Professional Documents
Culture Documents
BLLT J2 Vol 2 Specification 131212 Rev14
BLLT J2 Vol 2 Specification 131212 Rev14
Volume 2
Specification
2. MATERIALS
2.1 QUALITY
Unless otherwise specifically provided in this Contract, all items incorporated in the
completed work, such as equipment, materials and other articles are to be new and the most
suitable grade for the purpose intended.
9. NOTICE OF OPERATIONS
The Contractor shall give 48 hours notice in writing to the Engineer of his intention to start
any stage, element or part of the Permanent Works. In particular the Contractor’s attention is
directed at sub-clause 7.3 of the Conditions of Contract concerning work to be covered up,
put out of sight or packaged for storage or transport. Such notices shall be supplemental to
Contract – Volume 2 – Specification 1-12 01100
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
any information provided in the Contractor’s programme issued in accordance with
sub-clause 8.3 of the Conditions of Contract. When issuing such notices the Contractor
should note the requirements to be included in his QA scheme.
In addition to the programme submitted in accordance with sub-clause 8.3 of the Conditions
of Contract, the Contractor shall provide the Engineer with notice of his intended detailed
programme of works on a weekly basis. This notice shall be issued on the last day of the
week preceding the week to which the notice applies. The notice shall include steps to be
taken to recover any delays in the work detailed in the notice for the previous week. Where
such delays accumulate to the point where there is a significant effect on the Contractor’s
overall programme submitted in accordance with sub-clause 8.3 of the Conditions of
Contract, the Engineer may consider action under sub-clause 8.6 of the Conditions of
Contract concerning the rate of progress.
13. DRAWINGS
The Contractor shall carry out the Works in accordance with the intent expressed in the
drawings and specifications. The Contractor shall promptly notify the Engineer of any error
or omission in the drawings or specifications or any discrepancy between the drawings and
specifications. The Engineer will provide a clarification concerning any error, omission or
discrepancy so notified bearing in mind the requirements of sub-clause 1.5 of the Conditions
of Contract.
Dimensions shall not be scaled from the drawings. The Contractor shall advise the Engineer
when dimensions are not given or cannot be computed. In such case the Engineer shall
determine appropriate dimensions in consultation with the Contractor.
Contract – Volume 2 – Specification 1-19 01100
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
Drawings prepared by the Contractor and submitted to the Engineer for his approval shall be
of A3 size and conform to the format of the contract drawings. They shall be produced using
appropriate software compatible with the software used to produce the Contract Drawings.
Drawings prepared by the Contractor are assumed to include the “As built” drawings.
Drawings shall be submitted in the numbers required by the Conditions of Contract. In
addition a soft copy of all drawings submitted shall also be provided.
Working drawings shall be submitted with design calculations and supporting data in
sufficient detail to permit a structural review of the proposed design of temporary works.
When concrete is involved, such data shall include the sequence and rate of placement.
Payment shall be made as a lump sum covering all costs of survey and preparation of
working and as-built drawings. Survey includes but is not limited to topographic and
geological survey required for preparation of working drawings, and for the design and
construction of access, temporary, detour and diversion roads, and the reinstatement of local
roads which have been used for construction. As built records shall be prepared in
accordance with the formats and requirements of 22TCN 273-01 Specification for Road
Design.
Pay Item Description Unit
01100-11 Survey and Design of Construction Drawings lump sum
Payment will be made in instalments as follows: 30% of payment after completing survey
and receiving approval of the Engineer, 60% of payment in the period of implementation (6
months), 10% of payment after approval of the as-built drawings.
20. GRAVES
Any graves found during earthwork operations shall be reported to the Engineer for
appropriate Instructions.
1. DESCRIPTION
This specification section describes the work required for the relocation of utilities affected
by construction of the Permanent Works to be carried out by the Contractor. The relocation
work is to be carried out under the responsibility of the Contractor, to be reimbursed against
provisional sums. The Employer has arranged the relocation of electrical power, telephone
and communication lines, and gas pipelines. The Contractor shall be responsible for the
relocation of fresh water, sewerage / waste water, and any remaining utilities of whatever
nature which have not already been relocated by the Employer’s operations.
2. THE DRAWINGS
The Drawings show the location of above ground and below ground utilities as surveyed
during the detailed design. Where agreement has already been reached with the relevant
utility company regarding the design of a relocation, removal, or re-routing of a utility, the
details of the agreed relocation are shown on the Drawings. In some locations, provision has
been made on the Drawings for ducts to permit passage of utilities beneath the expressway,
however indication of these ducts on the drawings does not indicate approval by the relevant
utility for such a relocation.
4. BASIS OF PAYMENT
Payment shall be made under a provisional sum. This sum shall reimburse the costs of the
work of design and implementation of each utility relocation, which will likely be
undertaken in a number of separate contracts, and may be divided into components for
design and for implementation.
Pay Item Description Unit
01200-01 Relocation of Utilities provisional sum
1. GENERAL
1.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied to the works
covered by this Specification Section:
QCVN 09-08 Water quality - Ground water quality standard
QCVN 26-10 Acoustics - Noise in public and residential areas -
Maximum permitted noise level.
QCVN 27-12 Vibration and shock - Vibration causing by vehicles -
permitted maximum level in public and residential
areas
QCVN 03-08 Soil quality standards - Maximum allowable
concentration of heavy metal in soil.
QCVN 02-09/BYT Domestic supply water − Quality requirements
QCVN 05-09 Air quality - Ambient air quality standards
QCVN 06-09 Air quality - Maximum allowable concentration of
hazardous substances in ambient air
QCVN 40-11 Industrial waste water - Discharge standards
In addition , when working with hazardous chemicals, the Contractor shall comply with
manufacturers recommendations regarding transport, storage, handling, and disposal of each
product.
1.2 COMPLIANCE
The Contractor shall strictly comply with Vietnamese Laws and Standards regarding the
environment on all works associated with the Contract.
The Contractor shall comply with the donor’s safeguard policies by undertaking all
environmental and social requirements set out in the Contract Provisions.
A draft Environmental Management Plan forms part of the Contract. The Contractor shall
take ownership of this document and develop it by identifying particular environmental risks
arising from the Works, the mitigation measures to be applied, and monitoring to be carried
out. The plan shall be submitted to the Engineer for his consent not later than 30 days after
the date of commencement or 7 days prior to the start of significant work, including
temporary works, on site, whichever is sooner.
1.3 ORGANIZATION
The Contractor shall appoint an Environmental Officer with environmental/social
qualifications who shall remain in place for the duration of the Contract Period and shall be
responsible for ensuring implementation of all of the Contractor’s responsibilities regarding
environmental issues. The Environmental Supervision Officer shall report directly to the
Contractor’s project manager
2. ENVIRONMENTAL MONITORING
The environmental monitoring program shall commence promptly after commencement in
order to obtain baseline data prior to the start of construction activities, and shall continue
throughout the duration of the construction works. The environmental monitoring shall also
Contract – Volume 2 – Specification 1-27 01300
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
make reference to baseline data to be provided by the Engineer which was obtained during
the design phase of the project.
The Contractor shall undertake a condition survey for all areas and locations likely to be
affected by the construction of the Works, including but not limited to the Site and areas
adjacent to the site, access routes to and from the site and the Contractor’s off site working
areas, offices, accommodation, workshops and quarries. The condition survey shall be
carried out before the commencement of construction work.
The Contractor shall put in place monitoring and reporting procedures to measure the effect
of the construction work on the areas included in the condition survey and to ensure early
detection of conditions that necessitate particular mitigation measures. Monitoring will be
conducted by properly equipped and qualified personnel. The Contractor shall provide
specific descriptions and technical details of monitoring measures, including the parameters
to be measured, methods to be used, sampling locations, frequency of measurements,
detection limits (where appropriate), and definitions of thresholds that will signal the need
for corrective actions or mitigating measures. The Contractor shall also ensure that sound
engineering practices are followed and encourage on–the–job behaviour conducive to
environmental protection.
All monitoring shall be co-ordinated with provincial and local officials, community groups,
government departments, etc. concerned with environmental issues and shall include
obtaining the necessary clearances from the regulatory authorities. The Contractor shall:
report monitoring results directly to the Construction Supervision Consultant.
furnish information on the progress and results of any mitigation measures.
undertake additional monitoring when requested.
immediately report any potential environmental issues that could hinder the progress
of the Works.
3. MITIGATION MEASURES
The Contractor shall be responsible for implementing and managing mitigation measures
during the construction of the Works. Refer to the draft Environmental Management Plan.
4. REPORT
The Contractor shall prepare a monthly Environmental and Social report which shall include
at least the following items. The report shall be included in the Contractor’s monthly report
required by the Conditions of Contract.
The current work schedule for environmental management.
Monitoring results for routine checks and any spot checks.
Action taken to resolve unsatisfactory results from monitoring.
Details of any grievances or complaints from residents or other members of the
public including action taken to resolve the issue.
However if any incident or monitoring results indicate serious adverse impact or damage to
the environment, such incident or results shall be reported immediately to the Engineer and
the Employer.
No separate payment will be made for this work. The Contractor’s costs will be assumed to
be distributed as necessary across all rates in the Bills of Quantities.
1. DESCRIPTION
The clearing and grubbing shall comprise the removal and disposal of material within the
construction limits including but not limited to all vegetation and debris, and the removal of
top soil, except where objects or areas are designated to remain in place or are to be removed
in accordance with other Specifications sections.
This work shall include the protection and preservation of all areas and objects designated to
remain.
2. CONSTRUCTION REQUIREMENTS
2.1 GENERAL
The limits of the work and objects to be preserved are defined on the drawings. Where
required the Engineer will confirm the limits of work and the designation of objects to
remain. All disposal shall be to an approved waste disposal site provided by the Contractor.
2.2 PROTECTION OF AREAS DESIGNATED REMAIN
The Contractor will be responsible for the protection and routine maintenance of existing
shrubs, trees and grassed areas designated to remain and for all objects designated to remain.
On completion of the Works these areas and objects will be returned to the Employer in the
same condition they were in prior to the start of the Works. Any damage due directly or
indirectly to the Contractor's operations shall be made good at his own expense.
2.3 CLEARING AND GRUBBING AND TREE REMOVAL
All surface objects, trees, fallen timber, rotten wood, stumps, roots, snags, brush, other
vegetation, rubbish, and other protruding obstructions, with the exception of objects
designated to remain, shall be cleared and/or grubbed.
In areas of embankment all stumps and roots shall be removed to a depth at least 50 cm
below the original ground surface and at least 80 cm below the bottom of the lowest
pavement layer.
In areas of cut, all stumps and roots shall be removed to a depth of not less than 50 cm below
the finished subgrade level.
All pits, channels and ditches shall be cleaned of unsuitable material.
All voids left after clearing and grubbing shall be filled with suitable compacted material.
2.4 TOPSOIL STRIPPING
Refer to Specification 03100 Common excavation
2.5 DISPOSAL OF CLEARED MATERIAL
Saleable timber shall be neatly stored in an approved accessible location as directed and
shall be trimmed and stacked in accordance with the requirements of the appropriate
Government agency.
The Contractor shall not use un-saleable timber or saleable timber.
All timber, brush, stumps, roots, logs, and other refuse from the clearing and grubbing
operation and topsoil not required for re-use shall be disposed to an approved waste site
provided by the Contractor. The site shall be outside of the right of way
1. DESCRIPTION
Demolition and Removal of Existing Structures consists of the removal, wholly or in part,
and satisfactory disposal of structures and obstructions including but not limited to blocks of
masonry of an individual size greater than 1 cubic meter, of all buildings, hedges, fences,
structures, pavements regardless of its nature (asphalt, concrete, etc.), curbs, wells or
underground water tanks, soakaways or latrines, and any other obstructions which are not
designated or permitted to remain. Demolition includes the salvaging of designated
materials and proper backfilling (in accordance with specification requirements) of any and
all trenches, holes and pits resulting from demolition and removal work.
Right of way acquisition may not be complete in all areas at the start-up of the construction
period and the Contractor shall schedule the work associated with this Specification section
accordingly.
Obstructions or other items that are designated for removal and disposal elsewhere in the
Contract Documents shall be dealt with in accordance with stipulated requirements.
2. SUBMITTALS
The Contractor shall prepare and submit to the Engineer, for respective approval prior to
start the work, the following:
Shop Drawings in accordance with the provisions of Specification section 04100,
including detailed information regarding to the drainage structures, curbs, pavement,
etc. to be demolished and removed in accordance with the provisions and indications
of this Specification section.
Complete detail of the method, equipment and schedule to perform the demolition
and removal work pertinent to this item.
Inventory of the materials that could be recovered from demolition work, stockpiling
of suitable material from stripping that the Contractor pretends to use further in other
items.
Detailed drawing showing the area for disposal of material from this item, or for
stockpiling of recovered material when it is planned to use further for other items.
3. CONSTRUCTION REQUIREMENTS
3.1 GENERAL
Demolition and Removal of Existing Structures by the Contractor shall be provided, within
and adjacent to roadways, and on the right-of-ways, as shown on the Drawings or as directed
by the Engineer.
The Engineer may instruct that materials recovered from demolition work shall remain the
property of the Employer unless specifically provided otherwise in the Contract Documents.
All designated saleable material shall be removed, without unnecessary damage, in sections
or pieces that may be readily transported, and shall be stored by the Contractor at specified
places on the project as directed by the Engineer.
Basements or cavities left by structure removal shall be back-filled with acceptable material
to the level of the surrounding ground and, if within the prism of construction, shall be
compacted in accordance with Specification section 03400 “Embankment Construction”.
There will be no separate payment for backfilling and compaction the resulting cavities.
1. DESCRIPTION
Common Excavation consists of all excavation within the limits of the site after the
completion of clearing and grubbing and the removal of topsoil, with the exception of
structural excavation which is specified in Section 03200 “Structural Excavation”.
Common Excavation shall include the removal, handling and proper use or disposal of all
excavated materials regardless of their nature or existing condition, and the shaping and
preparation of the exposed surface of the excavation in accordance with these specifications
to the lines, levels, grades, dimensions and cross-sections shown on the Drawings subject to
approval by the Engineer.
The Contractor shall prepare and submit his method statement for the earthworks which
shall include an earthworks balance schedule or plan. The earthworks balance schedule or
plan shall include details of the use of suitable material, in particular the locations and
volumes for excavation and placement of materials. The plan shall be updated on a weekly
basis, in accordance with the progress of the works, and submitted with the Contractor’s
weekly work schedule until completion of the roadway excavation. Where appropriate the
Contractor shall use comparatively better materials in the upper levels of embankment
construction.
2. CLASSIFICATION OF EXCAVATION
Common Excavation shall be in four categories: a) Topsoil b) Soil Excavation, c) Rock
Excavation, and d) Excavation of Unsuitable Materials.
2.1 TOP SOIL
Topsoil shall be removed from the areas and to the depths indicated on the drawings and
subject to confirmation by the Engineer.
Topsoil removal shall be confined to the removal of soil which is sufficiently fertile to
encourage and sustain the growth of vegetation
Where “waterlogged” or “swampy” soils exist in place of topsoil in areas and depths
indicated on the drawings or otherwise determined by the Engineer such soils shall be
excavated and classified and treated as “unsuitable materials”.
2.2 SOIL EXCAVATION
All excavation except for Soft Rock, Hard Rock and Boulders regardless of the nature of the
soil or its existing condition.
This soil class includes all the types of soil excavation described in the Vietnamese
Standards for soil classification (Decision No.24/2005/QD-BXD), except for soft rock, and
boulders.
2.3 ROCK EXCAVATION
Common excavation classified as “Rock” shall be composed of the following materials:
Hard Rock: excavation that, in the opinion of the Engineer, is not practical without
the use of pneumatic tools or drilling and blasting operations. Hard rock shall not
include material which, in the opinion of the Engineer, can be loosened or excavated
with standard equipment. This soil class includes all the types of rock described in
the Vietnamese Standards for soil classification (Decision No.24/2005/QD-BXD).
3. CONSTRUCTION REQUIREMENTS
3.1 PREPARATION WORK
Prior to excavation all clearing and grubbing shall have been completed in accordance with
the appropriate specification to the satisfaction of the Engineer.
1. DESCRIPTION
1.1 GENERAL
Structural Excavation consists of the excavation for foundations to bridges, culverts,
sub-drains and other structures, excluding specific details which may be contained in other
specifications, as shown on the Drawings subject to the approval of the Engineer.
All material from structural excavation, so far as it considered suitable and subject to the
approval of the Engineer, shall be utilized for backfill or embankment construction, or shall
be removed from the Site if surplus to requirements.
All materials surplus to requirements shall be classified “Excavation of unsuitable material”
in accordance with the requirements of item 2(c) of specification 03100 “Common
Excavation” subject to the approval of the Engineer.
The Contractor shall prepare and submit his method statement for the earthworks which
shall include an earthworks balance schedule or plan. The earthworks balance schedule or
plan shall include details of all structural excavation, in particular the locations and volumes
for both excavation and placement of materials. The plan shall be updated on a weekly basis,
in accordance with the progress of the works, and submitted with the Contractor’s weekly
work schedule until completion of the roadway excavation. Where appropriate the
Contractor shall use comparatively better materials in the upper levels of embankment
construction.
Structural Excavation shall include all necessary materials and equipment for keeping the
excavation free of surface run-off and groundwater.
This Specification includes supplying, placing and compacting granular back-fill adjacent to
structures in the areas indicated on the drawings subject to the approval of the Engineer.
This Specification includes the supply and placing of approved foundation fill material to
replace unsuitable material encountered below the foundation level of structures.
Structural excavation shall include all necessary diversion of live streams, bailing, pumping,
draining, sheeting, bracing, necessary construction of cribs and cofferdams, and supply of
materials required and subsequent removal of cribs, cofferdams and remaining unsuitable
material and placing of all necessary backfill.
1.2 STRUCTURAL EXCAVATION CLASSIFICATION
Structural Excavation shall be classified as either
a) structural excavation in rivers (applicable only for the named piers listed in the Bill of
Quantities), and
b) structural excavation (for all other cases of structural excavation)
All classes of structural excavation shall be deemed to include all required equipment,
labour, incidentals, temporary materials and works necessary for and associated with the
excavation, including but not necessarily limited to:
providing pumps, cofferdams (regardless of their type or material), braced sheet
piling or any other methods proposed by the Contractor and subject to the approval
of the Engineer;
the Contractor’s observance of all rules and regulations of competent authorities
regarding the interference or maintenance of flow in the relevant canals, water
courses, channels or pipes;
2. CONSTRUCTION REQUIREMENTS
2.1 GROUNDWATER
Whenever groundwater is encountered or the excavation is taking place adjacent to
free-surface water, the Contractor shall take such measures as necessary to ensure that the
excavation and footing are kept free of water and in a stable condition. All such measures
shall be included in his method statement and subject to the approval of the Engineer.
2.2 COFFERDAMS
Suitable and practically watertight cofferdams shall be used wherever water-bearing strata
are encountered above the elevation of the bottom of the excavation.
The Contractor shall submit drawings showing his proposed method of cofferdam
construction together with calculations based on 10% water level (H10), an allowance for
local and general scour of the river bed and the minimum ship impact requirements to the
Engineer for his approval. At the Contractor’s expense, all designs shall be checked by an
Independent Professional Engineer who shall certify the adequacy and safety of the
proposed details.
Cofferdams or cribs for foundation construction shall extend well below the bottom of the
foundations and shall be well braced and as nearly water-tight as practicable.
The interior dimensions of cofferdams shall be such as to give sufficient clearance for the
construction of formwork and the inspection of their exteriors, and to permit pumping
outside the forms.
Cofferdams or cribs that have tilted or moved laterally during the process of sinking shall be
righted or enlarged so as to provide the necessary clearance.
When conditions are encountered which render it impractical to dewater the foundation
before placing the footing the construction of a concrete foundation seal of such dimensions
as shown on approved shop Drawings may be permitted all subject to the approval of the
Engineer. The foundation shall then be dewatered and the footing placed. When weighted
cribs are employed and the weight is utilized to partially overcome the hydrostatic pressure
acting against the bottom of the foundation seal, special anchorages such as dowels or keys
shall be provided to transfer the entire weight of the crib to the foundation seal. Where a
foundation seal is placed under water, the cofferdam shall be vented or ported at low water
level. Pumping for dewatering shall not commence until the seal has set sufficiently to
withstand the hydrostatic pressure.
Cofferdams shall be constructed so as to protect green concrete against damage from sudden
rises in the water level and to prevent damage to the foundation by erosion. No timber or
bracing shall be left in cofferdams or cribs without the approval of the Engineer.
Any pumping that may be permitted from the interior of any foundation enclosure shall be
done in such a manner as to preclude the possibility of any portion of the concrete materials
Contract – Volume 2 – Specification 3-6 03200
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
being removed. Any pumping required during concrete placing or for a period of at least 24
hours afterwards shall use a suitable pump located outside the concrete forms.
Unless otherwise provided, the Contractor shall remove cofferdams or cribs, together with
all associated sheets and braces, after the completion of the substructure. Removal shall be
effected in such a manner as not to disturb or damage any finished work.
The Contractor may propose a suitable alternative method to coffer dam construction. The
details of any such alternative shall be complete with all necessary drawings and calculations
certified by an independent engineer and shall be subject to the approval of the Engineer. All
costs associated with making such a proposal, whether it is accepted or rejected by the
Engineer, shall be borne by the Contractor.
2.3 PRESERVATION OF CHANNEL
Unless otherwise permitted, no excavation shall be made outside caissons, cribs, cofferdams
or sheet piles, and the natural stream bed adjacent to the structure shall not be disturbed
without the approval of the Engineer. If any excavation or dredging is made at the site of the
structure before caissons, cribs, or cofferdams are sunk in place, the Contractor shall,
backfill all such excavations to the original ground surface or stream bed with material
satisfactory to the Engineer after the foundation base has been completed. Material
deposited within the stream area from the foundation or other excavation or from the filling
of cofferdams shall be removed and the stream area kept free from obstruction.
2.4 EXCAVATION
Prior to starting excavation operations in any area, the Contractor shall :
ensure that all necessary Site Clearance and Demolition in that area has been
approved by the Engineer.
ensure that all cross-sectional elevations and measurements have been taken of the
undisturbed ground and submitted to the Engineer for his approval.
take steps on his own initiative to regulate the natural drainage of the surface water in
the area to prevent flooding of excavations.
Excavations for structures or structural footings shall be of sufficient size to permit the
placing of foundations of the full width and length shown indicated on the drawings. The
sides of excavations shall be adequately supported at all times. The elevations of the bottoms
of footings as shown on the Drawings shall be considered as approximate only and the
Engineer may order, in writing, such changes in dimensions or elevations of footings as may
be deemed necessary to secure a satisfactory foundation.
Boulders, logs, and any other unsuitable materials encountered in excavation shall not be
used for back-filling purposes and shall be disposed of.
After each excavation has been completed the Contractor shall submit the foundation to the
Engineer for his approval. No foundation or bedding material shall be placed until such
approval has been given.
All rock or other hard material encountered in foundations shall be cleaned of all loose
material and cut to a firm surface, either level, stepped or serrated, and all seams or crevices
shall be cleaned out and grouted, all subject to the approval of the Engineer.
Where the foundation is to rest on material other than rock, excavation to the final level shall
not be carried out until just before the foundation is to be placed. Where the foundation
material is soft or otherwise unsuitable, the Contractor shall remove the unsuitable material
and replace it with granular backfill to the approval of the Engineer. The granular fill shall be
placed and properly compacted in layers not exceeding 15cm up to the foundation elevation.
However where the foundation material has been rendered unsuitable for reasons
attributable to the Contractor he may replace the unsuitable material with granular material
Contract – Volume 2 – Specification 3-7 03200
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
as described above or suspend works on the foundation until such time as the material
becomes suitable. Either solution shall be at the Contractor’s expense without revision to the
contract period.
Where foundation piles are used the excavation of pile driving pits shall be completed before
pile driving begins and any blinding stone required shall be placed after piles have been
driven. Where it is not possible to drive piles after excavation, piles shall be driven from the
natural ground level subject to the approval of the Engineer. In such case surplus pile lengths
will not be measured for payment.
After both the excavation and the driving have been completed, all loose and displaced
material shall be removed to leave a smooth, solid bed on which to place the foundation.
Where a box culvert is to be located in embankment, the excavation shall be performed after
the embankment has been constructed to the proposed sub-grade level and properly
compacted subject to the approval of the Engineer.
2.5 BACKFILLING
On completion of the structure, excavated areas shall be back-filled with approved material
to the level of the finished ground surface.
Where terms “K95” or “K98” are used on the Drawings and the compaction standard is not
indicated, this shall be understood to refer to compaction to AASHTO T180 e.g. K95 refers
to compaction to 95% of the maximum dry density determined according to AASHTO
T180.
2.5.1 SOIL BACKFILLING
Back-fill shall be placed in layers not exceeding 15 cm and compacted to 95% of the
maximum dry density determined according to AASHTO T180 (alternatively the Contractor
may choose to compact to 98% of mdd to AASHTO T99).
For soil backfill to pile caps for viaduct, back-fill may be placed in layers not exceeding
25cm thickness, and shall be compacted to 90% of the maximum dry density determined
according to AASHTO T180 (alternatively the Contractor may choose to compact to 95% of
mdd to AASHTO T99).
2.5.2 GRANULAR BACKFILLING
Granular backfilling required for specific structures or other locations detailed in the
drawings or as required by the Engineer shall be placed in layers not exceeding 15 cm and
compacted to 95% of the maximum dry density determined according to AASHTO T180
(alternatively the Contractor may choose to compact to 98% of mdd to AASHTO T99).
The material shall be well-graded crushed or uncrushed gravel, stone, rock-fill or natural
sand or a well-mixed combination of any of these. Grading requirements for Granular
Backfill shall be as follows:
Maximum size 5 cm
Passing 4.75 mm sieve 25% to 90%
Passing 0.075 mm sieve 0% to 10%
Liquid limit TCVN4197-95 30% max.
2.6 BLINDING STONE
Blinding stone for use in foundations for structures as shown on the Drawings or as required
by the Engineer shall be provided as detailed below.
Blinding stone shall be approved cobble-stone or crushed rock of the maximum size
compatible with the thickness of the layer shown on the drawings subject to the approval of
the Engineer. Large stones shall have a minimum dimension of 7 cm. Large stones shall be
Contract – Volume 2 – Specification 3-8 03200
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
closely packed by hand to the dimensions shown on the drawings and then rammed by
mechanical rammer. Smaller stones with a minimum dimension of 3 cm shall then be placed
between the larger stones and the surface brought to the finished level shown on the
drawings or as required by the Engineer. The final surface shall be thoroughly compacted to
the satisfaction of the Engineer using a mechanical rammer or vibrating roller.
The Contractor may propose an alternative to the above process based on the use of graded,
crushed stone of a maximum size less than 5 cm. The proposal shall include the maximum
thickness of one layer, the proposed compaction methods and the suitability of the proposal
for use in a restricted working area all subject to the approval of the Engineer.
1. DESCRIPTION
This specification describes requirements and procedures for the provision of materials from
borrow pits for the following categories of work.
Borrow material for capping layers.
Borrow material for sub-grade.
Borrow material for road and counterweight embankment.
Borrow material for cohesive slope.
The Contractor shall use suitable material from borrow pits for constructing embankment,
backfill, sub-grade, shoulders, cohesive slope and other parts of the work as shown on the
drawings subject to the approval of the Engineer. Borrow material shall be provided from
sources which have been approved by the Engineer and only in those locations shown on the
drawings subject to the approval of the Engineer.
The Contractor shall prepare and submit his method statement for the earthworks which
shall include an earthworks balance schedule or plan. The earthworks balance schedule or
plan shall include details of the use of suitable material, in particular the locations and
volumes from which borrow material is to be provided. The plan shall be updated on a
weekly basis, in accordance with the progress of the works, and submitted with the
Contractor’s weekly work schedule until completion of the roadway excavation.
2. MATERIAL REQUIREMENTS
2.1 SUBMITTALS FOR MATERIALS
2.1.1 SHOP AND WORKING DRAWINGS AND SCHEDULES
The Contractor shall submit his method statement for the earthworks including complete
sets of drawings and schedules for the use of borrow materials to the Engineer for his
approval.
The Contractor’s method statement shall include a schedule of borrow materials he intends
to provide together with all necessary supporting information concerning the source. The
schedule of materials shall be properly incorporated into the Contractor’s earthworks
balance schedule or plan for the earthworks operation.
The Contractor shall be responsible for ensuring that all borrow pits have all necessary
licenses and approvals from the appropriate local and regulatory authorities for the operation
of the pit and the extraction of the borrow materials. All such licenses and approvals shall be
submitted with the supporting information. The supporting information concerning the
sources of borrow material shall also include, but not be limited to, the following:
The location of the material sources and the routes and procedures for delivery of
material to the Site.
The approximate anticipated volume of material to be supplied from each source
together with the dimensions and depths of borrow pit excavations.
The intended location for the use in the permanent works of material from each
borrow pit.
Proposed procedures for the testing and acceptance of materials from each source.
3. CONSTRUCTION REQUIREMENTS
All suitable materials provided from borrow sources shall be used and placed to the grades,
cross sections and other requirements indicated on the drawings subject to the approval of
the Engineer.
During the operation of the borrow pit the Contractor shall ensure the pit remains in a safe
properly drained condition. The drainage shall be kept functioning and in as good condition
as practicable and the sides and ends of borrow pits shall be maintained at the slopes
included in the Contractor’s submission.
Where a borrow pit includes materials of distinctive types, excavation shall be carried out in
a manner that ensures each type remains separate and that no mixing occurs. Excavation
shall also be carried out in such a way that excavated surfaces are free draining and that the
as dug moisture content of borrow material remains unaffected.
During excavation of the borrow pit temporary drainage shall be provided and maintained in
order to prevent excessive surface run off and the erosion and possible sliding of materials
onto adjacent properties or public roads. Temporary drainage shall be directed into the
existing local drainage system subject to suitable measures being taken to prevent silting or
flooding from such existing drainage.
All hauling trucks and other construction plant leaving the borrow area or the area of
placement on the site shall have wheels, wheel arches and other dirty sections washed before
entering onto public roads.
Trucks used for hauling borrow materials shall not be overloaded.
Trucks used for hauling borrow materials shall be covered with canvas to prevent materials
from being blown or falling off the truck.
1. DESCRIPTION
1.1 EMBANKMENT CONSTRUCTION
This specification describes requirements and procedures for the construction of the capping
layer, sub-grade, roadway embankment, and embankments and berms required for
surcharge.
1.2 SETTING OUT THE WORK, STAKING AND SURVEYING
This specification also describes the requirements and procedures for surveying, setting out
and staking.
Surveying, setting out and staking shall be performed by technically qualified survey crews
using survey instruments and supporting equipment fit for purpose, capable of achieving the
specified survey tolerances and the construction tolerances included in this and other
specifications.
The Contractor shall furnish the necessary equipment and material to survey, calculate, and
record data for the control of work and acceptable tools, supplies, and stakes and other
materials necessary to set out the works of the type and quality normally used in highway
survey work and suitable for the intended use.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied to the works
covered by this Specification Section.
TCVN 4447-12 Earth works – Construction and Acceptance
22TCN 346-06 Testing procedure on definition of compaction of road
foundation and embankment by sand cone method
22TCN 333-06 Procedures of soil and macadam compaction in
laboratory
22TCN 332-06 Testing procedures on definition of CBR value for soil
and macadam in laboratory
22TCN211-2006 Flexible Pavement
TCVN4195 - 4202-12 Construction soil
TCVN 9436-12 Highway embankment – construction and acceptance
AASHTO M145 Classification of Soils and Soil-Aggregate Mixtures for
Highway Construction Purposes
AASHTO T11 Materials Finer Than 75-µm (No. 200) Sieve in
Mineral Aggregates by Washing
AASHTO T27 Sieve Analysis of Fine and Coarse Aggregates
AASHTO T87 Dry Preparation of Disturbed Soil and Soil Aggregate
Samples for Test
3. CONSTRUCTION REQUIREMENTS
3.1 GENERAL
Prior to the construction of roadway embankments, all necessary clearing and grubbing,
removal of topsoil and surface drainage in the area shall have been performed in compliance
with the relevant specifications and to the satisfaction of the Engineer.
Embankment construction shall consist of:
constructing roadway embankments, including preparation of the area upon which
they are to be placed;
placing and compaction of approved material within roadway areas where unsuitable
material has been removed;
placing and compaction of embankment material in holes, pits, and other
depressions within the roadway area; and
construction of embankments and berms required for the surcharging associated
with soft ground treatment.
constructing the temporary drainage system which maintains the site as dry as
possible discharging by the natural gradient during construction.
Materials for embankments shall contain no muck, peat, sod, roots or other deleterious
matter. Rocks, broken concrete or other solid, bulky materials shall not be placed in
embankment areas where piling is to be placed or driven.
Where indicated on the drawings, the slopes of the embankment shall be constructed using
cohesive material.
3.2 SETTING OUT THE WORK, STAKING AND SURVEYING
3.2.1 APPROVALS
No survey work shall start until the Contractor’s method statement has been approved by the
Engineer in accordance with clause 2.2.2 of this specification. No work shall start on site
until the setting out of the work has been approved by the Engineer.
3.2.2 NOTICE
The Contractor shall give the Engineer 48 hours notice of intention to start any survey or
setting out work on site.
3.2.3 SURVEY POINTS
The Contractor shall check and correct as necessary to the satisfaction of the Engineer all
primary survey points provided in the Contract Documents. The Contractor shall establish
his own network of secondary survey points sufficient to control the lines, grades, levels and
position of the Works.
3.2.4 CROSS SECTION MARKERS AND CONTROL POINTS
The Contractor shall establish cross section markers at 20 m. intervals, or other intervals that
may be required by the Engineer, set out perpendicular to the centre line of the road. The
Contractor shall establish control points at the site of each structure, foundation or culvert.
Control points shall be positioned or of a sufficient number that there is a clear sight line to
all significant parts of the structure, foundation or culvert. Cross section markers and control
points shall be within the site boundary but outside areas directly affected by the Works.
Contract – Volume 2 – Specification 3-18 03400
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
Additional reference markers shall be established so that cross section markers and control
points can be re-established should they be damaged or destroyed during construction work.
All cross section markers, control points and reference markers shall be subject to the
approval of the Engineer.
3.2.5 CROSS SECTIONS
The Contractor shall take cross sections at 20 m intervals or such intervals as may be
required by the Engineer. The Contractor shall prepare and submit cross section drawings to
the Engineer for his approval. Drawings shall be provided in both hard and soft copies.
3.2.6 OTHER MARKERS, STAKES OR CONTROL POINTS.
The Contractor shall establish all other markers, stakes or control points necessary for the
correct setting out of the Works. Such items may be permanent for the duration of the works
or temporary for the particular work item. Such items shall include centre line markers,
stakes, profile boards and other markers required to set out and control each stage of the
construction of the road and drainage works and such markers or control points that may be
necessary to set out and control each stage of the construction of a particular structure,
foundation or culvert.
3.2.7 CONSTRUCTION TOLERANCES
The Contractor shall ensure that there are sufficient survey points, control points, cross
section markers, stakes and other markers to ensure that all Works are constructed within the
construction tolerances given in this and other sections of the specification.
3.2.8 REGISTER
The Contractor shall maintain a register of all survey points, control points, cross section
markers, stakes and other markers. The register shall record all checks carried out and all
events that may affect the items registered.
3.2.9 SURVEYING TOLERANCES
Staking Phase Horizontal Vertical
Control points ± 5 mm ± 3 mm
Centreline points (a) - (PoC), (PoT), (PoT), and (PoC) ± 5 mm ± 3 mm
including references thereto
Other center line points ± 10 mm ± 10 mm
Cross-section points, slope stakes, and slope stake references ± 20 mm ± 10 mm
(b)
Culverts, ditches, and minor drainage structures ± 10 mm ± 10 mm
Retaining walls ± 10 mm ± 10 mm
Railroad crossing structures ± 3 mm ± 3 mm
Bridge substructure ± 5 mm ± 5 mm
Bridge superstructure ± 3 mm ± 3 mm
Clearing and grubbing limits ± 200 mm -
Roadway subgrade finish stakes ± 10 mm ± 10 mm
Roadway finish grade stakes ± 3 mm ± 3 mm
Note:
(a) Center line points are point of curve (PoC), point of tangent (PoT) and point on curve (PoC).
(b) Take the cross sections normal to the centreline within ±1 degree (0.02 rad).
3.2.10 PERMANENT MONUMENTS AND MARKERS
The Contractor shall protect all existing land survey monuments and property markers
within or on the site boundary.
Liquid
3 limit,Plastic limit ASTM-D4318 1 / 5,000m3 1 / 2,000m3 1 / 2,000m3 1 / 2,000m3
and Plastic index
Internal Friction
4 ASTM-D3080 1/ 20,000m3 1/ 20,000m3 1/ 20,000m3 1/ 20,000m3
angle
AASHTO-T99
Moisture-Density
8 / AASHTO 1/ 5,000m3 1/ 2,000m3 1/ 2,000m3 1/ 5,000m3
Relation
T180
0.3%
edge
Cross-fall or camber
Discharge Capacity (m3/yr) at 1 day, ASTM D Greater than 500 Applied pressure
200kPa and hydraulic gradient i of 1. 4716-87 of 350kPa
The Contractor may propose alternative PVD material which has equivalent or better
characteristics with sufficient track record in a similar field.
1.3 CONSTRUCTION REQUIREMENTS
PVDs shall be installed by use of a mandrel. The installation method and equipment shall
satisfy the following criteria:
No frictional resistance between inside of the mandrel and the drain.
Minimal size of the mandrel compared with the drain to reduce the zone of smear.
An anchor shall prevent fines from entering into the mandrel during installation and
shall anchor the PVD efficiently during withdrawal of the mandrel.
The installation rig shall have proper means to assure that the mandrel is kept
vertical during the drain installation period.
The Contractor shall submit details of the sequence and method of installation. The
submittal shall as a minimum contain the following detailed information:
Size, type, weight, maximum pushing force, and configuration of the installation rig.
Dimensions and length of mandrel.
Dimension and details of anchor.
Description of proposed installation procedures.
Proposed methods for overcoming obstructions.
Proposed methods of splicing drains.
Approval by the Engineer shall not relieve the Contractor of his responsibility to install
PVDs in accordance with the plans and specifications. If, at any time, the Engineer considers
that the method of installation does not produce satisfactory drains, then the Contractor shall
alter his method and/or equipment as necessary to comply with the Contract.
The mandrel shall protect the prefabricated drain materials from tear, cuts and abrasion
during installation and shall be withdrawn after the installation of the drain. The drain shall
be provided with an anchor plate at the bottom, to anchor the drain at the required depth at
the time of mandrel removal. Dimension of anchor shall be (85x140)mm or as otherwise
approved by the Engineer.
3. SURCHARGE FILL
3.1 DESCRIPTION
The surcharge fill shall be placed gradually at the rate indicated on the Drawings. The
assumed duration of surcharging is shown on the Drawings. The Contractor shall prepare
their schedule based on this surcharge duration. The Engineer shall be responsible for
determining when consolidation requirements have been met, and will notify the Contractor
when the requirement has been met, and the surcharge may be removed. If the Engineer
determines that a longer surcharge duration than that shown on the drawings is required, and
the surcharging is a critical path activity, this may be the basis for a claim for an extension of
time.
Filling and waiting periods. The suggested filling period for improving the stability and the
estimated waiting period for the consolidation work are described on the Drawings. The rate
of filling has to be controlled to minimise any instability problem.
The side slope shall not be greater than 1 (V): 2 (H).
The Engineer’s criterion for acceptance of completion of consolidation is based on the
degree of settlement (defined as the ratio of the current settlement to the projected final
settlement estimated from Asaoka’s method) as stated on the Drawings. If not otherwise
stated on the Drawings, residual settlement (post-construction settlement) for acceptance in
15 years shall be less than:
10 cm near bridge abutment
20 cm near culvert
30 cm in fill area other than bridge abutment and culvert zone
4. INSTRUMENTATION
4.1 DESCRIPTION
The Contractor shall throughout the works supply, install and monitor various types of
instruments for monitoring settlement, horizontal deformation, pore water pressure and
ground water table in the fill and natural ground.
The instruments shall be placed as shown on the Drawings or as directed by the Engineer,
and shall be maintained by the Contractor during the construction period and up to the end of
the Contract.
The Contractor shall take utmost care to ensure that none of the instrumentation is damaged
or disturbed in any way, and kept in good working order as long as they are required. For all
those instruments, which project through and above the fill suitable barriers at a distance of
minimum 0.75 m around each individual instrument or group of instruments shall be
installed and warning signs shall be erected. Heavy construction equipment shall not be used
within 1.0 m distance of projecting instruments. Any instrumentation damaged or disturbed
by construction operations shall be replaced or repaired at the Contractor’s expense.
All instruments shall be labelled with their reference number at the location where the
readings or measurements are taken. The labelling shall be according to a system and
method to be agreed with the Engineer.
The installation of all instrumentation shall be as specified on the Drawings. All instruments
shall comply with the requirements in section 2.7 of this Specification for each particular
type.
Boreholes for instruments shall be drilled by a suitable method to provide a clean and stable
hole of the required diameter to the correct depth. Boreholes shall be cased as required.
Boreholes shall be drilled using clean water. Drilling mud or polymer additives shall only be
used with the approval of the Engineer.
During drilling, care shall be taken to ensure that a minimum of material is lost from outside
the casing. Surging of casing shall not be allowed, and flushing of drilling water up the
outside of the casing shall be kept to a minimum.
For any borehole or part thereof that requires grouting during the installation of instruments,
the grout shall be poured into the boreholes using a tremie pipe.
4.2 INSTRUMENT TYPES AND REQUIREMENTS
4.2.1 SETTLEMENT PLATE
Settlement plates shall consist of a base plate 500×500 mm connected to steel extension rods
and protection pipes as shown on the Drawings. Length of each extension rod shall be
exactly 1.0 m.
Piezometer/ Vacuum Gauge Excess piezometric pressure / vacuum versus time for
each piezometer / gauge and versus depth for latest set
of readings (plots).
4.4 MEASUREMENT AND PAYMENT
4.4.1 MEASUREMENT
The quantities of instruments to be paid for shall be the actual number of each type of
instrument supplied, installed and commission.
Monitoring and reporting shall not be measured separately for payment.
4.4.2 PAYMENT
This work measured as provided above shall be paid for at the Contract unit rate for each
particular instrument supplied and installed, which rates and payment shall be full
compensation for furnishing and placing all materials, including all labour, equipment, tools
and incidentals necessary to complete the work. This includes the maintenance of all
instruments during the contract period, and monitoring and reporting of all results.
Pay Items:
Pay Item Description Unit
03500-03 Settlement Plate each
5. GEOTEXTILES
5.1 DESCRIPTION
This item shall consist of supplying and installing approved geotextile material as a part of
the road earthworks.
5.2 MATERIALS
Unless otherwise shown on the Drawings or instructed by the Engineer, the materials to be
used shall be as follows:
(a) Separation Geotextile: Non-woven
Non-woven geo-textile sheets shall be UV-stabilized, made of 100% polypropylene yarns
which may be mechanically or thermally bonded from continuous filament.
The tensile strength shall be more than 12 kN/ m to ASTM D 4595 in both directions at the
breaking elongation of not more than 40%. Puncture resistance to ASTM D 4833 shall be at
least 350N.
(a) High Strength Geotextile: Woven
The geotextile sheets shall be UV-stabilized and made of polypropylene yarns.
The ultimate tensile strength to ASTM D 4595 shall be more than 200 kN/ m in both
directions at breaking elongation of not more than 20%.
5.3 CONSTRUCTION
Geotextile sheets shall be installed at the specified locations in the arrangement as shown on
the Drawings. Prior to laying of the geo-textile all preceding works shall have been
completed and the ground surface shall be cleared of all sharp materials that could puncture
or tear the fabric. The ground surface shall be flat and level and any unevenness shall not
exceed 100 mm and the inclination shall be less than 5%.
Laps in the geotextile material sheets shall be made by either overlapping each sheet by a
minimum of 300 mm or stitching using a 30 mm double overlocking seam. If vertical soil
drains are to be installed after the laying of the geo-textile, the Engineer may require the use
of stitched joints to minimize the disturbance to the geotextile during the subsequent work
on the soil drains joint direction.
5.4 MEASUREMENT AND PAYMENT
5.4.1 METHOD OF MEASUREMENT
Geotextile sheet shall be measured by square metres for the net area of geotextile shown on
the Drawings or instructed by the Engineer. No measurement will be made for joints or for
surplus material laid outside the requirements of the Engineer.
5.4.2 BASIS OF PAYMENT
The quantities, determined as provided above, shall be paid for at the Contract unit price for
the pay items as listed below. The prices and payment shall be full compensation for all costs
including furnishing, hauling, placing joining and for all materials, labour, tools, equipment
and incidentals necessary to complete the works as described in this Clause.
Pay Item Description Unit
03500-09 Separation Geotextile (12kN/m non-woven) m2
T = M x {(Nd/Vd) + (Nu/Vu)}
Where:
T: number of blade rotation (n/m)
∑M: total number of mixing blades
Nd: rotation speed of the blades during penetration (rpm)
Vd: mixing blade penetration velocity (m/min)
Nu: rotational speed of the blades during withdrawal (rpm)
Vu: mixing blade withdrawal velocity (m/min)
The number of blade rotation as defined shall not be less than 350. The mixing blade
shall be designed to ensure homogeneous mixture of the soil and the stabilizing
agent. Tolerance of deviation of the mixing blade diameter shall not be more than
5%.
The control of the mixing process shall be computerized to assure the best quality of
mixture. After the placement of each of the column, one printout result shall be
generated from the computer showing the column number, time, depth of the column,
content of cement slurry used in the mixing process and the number of rotation. The
process must be recorded and submitted for all the columns to be installed for the
checking of the integrity and quality of the end products.
6.3.3 DRY MIXING
The Contractor shall not use dry mixing type for this project.
6.3.4 FIELD TESTS
The test column in the field shall be tested as follows:
Unconfined compressive strength on cored samples from one column
Verification of column dimensions and uniformity of column by pulling-out an
entire test column (preliminary test column of 10m length) from the ground. The
column shall be inspected for size, shape and uniformity of the stabilization along
the entire length of the column. The Contractor shall submit the pulling method to
the Engineer for approval before operation.
Pile static load test on test column (preliminary test column of 20m length) using
kentledge, tension pile or ground anchorage system
Prior to the start of construction the Contractor shall submit to the Engineer for approval the
test procedures for determining unconfined compressive strengths and the diameter and
depth of columns. The cost of these tests shall be borne by the Contractor.
The unconfined compressive strengths of column at various levels including diameter and
depth of column must be determined. However, in case that the test for unconfined
compressive strength cannot be satisfactorily attained, pile load test may be required to
determine the capacity of column. The pile load test of column shall be conducted at 28 days
of curing time.
Any pile which fails the above tests shall be replaced by one or more piles by the Contractor
or as directed by the Engineer and an additional test shall be conducted for the replaced piles.
Contract – Volume 2 – Specification 3-42 03500
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
If, in the opinion of the Engineer, it is impractical or inadvisable to install substitute piles in
place of a failed pile, the Contractor shall submit proposals to rectify the defect. The
proposal is subject to the acceptance of the Engineer.
In addition, the Contractor shall at his expense carry out two more additional working load
tests. The piles for these tests shall be selected by the Engineer.
6.3.5 UNCONFINED COMPRESSION TEST
Unconfined compressive strength of column by the cored sample on site shall be made at
interval not more than 1 m with age of 28 days old having a value of no less than Qd. If the
requirements are not met, judgment shall be made by the Engineer.
6.3.6 VERIFICATION OF COLUMN DIMENSIONS
Verification of column dimensions shall be made as specified herein.
Column dimensions can be checked by exposing a top 2m portion of completed column
improved by deep mixing method. The column shall be inspected for size, shape and
uniformity of the stabilization. The Contractor shall submit the proposed method on the
exposure of column top portion for inspection to the Engineer for approval before operation.
6.3.7 PILE LOAD TEST ON COLUMN
Pile load test shall be performed in according to ASTM D1143-81 on a soil cement column
of age over 28 days applying 1.5 times of design working load shown in the drawing. The
pile top shall be properly prepared for the test. The method of testing shall be approved by
the engineer prior to execution of the work. Pile load test shall be performed with capacity of
not less than 31 ton for 0.70 m diameter cement columns when the maximum settlement at
pile head shall be less than 10% of column diameter.
6.3.8 FREQUENCY OF TESTING
The number of columns to be tested shall be as follows:
Take wet-grab samples of the soil / binder mixture at the rate of at least one sample
for each 600m3 of soil / binder production with a minimum of one sample per day.
Each sample shall be of sufficient size to produce four (4) specimens for testing. The
specimens shall be cylindrical with a nominal diameter of 75mm and length 150mm.
Test one cylinder for unconfined compressive strength at 7 days, one at 14 days, and
one at 28 days. Reserve the fourth cylinder and test at 56 days if the 28 day result
does not meet the required strength. Determine unit weight on each cylinder as part
of the unconfined compressive strength testing process.
Frequency of coring for determination of unconfined compressive strength shall be
performed at a ratio of two (2) % of total number of columns improved by deep
mixing method.
Frequency of verification of column size and uniformity of column by pulling-out
test shall be conducted one preliminary test column (non-working column prior to
the commencement of working columns).
Frequency of verification of column size at a top 2m portion shall be conducted at a
ration of one (1) % of total number of columns improved by deep mixing method. If
the Contractor changes a part of his construction method, additional test shall be
conducted.
Frequency of pile static load test shall be conducted for one preliminary test column
(non-working column prior to the commencement of working columns) and one
(1) % of total number of working columns improved by deep mixing method. If the
Contractor changes a part of his construction method, additional preliminary test
column shall be conducted and pile load test shall follow. If there is more than one
Contract – Volume 2 – Specification 3-43 03500
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
machine carrying out column construction, one preliminary test column shall be
carried out for each machine.
Preliminary test columns shall be constructed to the same diameter and length, and
with the same equipment as to be used for the working piles.
6.3.9 ALLOWABLE DEVIATION
The Contractor shall construct each column to the depth, spacing, vertical alignment,
location and with unconfined compressive strength as specified in the Drawing and these
Specifications. In such case that any column constructed with smaller diameter or specified
strength, the Engineer shall have the right to order construction of additional column or
reconstruct the defective column at the expense of the Contractor.
Allowable deviation shall be as follows:
Vertical Deviation of column shall not be more than 1%.
Position of each column and spacing between columns shall not be deviated more
than 100 mm in any direction.
Diameter of column shall not be less than 95% of specified diameter.
Unconfined compressive strength shall not be less than Qd kPa.
6.4 MEASUREMENT AND PAYMENT
6.4.1 MEASUREMENT
Cement columns shall be measured in linear meters from the tip of the column to the cut-off
level. The length of cement columns shall be in accordance with the dimensions shown on
the Drawings and accepted by the Engineer. Cut-off lengths will not be measured for
payment.
6.4.2 PAYMENT
The work measured as provided above will be paid for at the Contract unit price per linear
meter of cement columns. The payment shall be full compensation for furnishing and
placing all materials, including labour, tools, equipment, all kinds of tests as specified herein
or in the Drawings and incidentals necessary for the satisfactory completion of the work.
Pay Item Description Unit
03500-11 Soil Cement Columns (Working Pile)including Field Testing m
03500-12 Soil Cement Columns (Preliminary Test Column; Non-working
Pile) including Field Testing m
1. DESCRIPTION
Section 04100 works shall consist of constructing new reinforced concrete pipe culverts on
bedding and bearings as shown on the drawings and subject to the approval of the Engineer.
Inlet and outlet structures, headwalls, as well as associated erosion and scour protection
works are included in other specification sections.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be applied to Works covered by this
Specification.
22TCN 159-86 Concrete steel pipe culvert construction
TCXDVN 372-2006 Reinforced concrete drainage pipes
TCVN 9113:2012 Drainage reinforced concrete culvert pipe
ASTM C990 Joints for Concrete Pipe, Manholes, and Precast Box
Sections Using Preformed Flexible Joint Sealants
2.2 BEDDING
Granular material for bedding shall be in accordance with clause 4.2, table 4 of TCVN 7570
– 2006 subject to the approval of the Engineer.
Lean concrete for bedding shall be class C10 bedding or blinding concrete in accordance
with the requirements of Specification Section 07100 “Concrete and Concrete Structures”.
2.3 CONCRETE
Concrete used for all structural work described in this Specification Section shall be of the
classes indicated on the drawings and shall conform to the requirements specified in
Specification Section 07100 “Concrete and Concrete Structures”.
2.4 REINFORCING STEEL FOR CONCRETE
All reinforcing steel used in the works shall conform to the requirements specified in
Specification Section 07500 “Reinforcing Steel”.
2.5 REINFORCED CONCRETE CULVERT PIPES
Reinforced concrete pipes shall be of pre-cast reinforced concrete of concrete class C30 and
shall conform to specification section 07100 “Concrete and Concrete Structures”. Pipes
shall be cast with push fit or male / female joints and reinforcement in all pipes shall consist
of spiral steel cages with longitudinal bars all as indicated on the drawings unless otherwise
approved by the Engineer.
The Engineer shall periodically inspect the pre-cast concrete manufacturing plants to ensure
compliance with the approved method statements for manufacturing. The Contractor will
supply material samples for laboratory testing to ensure Quality compliance, and will make
the necessary arrangements to facilitate the inspections by the Engineer. Such inspections
shall include the inspection of reinforced pre-cast concrete items. All pre-cast items shall be
marked with a unique reference and no item shall be delivered to the construction site
without approval from the Engineer.
3. CONSTRUCTION REQUIREMENTS
3.1 SHOP DRAWINGS AND SCHEDULE
3.1.1 SHOP DRAWINGS
The Contractor shall prepare shop drawings and method statements showing his proposed
construction details for culverts indicated on the Drawings or as directed by the Engineer.
Shop drawings and method statements shall be submitted to the Engineer for his approval
prior to the start of the any construction work on the culverts, including the start of any
pre-casting works.
3.1.2 WORK SCHEDULING
Pre-casting and construction of the culverts shall not begin until the Engineer has approved
the Contractor’s shop drawings and method statements. The Contractor shall allow
sufficient time in his programme for the submission and approval of his shop drawings and
method statements and for any revision and re-submission of such documents that may be
required to incorporate the comments of the Engineer.
All necessary temporary drainage work or diversions of existing drainage shall be in place
and operating before construction of the culverts begins.
Sub-grade preparation or work on the pavement structure, either in the roadway or the
shoulder areas, shall not begin until the culverts, headwalls, and other minor structures
below sub-grade level are complete along that particular section of roadway.
3.2 INSTALLATION OF PIPE
3.2.1 SITE PREPARATION
The Contractor shall carry out any excavation and preparation of trenches for pipe culverts
that may be required in accordance with the provisions of Specification Section 03200
“Structural Excavation”. The Contractor shall be responsible for all dewatering and
temporary support works of the trenches and all other necessary temporary works that may
be required during construction.
The Contractor shall place supports and/or bedding material in accordance with the
Drawings requirements or as may required by the Engineer all in accordance with applicable
Specification Sections.
1. DESCRIPTION
This specification section describes the work required for the construction of drainage
ditches. The Contractor shall construct roadside ditches using mortared stonework,
reinforced concrete, or pre-cast concrete as shown in the Drawings, unless otherwise
directed by the Engineer.
2. MATERIAL REQUIREMENTS
2.1 MATERIALS
The Contractor shall submit to the Engineer for his approval details and samples of materials
he intends to use for the construction of ditches included in this specification section.
2.2 BEDDING
Granular material for bedding shall be in accordance with clause 4.2, table 4 of TCVN 7570
– 2006 subject to the approval of the Engineer.
Lean concrete for bedding shall be class C10 bedding or blinding concrete in accordance
with the requirements of Specification Section 07100 “Concrete and Concrete Structures”.
2.3 MORTARED STONE
Mortared stone lining shall conform to the requirements specified in Specification Section
04400 “Mortared Stonework”.
2.4 CONCRETE
Pre-cast and cast in situ concrete used for all structural work described in this Specification
Section shall be of the classes indicated on the drawings and shall conform to the
requirements specified in Specification Section 07100 “Concrete and Concrete Structures”.
2.5 REINFORCING STEEL FOR CONCRETE
All reinforcing steel used in the works shall conform to the requirements specified in
Specification Section 07500 “Reinforcing Steel”.
2.6 SUBMITTALS
2.6.1 SHOP AND WORKING DRAWINGS AND SCHEDULES
The Contractor shall prepare shop drawings, method statements and a schedule of ditches
showing his proposed construction details for the ditches indicated on the Drawings or as
directed by the Engineer. Shop drawing, method statements and schedules shall be
submitted to the Engineer for his approval prior to the start of the any construction work on
the ditches. The Contractor’s schedules shall include the location and profile of each length
of ditch. The profiles shall be co-ordinated with associated drainage features including
manholes, catch pits and culverts.
2.6.2 PROGRAMMING
Construction of ditches shall not begin until the Engineer has approved the Contractor’s
shop drawings, method statements and schedules. The Contractor shall allow sufficient time
in his programme for the submission and approval of his shop drawings and method
statements and for any revision and re-submission of such documents that may be required
to incorporate the comments of the Engineer.
1. DESCRIPTION
This Specification Section describes the requirements for the construction of Catch Basins,
Manholes, Inlets and Outlets to culverts and ditches.
2. MATERIAL REQUIREMENTS
2.1 MATERIALS
The Contractor shall submit to the Engineer for his approval details and samples of materials
he intends to use for the construction of Catch Basins, Manholes, Inlets and Outlets to
culverts and ditches included in this specification section.
2.2 BEDDING
Fine sand fill/bedding shall be black sand (river sand). The sand shall be a fine sand
complying with the requirements of Table 1 of TCVN 7570-06 with a fineness modulus of
0.7 to 2.0. Organic and other impurities shall be in accordance with table 2 of TCVN
7570-06 as follows:
Clay and balled impurities shall be less than or equal to 0.5%
Muds and dirt shall be less than or equal to 10%
It will not be necessary to determine the alkali reactivity or the chloride content of the sand
for this use.
Sand shall be sampled and tested in accordance with TCVN 7572:2006 (Aggregates for
concrete and mortar – Test methods)
Granular material for bedding shall be in accordance with clause 4.2, table 4 of TCVN 7570
– 2006 subject to the approval of the Engineer.
Lean concrete for bedding shall be class C10 bedding or blinding concrete in accordance
with the requirements of Specification Section 07100 “Concrete and Concrete Structures”.
2.3 CONCRETE
Pre-cast and cast in situ concrete used for all structural work described in this Specification
Section shall be of the classes indicated on the drawings and shall conform to the
requirements specified in Specification Section 07100 “Concrete and Concrete Structures”.
2.4 REINFORCING STEEL FOR CONCRETE
All reinforcing steel used in the works shall conform to the requirements specified in
Specification Section 07500 “Reinforcing Steel”.
2.5 MORTARED STONE
Mortared stonework shall conform to the requirements specified in Specification Section
04400 “Mortared Stonework”.
2.6 STEELWORK
Steelwork items shall comply with the requirements of 22TCN288:2002 and shall be
galvanised in accordance with AASHTO M232.
2.7 BRICKWORK
Brickwork shall conform to the requirements specified in Specification Section 04600
“Brick Masonry”.
3. CONSTRUCTION REQUIREMENTS
3.1 SHOP DRAWINGS AND SCHEDULE
3.1.1 SHOP DRAWINGS
The Contractor shall prepare shop drawings and method statements showing his proposed
construction details for the Catch Basins, Manholes, Inlets and Outlets to culverts and
ditches indicated on the Drawings or as directed by the Engineer. Shop drawings and method
statements shall be submitted to the Engineer for his approval prior to the start of the any
construction work, including the start of any pre-casting works.
3.1.2 WORK SCHEDULING
Construction of the Catch Basins, Manholes, Inlets and Outlets to culverts and ditches shall
not begin until the Engineer has approved the Contractor’s shop drawings and method
statements. The Contractor shall allow sufficient time in his programme for the submission
and approval of his shop drawings and method statements and for any revision and
re-submission of such documents that may be required to incorporate the comments of the
Engineer.
3.1.3 SITE PREPARATION
The Contractor shall carry out any excavation that may be required for Catch Basins,
Manholes, Inlets and Outlets in accordance with the provisions of Specification Section
03200 “Structural Excavation”. The Contractor shall be responsible for all dewatering and
temporary support works for the excavations and all other necessary temporary works that
may be required during construction.
3.2 DELIVERY, STORAGE AND HANDLING
Materials delivered to site shall be inspected for damage, unloaded, and stored with
minimum handling. Any damaged materials shall be rejected and replaced at the
Contractor’s expense.
3.3 CONNECTIONS
Culvert pipes or ditch sections shall be placed or cast and properly bedded before being cast
into or built into catch basins, manholes or inlet and outlet structures.
3.4 MANHOLE COVERS, CATCH BASINS AND FRAMES
Covers to manholes and catch basins shall be fabricated, supplied and installed complete
with steel frames and lifting points as indicated on the drawings.
1. DESCRIPTION
This Specification Section describes the requirements for the construction of mortared
stonework. This work consists of the lining of roadside drains and construction of inlets,
outlets and headwalls to culverts.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
Mortared stonework shall comply with the requirements of standard TCVN ISO 4085:1985
2.2 STONE
Stones shall consist of field stone or quarry stone. They shall be sound, tough, durable, dense,
resistant to the action of air and water, and suitable in all respects for the purpose intended.
Mortared Stonework: Unless otherwise indicated on the Drawings or directed by the
Engineer, the stone shall meet the gradation requirements shown in Table 1.
The Quality and dimensions of the stones shall be approved by the Engineer prior to their use.
Stones shall be as nearly rectangular in shape as practicable.
Table 1 Gradation Requirement for Stones (*)
Approximate Given Size Equivalent Cubic Total Size Smaller
Weight Volume Dimension than Given Size
(kg) (cu.m.) (mm) (%)
45 0.018 250 100
27 0.011 225 80
11 0.005 165 50
2 0.0003 75 10*
* Material shall consist of spills and rock fragments graded to provide a stable compact mass.
2.3 CEMENT MORTAR
Cement Mortar shall be in accordance with the provisions of Specification Section 08100
“Cement Mortar” or as directed by the Engineer.
2.4 SUBMITTALS
The Contractor shall submit to the Engineer for his approval two representative 50 kg
samples for each class of stone that he intends to use for mortared stonework. The Engineer
shall retain one of these samples for reference throughout the Contract Period. The
Contractor shall use in the works only the stone classes that have been approved by the
Engineer.
3. CONSTRUCTION REQUIREMENTS
3.1 SHOP DRAWINGS AND SCHEDULE
3.1.1 SHOP DRAWINGS
The Contractor shall furnish shop drawings containing the construction details for mortared
stonework. The shop drawings shall be included in the appropriate submissions to the
Engineer for his approval for the work included in Specification Section 04200 Ditches”
and Specification Section 04300 “Catch Basins, Manholes, Inlets and Outlets”. Construction
of mortared stonework shall not begin until the Contractor’s submissions have been
approved by the Engineer.
1. DESCRIPTION
This Specification section describes requirements and procedures for construction of rock
filled gabion baskets installed at locations indicated on the Drawings or as may be required
by the Engineer.
2. MATERIALS
2.1 BEDDING
Granular material for bedding shall be in accordance with clause 4.2, table 4 of TCVN 7570
– 2006 subject to the approval of the Engineer.
Lean concrete for bedding shall be class C10 bedding or blinding concrete in accordance
with the requirements of Specification Section 07100 “Concrete and Concrete Structures”.
2.2 GEOTEXTILES
Geotextile material shall be non-woven, continuous filament type, manufactured from
durable synthetic polymers. The fabric shall meet the requirements shown in the table
below:
Property Test Method Required VN standard
Values 22 TCN 248 - 98
The Contractor shall present relevant test results and justify that the geotextile is suitable for
the intended use. The geotextile shall be of a reputable manufacturer and shall be approved
by the Engineer. During construction, three random samples shall be selected from every
50,000 m2 of geotextile delivered to the Site for testing or at an outside laboratory, as
required by the Engineer. Geotextile shall be supplied in rolls, marked to show the length,
width, type and weight of the material. Each roll shall be packed in black plastic and shall be
protected from direct sunlight during transport and storage.
2.3 GABIONS
The wire mesh for gabion baskets shall be galvanized steel having a minimum size of
3.05-mm diameter and a tensile strength in the range of 350-500 MPa. The minimum zinc
coating of the wire shall be 0.24 kg/m2 of wire surface as determined by AASHTO T65. The
maximum linear dimension of the mesh openings shall not exceed 0.110 mm and the area of
mesh opening shall not exceed 0.041 m2.
2.4 ROCK FILL
Rock fill for gabions shall consist of hard, durable rock pieces that will not deteriorate when
submerged in water or exposed to severe weather conditions. Rock pieces shall generally be
uniformly graded in sizes ranging from 100 mm to 200 mm. Filled gabions shall have
minimum density of 1400 kg/m3. Voids shall be evenly distributed. Rocks shall meet the
requirements of AASHTO M63 except that the sodium sulphate soundness loss shall not
exceed 9% after 5 cycles.
4. CONSTRUCTION
4.1 PREPARATION OF SURFACES
The Contractor shall carry out any excavation that may be required for gabion work in
accordance with the provisions of Specification Section 03200 “Structural Excavation”. The
Contractor shall be responsible for all dewatering and temporary support works for the
excavations and all other necessary temporary works that may be required during
construction.
Geotextile shall be placed and stretched out on properly levelled surfaces to obtain a
continuous filter layer, without kinks and creases. Joints shall either have an overlap of not
less than 0.50 m or shall be seamed together with an overlap of not less than 0.25 m. Any
damage to the geotextile shall be the Contractor’s responsibility. Repair or replacement shall
be done at the Contractor’s cost to the satisfaction of the Engineer.
Bedding materials shall be placed as indicated on the drawings.
4.2 PLACING GABION BASKETS
Each Gabon unit shall be assembled by binding together all vertical edges with wire ties at
approx. spacing of 150 mm or by continuous stitching around the vertical edges with
connecting wire with an additional coil located at approximate 100 mm centers.
Empty baskets shall be set to line and grade as shown on the drawings or as directed by the
Engineer, and a standard fence stretcher or iron bar at each corner shall be used to stretch the
baskets and hold their alignment.
The baskets shall be filled with stone carefully placed by hand to assure alignment and avoid
bulges with a minimum of voids.
Alternate placing of stone and connecting wires shall be performed until the Gabon basket is
filled.
After filling the lid shall be bent over until it meets the sides and edges. The lid shall then be
secured to the sides, ends and diaphragms with wire ties or connecting wire in the manner
described for assembly.
1. DESCRIPTION
This Specification Section describes materials, methods and procedures for placement and
construction of non-load bearing brick masonry.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied to the works
covered by this Specification.
TCVN ISO4085:1985 Brick and stone structure – Instruction for Construction
and acceptance
TCVN 1451:1998 Solid Clay Bricks
TCVN 4453-95 Concrete & integral Steel concrete structure - Code of
Construction and acceptance standard
2.2 BRICKS
Unless otherwise approved by the Engineer, bricks used for masonry construction shall be
locally manufactured solid clay bricks. Bricks shall be of a uniform size, shape and colour,
and shall be clean and free from flaws and cracks. They shall have sharp, right angle edges
and even surfaces.
Bricks shall conform to requirements specified TCVN 1451:1998 or comparable
international standard subject to approval by the Engineer.
2.3 MORTAR
Unless otherwise approved by the Engineer, the mortar used for masonry construction shall
be in accordance with applicable conditions of Specification Section 08100 “Cement
Mortar”.
2.4 REINFORCING STEEL
Unless otherwise approved by the Engineer, reinforcing steel used in conjunction with
masonry construction shall be in accordance with Specification Section 07500 “Reinforcing
Steel”.
2.5 TIES AND ANCHORS
Metal ties and anchors shall have the size and shape as indicated on the Drawings and in
conformity with the requirements of TCVN 4453:1995. If ties and anchors are not detailed
on the Drawings the Contractor shall, prior to the commencement of work, submit to the
Engineer for his approval proposed ties and anchorage details noting sizes and locations for
all brick walls and partitions.
2.6 SUBMITTALS
2.6.1 BRICKS
The Contractor shall submit to the Engineer for his approval at least six samples of the brick
intended for use. Approved samples shall be retained by the Engineer for comparison with
and approval or rejection of bricks delivered to site for use in the Works.
1. DESCRIPTION
This work consists of supplying, processing, hauling, spreading, watering and compacting
graded aggregates conforming to the requirements of this Specification Section on prepared
and accepted surfaces, in accordance with details shown on the Drawings subject to
confirmation by the Engineer.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The most recent editions of the following standards shall apply to the materials covered in
this Section:
TCVN 8859:2011 Graded Aggregate Base and Subbase Pavement -
Specification for Construction and Acceptance
TCVN 8864 : 2011 Standard Test Method for Measuring Road Pavement
Surface Roughness Using a 3.0 m Straight Edge
22TCN 332-06 Testing procedures on definition of CBR value for soil
and macadam in laboratory
22TCN 333-06 Procedures of soil and macadam compaction in
laboratory
22TCN 346-06 Testing procedure on definition of compaction of road
foundation and embankment by sand cone method
AASHTO T104 Soundness of Aggregate by use of Sodium or
Magnesium Sulphate
AASHTO T180 Standard Method of Test for Moisture-Density
Relations of Soils Using a 4.54-kg (10-lb) Rammer and
a 457-mm (18-in.) Drop
2.2 MATERIAL SOURCES
Materials from all sources proposed by the Contractor shall be tested and submitted to the
Engineer for source approval in compliance with the requirements of this Specification
Section. The Engineer’s approval of a materials source does confer approval on all materials
delivered from that source. Sample sizes shall be at least 200kg for 37.5mm aggregate,
150kg for 25mm aggregate, and 100kg for 19mm aggregate.
2.3 STORAGE, MIXING AND HANDLING OF MATERIALS
Aggregates for base course and sub-base shall be stored in stockpiles that ensure the
materials remain free draining and are adequately separated to prevent cross contamination.
Stockpiles shall be placed on a properly prepared surface to ensure no contamination occurs
when materials are re-handled. Materials shall be placed in stockpiles and subsequently
re-handled in a manner which avoids segregation of the various sizes.
Materials of different sizes which are to be blended to meet the required gradation for base
course and sub-base shall be kept in separate stockpiles. Blending shall be carried out on a
properly prepared surface such that no contamination occurs. Blended materials shall be
stored in a separate stockpile. Blending shall not be permitted in-situ on the roadway.
35 40
Base Subbase
100
1 Los-Angeles wear of aggregate (LA), % TCVN7572-12:2006
25 35
2 Soaked CBR at maximum dry density - 22TCN332-06
6 6
3 Liquid Limit (WL), % AASHTO T89-02 (*)
45 60
4 Plasticity Index (Ip), % AASHTO T90-02 (*)
5 PP Index = Plasticity Index Ip x % material
18 20
passing portion 0.075mm
6 Percent by weight of aggregate with TCVN 7572-2006
98 98
diamond or flattened shapes, % (**)
7 Compacted Density % AASHTO T180
Note:
(*). Liquid Limit, Plasticity Index are specified by test with material passing sieve 0.425 mm.
(**). Aggregate with diamond or flattened shapes has thickness or width less than 1/3 length or
equivalent;
Test is conducted with various sieves of diameter of more than 4.75mm and accounting for more
than 5% of sample quantity.
Aggregate with diamond or flattened shapes content of taken sample is average results certified
for each sieve.
Aggregate with a Dmax = 37.5mm is appropriate for Sub-base
Aggregate with a Dmax = 25mm is appropriate Base Course
3. CONSTRUCTION REQUIREMENTS
As stated in the Conditions of Contract no works may be covered up or put out of site unless
the work has been accepted by the Engineer.
1. DESCRIPTION
This work shall consist of a course composed of paver-laid asphalt treated base course
constructed on a prepared and accepted aggregate base course in accordance with these
Specifications and the lines, levels, grades, dimensions and cross sections shown on the
Drawings and as required by the Engineer.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The reference standards shall be those set out in section 5100 Aggregate subbase and base
(for aggregate base material) and section 6200 Asphalt concrete binder and surface courses
(for asphaltic materials, filler, and construction requirements).
2.2 MATERIAL REQUIREMENTS
Aggregates shall conform to the requirements for aggregate base in Section 05100 except
that the grading shall be as shown in the Table below.
Aggregate Grading Combined Aggregates
Sieve Size % by weight passing
mm µm Crushed Rock
50 100
37.5 95 – 100
28 75 – 90
14 60 – 75
3.35 30 – 45
75 3–6
Asphaltic materials shall conform to the requirements of Section 06200 “Asphalt Concrete
Binder and Surface Course”. In the absence of any requirement or permission to the contrary,
asphalt cement of 60/70 penetration shall be used.
The Contractor shall prepare submittals in accordance with Section 06200 “Asphalt
Concrete Binder and Surface Course” Clause 3.7, including preparation of a Job-Mix Design.
Quantity of asphalt binder shall be 3.5-4.5% of the weight of the total mixture.
Job-Mix Design requirements shall be:
Item Criteria
Stability 7.5kN min
Flow 2.5-4.0 mm
Voids in total mix 4-6%
Voids filled with asphalt 65-75%
Filler shall comply with the requirements of Section 06200 Clause 3.4 of the Specifications.
Preparations of materials shall be carried out according to the requirements of Sections
05100 and 06200.
3. CONSTRUCTION REQUIREMENTS
Construction methods and testing shall conform to the requirements of Section 06200
“Asphalt Concrete Binder and Surface Course”.
The density of the compacted material, as determined by AASHTO T166, shall be at least
98 % of the density of laboratory compacted specimens composed of the same materials in
like proportions.
1. DESCRIPTION
This work shall consist of construction of dry lean concrete base course for cement concrete
pavement or asphalt concrete pavement in accordance with the requirements of these
Specifications and in conformity with the lines, grades and cross sections shown on the
drawings or as directed by the Engineer. The work shall include furnishing of all plant and
equipment, materials and labour and performing all operations, in connection with the work,
as approved by the Engineer.
2. MATERIALS
2.1 MATERIAL SOURCES
The Contractor shall indicate to the Engineer the source of all materials with relevant test
data to be used in the lean concrete work sufficiently in advance and the approval of the
Engineer for the same shall be obtained at least 45 days before the scheduled
commencement of the work. If the Contractor later proposes to obtain the materials from a
different source, he shall notify the Engineer for his approval at least 45 days before such
materials are to be used.
2.2 STORAGE, MIXING AND HANDLING OF MATERIALS
Materials shall be so stored and handled as to assure the preservation of their quality and
fitness for construction. Materials, even though approved before storage or handling, may
again be inspected and tested prior to use. Stored material shall be located to facilitate
prompt inspection.
Handling and stockpiling of aggregates shall be to the approval of the Engineer and at all
times be such as to eliminate segregation of the various sizes and contamination.
Aggregate stockpiles for lean concrete shall be protected from rain to prevent saturation of
the aggregates which would result in a reduction in the quality of the placed material or
adversely affect the placement of the material
Where separate size materials are to be blended to meet the gradation, such blending shall be
as directed by the Engineer and shall be accomplished prior to delivery to the roadway.
Mixing of separate materials on the roadway by motor grader will not be permitted.
2.3 UNACCEPTABLE MATERIALS
Materials that do not comply with the requirements of this Specification section shall be
rejected and removed immediately from the site of the Works unless otherwise instructed by
the Engineer. No rejected materials, the defects of which have been corrected, shall be used
until approval has been given by the Engineer.
2.4 CEMENT
Cement shall be in accordance with the requirements of Specification Section 07100
2.5 AGGREGATE
Aggregate for lean concrete shall not be alkali reactive and shall consist of hard, durable
particles of fragments of stone or gravel crushed to the size and of the quality requirements
of Specification Section 07100. Aggregate shall be cleaned and free from vegetable matter,
lumps or balls of clay and other deleterious substances. The material shall be of such nature
that it can be compacted readily to form a firm, stable base.
The aggregate material shall conform to the grading requirements below.
3. CONSTRUCTION
3.1 EQUIPMENT USED FOR LEAN CONCRETE BASE
Equipment and method used shall place the Lean Concrete Base to the line, levels, grades,
dimensions and cross-section shown in the Drawings and as directed by the Engineer.
The Engineer has the right to stop the use of any equipment or plant which he deems to be
inferior to the quality required and to instruct the removal of such equipment and to have it
replaced by suitable equipment or to alter the method of operation at any time.
The Contractor shall immediately comply with such instructions without being entitled to
any indemnities or extensions as a result of such instructions. The Contractor shall not be
allowed to use any equipment or plant before obtaining the approval of the Engineer, and the
Contractor shall undertake to follow sound technical methods in operation and to engage
skilled and trained operators, mechanics and labour to carry out the Works. The Engineer
has the right to expel any operators, mechanics or labour and to instruct suitable replacement
thereof at any time he deems such action is necessary.
3.2 TRANSPORTING, PLACING, SPREADING AND COMPACTING LEAN
CONCRETE BASE
Lean Concrete Base shall not be placed, spread or compacted while rain is falling, and no
compaction shall be carried out when moisture content of the material falls outside the
specified range.
3.2.1 TRANSPORTING
Plant mix lean concrete shall be discharged immediately from the mixer, transported directly
to the point where it is to be laid and protected from the weather by covering the tippers/
dumpers with tarpaulin during transit. The concrete shall be transported by tipping trucks,
sufficient in number to ensure a continuous supply of material to feed the laying equipment
to work at a uniform speed and in an uninterrupted manner.
3.2.2 PLACING
Lean concrete shall be laid/placed preferably by a paver. Where the space between box
culverts is not sufficient, the laying by hand will be accepted if approved by the Engineer.
The equipment shall be capable of laying the material in one layer in an even manner without
segregation, so that after compaction the total thickness is as specified. The paving machine
shall have high amplitude tamping bars to give good initial compaction to the base course.
The laying of two lane road base course may be done either in full width or lane by lane.
Preferably the lean concrete shall be placed and compacted across the full width of the road,
by constructing it in one go or in two lanes running forwards simultaneously.
1. DESCRIPTION
Prime coat shall consist of supplying and applying emulsified or cut back asphalt to
previously prepared absorbent surfaces such as sub-grade, granular sub-base or aggregate
base course; prior to placing subsequent bituminous layers. Prime Coat shall be applied to
the full width and in the locations indicated on the Drawings. Where indicated in this
specification the use of cover aggregate may be required.
Tack coat shall consist of furnishing and applying emulsified or cut back asphalt to a
previously placed asphaltic base or binder course and concrete bridge decks, approach slabs
and other concrete surfaces to receive asphaltic concrete wearing course.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied to the works
covered by this Specification Section:
TCVN 7494:2005 (ASTM D140-01) Bitumen. Method for sampling
TCVN 7495:2005 (ASTM D5-97) Bitumen. Test method for penetration
TCVN 7496:2005 (ASTM D113-99) Bitumen. Test method for ductility
TCVN 7500:2005 (ASTM D2042-01) Bitumen. Test method for solubility in
Trichloroethylene
TCVN 7502:2005 (ASTM D2170-01a) Bitumen. Test method for determination of
kinematic viscosity
TCVN 8817:2011 Cationic Emulsified Asphalt
TCVN 8818:2011 Cut Back Asphalt
TCVN 8819:2011 Specification for Construction of Hot Mix Asphalt
Concrete Pavement and Acceptance
AASHTO M81 Cut-back Asphalt Rapid Curing Type
AASHTO M82 Cut-back Asphalt Medium Curing Type
AASHTO M226 Viscosity Graded Asphalt Cement
2.2 MATERIALS
Material for the Prime Coat shall be Cut-back Asphalt Medium Curing Type MC30, or
MC70 (TCVN 8818 / AASHTO M82)
Material for the Tack Coat shall be Cut-back Asphalt Rapid Curing Type RC-70 (TCVN
8818 / AASHTO M81).
Where AC-20 is to be diluted with kerosene, the proportion of kerosene shall be subject to
the prior approval of the Engineer.
As alternatives to cut-back asphalts, cationic emulsified asphalts of the types and applied at
the application rates set out in TCVN 8819:2011 may be permitted subject to demonstration
of satisfactory performance to the approval of the Engineer.
Contract – Volume 2 – Specification 6-1 06100
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
2.3 SUBMITTALS
The Contractor shall submit to the Engineer for his approval the following items. These
items shall be submitted well in advance of the Contractor’s programmed start for this work.
a) A 5-litre sample of any Bitumen that the Contractor proposes to use in the works
together with a certificate from the Manufacturer. The certificate must state that
the materials comply with all the specification and grade requirements for the
prime coat and the tack coat given in this specification.
b) A satisfactory record of the calibration certificates of all instruments and gauges,
including the dipstick for the bitumen distributor, shall be submitted not less
than 30 days before construction begins.
c) A spray chart meeting the requirement of sub-section 3.2.3 of this specification.
The spray chart will also be required to enable equipment checks to be carried
out.
d) Samples of materials used in each day’s work shall be submitted in accordance
with Sub-section 3.5 of this specification. Daily records of sealing works done
and material application rates shall be submitted in accordance with this
specification, the Drawings or as required by the Engineer.
3. CONSTRUCTION REQUIREMENTS
3.1 WEATHER LIMITATION
Prime Coat and Tack Coat shall be applied only on dry surfaces, and shall not be applied
during high winds, rain, mist or fog or if rain is imminent and likely to interrupt the work.
3.2 EQUIPMENT
3.2.1 GENERAL
The equipment to be used by the Contractor shall include a power broom and/or a power
blower, a pressurized bitumen distributor and equipment for heating Bitumen. The Engineer
will not permit the use of gravity distributors.
3.2.2 DISTRIBUTOR
The distributor shall have a minimum capacity of 1,000 liters.
The distributor shall be so designed, equipped, maintained and operated that Bitumen at
even heat may be applied uniformly on variable widths of surface, at a controlled rate of
transverse and longitudinal spread within ±10 percent of the required rate of application.
The distributor equipment shall include a tachometer, pressure gauges, a calibrated tank
dipstick, a thermometer for measuring the temperature of the tank contents, and an
instrument for measuring the speed of travel at low speed. All measuring equipment on the
distributor shall have been recently calibrated and an accurate and satisfactory record of such
calibration shall be supplied to the Engineer.
3.2.3 INSTRUMENTATION/CALIBRATION
The distributor shall be equipped with a spray chart and operation manual which shall be in
good condition and carried with the sprayer at all times.
The operation manual shall include pipe flow diagrams and full instructions for all
operations of the distributor.
The spray chart shall show the relationship between speed and application rate for the
bitumen distributor being used as well as the relationship between pump speed and the
number of nozzles in use, based on a constant bitumen output per nozzle. The constant
nozzle output (liters/min) and the spraying pressure shall be noted on the spray chart.
1. DESCRIPTION
The work of asphalt Concrete Binder and Surface Courses under this specification consists
of the supply, spreading and compaction of hot asphalt mixtures produced in a central
mixing plant capable of providing dense durable binder and surface courses.
2. REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied to the works
covered by this Specification.
22TCN319-04 Polymer asphalt - Technical requirement and testing
method.
22TCN345-06 Technology process for construction and approval of
the thin covering layer of high roughness asphalt
concrete.
TCVN 7493 - 7504:2005 Bitumen – Testing methods for physico-mechanical
characteristic.
TCVN 8819:2011 Asphalt Concrete Pavement – Specification for
Construction and Acceptance
TCVN 8863:2011 Bituminous Surface Treatment – Specification for
Construction and Acceptance.
TCVN 8865:2011 Method for Measuring and Assessment Roughness by
International Roughness Index (IRI)
TCVN 8866:2011 Standard Test Method for Measuring Pavement
Macrotexture Depth Using a Volumetric Technique
TCVN 8867:2011 Flexible Pavement Standard Test Method for
determining the Elastic Modulus of Pavement
Structure using Benkelman Beam.
22TCN318-04 Testing process for determination of abrasion of
aggregate by Los Angeles Method.
AASHTO M17 Mineral Filler for Bituminous Paving Mixtures
AASHTO M20 Penetration Graded Asphalt Cement
AASHTO M226 Viscosity Graded Asphalt Cement
AASHTO T11-05 Materials Finer Than 75-µm (No. 200) Sieve in
Mineral Aggregates by Washing. ASTM C117-03
AASHTO T27-99 Sieve Analysis of Fine and Coarse Aggregates. ASTM
C 136-96
AASHTO T49 Penetration of Bitumen
AASHTO T50 Float Test for Bitumen
AASHTO T51 Ductility of Bitumen
10 mm 5 mm
Course Course surface
5 mm 5 mm
Center-side Location
Surface levels
20 mm 10 mm
8mm 5mm 5mm
Width
Thickness by Site Core Sample
Density by Plant Samples** 100%4% 100%3% 100%5%
5 mm 3 mm
Bitumen Contents by Plant Sample **
Surface Irregularity by 3m straight edge
IRI values ( m /km) Max. 2.00
Permeability (cm/sec) Min. 0.01
** means the basic value shall be taken as that confirmed by the Contractor in trials subject to the
approval of the Engineer.
1. DESCRIPTION
This Specification Section describes the requirements and procedures for the placement of
pavement composed of Portland cement concrete, constructed on a prepared base surface in
conformance with the lines, grades, thickness, and typical cross sections shown on the
Drawings.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied to the works
covered by this Specification.
Decision 1951/QD-BGTVT of 17/08/2012 Interim Provisions on the
Construction and Acceptance of Cement Concrete
Pavement
AASHTO M254 Corrosion Resistant Coated Dowel Bars
TCVN 8865:2011 Method for Measuring and Assessment Roughness by
International Roughness Index (IRI)
TC01:2010 Oil paper
ASTM E950 Standard Test Method for Measuring the Longitudinal
Profile of Travelled Surfaces with an Accelerometer
Established Inertial Profiling Reference
ASTM C31 (/C31M-03a) Standard Practice for Making and Curing Concrete
Test Specimens in the Field
ASTM C78 Flexural Strength of Concrete (Using Simple Beam
with Third-Point Loading)
ASTM C94 (/C94M-05) Standard Specification for Ready-Mixed Concrete
ASTM C143 (/C143M-05a) Standard Test Method for Slump of Hydraulic Cement
Concrete
ASTM C172-04 Standard Practice for Sampling Freshly Mixed
Concrete;
ASTM C174 (/C174M-06) Standard Test Method for Measuring Thickness of
Concrete Elements Using Drilled Concrete Cores
ASTM C494 (/C494M-05a) Standard Specification for Chemical Admixtures for
Concrete
ASTM C881 (/C881M-02) Standard Specification for Epoxy-Resin-Base Bonding
Systems for Concrete
ASTM C1077-06 Standard Practice for Laboratories Testing Concrete
and Concrete Aggregates for Use in Construction and
Criteria for Laboratory Evaluation
ASTM D994-98 (2003) Preformed Expansion Joint Filler for Concrete
(Bituminous Type)
3. CONSTRUCTION REQUIREMENTS
3.1 EQUIPMENT
The batching plant and equipment shall conform to the requirements of ASTM C94. If
slip-form-paving methods are used, a central plant mixer shall be used.
The Contractor shall furnish all equipment and tools necessary for handling materials and
performing all parts of the work.
Mixers and Transportation Equipment
(a) General
Concrete may be mixed at a central plant, or wholly or in part in truck mixers. Each mixer
shall have attached in a prominent place a manufacturer's nameplate showing the capacity of
the drum in terms of volume of mixed concrete and the speed of rotation of the mixing drum
or blades.
(b) Central Plant Mixer
Central plant mixers shall conform to the requirements of ASTM C94. The mixer shall be
examined daily for changes in condition due to accumulation of hard concrete or mortar or
wear of blades. The pickup and throw over blades shall be replaced when they have worn
down 19 mm or more. The Contractor shall have a copy of the manufacturer's design on site
showing dimensions and arrangement of the blades.
(c) Truck Mixers and Truck Agitators
Truck mixers used for mixing and hauling concrete and truck agitators used for hauling
central mixed concrete shall conform to the requirements of ASTM C94.
(d) Non-agitating Trucks
Non-agitating hauling equipment shall conform to the requirements of ASTM C94.
3.1.2 FINISHING EQUIPMENT
The finishing equipment shall be of sufficient weight and power for proper finishing of the
concrete. The finishing machine shall be designed and operated to strike off, screed and
consolidate the concrete such that laitance on the surface is less than 3 mm thick.
3.1.3 VIBRATORS
Vibrators shall be of either internal type with immersed tube or multiple spuds, or surface
type vibrating pan or screed. For pavements 20 cm or more thick internal vibrators shall be
used. They may be attached to the spreader or the finishing machine, or they may be
mounted on a separate carriage. Operating frequency for internal vibrators shall be between
8,000 and 12,000 vibrations per minute. Average amplitude for internal vibrators shall be
0.06 to 0.13 cm.
For pavements less than 20 cm thick, vibrating surface pans or screeds will be allowed.
Operating frequencies for surface vibrators shall be between 3,000 and 6,000 vibrations per
minute. The number, spacing, and frequency shall be as necessary to provide a dense and
homogeneous pavement. Adequate power to operate all vibrators shall be available on the
paver. The vibrators shall be automatically controlled so that they shall be stopped as
forward motion ceases. Hand held vibrators may be used in irregular areas.
3.1.4 CONCRETE SAWS
The Contractor shall provide enough saws of sufficient power to complete the sawing to the
required dimensions.
Contract – Volume 2 – Specification 6-32 06300
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
The Contractor shall provide at least one standby saw in good working order and a supply of
saw blades at the site of the work at all times during sawing operations.
3.1.5 SIDE FORMS
Straight side forms shall be made of steel and shall be furnished in sections not less than 3 m
in length. Forms shall have a depth equal to the pavement thickness at the edge. Flexible or
curved forms of proper radius shall be used for curves of 31 meters radius or less. Forms
shall be provided with adequate fixings so that when in place they will withstand, without
visible movement or settlement, any impact or vibration from the finishing or compaction
equipment.
Forms with battered top surfaces or forms that are bent, twisted or broken forms shall not be
used. Built up forms shall not be used. The top edge of the form shall not vary from a true
plane by more than 3 mm in 3 meters, and the vertical face shall not vary more than 6 mm.
The forms shall contain provisions for locking the ends of abutting sections together tightly
for secure fixing.
Wood forms shall not be used.
3.1.6 PAVERS
Pavers shall be fully energized, self propelled, and designed for the specific purpose of
placing, consolidating, and finishing the concrete pavement, true to grade, tolerances, and
cross section. They shall be of sufficient weight and power to construct the maximum
specified concrete paving lane width as shown on the Drawings, at adequate forward speed,
without transverse, longitudinal or vertical instability or without displacement. Pavers shall
be equipped with electronic or hydraulic horizontal and vertical control devices.
3.2 PREPARATION OF AGGREGATE BASE COURSE.
The Base Course shall comply with the requirements of specification section 05100
“Aggregate Sub-Base and Base”. After the base surface has been placed and compacted to
the required density, the areas shall be trimmed or graded to the plan grade elevation and
profile by means of a properly designed machine. The grade of the base surface shall be
controlled by a positive grade control system using lasers, string lines, or guide wires.
If the density of the base surface is disturbed by the trimming operations, it shall be corrected
by additional compaction and retested at the option of the Engineer before the concrete is
placed. If traffic is allowed to use the prepared grade, the grade shall be checked and
corrected immediately before the placement of concrete.
The prepared grade shall be moistened with water, without saturating, immediately ahead of
concrete placement to prevent rapid loss of moisture from concrete.
Damage caused by hauling or usage of other equipment shall be corrected and retested. If
damage occurs to the base and or subbase, the Contractor shall correct it to the full depth.
A template shall be provided and operated on the forms immediately in advance of the
placing of all concrete. The template shall be hand operated and not attached to a tractor or
other power unit. All excess material shall be removed. Low areas shall be filled and
compacted to a condition similar to that of the surrounding grade.
The accuracy of the template shall be maintained at all times and shall be checked daily.
3.3 FORM SETTING
Forms shall be set sufficiently in advance of the concrete placement to ensure continuous
paving operation. Before setting forms, the base surface shall be thoroughly tamped, either
mechanically or by hand, at both the inside and outside of the forms. After the forms have
been set to correct grade, forms shall be staked into place sufficiently to maintain the form in
position for the method of placement. Form sections shall be tightly locked and shall be free
from play or movement in any direction.
Contract – Volume 2 – Specification 6-33 06300
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
The forms shall not deviate from true line by more than 3-mm at any joint. Forms shall be so
set that they will withstand without visible movement or settlement any impact or vibration
from the finishing or compaction equipment. Forms shall be cleaned and oiled prior to the
placing of concrete. The alignment and grade elevations of the forms shall be checked and
corrections made by the Contractor immediately before placing the concrete.
3.4 HANDLING, MEASURING, AND BATCHING MATERIAL
The batch plant site, layout, equipment, and provisions for transporting material shall assure
a continuous supply of material to the work. Stockpiles shall be constructed in such a manner
that prevents segregation and intermixing of deleterious materials.
Aggregates that have become segregated or mixed with soil or foreign material shall not be
used. All aggregates produced or handled by hydraulic methods, and washed aggregates,
shall be stockpiled or binned for draining at least 12 hours before being batched. Rail
shipments requiring more than 12 hours will be accepted as adequate binning only if the car
bodies permit free drainage.
Batching plants shall be equipped to proportion aggregates and bulk cement, by weight,
automatically using interlocked proportioning devices of an approved type. When bulk
cement is used, the Contractor shall use a suitable method of handling the cement from
weighing hopper to transporting container or into the batch itself for transportation to the
mixer, such as a chute, boot, or other device, to prevent loss of cement. The device shall be
arranged to provide positive assurance that the cement content specified is present in each
batch.
3.5 MIXING CONCRETE
Concrete may be mixed at the work site, in a central mix plant or in truck mixers. The mixer
shall be of an acceptable type and capacity. Mixing time shall be measured from the time all
materials, except water, are emptied into the drum. All concrete shall be mixed and delivered
to the site in accordance with the requirements of ASTM C94.
(Mixed concrete from the central mixing plant shall be transported in truck mixers, truck
agitators, or non-agitating trucks.
3.6 LIMITATIONS ON MIXING AND PLACING
The elapsed time from the addition of cement material to the mix until the concrete is
deposited in place at the work site shall not exceed 60 minutes when the concrete is hauled in
non-agitating trucks, or 90 minutes when the concrete is hauled in truck mixers or truck
agitators.
Re-tempering concrete by adding water or by other means will not be permitted, except
when concrete is delivered in transit mixers. With transit mixers, additional water may be
added to the batch materials and additional mixing performed to increase the slump to meet
the specified requirements provided that the addition of water is performed within 45
minutes after the initial mixing operations and provided that the water/cement ratio specified
in the mix design is not exceeded.
3.6.1 VISIBILITY
Concrete shall not be mixed, placed, or finished when the natural light is insufficient, unless
an adequate artificial lighting system approved by the Engineer is used.
3.6.2 HOT WEATHER
During periods of hot weather when the maximum daily air temperature exceeds 30°C, the
following precautions shall be taken.
The forms and/or the base surface shall be sprinkled with water immediately before placing
the concrete. The concrete shall be placed at the coolest temperature practicable, and in no
case shall the temperature of the concrete when placed exceed 35°C.
Contract – Volume 2 – Specification 6-34 06300
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
The aggregates and/or mixing water shall be cooled as necessary to maintain the concrete
temperature at or not more than the specified maximum. Methods used may be as follows:
covering with wet burlap or cotton mats,
fog spraying or sprinkling with water,
shading the material storage areas or production equipment,
cooling the aggregate and water by refrigeration,
replacing a portion or all of the mix water with flaked or crushed ice to the extent that
the ice completely melts during mixing of the concrete,
or by other approved methods.
The finished surfaces of the newly laid pavement shall be kept damp by applying a water fog
or mist with approved spraying equipment until the pavement is covered by the curing
medium. If necessary, wind screens shall be provided to protect the concrete from an
evaporation rate in excess of 0.2 psf per hour as determined in accordance with Figure 2.1.5
in ACI 305R, Hot Weather Concreting, which takes into consideration relative humidity,
wind velocity, and air temperature.
When conditions are such that problems with plastic cracking can be expected, and
particularly if any plastic cracking begins to occur, the Contractor shall immediately take
such additional measures as necessary to protect the concrete surface. Such measures shall
consist of windscreens, more effective fog sprays, and similar measures commencing
immediately behind the paver. If these measures are not effective in preventing plastic
cracking, paving operations shall be immediately stopped.
3.7 PLACING CONCRETE
The prepared base surface shall be moistened with water, without saturating, immediately
ahead of concrete placement to prevent rapid loss of moisture from the concrete.
The Contractor has the option of placing the concrete with either side (fixed) forms or slip
forms. At any point in concrete conveyance, the free vertical drop of the concrete from one
point to another or to the base surface shall not exceed 1 meter.
Hauling equipment or other mechanical equipment can be permitted on adjoining previously
constructed pavement when the concrete strength reaches a flexural strength of 3,800 kPa.
Also, subgrade and subbase planers, concrete pavers, and concrete finishing equipment may
be permitted to ride upon the edges of previously constructed pavement when the concrete
has attained a minimum flexural strength of 2,750 kPa.
3.7.1 SIDE FORM METHOD
For the side form method, the concrete shall be deposited on the moistened grade to require
as little re-handling as possible. Unless truck mixers, truck agitators, or non-agitating
hauling equipment are equipped with means for discharge of concrete without segregation of
the materials, the concrete shall be placed and spread using an approved mechanical
spreading device that prevents segregation of the materials. Moving concrete by the use of
vibrators shall not be permitted. Placing shall be continuous between transverse joints
without the use of intermediate bulkheads. Necessary hand spreading shall be done with
shovels not rakes. Workmen shall not be allowed to walk in the freshly mixed concrete with
boots or shoes coated with earth or foreign substances.
Concrete shall be deposited as near to expansion and contraction joints as possible without
disturbing them but shall not be dumped from the discharge bucket or hopper onto a joint
assembly unless the hopper is centered above the joint assembly.
5 mm
Section 07100)
2.50
Surface Irregularity by 3m straight edge 2 per 100m2
IRI values (m /km) Each lane
Crossfall and surface levels shall be such that there are no areas of ponding on the pavement.
1. DESCRIPTION
This Specification Section provides requirements and procedures for furnishing Double
Bituminous Surface Treatment (DBST) of road surface in the locations shown on the
Drawings or as required by the Engineer. The DBST road surface shall consist of the
application of a bituminous prime coat followed by layers of bituminous seal coat with cover
aggregate constructed on a prepared base in accordance with Specification requirements and
in conformity with the lines, grades and typical cross-sections shown on the Drawings.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied to the works
covered by this Specification.
TCVN 8863:2011 Bituminous Surface Treatment – Specification for
Construction and Acceptance
TCVN 7493 - 7405:2005 Bitumen – Testing methods for physico-mechanical
characteristics
22TCN250-98 Technical specifications for construction and approval
of acid emulsified asphalt macadam pavement
22TCN354-06 Standard of acid emulsified asphalt – Technical
requirement and testing method.
AASHTO T11 Materials Finer than 75-µm (No.200) Sieve in Mineral
Aggregates by Washing
AASHTO T27 Sieve Analysis of Fine and Coarse Aggregates
AASHTO T84 Specific Gravity and Absorption of Fine Aggregate
AASHTO T85 Specific Gravity and Absorption of Coarse Aggregate
AASHTO T176 Plastic Fines in Graded Aggregates and Soils by Use of
the Sand Equivalent Test
2.2 MATERIALS
2.2.1 PRIME COAT
The bituminous Prime Coat material shall be in accordance with the requirements of
Specification Section 06100 “Prime Coat & Tack Coat”.
2.2.2 BITUMEN
The Bitumen shall be in accordance with the requirements of Specification Section 06100
“Prime Coat & Tack Coat”.
2.2.3 AGGREGATE
Table 1 Properties of Aggregate Surface Course
Property Required limit Test Method
1. Aggregate crushing value ≤8 TCVN 7572-11: 2006
(ACV), %
2. Los Angeles Abrasion Test TCVN 7572-12: 2006
(LA), %
a) For magmatic and
Contract – Volume 2 – Specification 6-45 06400
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
metamorphic rock ≤ 25 (30)
b) For sedimentary rock ≤ 35 (40)
3. Crushed aggregated content (at ≥ 85 TCVN 7572-18: 2006
least 2 fracture faces) of total
particles retained on 4.75mm
sieve, %
4. Elongation and flakiness index ≤ 15 TCVN 7572-13: 2005
(particles larger than 4,75mm), %
5. Content of soft and weathered ≤5 TCVN 7572-17: 2006
particles, %
6. Content of dust, mud, clay ≤1 TCVN 7572-8: 2006
(percent by weight), %
7. Content of clay lumps (percent ≤ 0,25 TCVN 7572-8: 2006
by weight), %
8. Bitumen adhesion with Pass TCVN 7504: 2005
aggregate
Numbers in brackets for roads with speed less than 60km/h
Table 1A Size of Aggregate for Bonded Surface Treatment - BST
Aggregate side (d/D)mm Minimum Maximum
nominal nominal
dmin Dmax
12.5 - 19 12.5 19
9.5 – 12.5 9.5 12.5
dmin: nominal minimum side of crushed aggregate
Dmax: nominal maximum side of crushed aggregate;
Particles which are bigger than (D) shall not exceed 15% by weight;
Particles which are smaller than (d) shall not exceed 10% by weight;
3. CONSTRUCTION REQUIREMENTS
3.1 QUANTITIES OF MATERIALS
The materials used for DBST shall conform to the approximate rates shown in Table 2,
unless otherwise approved by the Engineer.
Table 2 Required Aggregate and Bituminous Content
Type of Thickness Bituminous Fine aggregate
BST (cm) Spaying Volume placing aggregate Volume
sequence (kg/m2) sequence side (lit/m2)
(mm)
Two 2.0 – 2.5 The first 1.5 (1.8) The first 9.5 / 12.5 14 – 16
layer time time
The second 1.2 The second 4.75 / 9.5 10 – 12
time time
The figure in bracket (x) shall be applied for just-finished aggregate base course.
Prime coat is excluded in the above table. Typical application rate shall be 1kg/ m2.
3.2 SEQUENCE OF PLACEMENT AND OPERATIONS
The DBST road surface shall be constructed by initially applying the Prime Coat material on
a prepared approved base, in accordance with the requirements for construction of
Specification Section 06100 “Prime Coat & Tack Coat”.
Following a minimum period of 24 hours after the Prime Coat application, or longer if
necessary for the Prime Coat material to be completely absorbed, the bitumen for the 1st
application shall be placed.
Contract – Volume 2 – Specification 6-46 06400
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
Immediately after the above-mentioned placement of bitumen is completed, the aggregate
for the above 1st application of DBST shall be placed and uniformly spread and rolled.
No waiting time is required between the applications of surface treatment when using
asphalt binder; while a waiting time of at least 24 hours between applications is required
when using emulsified asphalt.
The 2nd application of bitumen and aggregate materials for DBST shall be performed
following the same procedure as for the 1st application.
3.3 WEATHER LIMITATIONS
Application of DBST shall be made only when the aggregate is in appropriate conditions
(dry when binder asphalt is used, and without excess of moisture when emulsified asphalt is
used), and the atmospheric temperature in the shade is 15°C or above and when the weather
is not foggy or rainy.
3.4 RATES AND TEMPERATURE OF APPLICATION
Prime Coat: Bituminous Prime Coat shall be applied at the rates and at temperatures
specified in Specification Section 06100 “Prime Coat & Tack Coat”.
Bitumen: Bitumen shall be applied at the rates described in Sub-section 3.1 (Table 2) of this
Specification Section, and at temperatures specified in Specification Section 06100 “Prime
Coat & Tack Coat”.
Aggregate: The DBST aggregate shall be uniformly spread over the applied surface at the
rates described in Sub-section 3.1 (Table 2) of this Specification Section. The exact rate of
application necessary to provide a sound uniform surface shall be established in the field and
be approved by the Engineer.
3.5 EQUIPMENT
The equipment to be used shall include hand or power-operated brooms, shovels, rakes,
self-powered Bitumen distributors or hand or power-operated spray pumps, broom dragging
equipment, and self-powered rollers. A sufficient number of stiff-fibers or steel-bristles push
brooms shall be included.
Application of the Bitumen by any means other than a pressure spray will not be permitted
and the equipment used shall be of such nature that the temperature of application of the
Bitumen can be accurately controlled within the limits specified and such that the rates of
application can be accurately controlled.
The rollers shall be of self-propelled steel wheel, vibratory or pneumatic type. The number
and weight of rollers shall be sufficient to compact the DBST surface to an approved
condition.
3.6 CONDITIONING OF SURFACES
Before placing the Prime Coat, the base shall be cleaned of all loose foreign materials. The
existing base shall be swept until the embedded large aggregate is exposed.
Before placing the bitumen and aggregate for DBST, the primed surface shall be cleaned
until the surface is free of mud or other covering.
3.7 SPREADING AND COMPACTION OF MATERIALS
3.7.1 APPLYING PRIME COAT AND BITUMEN
Application of asphalt shall be done at the rates of application described in Sub-section 3.1
(Table 2) of this Specification Section by means of a pressure distributor, in a uniform,
continuous spread within the specified temperature range.
1. DESCRIPTION
The work under this Specification section consist of providing a dense durable asphaltic
leveling mixture to level sags and depressions in old pavement and concrete bridge surfaces
prior to asphalt surfacing.
Asphalt leveling on bridge decks shall be placed after the installation of bridge
waterproofing, and just prior to asphaltic pavement placement.
2. REFERENCE STANDARDS
Asphalt concrete leveling course shall be prepared, constructed and tested in accordance
with Section 06200 of this Specification.
1. DESCRIPTION
This specification consists of the supply, transport and placing of concrete mixes of different
classes and concrete construction work in accordance with the lines, grades, sections and
other detail shown on the drawings or subject to approval by the Engineer.
The figure below shows the applicable referencing of structural members:
Wing Wall
Pile
Apron
2. REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied to the works
covered by this Specification.
TCVN 5438-04 Cements - Standard Specification for Terminology and
definitions
TCVN 5439-04 Cements - Standard Specification for Classification
TCVN 2682-09 Standard Specification for Portland cement
TCVN 4029-85 Cements - Technical requirement procedure for
physical contents testing
TCVN 4030-03 Cement. Test method for determination of fineness
TCVN 4031-85 Cements - Method for determination of standard
workability setting time and volume stability
TCVN 4032-85 Cements - Methods for determination of bending and
compressive strength
TCVN 6016-01 Cements - Test methods - Determination of Durability
3. CONSTRUCTION REQUIREMENTS
3.1 MATERIALS FOR CONCRETE
3.1.1 GENERAL
In principle ready mixed concrete from established suppliers shall be used for the project.
The Contractor shall submit a procurement plan and samples of all materials to be used in
concrete mixes together with test results confirming their compliance with this specification
for the approval of the Engineer.
The Contractor shall use approved materials to prepare mix designs and for trial mixes to be
approved by the Engineer.
Contract – Volume 2 – Specification 7-3 07100
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
No materials shall be delivered to the Site until materials, mix designs and trial mixes have
been approved by the Engineer. Material failing to meet the requirements must be moved
immediately out of the site.
3.1.2 PORTLAND CEMENT
Cement shall be Portland cement type I complying in all respects with ASTM C150
(AASHTO M85) or TCVN2682-2009, or Portland cement blend complying in all respects
with ASTM C1157-GU, or TCVN 6260 type PCB40. However the Contractor may submit
to the Engineer for his approval fully supported proposals for the use of other types of
cement. All cement shall be manufacturer’s standard cement unless otherwise specified on
the drawings. Only one brand of cement shall be used for all concrete works throughout the
Project unless otherwise authorized by the Engineer.
Cement shall be delivered to the Site in sealed bags or in bulk. The Contractor proposed
source of supply of cement shall be submitted to the Engineer for his approval. All deliveries
of cement to site shall include appropriate test certificates, certified by an independent
agency in the country of origin, confirming that the material delivered complies with the
specification.
Bagged cement shall bear the manufacturer’s name, cement type and the date of
manufacture and shall be stored in waterproof sheds or other such temporary buildings used
exclusively for the storage of cement. Cement shall be stored in dry conditions on areas
raised above ground level. Storage capacity shall be sufficient to hold enough cement for the
largest units to be cast. Bags shall not be stored more than 8 high and a free passage of at
least one meter shall be left between the cement and the side walls of the sheds.
Cement delivered by bulk carriers shall be stored in silos made for cement storage. All
handling shall be by methods that prevent contamination of the cement. The silos shall be
provided with interior moisture control devices that keep the cement dry and prevent
premature hydration. The silos shall be provided with access ladders and access points to
enable samples to be taken from various levels of each silo for testing purposes.
Access ways shall be provided between storage containers such that every container can be
visually inspected. Each delivery shall be stored separately from previous deliveries.
Deliveries shall be used in the order in which they were delivered. Any delivery which has
become caked or otherwise adversely affected shall be removed from the Site at the
Contractor’s expense.
The Contractor shall provide weighing machines which shall be kept permanently in each
shed for checking the weight of the bags.
3.1.3 WATER FOR CONCRETE MIXING AND CURING
The Contractor’s proposed water source shall be submitted to the Engineer for his approval
together with test results confirming that water from the source complies with
TCXDVN-302-2004. Periodic testing of the water source shall be made at least monthly.
Water for concrete mixes, curing concrete and other products containing cement shall be
clean water free from oil, salt, acid, sugar, vegetable or any other substance injurious to the
concrete unless otherwise authorized by the Engineer.
3.1.4 AGGREGATES
Aggregates shall be free of substances that react deleteriously with alkali in the cement
sufficiently to cause unacceptable expansion of the concrete. The Engineer’s approval of
aggregate sources will be based on satisfactory evidence furnished by the Contractor that the
aggregate is free from such materials. This evidence shall include certified records of tests
by a testing laboratory that the aggregates meet the requirements of ASTM-C227 and may
include service records of concrete of comparable properties placed under similar conditions
The 7-day test result is not an acceptance test, but is used to monitor early strength gain and
is expected to about 75% of the 28-day strength.
Table 2.2 Concrete class - location
Concrete Class Location
Class C50 Precast Girder (Super T)
Class C45 Precast Girder (I)
Class C40 Box Girder
Class C35 CIP Deck Slab (incl. Link Slab), Crossbeam of Super T
Class C30 Abutment, Pier, Precast Concrete Plank for Super T, Parapet,
Pedestal of Lamp Post, Approach Slab, Box culvert body, Pipe
culvert
Class C35 (Tremie Mix) Bored Pile
Class C25 Upper Sealing Concrete, Bridge Curbs
Class C20 Lower Sealing Concrete, Manhole, Catch basin, Ditch, Fence
column foundation
Class C15 Supporting block, Sign support foundation, Post, Traffic signage,
km post, Curb, Vehicular guardrail foundation, Slope protection
Class C10 Blinding Concrete
Class P Portland Cement Concrete Pavement (PCCP)
Acceptable ranges for concrete slump shall be determined by appropriate mix design and
subsequent trial mix testing. Slumps shall be measured in accordance with AASHTO T119.
3.2.1 APPROVED MIX DESIGN
The Contractor shall submit his proposed mix designs to the Engineer for his approval and
prepare samples in order to Engineer checked and approved samples before carrying out
Contract – Volume 2 – Specification 7-7 07100
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
mixing concrete on a large scale. The mix design shall include the target mean strength for
the mix and shall be submitted with the results of satisfactory tests from trial mixes. The mix
design and the trial mixes shall use only those materials that have previously been given
source approval by the Engineer.
In principle the concrete shall be proportioned in order to reliably meet the criteria for
acceptance through use of a target mean strength as follows.
Where the standard deviation is not more than 3.5MPa:
Target strength = specified strength + (1.4 standard deviation)
Where the standard deviation is more than 3.5MPa
Target strength = specified strength + (2.4 x standard deviation – 3.5)
No concrete work will be allowed to commence until the Engineer approves the Contractor’s
proposed mix design(s).
A new mix design shall be submitted to the Engineer for his approval if there are any
changes in characteristics or source of supply of any of the component parts of the mix. Any
delay due to such changes shall be entirely the responsibility of the Contractor.
During the execution of the Works, the Engineer may require additional tests to be made on
the work mix to check compliance with the approved Mix Design.
3.2.2 WATER - CEMENT RATIO
The Contractor’s proposed water content and water cement ratio shall be included in the mix
designs, supported by trial mixes, submitted to the Engineer for his approval. The water
content shall be the least amount that shall produce a workable homogeneous plastic mixture.
Excess water shall not be permitted and any batch containing such excess shall be rejected.
The total water content for any batch of concrete shall include an allowance for water
contained in the aggregates. The Contractor shall determine the water content of the
aggregates before concrete batching begins and admixture (if any). The water added to the
mix shall be adjusted for the water contained in the aggregates.
Frequent slump tests shall be carried out to ensure that the workability of the concrete
remains consistent.
3.2.3 ADJUSTMENTS DURING PROGRESS OF WORK
After a mix design has been approved, the mix shall not be changed during the progress of
the work except as follows:
If it is found impossible to obtain concrete of the desired workability with the mix
proportions originally determined, changes in aggregate weights may be made subject to the
approval of the Engineer.
If it is found impossible to produce concrete of the minimum compressive strength specified,
the cement content may be increased subject to the approval of the Engineer.
3.2.4 CONTENTS OF CHLORIDE AND SULPHATE
The amount of chloride in the concrete mass shall not exceed 1,000 ppm of the total concrete
mass, or 6,000 ppm of the amount of cement in the mix.
The amount of sulphate in the concrete shall not exceed 3,500 ppm of the total concrete mass
to TCVN141:1998..
The amounts of chloride and sulphate shall be determined by recognized methods of
laboratory analyses of the cement, aggregates, water and admixtures.
if No OK
Alternative 2
stop placing concrete
and rectify any defect Countermeasures to Acceptance of
Alternative 1 be taken the Lot
Remove and replace the defective concrete
without waiting the results of 28-day test by
the responsibility of the Contractor
*Note: This percentage or strength shall be decided in accordance with the test results of
trial mixing as mentioned in sub-section 3.1 Concrete Mix Design and with the proposal
by the Contractor.
1. DESCRIPTION
This Section specifies the materials and workmanship for fabrication, installation and testing
of pre-cast reinforced concrete piles.
The types of piles to be used shall be as indicated on the drawings. If the Contractor proposes
to use an alternative type of pile he shall provide the Engineer with information on the design
data, piling experience, records, and calculations supporting the pile design. All such
proposals shall be subject to approval by the Engineer.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied to the works
covered by this Specification.
ASTM D1143 Test Method for Piles Under Static Axial Compressive Load
In addition all materials and procedures shall comply with the requirements of the relevant
of ASTM standard in its latest edition, or other national standard specifications which may
be approved by the Engineer. Standard TCVN 9393:2012 may also be applied.
2.2 MATERIALS FOR PILING
2.2.1 SUPPLY OF MATERIAL
The Contractor shall submit to the Engineer for his approval, samples of the material to be
provided and the names of the manufacturers and suppliers who will supply the materials
required for pile construction. The Quality of the material provided shall be certified by the
supplier, and samples shall be tested under the supervision of the Engineer, at the
Contractor’s expenses.
2.2.2 CONCRETE
The concrete class to be used for pre-cast piles shall be as indicated on the drawings and
shall comply with the requirements of Specification - Concrete and Concrete Structures.
2.2.3 REINFORCING STEEL
The reinforcement steel to be used for pre-cast piles shall be as indicated on the drawings
and shall comply with the requirements of Specification - Reinforcing Steel.
3. CONSTRUCTION REQUIREMENTS
3.1 SUBMITTALS
The Contractor’s proposed method statement for pre-cast concrete piles shall be submitted
to the Engineer for his approval well before the start of pile driving. The method statement
shall include but not necessarily limited to the following:
The location and extent of necessary temporary works such as roads and bridges to
be used to transport materials and equipment to the pile driving sites.
Initial driving criteria to reach the bearing strata and design pile capacity.
The methods to be used for the precise location of the piles (geodetic positioning
method and equipment) in accordance with the Drawings.
Method of controlling groundwater.
1. DESCRIPTION
This specification describes the requirements and procedures for Soil Investigation in
locations as may be required by the Engineer or required by the Contractor for information
to confirm pile driving conditions or foundation bearing capacity.
2. REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied to the works
covered by this specification.
22TCN-259-2000 Specification for Geological Exploratory Drilling7250
ASTM D422 Particle-Size Analysis of Soils
ASTM D854-06 Specific Gravity of Soil Solids by Water Pycnometer
ASTM D1586 Penetration Test and Split-Barrel Sampling of Soils
ASTM D1587 Standard Practice for Thin-Walled Tube Geotechnical Sampling
of Soils
ASTM D2113-06 Standard Practice for Rock Core Drilling and Sampling of Rock
for Site Investigation
ASTM D2166 Unconfined Compressive Strength of Cohesive Soil
ASTM D2216 Laboratory Determination of Water (Moisture) Content of Soil
and Rock by Mass
ASTM D2487-06 Classification of Soils for Engineering Purposes (Unified Soil
Classification System)
ASTM D2435 Standard Test Methods for One-Dimensional Consolidation
Properties of Soils Using Incremental Loading
ASTM D2974 Moisture, Ash, and Organic Matter of Peat and Other Organic
Soils
ASTM D4318 Liquid Limit, Plastic Limit, and Plasticity Index of Soils
ASTM D4186 Standard Test Method for One-Dimensional Consolidation
Properties of Saturated Cohesive Soils Using Controlled-Strain
Loading
1. DESCRIPTION
The work under this Specification Section consists of the construction of Bored piles using
the reverse circulation drilling method, crab type hammers, and steel casing or any other
earth drill method approved by the Engineer, in accordance with this specification and in
conformity with the drawings or as may be required by the Engineer.
The work to be performed as specified in this Specification Section shall be carried out after
any required sub-soil investigations have been completed by the Contractor in accordance
with this specification, the drawings, or as may be required by the Engineer.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied to the works
covered by this Specification.
ASTM A36 Carbon Structural Steel
OCMA DFCP4 Drilling Fluid Materials Bentonite Oil Companies
Materials Association (OCMA)
API S13A Specification for Oil Well Drilling Fluid Materials
(APIS: American Petroleum Institute Standard)
22TCN272-05 Specification for Bridge Design
TCVN 9393:2012 Piles - standard test method in situ for piles under axial
compressive load
TCVN 9395:2012 Construction and Measurement of Bored Piles
TCVN 9396-2012 Bored piles – Determination of identity of concrete –
Pulsed ultrasonic method;
TCVN 9397-2012 Bored piles – Method of detection of defects by low
strain dynamic test.
2.2 MATERIALS FOR PILING
2.2.1 CONCRETE
Bored piles shall be constructed in accordance with the details shown on the drawings using
the class of concrete noted on the drawings and in accordance with Specification - Concrete
and Concrete Structures
Concrete shall be mixed and placed in accordance with the applicable provisions of
Specification - Concrete and Concrete Structures
2.2.2 REINFORCING STEEL
Reinforcement shall comply with the provisions of Specification - Reinforcing Steel
2.2.3 TEMPORARY CASINGS
Bored piles shall be excavated with a temporary steel casing through water and upper soil
layers which might otherwise collapse.
Temporary casings shall be free from significant distortion. They shall have a uniform
cross-section throughout each continuous length. During concreting they shall be free from
1. DESCRIPTION
The work shall consist of furnishing all materials, equipment, and labour necessary for
conducting high-strain dynamic tests on driven and cast-in-place piles. The Contractor shall
appoint an Independent Specialist to conduct all testing and shall supply materials,
equipment and labour as specified, for work prior to, during, and after the tests all to the
approval of the Engineer. Testing procedures shall conform to ASTM D4945-89 unless
noted otherwise. The shaft used for the test will be instrumented and tested by the
Independent Specialist, as approved by the Engineer, meeting requirements outlined in the
ASTM D4945-89 specification as well as those outlined below.
3. SPECIALIST
Testing is to be performed by an accredited Specialist from a firm with a minimum of four
(4) year experience in dynamic load testing. The actual test shall be conducted and/or
supervised by a practicing Geotechnical Engineer with at least five (5) years of dynamic
testing experience. The firm selected by the Contractor must be approved by the Engineer.
The Specialist must supply the following testing instrumentation in addition to
instrumentation outlined in ASTM specification D4945-89 Section 5:
a) Pile Driving Analyzer (PDA)
b) Calibrated Strain Transducers
c) Calibrated Accelerometer
4. REPORTING RESULTS
The Specialist shall promptly submit a report of the testing results to the Engineer for
approval. The field results from at least one (CAPWAP) analysis (case Pile Wave Analysis
Program) shall be submitted. The CAPWAP analysis shall be performed by an experienced
and qualified Engineer. The report shall also provide the following:
a) Wave Equation analysis results obtained prior to testing
b) CAPWAP analysis result.
c) For each impact the maximum measured force, maximum calculated tension
force, transferred energy to the gauge location, corresponding stresses, and the
Case Method bearing capacity.
d) Assessment of the test result with respect to both pile capacity and integrity.
5. METHOD OF PAYMENT
The quantity to be paid for shall be the number of bored piles tested and accepted. Any item
indicated and not otherwise described hereto shall be considered subsidiary to the work item
and shall not be paid for separately.
6. BASIS OF PAYMENT
Payment shall be made for each test together with the relevant report accepted by the
Engineer at the contract price shown below. The payment shall constitute full compensation
for the cost of Pile Dynamic Testing, the cost of appointing an Independent Specialist, all
instrumentation, testing and testing equipment, analysis and reporting, tools, labour and all
other incidentals necessary to complete the work prescribed in this Item.
Payment will be made under:
Pay Item Description Unit
07350-01 Pile Dynamic Test for Precast Concrete Pile each
07350-02 Pile Dynamic Test for Bored Pile (Dia. 1,000mm) each
07350-03 Pile Dynamic Test for Bored Pile (Dia. 1,200mm) each
07350-04 Pile Dynamic Test for Bored Pile (Dia. 1,500mm) each
1. DESCRIPTION
This work consists of the construction of pre-stressed concrete structures and pre-stressed
concrete portions of composite structures in conformity with the design, lines, grades, and
dimensions shown on the drawings or as may be established by the Engineer in accordance
with this and other relevant specifications.
The work shall include the supply and installation of any items necessary for the particular
pre-stressing system to be used, including but not limited to ducts, anchorage assemblies and
grout used for pressure grouting ducts.
It shall include the manufacture, transportation, and storage of beams, slabs, and other
structural members of pre-cast concrete pre-stressed by either pre tensioning or
post-tensioning methods. It shall also include the installation of all pre-cast pre-stressed
members.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied to the works
covered by this Specification.
AASHTO M235 Epoxy Resin Adhesives
22TCN 272-05 Specification standard for Bridge design
AASHTO LRFD Bridge Design Specifications, Deflection Criteria for Girders, Section
2.5.2.6.2.
ASTM A421-91 Un-coated Stress Relieved Steel Wire for Pre-stressed Concrete;
ASTM A416-99 Steel Strand, Un-coated Seven Wire Stress Relieved Strand for
Pre-stressed Concrete.
ASTM A722M-07 Uncoated High Strength Bars for Pre-stressing Concrete
22TCN 247-98 Construction and Inspection of pre-stressed RC bridge girder
TCVN 9114:2012 Product of pre-prestressed concrete – Technical specification and
acceptance
2.2 MATERIAL FOR PRESTRESSED CONCRETE
2.2.1 GENERAL REQUIREMENT
All materials to be furnished and used, but not covered in this specification, shall conform to
the requirements stipulated in other applicable specifications.
2.2.2 PRESTRESSING STEEL
High tensile strength steel wire shall be stress relieved and shall conform to the requirements
of ASTM A421-91 or equivalent for Un-coated Stress Relieved Steel Wire for Pre-stressed
Concrete
High tensile steel strand with low-relaxation shall be weld free and stress relieved after
stranding and shall conform to the requirements of ASTM A416-99, EN 10138 or equivalent
Steel Strand, Un-coated Seven Wire Stress Relieved Strand for Pre-stressed Concrete.
ASTM A416-99 EN 10138
Nominal diameter (mm) 12.7 15.2 15.7 (super)
Cross sectional area (mm2) 98.7 140 150
Nominal weight (kg/m) 0.775 1.10 1.17
Tensile strength (MPa) 1,860 1,860 1,860
Minimum characteristic breaking load (kN) 183.7 260.7 279.0
Elastic modulus (GPa) 195
Maximum relaxation at 0.7 Rm (20°C) at 1,000 h 2.5
(%)
Contract – Volume 2 – Specification 7-57 07450
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
High strength steel bars shall confirm to the requirements of ASTM A722M or equivalent
for Uncoated High Strength Bars for Pre-stressing Concrete.
Testing of pre-stressing reinforcement shall be in accordance with the requirements of the
ASTM Specifications for the type of system intended to be used or subject to approval by the
Engineer.
Table 1 Stress Limits for Prestressing Tendons
Condition Tendon Type
Stress-Relieved Strand Low Relaxation Deformed
and Plain Strand High-Strength Bars
High-Strength Bars
Pretensioning
Immediately prior to 0.70 fpu 0.75 fpu -
transfer (fpt + ΔfpES)
At service limit state 0.80 fpy 0.80 fpy 0.80 fpy
after all losses (fpe)
Posttensioning
Prior to seating – short 0.90 fpy 0.90 fpy 0.90 fpy
term fs may be allowed
At anchorages and 0.70 fpu 0.70 fpu 0.70 fpu
couplers immediately
after anchor set (fpt +
ΔfpES + ΔfpA)
At end of the seating 0.70 fpu 0.74 fpu 0.70 fpu
loss zone immediately
after anchor set (fpt +
ΔfpES + ΔfpA)
At service limit state 0.80 fpy 0.80 fpy 0.80 fpy
after losses (fpe)
fpu – Specified tensile strength of pre-stressing steel (MPa)
fpy – Yield strength of pre-stressing steel (MPa)
2.2.3 ANCHORAGES FOR POST TENSIONING
All anchorage assemblies shall be subject to the approval of the Engineer.
All post-tensioned pre-stressing steel shall be secured at the ends by means of approved
permanent type anchoring devices. The Contractor shall submit information and details,
including test certifications for by the Engineer.
End anchorage devices (stress and dead anchors) shall be designed and manufactured for the
types of tendons to be used. They shall have a previous service record of performance and
durability when used on similar type work.
All anchorage devices for post-tensioning shall be capable of holding the pre-stressing steel
at a load producing a stress of not less than 95 percent of the guaranteed minimum tensile
strength of the pre-stressing steel.
Fixed anchorages for tendons in pre-cast beams shall be of steel bearing plate type while all
remaining anchorages shall be those capable of adjustment by means of a threaded anchor
head and ring nut.
It shall be the responsibility of the Contractor to confirm the required bursting
reinforcements in the local zone for the particular shape and design of the anchorage devices
proposed.
All externally exposed steel parts shall be protected from corrosion. All threaded parts and
fittings shall be protected by greased wrappings or plugs until used. Anchorages shall be
kept free from dirt, mortar, loose rust or other deleterious materials. Damaged anchorage
parts shall not be used.
Contract – Volume 2 – Specification 7-58 07450
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
2.2.4 DUCTS (SHEATH)
Ducting for internal tendons shall be fully compatible with the proposed pre-stressing
system. The ducts shall be fabricated from corrugated galvanized sheet steel or semi-rigid
conduit.
Minimum duct thickness shall be as follows:
* 26 gauge for duct diameter less than or equal to 67 mm
* 24 gauge for duct diameter greater than 67 mm
* 31 gauge for bar tendons
Ducts shall have grouting connections at each end and shall have vent/drains at all
intermediate high and low points, subject to the approval of the Engineer.
2.2.5 GROUT FOR DUCTS
Unless otherwise specified in other prevailing sections or subject to approval by the
Engineer as a result of grouting trials, the grout shall:
a) Consist only of ordinary Portland cement, water and expansive admixtures
approved by the Engineer and used in accordance with the manufacturer’s
instructions;
b) Have a water to cement ratio as low as possible consistent with the necessary
workability, and under no circumstances shall the water/cement ratio exceed
0.40;
c) not contain admixtures containing chlorides, nitrates or similar electrolytic
conducting materials.
Premixed grouting material shall be used.
The grout shall conform to the following Standard ASTM Tests:
Property Test Value Test Method
Total Chloride Ions Max. 0.08% by weight of ASTM C 1152
Cementitious material
Fine Aggregate (If utilized) Max. Size: No. 50 Sieve (300 ASTM C 33
micron)
Volume Change at 24 hours 0.0% to + 0.3% ASTM C 1090
and 28 days
Expansion 2.0% for up to 3 hours ASTM C 940
Compressive Strength at 28 45 MPa ASTM C 942
days (Average of 3 cubes)
Initial set of the grout 3 hours minimum ASTM C 953
12 hours maximum
Bleeding at 3 hours Maximum 0.0 % ASTM C 940
Permeability at 28 days Maximum 2500 coulombs at 30 ASTM C 1202
Volts for 6 hours
Fluidity test
Efflux Time from Flow Cone ASTM Method
(a) Immediately after 20 Seconds Minimum ASTM C 939
mixing 30 Seconds Maximum
(b) 30 minutes after mixing 30 Seconds Maximum ASTM C939
with remixing for 30
seconds
The Contractor shall perform the following tests and report the results to the Engineer:
(1) One pressure bleed test per day per lot.
3. CONSTRUCTION REQUIREMENTS
3.1 GENERAL
The Contractor shall assign an experienced technician, skilled in the use of pre-stressing
system, who shall supervise the work being performed in compliance with these
specifications and to the satisfaction of the Engineer.
The Contractor shall provide all equipment necessary for construction and pre-stressing. The
equipment shall be of a currently manufactured model, and shall be in good working
condition. A pre-stressing system approved by the Engineer shall be used. If hydraulic jacks
are used they shall be equipped with accurate pressure gauges. The combination of jack and
gauge shall be calibrated and a graph or table showing the calibration shall be provided to the
Engineer. Should other types of jacks be used, calibrated proving rings or other devices shall
be furnished so that the jacking forces may be accurately known.
The requirements for concrete construction in Specification - Concrete and Concrete
Structures shall be complied with, except as may be modified in this specification.
Pre-stressed concrete shall be formed, stressed, placed, cured, and protected at shops,
manufacturing plants, and locations where the fabrication of such members may be properly
inspected and controlled and approved by the Engineer.
Vertical alignment and girder lengths shown on the drawings represent dimensions at the
time of final creep. Deflection criteria for girders shall be in accordance with 22 TCN 272-05,
longitudinal deflections may be rectified by an appropriate approved method.
3.2 SAMPLING AND TESTING
3.2.1 GROUTING TRIALS
Where full scale trials are required they shall begin at least 21 days before the planned
commencement of the fixing of ducts for pre-stressing in the permanent works unless
otherwise specified in the Contract.
5 mm
Tolerance
5 mm
Length
10 mm
Center Location
5 mm
Surface levels of Slab
Surface level of base of hand-railing
5 mm
Compressive Strength Refer to subsection 07100
Surface Irregularity by 3m straight edge
Bowing
3.14 TESTING FREQUENCIES
Testing frequencies shall be as follows:
1) PC Materials
Test Item Content Frequency By
- Breaking/yield strength,
Mechanical Properties Elongation, Elastic Modulus,
Relaxation - 01 set / 20 ton by
Prestressing
As shown
- Helically placed outer wires - 01 set / 100 ton in
left
Dimensions & shall have uniform pitch of not Vietnam
Permissible Variations less than 12 and not more than - 01 set = 3 samples
16 times the nominal diameter
of the strand.
Wedge Plate Test
- - 01 set/delivery or
Requirements
Dimension
01set/1000 wedge
Independent
plates delivered at the
Laboratory
Surface - Site (whichever
in Vietnam
hardness lesser)
- 01 set = 3 samples
- 01 set/delivery or
- 01set/1000 wedges
Dimension
Wedge Performance Requirements
specified
- Independent
surface
Laboratory
hardness
in Vietnam
Minimum
-
depth of
surface
hardness
Maximum
core -
hardness
- Under static forces, single
Strand-Wedge
Requirements
Performance
Connection
sheet Site
Dimensions - Wall thickness
- 01 set/delivery/lot Inspector
- Visual check
- 01 set = 3 samples
Note: Low relaxation test on prestressing strand can be omitted if the manufacturer
submits the test results for the same low relaxation type of the same diameter of PC strand
for which the test was carried out within the past one year.
2) Grout
Test Item Trial Mixing Just Before Grout Injection
07450–05 PC Strand kg
07450–06 PC Steel Bar kg
1. DESCRIPTION
This Specification Section describes the requirements and provisions for the supply, bending,
fabrication and placing of steel reinforcement of the type, size, shape and grade required in
accordance with the drawings as specified or as may be required by the Engineer.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied to the works
covered by this Specification Section.
TCVN 1651:2008 Steel for the reinforcement of concrete
AASHTO M31 Deformed and Plain Billet-Steel Bars for Concrete
Reinforcement
AASHTO T68 Distillation of Cut-Back Asphaltic (Bituminous)
Products
AASHTO M164M High-Strength Bolts for Structural Steel Joints
AASHTO M232 Zinc Coating (Hot-Dip) on Iron and Steel Hardware
ASTM A82 Cold-Drawn Steel Wire for Concrete Reinforcement
ASTM A153 Zinc-Coating (Hot-Dip) on Iron and Steel Hardware
ASTM A615 Deformed and Plain Billet-Steel Bars for Concrete
Reinforcement
ASTM A185 Welded Steel Wire Fabric for Concrete
Reinforcement
ASTM A615 Deformed and Plain Billet-Steel Bars for Concrete
Reinforcement
ACI 315 Details and Detailing of Reinforcement
ASTM A722M-07 Uncoated High Strength Bars for Pre-stressing Concrete
2.2 MATERIAL FOR REINFORCING STEEL
2.2.1 REINFORCING BARS
All reinforcing steel bars shall be deformed billet steel and shall meet the requirements of
TCVN 1651:2008. In case items are not covered by TCVN 1651:2008 then AASHTO
M31 (ASTM A615), Grade 60 or equivalent shall be used, except for plain round reinforcing
bars for which Grade 40 shall apply. Testing shall be in accordance with TCVN 1651:2008
with AASHTO T68 as the equivalent standard. Unit stress calculations for bars having an
area differing by 6 percent or more from the nominal bar area shall be made using the
measured bar area.
2.2.2 SPIRAL REINFORCEMENT STEEL
Spiral reinforcement steel shall comply with the requirements of TCVN 1651:2008 for spiral
reinforcement in reinforced concrete compression members.
3. CONSTRUCTION REQUIREMENTS
3.1 HANDLING AND PLACING REINFORCEMENT
All reinforcement steel shall be protected as far as practicable from mechanical injury or
surface deterioration, from rusting or other causes from the time of shipment until it is placed.
Reinforcement steel stored at the site shall be laid on wood floors or pillows suitably spaced
so that no reinforcement steel shall be laid upon or come in contact with the ground. When
the weather is dry and the time for storage before installation is limited, housing may be
omitted, but if rainy or exceptionally humid weather occurs or is anticipated, bars shall be
stored under cover.
3.2 STEEL QUALITY AND SUPPLY
Representative samples of all reinforcement steel that the Contractor proposes to use in the
Works must be submitted together with the manufacturer’s certificates stating clearly for
each sample the place of manufacture, expected date and size of deliveries to the Site, and all
relevant details of composition, manufacture, strengths and other qualities of the steel before
work is commenced to the Engineer for his approval.
In the event a reinforcement steel sample under test fails to meet the specification
requirements at any time, or the Engineer considers that samples which were presented to
him for test were not truly representative, or if it becomes apparent that reinforcement steel
which has not been approved has been used on the Works, the Engineer may instruct the
Contractor to break out and remove completely all such sections of the work already
constructed using such suspect reinforcement steel.
All testing of reinforcement steel bars shall meet the requirements and specification limits of
the ASTM/AASHTO designation for the particular size, and grade of steel.
3.3 BAR LISTS AND BENDING DIAGRAMS
The Contractor shall provide detailed bar lists and bending diagrams to the Engineer for his
review and approval. Fabrication and bending of reinforcement shall not begin until such
lists have been approved. Any expense incidental to the revision of material furnished in
accordance with such lists and diagrams to make it comply with the design drawings shall be
borne by the Contractor.
1. GENERAL
1.1 DESCRIPTION
This work shall consist of furnishing all materials and constructing railings on bridges.
Railings constructed at each location shall conform to the type and details specified in the
Contract Documents for that location.
1.2 REFERENCE STANDARDS
ASTM A500 Standard Specification for Cold-Formed Welded and Seamless Carbon
Steel Structural Tubing in Rounds and Shapes
ASTM A36 Standard Specification for Carbon Structural Steel
ASTM A325 Standard Specification for Structural Bolts, Steel, Heat Treated
1.3 CONSTRUCTION
Unless otherwise permitted by the Engineer, railing shall not be placed until the centering or
falsework for the span has been released, rendering the span self-supporting.
1.4 LINE AND GRADE
The line and grade of the railing shall be true to that specified in the Contract Documents and
may include an allowance for camber in each span but shall not follow any unevenness in the
superstructure.
Unless otherwise specified in the Contract Documents, railings on bridges, whether
super-elevated or not, shall be vertical.
2. METAL RAILING
2.1 MATERIALS AND FABRICATION
2.1.1 STEEL RAILING ON CABLE STAYED BRIDGE
The materials shall conform to the standards specified in the Table 1or equivalent.
Fabrication of steel railings shall conform to the applicable requirements of Specification for
Bridge Design 22TCN 272-05 and AWS D1.5-2002 “Bridge Welding Code”
Table1 Materials for Steel Railing
Member Material Standards
1. DESCRIPTION
This work shall consist of furnishing and installing metal items in structures which are not
otherwise provided for.
The following miscellaneous metal works shall be carried out under the provision of this
section:
(a) Stairs, Ladder, Door and Access Hatch and Handrails
Stairs and ladders shall be installed inside the pylons as shown on the Drawings. Handrails
shall be installed on pylon crossbeam as shown in the Drawings. Access hatch shall be
provided at top of pylon and crossbeam. Ladders shall be installed at girder end to access to
the inspection way. All these facilities shall be fabricated with galvanized steel, stainless
steel, or aluminium shapes, bars and expanded metals as indicated on the Drawings.
(b) Inspection way, Platform for Electric Facilities, Cable Rack Support for
Electric and Communication Cables
Inspection way, platform for electric facilities, cable rack support for electric and
communication cables shall be furnished and installed as shown on the Drawings. All the
elements of inspection way shall be fabricated with galvanized steel shapes, bars and
expanded metals.
(c) Miscellaneous Metal
Miscellaneous Metal shall include anchors for roadway lighting poles, tie-down cable fixing,
steel covers for inspection holes (including steel cover, fixture, fittings and all other
incidentals).
2. MATERIALS
Miscellaneous metal items shall be constructed of materials conforming to the following
AASHTO (or ASTM) material specifications or JIS equivalent:
Table 1 Materials
Materials Specifications
Steel bars, plates, and shapes ASTM A 36/A 36M, Grade 36 (Grade 250)
Bolts and nuts ASTM A 307
High-strength bolts, nuts, and washers AASHTO M 164 (AASHTO M164M) (ASTM A
325 (ASTM A 325M))
Steel castings As per Article 11.3.5, "Steel Castings"
Grey iron castings AASHTO M 105 or ASTM A 48/A 48M, Class 30
Sheet metal Commercial quality
Expanded metal (with carbon steel) ASTM A569
Expanded metal (with stainless steel or Commercial quality
aluminium)
Steel tubes for piping ASTM A53(F)
Bronze Commercial quality
3. FABRICATION
Fabrication of miscellaneous metal items shall be performed in a manner in conformance
with the practice in modern commercial shops. Burrs, rough and sharp edges, and other
flaws shall be removed. Warped pieces shall be straightened after fabrication and
galvanizing.
5. MEASUREMENT
Measurement of miscellaneous metal shall be by the scale weight (mass) except for the
following items:
stairs, ladder, inspection ways, and handrails inside the pylons
Manhole door to box girder
Measurement of stairs, ladder, inspection ways and handrails to the pylons is as a lump sum,
since these works are composed of various metal types including stainless and structural
steels, and aluminium.
Measurement of manhole doors to box girders shall be measured by each completed door.
When requested by the Engineer, each delivery shall be accompanied with a certified weigh
master's ticket. Scale weight (mass) is not required when calculated weight (mass) is shown
in the Contract Documents, in which case this weight (mass) shall be used as the basis of
payment.
Measurement shall include the weight of galvanized bolts for connections, but the weight of
galvanizing on the bolts is not included.
6. PAYMENT
Payment shall be full compensation for furnishing all labour, materials, tools, equipment,
and incidentals, and for doing all the work involved in furnishing and installing
miscellaneous metal, complete in place, as specified in the Contract Documents, specified in
these Specifications, and as directed by the Engineer.
Pay Item Description Unit of Measurement
07660-01 Inspection Way, Platform for Electric Facilities, Cable Rack
Support for Electric and Communication Cables (under bridge) kg
07660-02 Stair, Ladder, Handrail, Door, and Access Hatch to Pylon lump sum
07660-03 Miscellaneous Metal kg
Contract – Volume 2 – Specification 7-81 07660
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
07660-04 Manhole Door to Box Girder each
1. DESCRIPTION
This Specification Section describes the requirements and procedures for the supply and
installation of bridge bearing pads as indicated on the drawings, or as may be directed by the
Engineer.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
AASHTO Standard Specifications for Highway Bridges and the following Standards in their
latest edition shall be particularly applied to the works covered by this Specification Section.
AASHTO M183 Structural Steel
ASTM A36 Carbon Structural Steel
ASTM A123 Zinc (Hot-Dip Galvanized) Coating on Iron and Steel
Products
ASTM A570 Steel, Sheet and Strip, Carbon, Hot-Rolled, Structural
Quality
ASTM A615 Deformed and Plain Billet-Steel Bars for Concrete
Reinforcement
ASTM C881 Epoxy-Resin-Base Bonding Systems for Concrete
ASTM C1107 Standard Specification for Packaged Dry,
Hydraulic-Cement Grout (Nonshrink)
ASTM D412 Vulcanized Rubber and Thermoplastic Rubbers and
Thermoplastic Elastomer Tension
ASTM D429 Rubber Property-Adhesion to Rigid Substrates
ASTM D518 Standard Test Method for Rubber
Deterioration-Surface Cracking ASTM D573 Rubber -
Deterioration in an Air Oven
ASTM D746 Brittleness Temperature of Plastics and Elastometers
by Impact
ASTM D1149 Rubber Deterioration - Surface Ozone Cracking in a
Chamber
ASTM D2240 Rubber Property - Durometer Hardness
ASTM D3182 Materials, Equipment, and Procedures for Mixing
Standard Compounds and Preparing Standard
Vulcanized Sheets
ASTM D3183 Preparation of Pieces for Test Purposes from Products
ASTM D3184 Evaluation of NR (Natural Rubber)
ASTM D3185 Evaluation of SBR (Styrene-Butadiene Rubber)
Including Mixtures With Oil
3. ELASTOMERIC BEARINGS
3.1 GENERAL
Elastomeric bearings shall consist of laminated elastomeric pads or assemblies of laminated
elastomeric pads as indicated on the Drawings and as specified herein.
60 5
ASTM Standard Physical Properties Value
D2240 Hardness, ASTM D2240
D412 Tensile strength, min.kg/cm2 175
Ultimate elongation, min.% 425
Heat Resistance
Change in durometer hardness, max.points + 15
D573, 70 HR. Change in tensile strength, max. % - 15
@ 100°C Change in ultimate elongation, max. % - 40
Compressive Set
D395. 22 hours @ 100°C max. % 35
Method B
4. MECHANICAL BEARINGS
Mechanical Bearings shall be pot type bearings, pivot bearings or pin bearings as shown on
the Drawings. Pot bearing movement bearings will normally have sliding surfaces of
stainless steel and polytetrafluorethylene and may also have been fitted with guide bars or
keyways.
Bearings shall have surface protecting in accordance with requirements and procedures
noted under Specification section 07800.
4.1 MATERIALS
4.1.1 STEEL
All steel, other than stainless steel, used in the manufacture of the bearings shall conform to
ASTM A709. The stainless steel used in the manufacture of the sliding surface shall conform
to ASTM A 240 (Grade 304) and have a minimum thickness of 0.91 mm and a surface finish
in the finished bearing better than or equal to 0.20 micrometers, and the sliding surface in
contact with PTFE sheet shall be polished no less than 0.50 micrometers.
4.1.2 RUBBER PLATE AND SEAL RING
Rubber plate and compressive seal ring for pot bearings shall be Chloroprene Rubber with
material properties shall be as shown in the following Table.
Properties of Rubber Plate and Seal Ring
Item Unit Rubber Seal Ring Test
Plate Method
Shear Modulus Kgf/cm2 8±1.0 - ASTM
D412
Method A
Tensile Strength Kgf/cm2 - > 50 ASTM D
412 C
Elongation % > 400 > 200 ASTM D
412 C
Aging Test 25% elongation % -10 to +100 ASTM
(100ºC×70hr) stress change rate D573
Elongation change % - 50 max.
rate
Permanent compression deformation % 35 max - ASTM D
rate 395 B
(100ºC×20hr)
5. BEARING INSTALLATION
The bearings shall be clearly marked with their longitudinal and transverse axes, their type
number and their intended locations in the Works.
Unless otherwise approved by the Engineer bearing beds shall be of non-shrink grout
conforming to ASTM C1107, Grade A with compressive strength 50MPa, and should be
proposed by the Contractor for approval by the Engineer. Grout should have flow
characteristics such that the volume of the bed or plinth is completely filled with
homogeneous material when placed at the ambient temperatures, and having physical and
chemical properties compatible with the adjoining surfaces. Proposals for the thickness and
type of bearing plinths and beds shall be submitted by the Contractor and approved by the
Engineer in advance of bearing installation.
Anchor bolts shall unless otherwise specified on the Drawings or otherwise approved by the
Engineer conform to ASTM F1554 Grade 55. Anchor bolts shall be either threaded full
length or equipped with a satisfactory mechanical end anchorage. Details for any mechanical
end anchorage shall be included in the shop plans submittal for prior approval. All nuts shall
be ASTM A563 Heavy Hex Grade DH.
Steel dowels shall be provided and installed in accordance with requirements and with
accessories noted on the drawings. Dowels shall be smooth plain billet-steel bars
conforming to requirements of ASTM A615, yield strength min 400 MPa and shall be zinc
(hot-dip galvanized) in accordance with ASTM A123. Dowels 32mm diameter or larger
shall be carbon steel grade 1035 (yield strength min 305 MPa, tensile strength min 510 MPa,
elongation min 23%, Brinell hardness 140 ≥ HB ≥ 200).
Rubber filler to dowel caps shall be natural rubber with shore hardness 53A ± 5 bonded to
the inner and outer sleeves. Dowel top caps shall comprise steel sleeves in carbon steel pipe
for high temperature service to ASTM A106 Grade B (yield strength min 240 MPa, tensile
strength min 415 MPa, elongation min 30% longitudinal, min 16.5% transverse). The
Contractor can propose alternative / equivalent materials or solutions for dowel bars and
fittings subject to approval by the Engineer.
Dowels may be cast-insitu as shown on the drawings or drilled and grouted with an approved
epoxy compound. If dowels are drilled and grouted:
holes shall provide at least 10 mm in diameter greater than the largest diameter of the
dowel;
holes shall be thoroughly cleaned with compressed air and water prior to grouting of
dowels so as to remove all loose or extraneous materials;
the epoxy compound used shall be ASTM C881, Type IV or approved equivalent
and mixed and placed in accordance with manufacturer’s requirements.
Bearings shall not be dismantled. Any transit bolts, straps or other temporary fixing shall not
be removed until the bearing is fixed in its final position and the structure immediately above
6. TESTING OF BEARINGS
The testing of selected bearings shall be arranged with the Engineer prior to their inclusion
in the Works. The testing shall be done at an independent testing facility approved by the
Engineer.
6.1 MECHANICAL BEARING TESTS
6.1.1 VERTICAL PROOF LOAD TEST OF COMPLETE BEARING
The vertical proof load shall be 1.5 times the maximum vertical load specified in the bearing
schedule. The proof load shall be maintained for a minimum period of three minutes.
6.1.2 HORIZONTAL PROOF LOAD TEST OF COMPLETE BEARING
Bearings, which are required to resist lateral forces, shall be further tested to 1.5 times the
lateral load stated on the Drawings while loaded in compression to the minimum vertical
load shown on the Drawings. The load shall be maintained for three minutes.
6.1.3 ROTATION TEST OF COMPLETE BEARING
The bearings shall be tested in rotation to the value for rotation shown on the Drawings while
being loaded in compression to the maximum vertical load shown on the Drawings.
Bearings, which are required to resist lateral forces, shall also have the specified lateral load
stated on the Drawings applied during this test.
The direction of application of the lateral load and the axis of rotation shall be compatible
with the in-service loads and rotational requirements. The lateral load shall be applied using
a calibrated sliding surface to minimize any frictional restraint. All PTFE and stainless steel
interfaces shall be lubricated prior to the test. The test loads shall be maintained for three
minutes.
07810-01 Pot Bearing including anchor bolts, Type 1 (capacity, fix / movable
as shown in BOQ) each
07810-02 Pot Bearing including anchor bolts, Type 2 (capacity, fix / movable
as shown in BOQ) each
07810-03 Pot Bearing including anchor bolts, Type 3 (capacity, fix / movable
as shown in BOQ) each
Etc.
07820-01 Non-shrinkage mortar for bearing pads m3
07820-02 Tapered steel filler plate for pot bearing installation (nominal 30mm
thickness) ton
1. DESCRIPTION
The work under this Specification Section consists of the supply, transport and installation
of waterproofing membranes in accordance with the information, procedures and details
stated in this Specification Section and in conformance with the drawings, and as required by
the Engineer. Waterproofing membranes may include sprayed membranes, painted
waterproofing, and sheet membranes.
The Contractor shall apply bituminous membranes and deck waterproofing membranes to
all surfaces as indicated on the drawings, including but not limited to wing walls, retaining
walls, abutment walls, and similar foundations, and to the bridge decks.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied to the works
covered by this Specification Section.
AASHTO M243 Field Applied Coating of Corrugated Metal Structural
Plate for Pipe, Pipe Arches, and Arches
ASTM D41-05 Asphalt Primer Used in Roofing, Damp proofing, and
Waterproofing
ASTM D173-03 Bitumen Saturated Cotton Fabrics Used in Roofing and
Waterproofing
ASTM D449-03 (Type III) Standard Specification for Asphalt Used in
Damp proofing and Waterproofing
ASTM D517-98 (2003) Standard Specification for Asphalt Plank
2.2 BRIDGE DECK WATERPROOFING MEMBRANE
All the materials to be used for furnishing and installing the deck waterproofing membrane
shall be certified by the manufacturer and shall be approved by the Engineer before they are
used in the Works.
The Contractor must provide evidence to demonstrate that the proposed deck waterproofing
system meets the following performance criteria and mitigates concerns regarding common
problems such as leakage, poor bonding or softening of the membrane.
Impermeable to water
Good adhesion to the deck (at least 1MPa after 2 hours cure)
Good adhesion to surfacing
Capable of bridging shrinkage cracks in concrete (up to 2mm)
Tolerant of deck texture and detail
Tough to withstand site damage including paving equipment
Safe to apply
Able to withstand elevated surfacing temperatures
Applied over a wide range of ambient conditions
3. CONSTRUCTION REQUIREMENTS
3.1 PRODUCT DELIVERY, STORAGE AND HANDLING
The Contractor shall deliver products to the job site in their original unopened containers
clearly labelled with the manufacturer’s name, brand designation, type and class as
applicable.
The Contractor shall store products in an approved dry area and shall protect them from
contact with soil and from exposure to the elements. Products shall be kept dry at all times.
Products shall be handled in a manner that will prevent breakage of containers and damage
to products.
3.2 PREPARATION OF SURFACE
The surface to which the waterproofing is to be applied shall be cleaned of all loose and
foreign materials, dirt, grease or oil and shall be dry. When necessary the Engineer may
require the surface to be scrubbed with water and a stiff brush, after which the surface shall
be allowed to dry before application of the primer.
Concrete to which the deck waterproofing membrane is to be applied shall be prepared in
accordance with the manufacturer’s recommendations.
3.3 APPLICATION
3.3.1 DECK WATERPROOFING MEMBRANE
The deck waterproofing membrane shall be a proprietary waterproofing system of the
thickness indicated on the drawings and as approved by the Engineer, and shall be applied in
Contract – Volume 2 – Specification 7-95 07840
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
accordance with the manufacturer’s recommendations. The installation shall be undertaken
by skilled operatives as approved by the product manufacturer. Acceptance testing shall
include testing by an electronic pinhole detector to demonstrate the absence of pinholes.
3.3.2 BITUMINOUS WATERPROOFING MEMBRANE
The Contractor shall furnish and install the bituminous membrane as specified herein to all
surfaces indicated on the Drawings including, but not limited to, abutment, wing-walls,
retaining walls, and similar foundations where directed by the Engineer. The work shall
include the supply and application of bituminous membranes on all surfaces specified to
receive waterproof membrane.
Concrete or other surfaces, which are to be protected by bituminous membrane, shall be
thoroughly cleaned before the primer is applied.
They shall then be brush or spray painted with two coats of tar or asphalt primer for
absorptive treatment. Below ground not less than two coats shall be applied at a rate of 0.56
litters per square meter of surface.
On the well-primed surface one application of tar or asphalt seal coat shall be applied by
brush at a rate of 0.45 liters per square meter. Care shall be taken to confine all paints to the
areas to be waterproofed and to prevent disfigurement of any other parts of the structure by
dripping or spreading of the tar or asphalt.
1. DESCRIPTION
This Specification Section describes the requirements for expansion and fixed joints as
indicated on the drawings, including pre-moulded joint filler and joint sealer. The Contractor
shall furnish all required materials and install expansion joints, fixed joints, pre-moulded
joint filler and joint sealer in accordance with the details indicated on the drawings and as
specified herein. This work shall include the supply and installation or application of all
necessary hardware including anchor bolts and studs, sealants, adhesives, epoxies, and other
accessories.
Expansion joints are generally proprietary systems and for this reason the specification
requirements are indicative only. The Contractor may propose for consideration by the
Engineer alternative systems for consideration that meet other standards or use other
material types but should be able to demonstrate that the proposed joint systems are durable,
have proven reliability, and have equivalent or better performance.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied to the works
covered by this Specification Section.
AASHTO M297 Preformed polychloroprene elastomeric joint seals for
Bridges
ASTM A36 Standard Specification for General Requirements for
Rolled Structural Steel Bars, Plates, Shapes, and Sheet
Piling
JIS G 5502 Spheroidal Graphite Iron Castings
ASTM A123 Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel
Products
ASTM A536 Standard Specification for Ductile Iron Castings
ASTM A588 Standard Specification for High-Strength Low-Alloy
Structural Steel, up to 345 MPa Minimum Yield Point,
with Atmospheric Corrosion Resistance
ASTM A709 Standard Specification for Structural Steel for Bridges
ASTM D395 Rubber Property—Compression Set
ASTM D412 Vulcanized Rubber and Thermoplastic Rubbers and
Thermoplastic Elastomer - Tension
ASTM D471 Rubber Property - Effect of Liquids
ASTM D994 Preformed Expansion Joint Filler for Concrete
(Bituminous Type)
ASTM D1149 Rubber Deterioration - Surface Ozone Cracking in a
Chamber
ASTM D2240 Rubber Property - Durometer Hardness
50 5
ASTM D412 Elongation at break 400%
ASTM D2240 Hardness (Durometer A)
ASTM D395 Compression set 20% max.
(Method B) 22 hours at 70°C
ASTM D1149 Ozone resistance: No cracks
Exposure to 100 ppm ozone for 70 hours at 38°C
sample under 20% strain
ASTM D471 Oil deterioration: 120% max.
Volume increase after immersion in ASTM Oil # 3
for 70 hours at 100 °C
The dimensions of the neoprene portion of the joint shall be correct to zero millimeters under
and plus 6-mm over in width and length, and from zero millimeters under to plus 3-mm in
thickness of the exterior dimensions required on the drawings, measured at 21°C.
When test specimens are cut from the finished product a 10-percent variation in Physical
Properties will be allowed.
2.2.2 FINGER JOINTS
Finger joints shall have movement ranges of between 100mm (+/- 50 mm) to 450 mm (+/-
225mm) according to model and comprise cantilever interlocking steel fingers. Water
tightness is guaranteed by an elastomeric drainage channel.
Material for the steel fingers shall be either spheroidal graphite iron casting to ASTM A536
grade 65-45-12 or JIS G5502 grade FCD 450-15, or steel plate to ASTM A588 or ASTM
A709 Grade 50 or as otherwise approved by the Engineer.
The running surface of finger joints shall be treated to provide anti skid resistance through
application of a multilayered epoxy resin coating incorporating alumina crystals, or similar
method to the approval of the Engineer. The Contractor shall provide evidence of testing to
demonstrate the durability of the anti skid coating.
2.2.3 FIXING
The sealant for sealing joints between the expansion joint units, along the edges of the
expansion joint, and the bolts and plugs shall be a high solid, one-part polyurethane based
sealant that cures quickly, without shrinkage, into a rubber with high elongation
characteristics and excellent recovery.Sealant shall be capable of bonding to concrete, steel,
and neoprene without the use of a primer. When cured, the sealant shall possess excellent
abrasion resistance and shall resist attack by salt, oil, and road chemicals. The sealant to be
used shall meet the requirements of the manufacturer of the neoprene expansion joint.
The flexible epoxy for filling voids around the nut fasteners shall consist of a
two-component flexible epoxy sealant having the following physical properties:
Base Material: Flexibilized Epoxy Resin
Flexible epoxy shall be supplied either in cans or preassembled cartridges. Flexible epoxy
shall meet the requirements of the manufacturer of the expansion joint. Flexible epoxy shall
also be compatible with and have the physical characteristics when cured, similar to the
neoprene of the joint.
The adhesive/sealant bedding epoxy for bonding the expansion joint to concrete or steel
shall be supplied in pre-measured cartridges or cans and shall consist of a two-component
flexible epoxy having the following physical properties:
Base Material: Epoxy Resin
Tensile Strength: 211 kg/cm2
Elongation: 7% at 24°C
Water Absorption: 1.0% maximum
Bond Strength to concrete: Concrete fails before bond
Structural steel anchors shall be fabricated and hot dip galvanized in accordance with the
requirements of ASTM A123.
Anchor bolts for joint seals shall be hot dip galvanized in accordance with ASTM A153
commercial grade bolts set in epoxy mortar in holes cored in the deck in accordance with
approved shop drawings.
The surface of holes cored in the concrete shall be carefully prepared to provide a cleaned
textured surface to which the epoxy mortar can successfully bond. Faces shall be
mechanically tooled until surface glaze and contamination have been removed; dusted to
remove all residues; dried thoroughly and then primed with hydrophobic epoxy resin
immediately prior to setting the anchor bolts in epoxy mortar. Bolts shall be degreased with
white spirit alcohol and dried thoroughly. Coring and setting the anchor bolts shall not be
done until a minimum of 7 days after concrete is poured.
Epoxy mortar shall consist of a mixture of aggregate and epoxy binder. Aggregate shall
consist of clean, hard quartzite particles with a maximum size of 2 millimeters. Aggregate
shall be dried until the moisture content is less than 0.2 percent by weight and then shall be
sealed in plastic containers until required for mixing on site. Binder for epoxy mortar shall
be two part, cold curing, solventless epoxy produced by an approved manufacturer. Primer
shall be compatible with the epoxy resin binder and shall be supplied by the same
manufacturer. The type of resin selected shall be that recommended by the manufacturer for
this application and shall meet the requirements of the supplier of the component on which it
is to be used.
Components of the epoxies shall be proportioned, mixed, applied and cured strictly in
accordance with the manufacturer’s printed recommendations. Mixing shall be carried out
with an efficient mechanical device which ensures that all components are fully dispersed
and wetted. The two parts of the epoxy binder for the mortar shall be thoroughly mixed first
without frothing and the aggregate added progressively. Mixed epoxy mortar which has
begun to cure before it has been placed and compacted, will be rejected and a fresh batch
shall be mixed.
2.3 SUBMITTALS
The Contractor shall submit to the Engineer, for his approval, complete Shop Drawings of
all expansion joints. The Shop Drawings shall include a movement chart showing the total
anticipated movement of the structure and the required setting width of the joint assembly at
various temperatures. All movements due to shrinkage, creep, mid-slab deflection, and
similar data, may not be incorporated into this chart but shall be considered by the
Contractor and approved by the Engineer prior to final installation and adjustment.
3. CONSTRUCTION REQUIREMENTS
3.1 METHOD OF CONSTRUCTION AND INSTALLATION
The Contractor shall obtain installation instructions from the supplier of the expansion joint
material and comply with the instructions provided for the installation of the joint. The
adequacy of the joint design and installation details shall be subject to the approval of the
Engineer. The Contractor shall obtain the technical assistance of a field representative from
the manufacturer of the joint during its installation. Proper adjustment shall be made for
temperature at the time of installation.
Concrete on which expansion joints are to be set shall be dry, clean and free from dirt, grease,
latency and contaminants; level and sound with no broken or spilled concrete. No joint shall
be placed until the Engineer has inspected and approved the seat conditions.
After coating the seat area with the specified sealant adhesive, the joint shall be positioned
over the anchor bolts and the nuts securely tightened. All loose or long anchor bolts shall be
corrected in a manner approved by the Engineer.
All joints between units, around connecting bolts, and cavity plugs shall be carefully sealed
with sealant in a neat workmanlike manner to keep out water and protect against corrosion.
Neoprene surfaces to be in contact with sealant shall be buffed at the plant or wire brushed
prior to installation to provide a bonding surface for the sealant.
Prior to filling the space in the bolt wells, the Engineer shall inspect the anchor bolts and the
tightening of the nuts to the manufacturer’s specified torque. Any wells sealed without the
Engineer’s approval shall be opened and resealed after approval at the Contractor’s expense.
The finished joint shall present a smooth, neat appearance with no protruding bolts or rough
joints. Excess sealant shall be wiped or scraped away before it becomes hard.
3.2 PRE-MOULDED JOINT FILLER
Pre-moulded joint filler shall conform to the requirements of ASTM D994 with a nominal
thickness of 20 mm. Joint filler must be compatible with joint sealant.
The filler for each joint shall be furnished in a single piece for the full depth and width
required for the joint. When the use of more than one piece is required for a joint, the
abutting ends shall be fastened securely and held accurately to shape by stapling or other
positive fastening means.
3.3 JOINT SEALER
Joint sealer shall be in accordance with ASTM D6690.
Each lot or batch of sealing compound shall be delivered to the job site in the manufacturer's
original sealed container. Each container shall be marked with the manufacturer's name,
batch or lot number, and the safe heating temperature and shall be accompanied by the
manufacturer's certification stating that the compound meets the requirements of this
specification.
1. DESCRIPTION
This work consists of the provision and installation of the bridge drainage system. Work
shall be in accordance with the drawings subject to the approval of the Engineer.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied to the works
covered by this Specification Section.
ASTM D1785 Standard Specification for Polyvinyl Chloride (PVC)
Plastic Pipe
ASTM A53 / A53M Standard Specification for pipe, steel, black and
hot-dipped, zinc coated, welded and seamless
ASTM A48 Specification for grey iron casting, Class 50
ASTM A36 Standard Specification for Carbon Structural Steel
ASTM A240 Standard Specification for Chromium and
Chromium-Nickel Stainless Steel Plate, Sheet, and
Strip for Pressure Vessels and for General
Applications.
2.2 DRAIN PIPES
Pipe and fittings shall be of the size and types indicated on the drawings. If not indicated on
the Drawings, PVC drainage pipes shall be to ASTM D1785 , Type I, Grade 1, Schedule 80,
and steel drainage pipes shall be to ASTM A53 / A53M Type F, schedule 80, hot dip zinc
coated.
2.3 CATCH PIT AND GRATING
Catch pits and gratings shall be Gray Iron Casting with reliability test greater than grade 50
as required by AASHTO A48 for heavy items, of the shape and size and with the connection
requirements as indicated on the drawings.
2.4 FIXING BRACKETS
The materials for fixing brackets shall conform to ASTM A36, hot dip galvanized to ASTM
A153 for steel drainage pipes, and ASTM A240 Grade 304 for PVC drainage pipes, or
equivalent standards to the approval of the Engineer.
2.5 SUBMITTALS
The Contractor shall submit his method statement to the Engineer for his approval. The
method statement shall include but no be limited to arrangements and details of pipes fittings
and joints, means of casting the catch pit into the structure and details of fixing pipe brackets
to concrete surfaces.
The Contractor shall submit to the Engineer for his approval manufacturer’s certificates
confirming that all materials meet the requirements of the relevant standards and
specifications. Certificates are required for pipes and all pipe fittings and the catch pit and
grating.
1. DESCRIPTION
This work consists of the preparation and supply of cement mortar in accordance with all the
requirements of this Specification Section for masonry and for any other incidental works.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied to the works
covered by this Specification section.
AASHTO M45-06 Aggregate for Masonry Mortar
AASHTO M85-06 Portland Cement
ASTM C207-06 Hydrated Lime for Masonry Purposes
TCVN 3121: 2003 Cement Mortar – Specification standard for testing
2.2 MORTAR
The materials to be used for preparation of mortar shall fulfil the following requirements:
a) Cement shall conform to the requirements of AASHTO M85-06.
b) Fine aggregate shall conform to the requirements of AASHTO M45-06.
c) Hydrated lime shall meet the requirements for residue, popping and pitting, and
water retention specified for Type N lime in ASTM C207-06.
d) Water shall conform to the requirements for concrete under Specification
Section 07100 “Concrete and Concrete Structures”.
e) Unless otherwise directed by the Engineer, masonry mortar shall be composed
of one part Portland cement and three parts fine aggregate by volume, to which
hydrated lime may be added in an amount equal to 10 percent of the cement by
weight. Mortar shall have a compressive strength of at least 50 kg/cm2 at 28
days.
3. CONSTRUCTION REQUIREMENTS
All the materials except water shall be mixed, either in a tight box or in an approved mortar
mixer, until the mixture assumes a uniform color, after which water shall be added and the
mixing continued for a five to ten minutes period. The quantity of water shall be such as to
produce a mortar of the required consistency but shall be no more than 70 percent of the
weight of the cement used.
Mortar shall be mixed only in those quantities required for immediate use. If necessary,
mortar may be re-tempered with water within 30 minutes from the time of the initial mixing
process. Re-tempering after this time will not be permitted.
Mortar that is not used within 45 minutes after the water has been added shall be discarded.
1. DESCRIPTION
This work consists of the provision and planting of grass, flowers, shrubs and trees at
locations shown on the Drawings, or as indicated by the Engineer.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied.
ASTM C602-07 Agricultural Liming Materials
2.2 GRASSING, TREES AND SHRUBS FOR PLANTING
2.2.1 GRASSING
(a) Grass seed
The Contractor shall submit for the Engineer’s approval a selection of available suitable seed
for grass cover. Seed shall be free from disease, mildew or mould and clean of any noxious
weed seed. All selected seed shall be obtained from a reputable approved source.
(b) Sodding
The species of grass selected shall be rapid spreading, free of disease and noxious weeds and
shall be deep rooted. The source of sods will be approved by the Engineer before cutting and
delivery to the Project and the Contractor shall notify the Engineer not less than 3 days
before cutting of sods begins. Sods shall be planted with their root system substantially
undamaged and cut into blocks with moist earth in which they have grown. Sods shall be laid
within 5 days of cutting. Sod blocks shall be hauled and stored in such manner that they will
be protected from direct sunrays, provided with air circulation, and prevented against drying.
(c) Sprigs
These shall be healthy living stems (stolons or rhizomes) with attached roots or perennial
turf forming grasses such as Buffalo, Kikuyu, Paspalum, Carpet grass harvested without
adhering soil. They shall be obtained from approved sources which are quick spreading and
capable of forming a thickly matted growth.
2.2.2 TREES AND SHRUBS FOR PLANTING
The plants shall comply with the following requirements:
- Height of trees shall be between 3.0 m and 4.0 m, root bulb shall be removed with care,
bound in jute bags, with soil root bulb size of 60 x 60 x 60 cm.
- Height of shrubs shall be not less than 120 cm, width of canopy 0.8-1.2m, soil root bulb
size of 30 x 30 x 30 cm.
- When dispatching trees to the site the trees shall be tied to support posts or similar in
order that the trees are not damaged.
- Plants shall be free of disease, infestation and shall have good healthy branches.
- Planting holes: minimum size of 100 x 100 x 100 cm for trees, and 50 x 50 x 50 cm for
shrubs and ornamental plants.
Shrubs shall be of species suitable for the particular local environment and for planting in the
median of the highway. Species of the type “Nemimm Oleamder L.” or “Cassia sp” or other
similar species approved by the Engineer shall be used. Species shall be capable of providing
a dense growths and a height of 2m at maturity
3. CONSTRUCTION REQUIREMENTS
3.1 HARVESTING
The Contractor shall notify the Engineer at least 5 days before sods are to be harvested, and
the source shall be approved by the Engineer before harvesting begins.
To begin harvesting, grass and woods shall be mowed to a height of 50 to 75 mm and all
clippings removed. Sods shall then be loosened by cross-disking, shallow ploughing or other
acceptable methods. After being loosened from the soil, sods shall be gathered in small piles
or windrows, watered and kept moist until planted.
Not more than 24 hours shall elapse between harvesting and planting, except that when
weather or other uncontrollable condition interrupts the work, in which case additional time
may be permitted, provided that the sods are still moist and viable. Sod, shrubs and trees that
have heated in stockpiles, permitted to dry out or otherwise seriously damaged during
harvesting or delivery shall be immediately rejected and disposed of as directed by the
Engineer.
3.2 ADVANCED PREPARATION AND CLEANUP
After grading and before applying fertilizer and ground limestone, the areas to be sodged
shall be racked or otherwise cleared of stone larger than 50 mm in diameter, sticks, stumps
and other debris which might interfere with sodding, growth of grass, or subsequent
maintenance of grass-covered areas. If any damage by erosion or other causes has occurred
after grading of areas and before the application of fertilizer and ground limestone, the
Contractor shall repair such damage. This may include filling gullies, smoothing
irregularities, and repairing other incidental damage.
3.3 TOPSOIL PLACEMENT
Placement of topsoil shall be carried out in accordance with the provisions of Specification
Section 08300 “Topsoiling”.
3.4 APPLYING FERTILIZER AND GROUND LIMESTONE
Following advance preparation and cleanup, fertilizer shall be uniformly spread at a rate
approved by the Engineer.
If the use of ground limestone is required, it shall be spread at a rate approved by the
Engineer.
Materials shall be incorporated into the soil to a depth of not less than 50 mm by disking,
racking, or other methods acceptable to the Engineer. Stones larger than 50 mm in diameter,
large clods, roots, and other litter brought to the surface by this operation shall be removed.
On steep slopes where fertilizer and ground limestone cannot be incorporated effectively by
mechanical equipment, they may be applied with power sprayers, blower equipment or other
approved method and need not be incorporated into the soil.
3.5 PLANTING
(a) General
Works shall not take place until tree planting in the area has been completed. Surfaces shall
be scarified and shaped after removing debris, gravel and weeds. All stones of more than 3
cm diameter shall be removed. The surfaces shall be made up as necessary with good quality
topsoil so as to ensure that the finished thickness of the work (including any sod or top
dressing) is not less than 30 cm. For grassing on embankments made of erodible material, a
cohesive material shall be incorporated with clay content at least 25% and plasticity index at
1. DESCRIPTION
This work consists of the preparation of the ground surface for topsoil application, removal
of topsoil from areas to be stripped on the site or from approved sources off the site, and
placing and spreading of the topsoil on prepared areas.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied to the works.
ASTM C117-04 Materials Finer than 75-μm (No.200) Sieve in Mineral
Aggregates by Washing.
2.2 MATERIALS FOR TOPSOIL
Topsoil shall be the surface layer of soil with no admixture of refuse or any material toxic to
plant growth, and it shall be reasonably free from subsoil and stumps, roots, brush, stones
(50 mm or more in diameter), clay lumps or similar objects.
Brush and other vegetation that will not be incorporated into the soil during handling
operations shall be cut and removed.
Ordinary sods and herbaceous growth such as grass and weeds are not to be removed but
shall be thoroughly broken up and intermixed with the soil during handling operations.
The topsoil or soil mixture, unless otherwise specified or approved, shall have a pH range of
approximately 5.5 to 7.6.
The organic content shall be not less than 3% but not higher than 20%.
The material passing the 0.075 mm sieve, as determined by the wash test in accordance with
ASTM C117-04, shall be not less than 20% but not higher than 80%.
The Contractor may amend natural topsoil with approved materials and methods to meet the
above specifications.
2.3 OBTAINING TOPSOIL
Prior to the stripping of topsoil, briars, stumps and large roots, rubbish or stones found on
such areas, which may interfere with subsequent operations, shall be removed.
Heavy sod or other cover, which cannot be incorporated into the topsoil by disking or other
means, shall be removed.
When suitable topsoil is available on the site, the Contractor shall remove this material from
the areas. The topsoil shall be spread on areas already tilled and smooth graded, or
stockpiled in areas approved. Any topsoil stockpiled by the Contractor shall be re-handled
and placed without additional compensation. Any topsoil that has been stockpiled on the site
by others, and is required for top soiling purposes, shall be removed and placed by the
Contractor. The sites of all stockpiles and areas adjacent thereto which the Contractor has
disturbed, shall be graded if required and put into a condition acceptable for seeding.
When suitable topsoil is secured off site, the Contractor shall locate and obtain the supply,
subject to the approval of the Engineer. Topsoil shall be hauled to the site of the work and
placed for spreading, or spread as required. Any topsoil hauled to the site of the work and
stockpiled shall be re-handled and placed without additional compensation.
3. CONSTRUCTION REQUIREMENTS
3.1 GENERAL
The areas to be topsoiled are shown on the Drawings or as indicated by the Engineer. If
topsoil is available on the site, the Engineer will approve the location of the stockpiles or
areas to be stripped of topsoil and the stripping depths.
Suitable equipment necessary for proper preparation and treatment of the ground surface,
stripping of topsoil, and for the handling and placing of all required materials shall be on
hand and in good condition.
3.2 PREPARING THE GROUND SURFACE
Immediately prior to dumping and spreading the topsoil on any area (except directly on a
rock surface), the surface shall be loosened by discs or spike tooth harrows, or by other
approved means, to a minimum depth of 50 mm to facilitate bonding of the topsoil to the
covered subgrade soil. The surface of the area to be topsoiled shall be cleared of all stones
larger than 50 mm in any diameter and all litter or other material which may be detrimental
to proper bonding, the rise of capillary moisture, or the proper growth of the desired planting.
Limited areas, as shown on the Drawings, which are too compact to respond to these
operations, shall receive special scarification.
Grades on the area to be topsoiled, which have been established by others as shown on the
Drawings, shall be maintained in a true and even condition. Where grades have not been
established, the areas shall be smooth graded and the surface left at the prescribed grades in
an even and properly compacted condition to prevent, insofar as practical, the formation of
low places or pockets where water will stand.
Areas to be topsoiled that require filling material to reach the lines and levels described on
the Drawings, shall be filled up to a level that top- soiling can be applied properly as
specified in this Specification Section.
3.3 PLACING TOPSOIL
Topsoil shall be evenly spread on the prepared areas to a uniform depth of 150 mm after
compaction, unless otherwise shown on the Drawings. Spreading shall not be done when the
ground or topsoil is excessively wet, or otherwise in a condition detrimental to the work.
Spreading shall be carried out so that seeding operations can proceed with a minimum of soil
preparation or tilling.
After spreading, any large, stiff clods and hard lumps shall be broken with a pulverizer or by
other effective means, and all stones or rocks (50 mm or more in diameter), roots, litter, or
any foreign matter shall be raked up and disposed of by the Contractor. After spreading is
completed, topsoil shall be satisfactorily compacted by rolling or by other approved means.
The compacted topsoil surface shall conform to the required lines, grades, and cross sections.
Any topsoil or other dirt falling upon pavements as a result of hauling or handling of topsoil
shall be promptly removed.
1. DESCRIPTION
This Item consists of the supply and installation of traffic signs in accordance with the
Drawings, or as required by the Engineer.
The traffic signs shall comply in all respects with the applicable Vietnamese signage
standards. The categories of road signs are designated as warning signs, regulatory signs,
and guide signs.
Traffic signs shall be classified as standard or non-standard. Standard signs have a standard
shape and a fixed range of sizes. All other signs are classified as non-standard signs.
The size is the length of the side of triangular signs (measured from the points of intersection
of the extension of the edges), the horizontal width of octagonal signs and the diameter of
circular signs.
All traffic signs shall be made retro-reflective by the application of retro-reflective sheeting,
fixed over aluminium sheeting as per these specifications.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied to the works
covered by this Specification.
QCVN 20:2010/BGTVT National technical regulation on aids to navigation
QCVN 39-2011/BGTVT National technical code on inland waterway signaling;
QCVN 41:2012/BGTVT National Technical Regulation on Road Signs and
Signals
22TCN 269:2000 Regulations on Navigation signals equipped for
domestic waterways in Viet Nam;
22TCN 331-05 Instruction panels on Expressway
TCVN 7887:2008 Specification for Retro-reflective sheeting for traffic
Control
AASHTO M111-04 Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel
Products
ASTM A53-07 Pipe, Steel, Black and Hot-Dipped, Zinc-Coated,
Welded and Seamless
ASTM B209-07 Aluminium and Aluminium-Alloy Sheet and Plate
ASTM D4956-07 Standard Specification for Retro-reflective Sheeting
for Traffic Control
ASTM E810-08 Standard Test Method for Coefficient of
Retro-reflection of Retro-reflective Sheeting
TCVN2101:1993 Painting – method to determine brightness of
retro-reflective sheeting
3. CONSTRUCTION REQUIREMENTS
3.1 CONFIRMATION OF DESIGN
The designs shown on the Drawings shall be subject to amendment, and confirmation of the
details shall be obtained from the Engineer before any signs are made.
3.2 APPLICATION OF SHEETING TO THE SIGN PLATE
The preparation of the sign plate, and the application of the sheeting to the plate, shall be
done in accordance with the sheeting manufacturer’s instructions. The material shall cover
the sign surface evenly and shall be free from twists, blisters, cracks and folds. Cut-outs to
produce legends and borders shall be bonded with the sheeting in the manner specified by
the sheeting manufacturer.
3.3 WARRANTY
The Contractor shall obtain the following from the sheeting manufacturer and then submit
the same to the Engineer:
a) A Lot Certificate stating that the sheeting material lot being supplied to the sign
supplier under the purchase order conforms to the standards specified herein for
retro-reflective sheeting, and
b) A seven-year warranty for satisfactory field performance including stipulated
retro-reflectance of the retro-reflective sheeting.
In addition, a seven-year warranty for satisfactory in-field performance of the finished sign
inclusive of the letters / legends and their bonding to the sheeting shall be obtained from the
sign supplier and passed on to the Engineer, who shall keep it until the expiration of the
Defects Liability Period of the Contract (the time when the warranty will be transferred to
the Client). The warranty shall place the obligation on the sheeting manufacturer, as well as
the sign supplier, to replace, repair, or restore the retro-reflective efficiency in any case of
defects. All signs shall be dated during fabrication with an indelible marking to indicate the
type of sheeting used, the name of the manufacturer, and the start date for the warranty.
Warranty shall be provided in the original and shall have legal jurisdiction in Vietnam.
3.4 ERECTION OF POSTS
The posts shall be erected vertically in position inside the formwork of the foundation block
prior to the placing of the concrete and shall be adequately supported by bracing to prevent
movement of the post during the placing and setting of concrete. The foundations shall be as
shown on the Drawings or as directed by the Engineer. After the concrete has set sufficiently,
the spaces around the concrete foundation shall be refilled to the required elevation with
suitable material, which shall be thoroughly tamped in layers of not more than 150 mm
thickness. Surplus excavated material shall be disposed of by the Contractor as directed by
the Engineer.
1. DESCRIPTION
This work consists of the supply and construction of posts and guardrails
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be applied to the works.
QCVN 41:2012/BGTVT National Technical Regulation on Road Signs and
Signals
TCVN 5729-97 Specification for expressway design
AASHTO M111-04 Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel
Products
AASHTO M183 Structural Steel
AASHTO M232-06 Zinc Coating (Hot-Dip) on Iron and Steel Hardware
2.2 GUARDRAILS
The rail shall be corrugated sheet steel beams of the type, section and thickness indicated on
the Drawings. All rails shall be free from abrasions, rough or sharp edges and shall not be
kinked, twisted or bent.
Guardrails shall be made of steel with a thickness of no less than 4mm and shall:
a) elongate not less than 12 percent in a 5 cm long specimen under tensile test;
b) have an ultimate tensile strength of not less than 3,700 kg/cm2;
c) have a beam strength including joints of 680 kg at a deflection of 5 cm when
tested on a clear span of 365 cm with a load applied through an 8 cm wide flat
surface at the center; and
d) have joints capable of withstanding a side pull of 2,200 kg;
e) Guardrails shall be galvanized in accordance with AASHTO M111-04. All
galvanizing shall be done after fabrication.
Where applicable, and if approved by the Engineer, the use of materials for guardrail
complying with the standards of Vietnam will be accepted.
2.3 GUARDRAIL HARDWARE
Offset blocks shall be steel sections of the type, dimensions, and thickness shown on the
Drawings.
Splices and terminal pieces shall be of the type, dimensions and thickness shown on the
Drawings, and shall be of such strength as to develop the full design strength of the rail
elements.
Unless otherwise specified, all fittings, bolts, washers and other accessories shall be
galvanized in accordance with the requirements of AASHTO M232-06. All galvanizing
shall be done after fabrication.
Reflector tabs shall be made of 2 mm thick aluminium covered with High Intensity
retro-reflective sheeting in accordance with Specification Section 08400 “Road Signs”, and
shall be attached to the rail at the spacing shown on the Drawings using a secure,
3. CONSTRUCTION REQUIREMENTS
3.1 POSTS
Holes shall be dug or drilled to the depth indicated on the Drawings, or the posts may be
driven by approved methods and equipment provided that they are erected in proper position
and do not become distorted, burred or otherwise damaged.
Posts shall be set vertically in the position shown on the Drawings and, where embedded in a
concrete foundation block, shall remain undisturbed for a minimum 48 hours.
The space around the post shall be backfilled to the ground line with approved material in
layers not exceeding 100 mm and each layer shall be moistened and thoroughly compacted.
When backfilling and tamping are completed the posts shall be held securely in place.
Posts for guardrails on bridges and culverts may be bolted to the structure as detailed on the
Drawings. The anchor bolts shall be set to the proper location and elevation with templates,
and carefully checked.
3.2 RAIL ELEMENTS
to line and grade. The height of the rail above ground level must be within 10mm of the
Rail elements shall be erected in a manner resulting in a smooth, continuous beam that is true
height shown on the Drawings. All bolts, except adjustment bolts, shall be drawn tight. Bolts
shall be of sufficient length to extend beyond the nuts at least 5 mm but not more than 100
mm.
Where galvanized surfaces have been abraded so that the base material is exposed, the
threaded portions of all fittings and fasteners and cut ends of bolts shall be protected in a
manner as using a zinc based coating in accordance with Subsection 2.5.
All rails shall be erected and adjusted so that the longitudinal tension shall be uniform
throughout the entire length of the rail.
1. DESCRIPTION
This work consists of the provision and placing of markings on the finished pavement.
The thermoplastic compound shall be screeded or sprayed onto the pavement surface in a
molten state by a suitable machine capable of controlled preparation and laying together
with the surface application of glass beads at a specific rate. Upon cooling to ambient
pavement temperature, it shall produce an adherent pavement marking of specified thickness
and width and capable of resisting deformation by traffic.
The thermoplastic compound shall be applied to the size, shape and location of the markings
shown on the Drawings, or as required by the Engineer.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied to the works
covered by this Specification.
QCVN 41:2012/BGTVT National Technical Regulation on Road Signs and
Signals
TCVN 8786:2011 Traffic Paints. Road Marking Materials: Water based
paints Specification and Test Method
TCVN 8787:2011 Traffic Paints. Road Marking Materials: Solvent based
paints Specification and Test Method
TCVN 8788-2011 Traffic Paints. Road Marking Materials - Technical
requirements and test methods
TCVN 8791-2011 Traffic Paints. Thermoplastic pavement markings -
Road markings, construction and acceptance
AASHTO M247-05 Glass Beads Used in Traffic Paints
AASHTO M248-03 Ready-Mixed White and Yellow Traffic Paints
AASHTO M249-03 White and Yellow Reflective Thermoplastic Stripping
Material (Solid Form)
2.2 PAINT FOR PAVEMENT MARKINGS
The thermoplastic material shall be homogeneously composed of aggregate, pigment, resins
and glass reflectorizing beads. The thermoplastic material shall be factory-mixed, from an
approved manufacturer, and shall be of a tropical grade suitable for application, by the
means proposed, to the specified road surfaces.
The thermoplastic material shall be sampled and tested in accordance with the appropriate
ASTM method (ASTM D7307-06 Standard Practice for sampling of Thermoplastic Traffic
Marking Materials and ASTM D4797-88 (2007) – Standard test methods for Chemical and
Gravimetric Analysis of White and Yellow Thermoplastic Traffic Machine Containing lead
Chromate and Titanium Oxide). The Contractor shall furnish to the Engineer a copy of
certified test reports from the manufacturer of the thermoplastic material showing results of
all tests specified herein and shall certify that the material meets all requirements of this
Specification.
3. CONSTRUCTION REQUIREMENTS
3.1 PREPARATION OF ROAD SURFACE
The work of road marking shall include the following:
a) Cleaning of the pavement surfaces to remove all dust, dirt, grease, oil and other
foreign matter.
b) Application, protection and drying of paint coatings.
c) Protection of pedestrians, vehicular or other traffic.
d) Protection of all parts of the road structure and its appurtenances against
disfigurement by spatters splashes or smirches of marking material.
e) Supply of all tools, labour and marking materials necessary for the entire work.
Thermoplastic shall not be applied during rain or wet weather or when air is misty, or when
in the opinion of the Engineer, conditions are unfavourable for the work. Thermoplastic shall
not be applied on damp pavement surfaces, or on pavement which has absorbed heat
sufficient to inhibit the thermoplastic from setting properly.
3.2 APPLICATION OF THERMOPLASTIC MATERIAL
Thermoplastic shall not be placed on a sealed surface sooner than three (3) days after
application of the final seal coat or Asphaltic Concrete surfacing.
The precise dimensions and positions of all pavement markings shall be set out and marked
on the pavement before the thermoplastic is applied.
The thermoplastic material shall be melted in a heater fitted with a mechanical stirrer to give
a smooth consistency to the material and to avoid local overheating. The temperature of the
mass shall be maintained within the range specified by the manufacturer.
1. GENERAL
This work consists of the removal of coatings and application of protective coatings to metal
(including galvanizing), timber, or concrete surfaces to control corrosion or deterioration.
This section is applicable to all painting works except for the painting of steel bridges, which
is addressed separately in Section 07670 Painting of Steel Bridges.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be applied to the works.
AASHTO M111-04 Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel
Products
AASHTO M232-06 Zinc Coating (Hot-Dip) on Iron and Steel Hardware
HM-22. ASTM A153/A153M-00
ASTM A653/A653M-07 Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron
Alloy-Coated (Galvanealed) by the Hot-Dip Process
ASTM D3359-08 (Method A) Measuring Adhesion by Tape Test
ASTM D4138-07 Measurement of Dry Film Thickness of Protective
Coating Systems by Destructive Means
ASTM D4285-06 Indicating Oil or Water in Compressed Air
ASTM D4417-03 Field Measurement of Surface Profile of Blast Cleaned
Steel
ASTM E337-07 Measuring Humidity with a Psychrometer (the
Measurement of Wet- and Dry-Bulb Temperatures)
SSPC SP1 Solvent Cleaning-Editorial (November 1, 04)
2.2 MATERIALS FOR PAINTING
Only certified manufacturers approved by the Engineer will be allowed to supply paints for
the Works.
All paints shall be obtained from the approved manufacturers, and variation on the paint
material (type, date, etc.) for a commenced work will be rejected.
In case of multiple coats painting system, each coat of paint shall be compatible with the
previous one.
Galvanization of metallic elements shall in general conform to the requirements of
AASHTO M111-04. Material thinner than 3.2 mm might be galvanized before fabrication in
conformity with the requirements of ASTM A653-07. Galvanization of iron and steel
hardware and nuts and bolts shall conform to the specifications of AASHTO M232-06.
2.3 SUBMITTALS
2.3.1 SAMPLES AND DATA
The Contractor shall provide the Engineer with technical data, and the manufacturer’s
specifications for his review and approval.
3. CONSTRUCTION REQUIREMENTS
In general, the Contractor shall perform the work according to the accepted “Programme”. If
the measures fail to perform as intended, the Contractor shall immediately stop work and
take corrective action. Moreover, the Contractor shall collect and properly dispose of all
material including waste water that is used in preparations, cleaning, or painting.
3.1 PROTECTION OF THE WORKS
The Contractor shall perform the following to protect the Works:
Protect adjacent surfaces that are not to be painted by using tarps, screens, paper,
cloth, or other suitable means; and
Prevent contamination of freshly-painted surfaces by dust, oil, grease, or other
harmful or deleterious material.
3.2 SURFACE PREPARATION
The Contractor shall notify the Engineer in writing at least 7 days before beginning
operations, shall prepare the surface, immediately before painting, according to the
following:
Clean the surface to the specified cleanliness level;
Remove dirt, dust, and other contaminants from the surface using methods
recommended by the paint manufacturer and approved by the Engineer;
1. DESCRIPTION
This work consists of the construction of concrete curbs.
Moreover, this work shall also include curb markings of red and white paint where shown on
the Drawings or where indicated by the Engineer.
2. MATERIAL REQUIREMENTS
2.1 REFERENCE STANDARDS
The following Standards in their latest edition shall be applied to the works covered by this
Specification.
AASHTO M33-03 Preformed Expansion Joint Filler for Concrete
(Bituminous Type)
AASHTO M248-03 Ready-Mixed White and Yellow Traffic Paints
2.2 BEDDING
The thickness of bedding material shall be in accordance with the requirements shown on the
Drawings or as indicated by the Engineer.
2.3 CONCRETE
Concrete shall be as shown on the Drawings and shall be in accordance with the provisions
and requirements of Specification Section 07100 “Concrete and Concrete Structures”.
2.4 CEMENT MORTAR
Cement Mortar, shall be in accordance with the provisions and requirements of Specification
Section 08100 “Cement Mortar”.
2.5 CURB PAINT
Unless otherwise indicated on the Drawings, or by the Engineer, paint for curbs shall be in
accordance with the specifications of AASHTO M248-03 and Specification Section 08800.
3. CONSTRUCTION REQUIREMENTS
3.1 CONCRETE CURBS
Excavation shall be made to the required depth, and the base shall be compacted to a firm
even surface.
All soft and unsuitable material shall be removed and replaced with a material that complies
with the provisions and requirements of its respective specifications, and it is approved by
the Engineer.
If so indicated on the Drawings, the bed course material shall be placed and compacted to
form a uniform bed course of the required thickness.
Mortar joints shall be filled for whole cross section, and the joint shall be of 10mm.
The finished work shall be true to line grade and level to within 3 millimeters and shall
present a smooth appearance free from kinks and distortions visible to the eye.
Concrete shall be in accordance with the provisions and requirements of Specification
Section 07100 “Concrete and Concrete Structures”
1. DESCRIPTION
This work shall consist of the furnishing and laying of interlocking concrete blocks (or
bricks) to the lines, grades and locations shown on the Drawings or instructed by the
Engineer.
2. MATERIALS
Concrete Blocks and bricks shall be made by an approved manufacturer with recent
experience of supplying blocks to the local authority and shall conform to the following
specifications:
(a) Shape and Colour
General shapes and colour of interlocking blocks shall be decided by the Engineer before
orders are given to the suppliers or manufacturers
(b) Thickness
The following minimum thickness shall apply: 6 cm for sidewalk for pedestrian; 8 cm for
medium/heavy traffic of passenger car, pick- up, bus and truck; 10 cm for super heavy traffic
including crane, loader, et
(c) Dimension Tolerance
Dimension tolerances shall be 2 mm for length and width, and 3 mm for thickness
(d) Compressive Strength
The compressive strength average shall be not less than 45 MPa and the crushing strength of
any individual block shall be not less than 40 MPa.
Bricks/ tiles shall conform to TCVN 1450-86 and shall be Class A oven-burnt brick, of
accurate dimensions and size, dark brown color, no cracks or curves. Compressive strength
shall be > 7.5 MPa.
The base shall be granular base course material complying with clause in section 05100 of
these Specifications.
The sand for block/ brick/ tile bedding shall be course sand, which shall be clean, dry and of
moisture content approximately 4 - 8%.
Filler sand shall be finer than 1.18 mm and shall contain approximately 10% silt material
3. CONSTRUCTION REQUIREMENTS
(a) Foundation
The base course shall be of the dimensions shown on the drawings and provide a minimum
CBR value of 50 - 80%. The base course surface shall be laid to the falls required for the
finished block surface. All work on kerbs and other edge boundaries shall be completed
before the blocks or bricks or tiles are laid.
(b) Bedding
The bedding sand shall be dry, spread loose 20% thicker than compacted design thickness
shown on drawings. Using a wooden straightedge, the bedding sand shall be spread and
tamped to follow the designed road surface. Before and after being leveled, bedding sand
shall not be compacted. Where previously prepared bedding is compacted unintentionally,
that portion shall be made loose and leveled again.
(c) Placing of Block/Brick
Contract – Volume 2 – Specification 8-32 08910
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
Placing of blocks or bricks shall start from the edge of the kerbs and follow the design
pattern instructed by the Engineer. The space between the units shall be 2 to 4 mm to
accommodate insertion of filler sand, and work shall be straight and controlled by string
lines and straightedges. Cuts in blocks shall be made with a concrete saw or proprietary
block cutter. Damaged blocks/ bricks shall be rejected and shall not be placed.
(d) Compaction
After blocks/ bricks are laid they shall be compacted with a vibrating plate compactor of
specification as follows:
- Plate area 0.35 - 0.50 sq.m
- Centrifugal force 16 - 20 KN
- Frequency 75 - 100 Hz
- No. of passes Approximately 3 to 4 passes
Block/ brick damaged by this initial compaction shall be replaced by new blocks. After
initial compaction is completed, filler sand shall then be spread and swept to fill the spaces
between block/ bricks. Final compaction shall be done using the same vibrating plate
compactor until the bedding of the blocks/ bricks has been completed. Block/ brick for heavy
traffic shall also be given a final compaction by a tyre roller (TR) of 10 - 14 tonne capacity.
(e) Maintenance
For several weeks or as directed by the Engineer after the block road is opened to traffic,
maintenance is required by refilling the spaces between block/ bricks with filler sand. Ideally,
refilling sand shall be continued before interlocking of block/ brick takes place.
1. DESCRIPTION
This work consists of the supply and installation of slope protection to cuttings and
embankments, and slope protection for abutments as shown on the drawings or as may be
required by the Engineer.
2. MATERIAL REQUIREMENTS
2.1 MATERIALS
2.1.1 CONCRETE
Concrete shall be class C20 concrete, either pre-cast or cast in-situ as indicated on the
drawings and in accordance with the requirements of Specification Section 07100 “Concrete
and Concrete Structures”.
2.1.2 REINFORCING STEEL
Reinforcing steel shall conform to the requirements of Specification Section 07500
“Reinforcing Steel”.
2.1.3 CRUSHED AGGREGATE
Crushed aggregate shall be placed in layers and compacted to 95% of the maximum dry
density determined according to 22TCN 333-06
The material shall be well-graded crushed or uncrushed gravel, stone, rock-fill or natural
sand or a well-mixed combination of any of these. Grading requirements for Granular
Backfill shall be as follows:
Maximum size 5 cm
Passing 4.75 mm sieve 25% to 90%
Passing 0.075 mm sieve 0% to 10%
Liquid limit AASHTO T89 or TCVN4197-95 30% max.
2.1.4 MORTAR
Mortar shall conform to the requirements of this specification Section 08100 “Cement
Mortar”.
3. CONSTRUCTION REQUIREMENTS
Fabrication and construction of slope protection shall be as shown on the drawings.
Construction shall not begin until such time as the construction of the Embankment to the
correct line and level has been approved by the Engineer.
Pre-cast elements shall not be transported to the work site until the concrete has been cured
and has reached the required strength. Ends of pre-cast units to be cast into joints shall be
prepared in accordance with the requirements for construction joints in but without shear
keys.
Excavation shall be carried neatly to the required line and level. Excavations shall not be
further compacted and they shall be free of high or low spots such that the pre-cast beam
sections, when placed, are fully supported along their length and not subject to undue
bending such that they may crack or otherwise be damaged.
Joints shall be cast in-situ fully in accordance with Specification Section 07100 “Concrete
and Concrete Structures” despite the small volume required. Care shall be taken to ensure
that the “box” formed by the beam ends is properly sealed to avoid grout loss during casting.
Contract – Volume 2 – Specification 8-34 08950
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
For type 2 protection crushed aggregate shall not be placed until such time as the concrete in
the joints has reached an acceptable strength subject to the approval of the Engineer.
1. DESCRIPTION
This Specification section details the requirements for furnishing and erecting Type 1 (Chain
Link) and Type 2 (Barbed Wire) fencing and noise barriers in accordance with these
specifications and the details lines and grades shown on the drawings to the approval of the
Engineer.
2. MATERIALS
2.1 FABRIC AND WIRE
The chain link fabric shall be woven 4 mm galvanized steel wire in a 63 mm mesh and shall
meet the requirements of ASTM A 392 Class 2.
Barbed wire shall be zinc coated wire in accordance with ASTM A121 - 07 Standard
Specification for Metallic-Coated Carbon Steel Barbed Wire
2.2 POSTS, RAILS AND BRACES
Line posts, rails, and braces shall be galvanized steel pipe conforming to the requirements of
ASTM F 1083. The steel used in all structural shapes shall conform to the requirements of
ASTM A 572, Grade 45, and shall be galvanized in accordance with the requirements of
ASTM F 1234, Type A. Post, rails, and braces shall demonstrate the ability to withstand
testing in salt spray in accordance with ASTM B 117 with 5% or less red rust over a
1,000-hour period.
2.3 GATES
Gate frames shall consist of galvanized steel pipe and shall conform to the specifications for
the same material under clause 2.2 above. The fabric shall be of the same type material as
used in the fence.
2.4 WIRE TIES AND TENSION WIRES
Wire ties for use in conjunction with a given type of fabric or barbed wire shall be of the
same material and coating weight identified with the fencing type. Tension wire shall be 4.5
mm marcelled steel wire with the same coating as the fabric type or barbed wire and shall
conform to ASTM A 824.
2.5 CONCRETE
Concrete shall be the grade noted on the drawings in accordance with and Specification
section 07100 “Concrete and Concrete Structures”.
2.6 MARKING
Each roll of fabric or barbed wire shall carry a tag showing the kind of base metal (steel,
aluminium, or aluminium alloy number), kind of coating, the gauge of the wire, the length of
fencing or wire in the roll, and the name of the manufacturer. Posts, wire, and other fittings
shall be identified as to manufacturer, kind of base metal (steel, aluminium, or aluminium
alloy number), and kind of coating.
3. CONSTRUCTION
3.1 INSTALLING POSTS
All posts shall be set in concrete at the required dimension and depth and at the spacing
shown on the Drawing. If not indicated, posts shall be spaced not more than 3 meters apart
and shall be set a minimum of 0.90 meters in to concrete footings. The postholes shall be in
proper alignment so that there is a minimum of 75 mm of concrete on all sides of the posts.
4. SUBMITTALS
Prior to placing any fencing, the Contractor shall submit for review and approval complete
fencing shop drawings. Shop drawings shall indicate all materials to be used, line posts, rails
and bracing gates, fence and gate foundations, and fabric and wire. Drawings shall include
all dimensions and location information for the field erection of all fence and gates.
Prior to or concurrent with the submittal of fence shop drawings, the Contractor shall submit
to the Engineer for review and approval manufacture’s information and data for all fencing
materials supposing conformance with specification requirements.
1. DESCRIPTION
This Specification section details the requirements for furnishing and erecting anti-glare
panels fixed to the central median concrete barrier. The purpose is to prevent glare from
headlights of vehicles travelling on the opposite direction from distracting expressway users.
2. MATERIALS
Anti-glare panels and their fixings shall be entirely constructed of corrosion resistant
material, having stable chemical properties, and resistant to the effect of salt, ultraviolet rays.
Physical properties of the anti-glare board material shall meet the following, or shall provide
equivalent performance.
Tensile strength: ≥ 70MPa
Flexural Strength: ≥ 100MPa
Density: 1700-1800 kg/ m3
Board colour shall be green, and shall have good colour stability.
Working temperature range: 10 - 70 Degrees Centigrade
Board thickness shall be at least 4mm, and of the dimensions shown on the Drawings.
Attachment to the concrete median shall be by stainless steel expanding bolts. To ensure
durability, no element of the anti-glare panel and fixings may use mild steel or galvanized
steel. Only plastics, aluminium and stainless steel are permitted. The fixing should allow
easy adjustment of the angle of the panels.
Anti-glare board shall be constructed of glass fiber reinforced plastic, with a matrix of
polyester or epoxy resin.
Lightly curved panels are preferred in order to give a uniform appearance even in case of
minor variation in installation angle of the panels.
3. CONSTRUCTION
Correct installation and alignment of the panels is critical to give a uniform appearance.
Tolerance for installation shall be +/-5mm for horizontal position of the base, +/-5mm for
horizontal position of the top of the board, +/- 1 degree for verticality, +/- 1 degree for
rotation angle of the boards.
1. GENERAL
Furnishing of a commercially available mechanically stabilized earth wall system at the
locations indicated on the drawings which shall be designed by and constructed under the
control of a specialist company.
The design life of the structures shall be 120 years, and the materials proposed for the facing
panels, connections, and soil reinforcement shall be selected for their durability.
The wall designer shall indemnify the Employer for any losses resulting from defects or
deficiencies in their design for a period of 5 years from completion of the walls. The wall
designer shall carry adequate professional indemnity insurance for this purpose and shall
submit evidence of this fact prior to their approval by the Engineer. The Contractor shall
further indemnify the Employer against any losses relating to patent infringement in the
works.
The design method used shall comply with the AASHTO Bridge Design Specifications for
mechanically stabilised walls, or equivalent. Fill shall be frictional fill in accordance with
the specification for sand fill material in Section 03200 of this Specification, and having
fines passing the 0.075mm sieve of less than 10%.
Highway loading used in design shall be to AASHTO standard.
Design shall include examination of both internal and external stability cases. If the
founding soil is shown on the drawings as being subject to improvement works whether by
deep soil mixing, sand drains or sand compaction piles or other, the wall designer shall
check whether the foundation as specified meets with the requirements of their design. If the
foundation is not adequate the wall designer shall carry out modification of the foundation
design so that it meets their requirements.
In cases where the wall designer believes that the soils data is insufficient or inadequate with
regards to quality or quantity, the Contractor shall carry out supplementary investigation as
necessary for the wall design. No additional payment for such supplementary investigation
will be made.
2. MATERIALS
Reinforcement shall be inextensible type i.e. metallic strips, sheets, grids or meshes with an
elongation at working stress of less than or equal to 1%.
Facing panel shape and decorative finish shall be proposed by the Contractor for approval by
the Engineer.
Facing panels shall in principle be precast concrete with raised-relief finish to give good
resistance to graffiti.
The reinforced wall system shall be capped by a parapet system and a finish that
complements or replicates the parapet detail of the adjacent bridge. The reinforced soil
designer shall incorporate parapet details indicated on the drawings.
The Contractor shall carry out a fully erected wall panel with the specified surface finish for
the approval of the Engineer at least 3 weeks before the erection of units on site. The cost of
the trial panels shall not be measured separately for payment but will be deemed included in
the unit rates.
3. CONSTRUCTION
Construction of mechanically stabilised earth wall shall not commence until soil
stabilisation works for the foundation have been completed.
Contract – Volume 2 – Specification 8-40 08980
North-South Expressway Construction Project (Ben Luc - Long Thanh Section)
Package J2: July 2014
Checking of the chemical, mechanical and compaction properties of the fill shall be made
during construction to ensure compliance with the wall designer’s requirements.
1. DESCRIPTION
This Specification details the requirements and procedures for furnishing and installing all
materials and equipment necessary for the highway and bridge lighting systems, other
electrical systems and the modification of existing systems when required, all in accordance
with the Drawings, this Specification section, or such additional details and clarifications as
may be provided by the Engineer. The locations of poles, accessories and attachments shown
on the Drawings are approximate. Exact locations are to be determined on site and
confirmed by the Engineer. This section does not cover electrical works and lighting for
buildings.
The scope of work included in this Specification section covers the supply, delivery to site,
erection, testing and commissioning of all materials and equipment required in connection
with the Electrical Installation to the extent described and shown on the Drawings and
includes but is not necessarily limited to:
a) Preparation and submission of Shop Drawings
b) Submission of detailed Material Lists
c) All work associated with the removal of sections of the existing systems and the
incorporation of the remaining sections in the permanent works.
d) Site measurement of ambient lighting levels to assist the Engineer in his review
of the lighting details shown in the Drawings
e) Countermeasures to the phenomenon of Karman vortex on the bridge lighting
poles. The Contractor shall prepare and submit related data and proposed
countermeasures to the Engineer for approval.
f) Design of necessary power capacity based on the Contractor’s proposed
equipment and arrangement, and submission to the Engineer for approval. The
power capacities shown on the Drawings are for reference only.
g) Negotiation with the power company of a targeted power factor, and design of
appropriate arrangement of equipment to achieve the targeted power factor.
h) All other electrical equipment and services needed to complete a serviceable
facility fit for purpose in accordance with relevant codes and local regulations
for Electrical Installations.
The Electrical work shall be carried out under the supervision of a licensed Electrical
Engineer.
Permissible designed voltage drops are:
Total Voltage Drop shall be 5 % maximum; and generally
Voltage drop between the supply point / SS panel and MDP panel or DB panel
should be designed to be less than 3 % for any type of feeder;
Voltage drop between DB panel and end of lighting circuit should be designed to be
less than 2 % maximum for any type of cable;
The Contractor shall select the appropriate lamps and system as shown in the detail
drawings.
3. CONSTRUCTION REQUIREMENTS
3.1 EXECUTION OF THE WORK
The actual fabrication, installation, and testing of the work described in this Specification
section shall be carried out by trained and experienced personnel who are familiar with the
requirements for this work and with the manufacturer’s recommendations for installation of
the specified items.
All work shall comply with the Drawings, this Specification section and the codes,
regulations and requirements stipulated in this Specification section or by the relevant
Vietnamese Authorities.
3.2 LIGHTING UNITS
Lighting units as shown on the Drawings shall consist of lamps, canopy, body, electrical
control ballasts, and mounting accessories.
The Contractor shall submit for approval light distribution diagrams for each type of lantern
he proposes to install. Unless specifically shown on the drawings or instructed by the
Engineer, all lanterns should be of the semi-cut off or fully cut off type.
Permitted spill light levels shall be controlled on both the front and rear of the lighting unit as
follows: At the right of way limit on the opposite side of the road – maximum 5 Lx, and at
the right of way limit to the rear of the lighting unit – zero. The Contractor shall submit
factory test data to demonstrate conformance with these spill light levels.
3.3 LIGHTING CONTROL PANELS
The lighting control panels shall be included as feeders of the power source fed to the
circuits of the street lighting. The panels shall be as shown on the Drawings or equivalent
subject to approval by the Engineer.
The panels shall be substantial, free-standing structures on a concrete foundation a minimum
of 40 cm above ground level or mounted on the substation pole.
Panel roofs shall be in conformance with the Drawings or equivalent subject to approval by
the Engineer.
1. DESCRIPTION
The work under this clause shall include the provision of foundations, lighting blisters,
anchor bolts, junction boxes and conduit, duct bank, for electrical works in both bridge and
earthworks sections as required in the drawings, and as necessary for the installation of the
electrical facilities as described in Specification Section 09100.
2. MATERIALS
All materials used shall conform to the details given in the Drawings. In the absence of any
details in the drawings, the work shall be carried out in accordance with the relevant sections
of the Specifications and the instruction of the Engineer.
(a) Conduit Pipe
Conduit/ducts to be installed below ground or embedded in concrete shall be HDPE or FEP
or equivalent, except where crossing roads where steel conduit shall be used. Conduit to be
installed above ground or on the surface of structures shall be steel or equivalent subject to
approval by the Engineer
HDPE (High density polyethylene) duct shall conform to IEC 61386-2, JISC 3653, or
equivalent and FEP (Fluorinated Ethylene Propylene) duct shall conform to IEC 61386 or
JISC 3653 or equivalent. Size of pipe / duct shall follow standard sizes manufactured in Viet
Nam.
Exterior and interior surfaces of all steel conduits shall be uniformly and adequately
zinc-coated by a hot-dip galvanizing process.
Conduit to be embedded in concrete shall be PVC in accordance with the requirements of
IEC61084-2-1 or JIS C 8430.
(b) Manhole
Manhole to be installed for underground cables and communication cables shall be pre-cast
concrete or as shown on the drawings in accordance with Vietnam standards.
(c) Junction box
Junction box type-A, B and C of appropriate dimensions shall be installed as shown in the
Drawings. The body shall be fabricated from 3.2 mm mild steel sheet, hot-dip-galvanized.
Covers shall be 3mm type SUS 304 stainless steel or hot dip galvanised 3.2 mm mild steel
sheet. No sharp projections from screws or other objects shall be permitted within the box.
The covers shall be watertight by rubber gasket.
3. CONSTRUCTION
3.1 ANCHOR BOLTS IN CONCRETE STRUCTURES
Details of anchor bolts shall be in accordance with the Drawings. Anchor bolts shall be fixed
in the concrete structure positions and held in place by means of templates until the concrete
has set.
3.1.1 FOUNDATIONS FOR LIGHTING POLES
Concrete for foundations for lighting poles and pedestals of cabinets shall be of the class
shown on the Drawings.
All details of concrete and reinforcement for foundations shall conform to the requirements
of the appropriate specification.