SITE VISIT REPORT

DATE :- 2/2/2024
VISITED BY :- ANOOP.V.G.
NOTES

1. SITE LEVELLED WITH RED SOIL AND LEVEL WILL CHECK TOMORROW ALONG WITH
CHIRANJITH SIR
2. One tree was there in the center of the plot and it will cut ( Told by Bipas Ji )
3. One EB line was going through the center of the plot and its shifting work also
under progress.

4. Water connection have there at site.


5. Outer boundary wall work are also on progress.
6. One labour shed was there at site we can use it also. Will confirm it by Bipas Ji.