosed Automatic Circuit Breaker 100 AT, 125 AT, 200 AT, 2P, 225 AT, 2P, 240V NEMA I,
NEMA 3R, NEMA 4x Flushedl Surface Mounted
Unit of Measurement set
Output per hour 1 set
A. labor
Note:
Labor Includes removal of circuit breaker,
Alignment, mounting and removal of hub/hole, installation of
pipe/fittings, re-installation of circuit breaker, termination of
wires, testing and commisioning.
B. Equipment
".
F. Materials
a. Main Enclosed Automatic Circuit Breaker 100 AT, set 1.00 Prices of materials are variable per Region/
125 AT, 200 AT , 2P, 225 AT, 2P, 240V NEMA I, District based on the prevailing unit prices in the
NEMA 3R, NEMA 4x Flushedl Surface Mounted locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee
Item No./Description 1102 Low Voltage Switch Board Main 2500-4000 AT, 3P, 240V NEMA I with Breaker
Unit of Measurement set
Output per hour 1 set
A. Labor
B. Equipment
-.
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 1 set
E. Direct Unit Cost (C + D)
F. Materials
a_ Low Voltage Switch Board Main 2500-4000 AT, 3P, Material Cost by Specialty Works or Manufacturer's/Supplier's
240V NEMA I with Breaker Quotation (attach at least 3 quotations)
A. Labor
Note:
Labor Includes removal of circuit breaker,
Alignment, mounting and removal of hublhole, installation of
pipelfittings, re-installation of circuit breaker, termination of
wires, testing and commisioning.
B. Equipment
",
F. Materials
a. Main Enclosed Automatic Breaker 250-500 Amp set 1.00 Prices of materials are variable per Region!
District based on the prevailing unit prices in the
locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
A. Labor
See derivation for Item 1103(2)-ltem 1103(13) Labor Rates are variable per Region/District
based on minimum wage as approved by
. DOLE. Refer to the Schedule of Labor Rates .
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
-.
F. Materials
See derivation for Item 1103(2)-ltem 1103(13) Prices of materials are variable per Region!
District based on the prevailing unit prices in the
locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
Item No./Description : 1103(2) Fluorescent Lighting Fixture with Ballast lLight Emitting Diode (LED) Bulb, 1 Bulb
Unit of Measurement set
Output 1 set
A. Labor
Note:
Labor Includes installation of scaffolding,
alignment of fixtures, disassemble of lighting fixture,
permanent Installation of insullation material, testing and
commisioning.
Name and Capacity No of Unit/s No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
"
1 set
E. Direct Unit Cost (C + D)
F. Materials
a. 1 -20Watts-40Watts f10urescent lighting fixture, Box set 1.00 Prices of materials are variable per Regionl
type, Diffuser type, Mirrorized Aluminum Louver, District based on the prevailing unit prices in the
Industrial type (Recessed and Surface Mounted) locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
Item No./Description : 1103(2) Fluorescent Lighting Fixture with Ballast /Light Emitting Diode (LED) Bulb, 2 Bulbs
Unit of Measurement set
Output 1 set
A. Labor
Note:
Labor Includes installation of scaffolding,
alignment of fixtures, disassemble of lighting fixture,
permanent Installation of insullation material, testing and
commisioning.
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
"
F. Materials
a. 2 -20Watts-40Watts f10urescent lighting fixture, Box set 1.00 Prices of materials are variable per Region!
type, Diffuser type, Mirrorized Aluminum Louver, District based on the prevailing unit prices in the
Industrial type (Recessed and Surface Mounted) locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee,
Item No./Description 1103(2) Fluorescent Lighting Fixture with Ballast lLight Emitting Diode (LED) Bulb, 3 Bulbs
Unit of Measurement set
Output 1 set
A. Labor
Note:
Labor Includes installation of scaffolding,
alignment of fixtures, disassemble of lighting fixture,
permanent Installation of insullation material, testing and
commisioning.
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
"-
F. Materials
a. 3-20watts-40watts f10urescent lighting fixture set 1.00 Prices of materials are variable per Regionl
Box type, Diffuser type, Mirrorized Aluminum Louver, District based on the prevailing unit prices in the
Industrial type (Recessed and Surface Mounted) locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
Item No.lDescription 1103(2) Fluorescent Lighting Fixture with Ballast ILight Emitting Diode (LED) Bulb, 4 Bulbs
Unit of Measurement set
Output 1 set
A. Labor
Note:
Labor Includes installation of scaffolding,
alignment of fixtures, disassemble of lighting fixture,
permanent Installation of insullation material, testing and
commisioning.
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
",
F. Materials
a. 4-20watts-40watts flourescent lighting fixture set 1.00 Prices of materials are variable per Regionl
Box type, Diffuser type, Mirrorized Aluminum Louver, District based on the prevailing unit prices in the
Industrial type (Recessed and Surface Mounted) locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
Item No.lDescription 1103(5) Downlight/Pinlight Fixture with One- Compact Fluorecent Lamp (CFL) or LED Bulb, 1 Bulb
Unit of Measurement set
Output per hour 1 set
A. Labor
Note:
Labor Includes installation of scaffolding,
alignment of fixtures, disassemble of lighting fixture,
permanent Installation of insullation material, testing and
commisioning.
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Item No./Description 1103(5) DownlightJPinlight Fixture with Two- Compact Fluorecent Lamp (CFL) or LED Bulb, 2 Bulb
Unit of Measurement set
Output 1 set
A. Labor
Note:
Labor Includes installation of scaffolding,
alignment of fixtures, disassemble of lighting fixture,
permanent Installation of insullation material, testing and
commisioning.
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
"0
F. Materials
a. 2- 8Watts-21 Watts DownlightlPinlight, set 1.00 Prices of materials are variable per Region!
RecessedlSurface Mounted with or without glass District based on the prevailing unit prices in the
locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
A. Labor
Note:
Labor Includes, installation of scaffolding,
alignment of lighting fixture, termination of wire, testing,
commissioning and painting.
Name and Capacity No of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted, Scissor Lift, Rough Terrain 1 1.00 See latest ACEL rental rates.
(Gas/Diesel)
Minor Tools (10% of Labor Cost)
F. Materials
a. High Bay Aluminum Reflector, Dome Luminaire set 1.00 Prices of materials are variable per Regionl
70Watts - 250 Watts District based on the prevailing unit prices in the
locality which include payment of local taxes
and hauling cost to the project site. Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
Item No./Description 1103(12) Die-Cast Aluminum Floodlight with Electrocoat Paint Finish
Unit of Measurement set
Output 1 set
A. Labor
Nole:
Labor Includes, installation of scaffolding,
alignment of lighting fixture, termination of wire, testing,
commissioning and painting.
Name and Capacity No of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
a. Truck Mounted, Scissor Lift, Rough Terrain 1 1.00 See latest ACEL rental raets.
(Gas/Diesel)
C. Total (A + B)
D. Output = 1 set
E. Direct Unit Cost (C + D)
F. Materials
a.Die-Cast Aluminum Floodlight with electrocoat paint set 1.00 Prices of materials are variable per Region/
finish 70Watts - 250 Watts District based on the prevailing unit prices in the
locality which include payment of local taxes
and hauling cost to the project site, Refer to the
Construction Material Price Data established
quarterly by Central Office Price Monitoring
Committee.
A. Labor
Name and Capacity No. of UniUs No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
A. Labor
B. Equipment
.J
F. Materials
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
Item No./Description 1202(2)a Fire Pump with complete control and standard accessories
Unit of Measurement set
Output 1 set
A. Labor
B. Equipment
F. Materials
Item No./Description 1202(2)b Jockey Pump with complete control and standard accessories
Unit of Measurement set
Output 1 set
A. Labor
B. Equipment
F. Materials
a. Jockey Pump complete with controller and set 1.00 Prices of materials are variable per Region/
NEMA 3R and other accessories: valve, suction District based on the prevailing unit prices in
the locality which include payment of local
and discharge gauge, flow meter and other
taxes and hauling cost to the project site.
accessories specified in mechanical plan and Refer to the Construction Material Price Data
specifications established quarterly by Central OfficePrice
b. Consumables (5% of Materials Cost) Monitoring Committee.
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Sprinkler Head, upright/pendent/wall pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
A. Labor
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. Alarm Check Valve pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. OS & Y Gate Valve 175 psi pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
oJ
F. Materials
A. Labor
B. Equipment
.J
F. Materials
a. Pressure Relief Valve pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. Pressure Relief Valve pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. Inspector Test Valve pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. Inspector Test Connector pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee
A. Labor
Note:
Straight line installation for ceiling height of up to
3.5m. Labor output includes setting, scafolding, cutting,
fixing of pipe from elbow, tee, flange, valve and painting.
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. 25 mm 0 - 50 mm 0 x 6.00 m Black Iron (B.I.) Prices of materials are variable per Region/
length 1.00 District based on the prevailing unit prices in
Pipe
the locality which include payment of local
b. Consumables (5% of Materials Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
A. Labor
Note:
Straight line installation for ceiling height of up to
3.5m. Labor output includes setting, scafolding, cutting,
fixing of pipe from elbow, tee, flange, valve and painting.
Name and Capacity No. of Unitls No. of Houris Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. 65 mm 0 -150 mm l2I x 6.00 m Black Iron (B.I.) Prices of materials are variable per Region/
length 1.00 District based on the prevailing unit prices in
Pipe
the locality which include payment of local
b. Consumables (5% of Materials Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
A. Labor
(Labor.. cost for these items are to be consideredlincluded in the installation of pipes.)
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. B.l. 90 elbow/B.l. Tee/ Bell Reducerl Blind Prices of materials are variable per Region!
District based on the prevailing unit prices in
Flange/ Slip Flange/ Riser Nipple/ Threadolet! Pipe pc 1.00 the locality which include payment of local
Sleeve taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
b. Consumables (5% of material cost)
established quarterly by Central Office Price
Monitoring Committee.
Item No./Description 1202(10) Fire Hose Valve siames 150 mm 11lx 2 w x 65 mm 11lwith cap
Unit of Measurement set
Output 1 set
A. Labor
B. Equipment
.J
F. Materials
A. Labor
Name and Capacity No. of Unitls No. of HourIs Hourly Rate Amount (PhP)
B. Equipment
.J
F. Materials
a. Fire Hose Cabinet set 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of Materials Cost)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
A. Labor
B. Equipment
.J
F. Materials
a. Fire Extinguisher set 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.
272
C. CALCULATION OF CYCLE TIME FOR HAULING EQUIPMENT
NOTE:
The assumed travel time for loaded and unloaded dump trucks for each type of road surface and
terrain condition are for normal conditions. It may vary depending on traffic and road surface
conditions and other fa9:0rs provided that a detailed justification/explanation to be supported with
corresponding data and relevant information should be presented.
273
SECTION D
274
D. COMPUTATION OF LABOR RATES
The estimated labor rates for each region/district office were computed in accordance with D.O.
40, Series of 2009, Re: Guidelines for the establishment of Construction Materials Price Data,
Standard Labor and Equipment Rental Rates (or latest issuance), and based on the minimum
wage rate as published by the National Wages and Productivity Commission, Department of
Labor and Emolovment (DOLE)'
The computed labor rates including all component costs such as basic wage plus emergency cost
of living allowance (ECOLA) and worker's statutory monetary benefits and others are in
accordance with the existing~ laws and government regulations. It shall be updated as the need
arises based on the latest issuances for new minimum wages by the NWPC/DOLE and/or any
amendments to the benefits of the workers.
CASE II - In cases wherein project/s traverse/s certain provinces within the jurisdiction of
only one (1) Regional Office, the average labor cost of the said Regional Office
shall be utilized.
CASE III - In cases wherein project/s passes numerous pfovinces within the jurisdiction of
.two (2) or more Regional Offices, the average labor cost of the said Regional
Office with the longest work coverage or with largest major scope of works
shall be utilized.
275
~ II: II:
:)
000 1.0 1.0
....• ....• ..... 1.0 Vl Vl m ,...
<t
~
0"\
Vl .n .n
Vl 0"\ 0"\ 00
~ Q. 0 <i
....• oci ....; ....; <i
,...
0
II: :I: ....• ....• 0
N
..... 0
....• 0"\ 0"\ 0"\ 00
i ~ ~
II: 00 00 <t
cri 0 ....; ....; oci .n m
,... ,... ,...
Vl Vl
Q. 0 0"\
0"\
N
0"\
<t
00
<t
00 ,... m
00
1.0
1.0
Vl
~ II: :I:
0
m ,... ,... ,... ,...
00 Vl Vl 00 00 0 m
m m 0 0
r'
Vl
N ....;
"0 I-
e lci 0 N 0 0 lci
~ ~ 0
Z 0"\ N m m .....
0 ,...
- .....- ....• m m 0"\ ....•
0"\ 0"\ 1.0 <t
'"
b.O
.::;
II:
~
Q. 0"\ 0 0
<t- m- ....• 0"\- 00- 00 ..... ....•
1.0- <t-
N N N N ....• .....
b.O
'"
l-
~
e- § 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
~'" Ib
~
0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0
..... ..... ....• ....• ..... ..... ....• ..... .....
e 0..
'"
Vl V!
l-
e- ii:
O ~ :I:
N
Z
~ !:; 0 0 0 0 0 0 0 0 0
~
Q)
-
o
'"
0.. 0 0..
o
V') >-
V!
o
o
U 0 0 0 0 0 0 0
LLI '" ~ 0 0 0 0 0 0 0 0 ,...
0 o
''""
m
0 0 0 0 0 0 0 cri N Vl-
0..
- - - - - - -
V! 0"\ 0"\ 0"\ 0"\ 0"\ 0"\ 0"\
~
0-
V! 0 0 0 0 0 0 0 0"\ N
a:: W
:::>
V! ....• ..... ..... ..... ....• ..... ..... 0"\ 00 QJ
>
r::T
o
a:: '"
>-
o
.0
co
e Ie
~ :I:
:I: 0 00 Vl Vl ,...
..... 00 00 0
m
QQ
~co
o
o
&
~ r'
0 0 0
o
I- Vl 00 N N
CO '" > ....; cri N N .n 00
..• 0~
I- Z lci lci
,...
0 o
0..
,... u QJ
<C .....
- - - - - - - -
rtl <t 0 Vl Vl Vl 1.0 1.0 1.0
.....
....I ",-
C
Q. 1.0 <t <t m N N .s::
..... ....• ..... ..... ..... ....• ..... ..... 0"\ c C 0- QJ
u a:l
.•...
'" co 00"0
u.. .•..o
QJ :p '';:; c: co
e Cl: z'>"
0
::> ::> co ·u
o
Ec: :sc:
.0.00
V>
Z u m- ~
V! X >- a Vl
-o
0 0 0 0 0 0 0 0 0 QJ co ci +
>
e zC
00 0"\ 0 0 <t 00 00 N 0
.n .n
"0 "0
~ oci oci cri cri N cri lci C 000 >-
...
o
0-
:::> ~ ,...
m 1.0 0"\ 0"\ Vl 0 0 Vl 1.0
1.0 1.0 1.0 1.0 1.0 o
U U 0
I.n V') a.ri'
co
0-
...•..
00 Vl
i= ::E:
<t V> m
o -OJ -Q) 0-
f;
:;::; u ....•
....I ;:
N QJ QJ ~
<C e
:::> ~ ~ 0 o
C
a.. ~ ~ 0 0 0
~ .n
0 0 0 0 0 0 .0 *f; c.c.w ::::
::::> :I: 0
,... N
0
Vl
,... ,...
0 0
0
0
.n .n
0 0
0 0
0 .J co
--'QJ c E E .0
CO C m- ~ ....•
I- Vl c
o UJ UJ
-
N <t <t 00 Vl
e ~ Z 0"\ N <t m ..... ..... 0"\ 1.0
f; E
0 6 cri' ,...- ,...- 1.0- ui" Vl- m- .....
<t ~ 110 ~
:.;;; ~ •... C C co
~ .;::
~ ~ N ..... ..... ....• ..... ..... ..... ....• ..... >-
.0
QJ
C.
'';:;
c
~
c
V)
~'"
QJ QJ QJ
LLI "0
....I OJ Ci1
V>
U .!!! >- N 0.
Q. .IE.- Vi
~ ~ 0 0 0 0 0 0 0 0 0 C.
:;::;
co
"0 M a.a.E
QJ QJ 0
·c en
00 0"\ 0
oci oci cri cri N
0
cri lci
<t 00
.n .n
00 N 0
:; Vl
~a::a::~
~ <C ,...
N
£
~'"
m 1.0 0"\ 0"\ Vl 0 0 Vl 1.0 E b.O ~ ~
0 *QJ
<C 00 1.0 1.0 1.0 1.0 1.0 Vl <t
V')
QQ ~ 5 5 c
b.O co >- E E ~
e
0 l- :s: £c: <! « u
M >- V! ~ "'C 'Vi
ci :::>
"'0
-'"'"
0
>-
~'" :~
vi" '"
0- z
·u 0
'"
Ie ·c i=
c:: :::> 0.. .9 .9co
'" ~ ...•
LI"l
ii: '"
0;
a
-''e"_..c.•...OJ u 0;
- -
N
~ ~
V! C.
0
0 c.
0 0
'" "0 0
'" C .0
u e co •...
0 2 QJ
--' C .0
co
.2 '" .0 E
.e-
"0
QJ
E 0
--' 0
.0
'" Qj':::>"
OJ OJ co
"0
U u.. :3 :::: c.
.::; co ~ "0
--'
-
.0
c c
'+-
0 N
e~ co co cr "'"
UJ Vl cr --' :;< ~
E "0E >- >- UJ •... "0 'f'
'":;::;
OJ ~
.!!! QJ > :;: .s::
co .~ ~
QJ
·E :;<C'"
0 > '" ~
i=
...
0 coQJ :cQJ .99
--'
QQ
:c ::; Ci :;< QJ
Vl Vl =>
~ U~
...o
V!
Z
~ w
0
i=
~ ~ 0
II:
:) 0
0 Z
ci ....• N m <t Vl 1.0 ,... 00 0"\
bz
~ ~
u I- V! U
0
-' o II:
SECTION E
277
E. EQUIPMENT RENTAL RATES
Rental of equipment presented in the Detailed Unit Price Analysis (DUPA) are based on the prevailing "Association of
Carriers and Equipment Lessors, (ACEL) Inc." rental rates approved for use by the DPWH (Presently it is the 2014
ACEL Rates). Rental rates of equipment not indicated in the ACEL booklet shall be taken from the rental rates
prepared by the Bureau of Equipment. For simplicity in computation, the operated rental rates are preferred over the
bare rental rates as the former includes operator's wages, fringe benefits, fuel, oil, lubricants and equipment
maintenance.
E.! List of equipment adopted in the standard DUPA with make, model and capacity
HEEL
I
RENTAL RATE
Earthmoving
DESCRIPTION
Equipment
I MODEL CAPACITY
ER
1.
1.1 Bulldozer D6H SERIES II PSDS/DD 165 PhP 3,379.00
1.2 Payloader LX80- 2C 1.50 m3/1.95 vd3 110 PhP 1,733.00
1.3 Motorized Road Grader G710A 140 PhP 2,173.00
2. Compaction Equipment
2.1 Plate Compactor 400-500 Gasoline Engine 5 PhP 123.00
3. Lifting Equipment
3.1 Crawler Crane All Models 21-25 mt 145 PhP 1,522.00
3.2 Crawler Crane All Models 36-40 mt 190 PhP 1,902.00
3.3 Crawler Crane All Models 41-45 mt 190 PhP 2,151.00
3.4 Truck Mounted Crane All Models 20-25 mT 200 PhP 1,631.00
3.5 Truck Mounted Crane All Models 31-35 mt 238 PhP 1,861.00
3.6 Truck Mounted Crane All Models 41-45 mt 246 PhP 2,606.00
3.7 Truck Mounted, Scissor Lift, Terrain Gas/Diesel Driven 40 ft hts x 46 ft range PhP 1,386.00
4. Excavating Equipment
3 3 99 PhP 1,537.00
4.1 Backhoe SE 130 LC-2 0.80 m /1.04 vd
3 3 99 PhP 1,998.10
4.2 Backhoe w/ Breaker SE 130 LC-2 0.80 m /1.04 vd
3
4.3 Backhoe, Wheel Mounted PW60N-l 0.28 m3/0.37 vd 50 PhP 922.00
4.4 Portable Breaker WACKER PORTABLE PETROL BREAKER, BHF30S 4 PhP 129.38
5. Foundation Equipment .J
6 Concreting Equipment
6.1 Concrete Screeder Wacker Truss Screed 5.50 PhP 545.00
6.2 Concrete Paver COMMANDER III, FOUR-TRACK PhP 6,765.00
6.3 One Bagger Mixer 4-6 ~/min PhP 172.00
6.4 Transit Mixer All Models 5-6 vd3 175 PhP 1,318.00
7 Hauling Equipment
7.1 Dump Truck All Models 12 vd3 290 PhP 1,420.00
7.2 Cargo/Service Truck All Models 2-5 mt 160 PhP 783.00
7.3 Boom Truck All Models 2-5 mt 160 PhP 1,017.90
7.4 Cargo/Service Truck All Models 9-10 mt 270 PhP 1,212.00
7.5 Water Truck/Pump All Makes 16000 L 360 PhP 2,450.00
8 Air Equipment
8.1 Air Compressor All Models 356-450 dm 130 PhP 965.00
8.2 Air Compressor All Models 161-185 dm 69 PhP 502.00
8.3 Air Compressor, Portable All Models 120-160 dm 51 PhP 450.00
8.4 Air Compressor All Models 15-35 dm 20 PhP 205.00
8.5 Diamond Drill CP-8 PhP 201.25
8.6 Jackhammer PhP 150.00
8.7 Pneumatic Drillina Machine PhP 170.00
278
SOLID SIZE tLY
DESCRIPTION OUTPUT/DISCHARGE (Ipm) ENTAL RA
CAPACITY (mm)
9 Pumping Equipment
9.1 Water Pump, 100 mm suction 0 2,667 50 16 PhP 266.25
9.2 Water Pump, 100 mm suction 0 1,800 7.50 PhP 123.38
9.3 Pumocrete PhP 2 076.00
11 Shop Equipment
11.1 Welding Machine Electric Driven/DC Output 500 PhP 391.00
11.2 Weldina Machine ,
Gas/Diesel Driven 300 48 PhP 371.00
FLYWHEEL
DESCRIPTION MODEL CAPACITY •• ~L RATE
I II I HORSEPOWER
12 Special Support Equipment
12.1 Chainsaw HUSQVARNA 2100 CD with CR22, 7 ft Reach, 9 in Standard Blade PhP 75.36
13. Miscellaneous Equipment
13.1 Concrete Vibrator Flexible Shaft Type 2" Head !I} with 5 Amperes Gasoline Drive Unit PhP 91.25
13.2 Bar Cutter 25 mm Maximum Rebar 0 (Grade 40), Single Phase PhP 219.75
13.3 Bar Bender 25 mm Maximum Rebar 0, Three Phase PhP 351.50
14. Others
14.1 Drop Hammer w/ accessories 20 mt PhP 5,000.00
14.2 1 Air Compressor w/2 Jack Hammer PhP 1,265.00
14.3 Cutting Outfit PhP 45.45
279