Professional Documents
Culture Documents
Application
District of Squamish Presentation at Public
Information Meeting
Nov 24, 2014
Outline
Background
Hazard Policies
Next Steps
Background
The Cheekye Fan
Resource
Hazard Policies
Hazard and Risk
Hazard: Debris flow volume and frequency
Risk: Probability X Consequences
Almost
certain
Probability
Very
Unlikely
Consequences
Incidental Catastrophic
History
Expert Panel
Recommendations
We Are Here
Environ- Operations
Inputs Mitigation Design
mental and
Strategy Maintenance Concept
Review
District/
Peer Review
Provincial Council
Review
OCP/Rezoning
Application Intro to Staff Public
Review Council Review Meeting
Next Steps
Next Steps
• Continued review
• Begin to update policies
• Council update
• Further public comment
THANK YOU
http://www.squamish.ca/showcase
21
Current Elements at Risk
22
First Nation Cheekeye
IRs Subdivision
Hwy. 99
BC Rail Possible
Development
Area
Airport BC Hydro
Transmission
Line
Schools
First Nation
IR
Elements at Risk
Brakendale
23
24
The July 2010 rock avalanche and debris
flow at Capricorn Creek, Mount Meager
25
SQUAMISH
Lower fan
Upper fan Cat Lake
26
SQUAMISH
Squamish River
BRACKENDALE
Approx. fan boundary
Highschool
27
The Steps
Hazard Recognition
Frequency-Magnitude Analysis
Hazard Intensity Mapping
Consequence Determination
Risk Calculations
Risk Evaluation
Risk Reduction
Not completed
Development
28
Glacial History
29 SOURCE: FRIELE
Fan Evolution
30
Dendrochronolgy
• ~60 wedges,
cores, discs
sampled along
channel
• Cross-sections
reconstituted
along confined
reaches
• Discharge
back-calculated
31
Test Trenching Program
Objectives:
• Determine size of Garbage Dump debris flow
• Update frequency-magnitude analysis
32
Test Trenching Program
Fluvial
5m Gravels Garbage Dump event
1m
Fluvial
Gravels
Cheakamus R.
BC Hydro
Sub
Hwy. 99
Airport
Worst Estimate
3
2500 yr 2.4 Mm 3
period, debris flows
Austria
500 yr 1.4 Mm 3
1,000,000
3
200 yr = 0.8 Mm
500,000
3
100 yr = 0.6 Mm
3
50 yr = 0.4 Mm
3
20 yr = 0.2 Mm
100,000
10 100 1,000 10,000 100,000
35 Return Period (years)
What does 5.5 Mm3 debris mean?
5.5 million cubic metres is roughly twice the volume of BC Place Stadium
36
Rock Avalanche Modeling
37
BC Hydro
Sub
Brackendale
Brackendale
100-year return period event, unmitigated
39
BC Hydro
Sub
Brackendale
Sedimentation basin
• In Safety Risk one differentiates between Individual Risk Safety and Group
Risk Safety
• Individual Risk: Unacceptable for current development
• Group Risk: Unacceptable for current development
• Highway Users: Unacceptable Group Risk
given risk tolerance standards practiced, for example, by the District of North
Vancouver.
43
Safety Target Risk Criteria
Squamish River
Downstream view
46
Main Barrier
(preliminary design concept)
Upstream view
47
Main Barrier
(preliminary design concept)
Upstream view
48
I.R. 11
Principal retention
basin
BC Hydro Sedimentation basin
Sub
Brackendale
49
Vision of Post-Mitigation Design
Site Investigation
51
Questions?
52
1.00E-01
1.00E-03
1.00E-04 Post-Barrier
(Future Buildings)
1.00E-06
ALARP
1.00E-07
ACCEPTABLE
1.00E-08
1 10 100 1000 10000
N (Number of Fatalities)
Risk Reduction Benefits
~ 6900 yrs BP
Debris flow deposits
~ 11,600 yrs BP
Stump Lake
A’
V = 15-30 m/s
Cheekeye River
55 A
Proposed Cheekeye
Development
PUBLIC INFORMATION MEETING
Monday November 24th
Request
Amendments to the District of Squamish’s official community plan and zoning
bylaw to permit a new single family neighbourhood, educational/community
uses, parks, greenways and trails.
Background
1970’s-80’s
241 manufactured home strata plan was registered on the property (still exists) and
site servicing completed (existing paved road layout remains)
Project halted due to the threat of a debris flow originating from the Cheekeye River
Crown retained ownership of the lands
1993
Identified in the Thurber/Golder Cheekye River Terrain Hazard and Land Use Study.
Subsequently incorporated into the Squamish Official Community Plan.
2008
Umbrella Agreement between Squamish Nation and District of Squamish recognizes
further development potential of these lands
2011
Accord between the Squamish Nation and the District of Squamish recognizing
future development potential of the lands
Development Proposal
Complement Brackendale’s existing community by
introducing affordable housing options close to existing
schools, services while also extending the park and
greenway system, trails and constructing the needed
hazard debris barrier.
Single Family Lots
Single Family # Approx. Size Approx. % of
Lots (sq. ft) Frontage (ft) Lots
Small Lots 79 2850 30 11
Public Information Meeting is the initial step in the development approval process