Professional Documents
Culture Documents
Item Unit
Description Unit QTY Total Price
No Price
1.0 Architectural
1.5 Perform radiation leakage test from authorized third party for PET CT area L.S 1.0 0
Perform radiation leakage test from authorized third party for other medical
1.6 L.S 1.0 0
equimpment rooms
2.0 Electrical
Supply & install of panel boards 3 PH, 5 W, 400 V, 60 Hz.,wall mounted fully
wired. the panels should contain of main breaker, branch circuit breakers of
required rating including distribution bars, internal wires installation,
distribution boxes, earth terminal and measuring devices of the current and
voltage as per existing on the site
Distribution Panel Board, 100A Main CB For XRAY as per SIEMENS specifications
2.1 The panel will include a separate breaker located next to it for maintenance L.S 1 0
control ncluding all necessary accessories to finish the work for all equipment
Distribution Panel Board, 40A Main CB For Mamo as per SIEMENS specifications
2.3 The panel will include a separate breaker located next to it for maintenance L.S 1 0
controlncluding all necessary accessories to finish the work for all equipment
Install of panel boards 3 PH, 5 W, 400 V, 60 Hz.,wall mounted fully wired. the
panels should contain of main breaker, branch circuit breakers of required
rating including distribution bars, internal wires installation, distribution boxes,
earth terminal and measuring devices of the current and voltage as per existing
on the site
Supply & install of flexible power cable (5x35mm2) from main distribution board
2.5 to equipment UPS for MRI Scan Room Lm 20 0
Supply & install of flexible power cable (5x50mm2) from main distribution board
2.6 Lm 10 0
to equipment generator for MRI Room
Supply and install hot dip galvanized steel cable tray for MRI room including
2.8 fittings, elbows, connectors, C-channel and all necessary accessories to finish Lm 7 0
the work
Supply and install hot dip galvanized steel cable Ladder for MRI equibment room
2.9 including fittings, elbows, connectors, C-channel and all necessary accessories Lm 10 0
to finish the work
Supply and installation transformar 4kva bender IPP including all necessary
2.1 L.S 1.0 0
accessories to finish the work for all equipment
3.0 Mechanical
Supply and installation of the non-magnetic quench pipe from the magnet room
to the outside of the building inclining fittings & end-terminals using
3.1 LM 15.0 0
recommended dimensions provided in calculation charts. including all necessary
accessories to finish the work for all equipment and final cover.
Supply and installation of chilled water line (supply and return copper pipes with
3.2 Lm 38.0 0
complete fittings and insulation as required).
Supply and installation of chilled water line 12L (supply and return copper pipes
3.3 with complete fittings and insulation as required) including all necessary Lm 15.0 0
accessories to finish the work for all equipment