POURING SCHEDULE

DATE: MARCH 13, 2024 ( WEDNESDAY )

TIME CONTRUCTOR NAME LOCATION DR ACT VOLUME STRUCTURE PUMP C/O REMARKS
4PM EARLIEST BATCHING POSCO TO FOLLOW QUEJADO
12NN EARLIEST BATCHING ITD BOREDPILE TO FOLLOW
9AM ARIEL LACAP MANFIELD 1500-28-3/4 1500-28-3/4 8 SLOPE PROTECTION RICA NOTE: PLUS ON CALL
9AM GALLMAN EMPIRE BLDRS. INC MABALACAT 3000-28-3/4 3000-28-3/4 12 SLOPE PROTECTION RICA NOTE: SUKAT BEFORE POURING
7PM SETUP: ITALIAN THAI DEVP. CO CLARK STATION 40MPA 40MPA 28 P1112NB PIER HEAD BGC BOOM 38 PAT
ADDTNL SCHEDULE: SINOMA CBMIPH CONST. COMP. MABALACAT 4000-28-3/4 4000-28-3/4 31 QUEJADO NOTE: PPE REQUIRED

79.0
NOTE: TO FOLLOW ADDITIONAL SCHEDULE C/O PAT.

G1 -
3/4 - 51.0
3/8 -
BLENDED - 28.0

TOTAL: 79.0

NO QUOTATION, NO SITE SURVEY, NO BATCH!


"Schedules may change the day of pouring due to clients request ."

PREPARED BY: ANNA MICAELLA R. GONZALES