School Disaster Risk Reduction Management Plan

Pillar 1 Pillar 2 Pillar 3 Indicative Fund Source


Thematic Areas Safe Learning Facilities School Disaster Management (Activity) Disaster Risk Reduction in Education Schedule
(Activity) (Activity)
- Conduct Clean-Up Drive
- Hazard Risk assessment - Safe school site & resilient -conduct child-led school-based Risk- June- March 2018 MOOE
Prevention and Mapping classroom Reduction Workshop
Mitigation - Retrofitting/ Repair of - Solid Waste Management
Classroom
- Installation of Threated
Windows Nets
- Organized School DRRMC Team
- Provide an early warning Putting-up signage on early - Facilitate the use of schools June-March 2018 MOOE/LGU
system within the school warning as evacuation center
Preparedness premises - Evacuation Plan - Conduct training of teachers
- Conduct hazard drills and pupils
- Formulated contingency plan - Administer school status
- Prepared Medicine & Emergency report
kit Updated emergency Phone
numbers
MOOE/LGU
- Provide base line data on - Construct of TSLs (temporary - Conduct debriefing on
Response affected learning Space) possible victims on disaster
- Replication of Schools as
School of Peace

Recovery and - Restore affected area -Conduct a total clean-up Drive on affected - Conduct school raid damage LGU
Rehabilitation areas assessment
Monitoring and SCHOOL DRRM SCHOOL DRRM SCHOOL DRRM
Evaluation BDRRM C BDRRM C BDRRM C
MDRRMC MDRRMC MDRRMC
Climate Change - Pruning of Trees within MOOE/LGU/PTA
school premises Tree Growing - Proper Waste Disposal
Prepared by: Noted by:

VENIS R. PUBLICANO ALICIA C. UGUIS

School DRMM Coordinator School Principal III


HAZARD VULNERABILITY CAPACITY ASSESSMENT
HAZARD VULNERABILITIES CAPACITY RISK ASSESSMENT
Students Organizational Policies High
Teachers
Fire Employees
Stakeholders
Building and Classroom
School Properties
Students Organizational Policies High
Teachers
Earthquake Employees
Stakeholders
Building and Classroom
School Properties
Students Organizational Policies High
Teachers
Typhoon Employees
Stakeholders
Building and Classroom
School Properties
Sample Early Warning Plan for Flood
Level Criteria Interpretation Warning Signal Required
Action
0 No Flood Classes Ongoing None Conduct classroom
instruction as
usual.
1 Floodwaters Alert 5 rapid whistle Move all school
clogging and blows records, lesson
overflowing school plans and materials
drainage ditches to an elevated
shelf.
2 Floodwaters Prepare to 10 rapid whistle Shut down all man
beginning to enter evacuate blows power sources.
classrooms Move pupils to an
elevated place.
3 Floodwaters Campus 15 rapid whistle Evacuate to a safe
reaching one foot completely blows location outside
high from the floor evacuated the campus. Ring
priority items
along.
SCHOOL DISASTER RISK REDUCTION MANAGEMENT ACTION PLAN
KRA OBJECTIVES TIMELINE ACTIVITIES BUDGET SOURCE OF
FUND
A. Human To conduct lectures Semester (a Lecture with the
Resource on Updates from week before the SDRRM Team Php 3,000.00 MOOE
Management NDRRMC scheduled Fire (1 500.00 per
and Earthquake Semester)
Drill)
B. Learning 1. To identify March 2022 Survey school Php 500.00 MOOE
Environment school hazards premises to list
2. To create a down school
school DRRM March 2022-07- hazards
Team 10 -O- -O-
comprising of
teaching and By Semester Creation of
non-teaching SDRRMC Team
staff.
3. To conduct a Php 4,000.00 MOOE
Fire and Fire and Earthquake
Earthquake Drill Drill

Prepared by: Noted by:


VENIS R. PUBLICANO ALICIA C. UGUIS EMD
School DRRM Coordinator Teacher-in-Charge