You are on page 1of 20

THK/HEIGHT LENGTH WIDTH TRANS.

ITEM
meters meters
FOOTING 0.15 0.60 0.60 0.60
COLUMN 4.50 0.20 0.20
BEAM1 0.20 11.00 0.20
BEAM2 0.20 7.50 0.20
WF 0.15 60.00 0.30 0.40
WALL 4.00 60.00
SLAB1 0.10 7.50 11.00 7.50

DESCRIPTION CONSTANT
ITEM NO. QUANTITY TOTAL QUANTITY
Materials Mixing (A)
I FOOTING 0.05 0.49
Cement 9.00 0.49 4.37
Sand 0.50 0.03 0.24
Gravel 1.00 0.05 0.49
10mmØ Bars 1.00 9.00
Tie Wire 0.15 1.35

II COLUMN 0.18 1.62


Cement 9.00 1.62 14.58
Sand 0.50 0.09 0.81
Gravel 1.00 0.18 1.62
12mmØ Bars 3.20 28.80
8mmØ Bars 5.40 48.59
Tie Wire 0.98 8.86

V BEAM1 0.44 0.88


Cement 9.00 3.96 7.92
Sand 0.50 0.22 0.44
Gravel 1.00 0.44 0.88
10mmØ Bars 7.33 14.67
8mmØ Bars 10.80 21.59
Tie Wire 1.97 3.94

VI BEAM2 0.30 0.60


Cement 9.00 2.70 5.40
Sand 0.50 0.15 0.30
Gravel 1.00 0.30 0.60
10mmØ Bars 5.00 10.00
8mmØ Bars 7.72 15.45
Tie Wire 1.41 2.82

VII WALL FOOTING 2.70 2.70


Cement 9.00 24.30 24.30
Sand 0.50 1.35 1.35
Gravel 1.00 2.70 2.70
10mmØ Bars 32.00 32.00
Tie Wire 1.80 1.80

VIII WALL 240.00 240.00


4" CHB 12.50 3000.00 3000.00
Cement 0.79 190.08 190.08
Sand 0.04 10.44 10.44
10mmØ Bars 323.33 323.33
Tie Wire 6.00 6.00

VIII SLAB1 8.25 8.25


Cement 9.00 74.25 74.25
Sand 0.50 4.13 4.13
Gravel 1.00 8.25 8.25
8mmØ Bars 49.24 49.24
Tie Wire 1.38 1.38
Materials Quantity Units
Cement 320.90 Bags.
Sand 17.708 Cu.m.
Gravel 14.54 Cu.m.
12mm (DRB) 28.80 Length
10mm (DRB) 389.00 Length
8mm (DRB) 134.86 Length
Tie Wire 26.133 Kg.
4" CHB 3000.00 Pcs.
TRANS. LONG. VERT.
no. of bars meters no. of bars meters no. of bars
5.00 0.60 5.00
4.80 4.00
11.00 4.00
7.50 4.00
66.00 2.00
66.00 6.67 10.00 150.00
12.50 11.00 18.33

UNITS
Cu.m.
Bags.
Cu.m.
Cu.m.
Length
Kg.

Cu.m. COLUMN TIES


Bags. SPACING
Cu.m. NO. OF TIES
Cu.m. TOTAL NO. OF TIES
Length TOTAL LENGTH
Length PCS
Kg.

Cu.m. BEAM 1 TIES


Bags. SPACING
Cu.m. NO. OF TIES
Cu.m. TOTAL NO. OF TIES
Length TOTAL LENGTH
Length PCS
Kg.

Cu.m. BEAM 2 TIES


Bags. SPACING
Cu.m. NO. OF TIES
Cu.m. TOTAL NO. OF TIES
Length TOTAL LENGTH
Length PCS
Kg.

Cu.m. WF1
Bags. SPACING
Cu.m. TOTAL NO. OF TRANS
Cu.m. TOTAL LENGTH
Length PCS
Kg.

Sq.m.
Pcs.
Bags.
Cu.m.
Length
Kg.

Cu.m.
Bags.
Cu.m.
Cu.m.
Length
Kg.
TIES VHLT BARS
NO. OF ITEM
Ø size
10mmØ Bars 9.00
8mmØ Bars 12mmØ Bars 9.00
8mmØ Bars 10mmØ Bars 2.00
8mmØ Bars 10mmØ Bars 2.00
10mmØ Bars
10mmØ Bars
8mmØ Bars

BED BARS LENGTH


Long. 0.60
Trans. 0.60

Total

COLUMN TIES BARS LENGTH


0.05 0.10 0.15 Vert. 4.80
4.00 5.00 32.00 Ties
41.00 Vert.
Total
32.39 Ties
5.40

BEAM 1 TIES BARS LENGTH


0.05 0.10 0.15 Long. 11.00
4.00 5.00 32.00 Ties
82.00 Total Long.
64.78 Ties
10.80

BEAM 2 TIES BARS LENGTH


0.05 0.10 0.15 Long. 7.50
4.00 5.00 20.33 Ties
58.67 Total Long.
46.35 Ties
7.72

WF1 BARS LENGTH


0.40 Long. 66.00
150.00 Trans.
60.00 Long.
10.00 Total Trans.
32.00

BARS LENGTH
Long. 66.00
Vert. 10.00
Long.
Total Vert.
323.33

SLAB BARS LENGTH


Long. 11.00
Trans. 7.50

Total
NO. OF BARS LENGTH/PCS TIE WIRE
5.00 6.00 LENGTH INTERSECTION
5.00 6.00 0.30 25.00
0.50 Total 0.15
Total 0.50
1.00

NO. OF BARS LENGTH/PCS TIE WIRE


4.00 6.00 LENGTH INTERSECTION
41.00 0.30 164.00
Vert. 3.20 Total 0.98
Ties 5.40

NO. OF BARS LENGTH/PCS TIE WIRE


4.00 6.00 LENGTH INTERSECTION
82.00 6.00 0.30 328.00
Long. 7.33 Total 1.97
Ties 10.80

NO. OF BARS LENGTH/PCS TIE WIRE


4.00 6.00 LENGTH INTERSECTION
58.67 6.00 0.30 234.67
Long. 5.00 Total 1.41
Ties 7.72

NO. OF BARS LENGTH/PCS TIE WIRE


2.00 6.00 LENGTH INTERSECTION
150.00 6.00 0.30 300.00
Long. 22.00 Total 1.80
Trans. 10.00
32.00

NO. OF BARS LENGTH/PCS TIE WIRE


6.67 6.00 LENGTH INTERSECTION
150.00 6.00 0.30 1000.00
Long. 73.33 Total 6.00
Vert. 250.00
323.33

NO. OF BARS LENGTH/PCS TIE WIRE


18.33 6.00 LENGTH INTERSECTION
12.50 6.00 0.30 229.17
33.61 Total 1.38
Total 15.63
49.24
WIRE
LENGTH/KG
50.00
0.15

WIRE
LENGTH/KG
50.00
0.98

WIRE
LENGTH/KG
50.00
1.97

WIRE
LENGTH/KG
50.00
1.41

WIRE
LENGTH/KG
50.00
1.80

WIRE
LENGTH/KG
50.00
6.00

WIRE
LENGTH/KG
50.00
1.38
BASE PAD
VOLUME CEMENT(Bags) SAND (cu.m.) GRAVEL (cu.m.)
2.42 21.78 1.21 2.42

TOP/BOTTOM SLAB

BARS LENGTH(m) PIECES LENGTH/PIECE


VERTICAL 1.7 11 6
HOR 3 7 6
TOTAL

WALLS

BARS LENGTH(m) PIECES LENGTH/PIECE


VERTICAL 0.8 18 6
HOR 4.8 6 6
TOTAL

STAIRS

BARS LENGTH(m) PIECES LENGTH/PIECE


LONG 1 5 6
BEND 1.8 5 6
TOTAL

BILL OF MATERIALS
ITEMS QUANTITY UNITS AMOUNT
I.CONCRETE AND MASONRY WORKS
Cement 22 Bags PHP 230.00
Sand 1.21 cu.m. PHP 500.00
Gravel 2.42 cu.m. PHP 800.00
10mm BARS 30 Length PHP 180.00
Tie Wire 1.35 Kg. PHP 80.00
II. FORM WORKS
15pcs-2"x2"x10' 50 bd.ft. PHP 25.00
10mmx4'x8' Mar.
5 Pcs. PHP 345.00
Plywood
C.W. Nails, 2 1/2" 2 Kg. PHP 60.00
TOTAL
LABOR (40%)
O.C.M.
TOTAL COST
BARS TIE WIRE (Kgs)
29.97 1.354838709677

TIE WIRE

NO. OF BARS LENGTH OF TIE INTERSECTION LENGTH/KGS


3.12 0.4 77 62
3.5 TOTAL 0.50
13.23

TIE WIRE

NO. OF BARS LENGTH OF TIE INTERSECTION LENGTH/KGS


2.40 0.4 108 62
4.8 TOTAL 0.70
14.40

TIE WIRE

NO. OF BARS LENGTH OF TIE INTERSECTION LENGTH/KGS


0.83 0.4 25 62
1.5 TOTAL 0.16
2.33

COST

PHP 5,009.40
PHP 605.00
PHP 1,936.00
PHP 5,394.00
PHP 108.39

PHP 1,250.00

PHP 1,725.00

PHP 120.00
PHP 16,147.79
PHP 6,459.11

PHP 22,606.90
BILL OF MATERIALS
Project BASE PAD
Location LAMBAYONG-MATIOMPONG

ITEM DESCRIPTION QUANTITY UNITS U/P AMOUNT


I CONCRETE AND MASONRY WORKS
A. Materials
Cement 33 Bags 230.00 7,590.00
Sand 4.00 cu.m 500.00 2,000.00
Gravel 4.00 cu.m 800.00 3,200.00
10mm BARS 30 Length 180.00 5,394.00
Tie Wire 1 Kg. 80.00 108.39

III FORM WORKS


A. Materials
15pcs-2"x2"x10' 50 bd.ft. 25.00 1,250.00
10mmx4'x8' Mar. Plywood 5 Pcs. 750.00 3,750.00
C.W. Nails, 2 1/2" 2 Kg. 60.00 120.00

TOTAL MATERIAL COST 23,412.39


LABOR COST (40%) 9,364.95
TOTAL PROJECT COST 32,777.34

Prepared by:
BILL OF MATERIALS
Project BASE PAD
Location 5995 - BOSTON

ITEM DESCRIPTION QUANTITY UNITS U/P AMOUNT


I CONCRETE AND MASONRY WORKS
A. Materials
Cement 33 Bags 230.00 7,590.00
Sand 4.00 cu.m 500.00 2,000.00
Gravel 4.00 cu.m 800.00 3,200.00
10mm BARS 30 Length 180.00 5,394.00
Tie Wire 1 Kg. 80.00 108.39

III FORM WORKS


A. Materials
15pcs-2"x2"x10' 50 bd.ft. 25.00 1,250.00
10mmx4'x8' Mar. Plywood 5 Pcs. 750.00 3,750.00
C.W. Nails, 2 1/2" 2 Kg. 60.00 120.00

TOTAL MATERIAL COST 23,412.39


LABOR COST (40%) 9,364.95
TOTAL PROJECT COST 32,777.34

33,000.00

Prepared by:
BILL OF MATERIALS
Project BASE PAD
Location BAGANGA

ITEM DESCRIPTION QUANTITY UNITS U/P AMOUNT


I CONCRETE AND MASONRY WORKS
A. Materials
Cement 33 Bags 230.00 7,590.00
Sand 4.00 cu.m 500.00 2,000.00
Gravel 4.00 cu.m 800.00 3,200.00
10mm BARS 30 Length 180.00 5,394.00
Tie Wire 1 Kg. 80.00 108.39

III FORM WORKS


A. Materials
15pcs-2"x2"x10' 50 bd.ft. 25.00 1,250.00
10mmx4'x8' Mar. Plywood 5 Pcs. 750.00 3,750.00
C.W. Nails, 2 1/2" 2 Kg. 60.00 120.00

TOTAL MATERIAL COST 23,412.39


LABOR COST (40%) 9,364.95
TOTAL PROJECT COST 32,777.34

Prepared by:
BILL OF MATERIALS
Project BASE PAD
Location BOSTON

ITEM DESCRIPTION QUANTITY UNITS U/P AMOUNT


I CONCRETE AND MASONRY WORKS
A. Materials
Cement 33 Bags 230.00 7,590.00
Sand 4.00 cu.m 500.00 2,000.00
Gravel 4.00 cu.m 800.00 3,200.00
10mm BARS 30 Length 180.00 5,394.00
Tie Wire 1 Kg. 80.00 108.39

III FORM WORKS


A. Materials
15pcs-2"x2"x10' 50 bd.ft. 25.00 1,250.00
10mmx4'x8' Mar. Plywood 5 Pcs. 750.00 3,750.00
C.W. Nails, 2 1/2" 2 Kg. 60.00 120.00

TOTAL MATERIAL COST 23,412.39


LABOR COST (40%) 9,364.95
TOTAL PROJECT COST 32,777.34

Prepared by:

You might also like