1 General
1.1 Introduction
The purpose of this document is to help (new and inexperienced) process engineers to get a good idea on how TEG
Flash drum design. TEG flash drum is downstream of TEG high pressure contactor, before rich TEG flow go towards
Flash drum, high pressure will reduced to 5-6 barg & then it will feed to Flash drum.
In Glycol contactor, TEG will absorb few amount of Light & Heavy hydrocarbons at high pressure, while reducing the
pressure before entering the Flash drum inlet, Three phases will appear at Low pressure 5-6 bar, Light hydrocarbon will
go from Top of flash drum, Heavy hydrocarbon condensate & Rich TEG separate by Gravity difference via Bucket weir.
In TEG flash drum, below internals normally recommended on the basis of oil content,
Normally residence time criteria will be 25-30 min for TEG flash drum.
The referenced project documents are listed as below for Flash drum design calculations,
Document title
Scope of supply & client specifications. (SMS)
Performance criteria
2. TEG Flash drum sizing steps:
The TEG flash drum sizing to be carry with Frames P-PC-CAL-HS (Horizontal separator).
Enter the Gas, Oil & TEG properties from simulation as input to Vessel sizing sheet. Check provided client
PDS has given nozzle sizes for Flash drum & its adequacy as per momentum criteria. If not provided then
fixed the nozzle sizes as per recommended momentum.
Enter the Wave motion criteria if given by client for FPSO. If vessel is going to be installed on platform or
onshore then select no option for wave motion.
Assume the Diameter & Length by considering L/D ratio between 2.5 to 5 (as per GPSA) for initial estimate of
levels of condensate & TEG.
See below example, we kept the levels as per 100 min between LLIL-LIL, LIL-HIL & HIL-HHIL.
TEG weir is selected as 820 mm which is less than Bucket left weir 875 mm, so TEG withdraw from TEG
compartment at downstream compartment of flash drum & Interface level to be maintain upstream of bucket
left weir.
Residence time will be estimated as 65 min as highlighted in yellow color which is between the bottom of vessel to
normal interface level (NIL) which is upstream of bucket left weir.
The design exercise carried out for south ghawar, always refer while design Flash drum: