AL SERH AL KABEER CONSTRUCTION

HEALTH, SAFETY AND ENVIRONMENT PLAN

CRADLE INSPECTION CHECKLIST

Site Number Site location


Cradle Number Project Manager
Project Engineer Safety Officer
S.
3rd Party Documentation and requirements Yes No N/A Comments
No
1 Valid 3rd Party Safety Inspection Certificate available
2 Operator 3rd party competency certificate available
Cradle is ready for 3rd party safety inspection and
3
certification after modifications, alteration, erection etc.
S.
Electrical Control Box Yes No N/A Comments
No
1 Are all cords and plugs in good condition (No exposed
conductors or broken insulation)
2 Are all control buttons or electrical switches, receptacles,
cracked, broken, or have exposed contacts?
3 Is the control box cover is closed well?
4 Is the emergency stop switch is working in good
conditions?
5 Are AC conductor is working in good condition?
6 Is the indicator light of the power supply is working in
good condition?
7 Is the universal switch for up and down movements is
working in good condition?
8 Is the single phase power supply is plug properly (If
needed, if no need unplugged the socket and place
inside of the control box properly)
S.
Hoist Motor Yes No N/A Comments
No
1 Are the bolt & safety pin is connected or tightened
properly with the end stirrups?
2 Is there any oil leak from the gear?
3 Are the electro-magnetic break is slipping manually?
4 Is there any abnormal sound while operating?
5 Is there a heating from electric motor after operating?

6 Are the hoists motor body is in good condition? (No sign


of broken parts or cracks)
7 Are the limit switches fixed and working properly?
S.
Safety Breaks Yes No N/A Comments
No
1 Will the lock rope prevent the cradles from tilting or
falling?
2 Are the safety wire twisted instead properly?
3 Are the safety wire tighten by wire weights or loose, and
ASAK/HSE/1107/CRC/01 REV. DATE: 10 July, 2019
AL SERH AL KABEER CONSTRUCTION
HEALTH, SAFETY AND ENVIRONMENT PLAN

if it is straight or twisted?
4 Are the bolts tightening properly on the bracket of end-
stirrups?
S.
Deck Platforms Yes No N/A Comments
No
1 Are the side frames connected and fixed properly on the
platform base?
2 Are the end-stirrups fixed properly on the both end of the
platform?
3 Are the bolts complete & tightening Properly?
4 Are the platforms clear from bent or distorted, crack in
welding and damage?
S.
Fixing Brackets and Hanging Device Yes No N/A Comments
No
1 Is the support is suitable to the required length?
2 Are all bolts complete & tightening properly?
3 Timbales and “D” Shackles are in good fixed condition?
4 Are counter weights or anchored bolts fixed and
tightened?
5 Is the tie rope is tighten and fixed well?
6 Are the counterweights have enough quantity and placed
steadily?
S.
Steel Wire Rope Yes No N/A Comments
No
1 Are the wire ropes connected properly on the supports?
2 Are the wire ropes suitable for the required height?
3 Are the wire ropes are in good condition? (Not twisted or
excessive worn, rusted, distorted and damage?
4 Are the wire ropes has sharpened end?
5 Are the wire rope clamp has thimble and pressed by
ferrule?

i. Appropriate required PPE and life line has been provided to


the labors working in cradles?
ii. Cradles erection is completed and approved to generate
MR for third party safety inspection?

Project Manager Sign Safety Officer Sign and


& Date Date
Project Engineer Sign Site Foreman Sign and
& Date Date

ASAK/HSE/1107/CRC/01 REV. DATE: 10 July, 2019