You are on page 1of 7

CONCRETE MIXTURE

Type of Construction Proportion


Sidewalk, 4" thick 1:2:4
Floor slab, 4" thick 1:2:4
Wall 1 : 2.5 : 5
Footing 1 : 2.5 : 5
Post 1 : 2.5 : 5
Machinery foundation 1:3:6
Reinforced concrete 1:2:4
Foundations 1 : 2.5 : 5
Top dressing on wearing surp. 1:2
Water proofing

QUANTITY OF CEMENT AND SAND FOR PLASTERING


per SQUARE METER per 100 CHB
CEMENT IN BAGS CEMENT IN BAGS
No. of Faces to be plastered SAND in SAND in
40kg mixture 40kg mixture
cu.m. cu.m.
B C D B C D
ONE FACE 0.300 0.225 0.188 0.025 2.304 1.536 1.152 0.128
TWO FACES 0.600 0.450 0.375 0.025 4.608 3.072 2.304 0.256

LENGTH OF STEEL REINFORCEMENT FOR


CONCRETE HOLLOW BLOCK
VERTICAL REINFORCEMENT HORIZONTAL REINFORCEMENT
Length of Bars in Meter Length of Bars in Meter
Spacing in Spacing in
cm Per Block Per Sq.M. layers Per Block Per Sq.M.

0.40 0.235 2.93 2 0.364 3.30


0.60 0.171 2.13 3 0.172 2.15
0.80 0.128 1.60 4 0.138 1.72

CHB REINFORCEMENT

Spacing of Vertical Bars Length of Bars in Meter Per


in Meter Block Square Meter
0.40 0.25 3.00
0.60 0.17 2.10
0.80 0.12 1.50
Horizontal Bars Every
2 0.22 2.70
3 0.15 1.90
4 0.13 1.70
5 0.11 1.40

STANDARD WEIGHT OF PLAIN OR DEFORMED ROUND


STEEL BARS
in KGS
SIZE
5.0 m 6.0 m 7.5 m 9.0 m 10.5 m 12.0 m 13.5 m
8mm dia 1.98 2.37 2.96 3.56 4.15 4.74 5.33
10mm dia 3.06 3.70 4.62 5.54 6.47 7.39 8.32
12mm dia 4.44 5.33 6.66 7.99 9.32 10.66 11.99
13mm dia 5.21 6.25 7.83 9.38 10.94 12.50 14.07
16mm dia 7.90 9.47 11.84 14.21 16.58 18.95 21.32
20mm dia 12.33 14.80 18.50 22.19 25.89 29.59 33.29
25mm dia 19.27 23.12 28.90 34.68 40.46 46.24 52.02
28mm dia 24.17 29.00 36.25 43.50 50.75 58.00 65.25
30mm dia 27.75 33.29 41.62 49.94 58.26 66.59 74.91
32mm dia 31.57 37.88 47.35 56.82 66.29 75.76 85.23
36mm dia 39.96 47.95 59.93 71.92 83.91 95.89 107.88

QUANTITY OF CEMENT AND SAND INSTALLATION OF


TILES
Stock pcs./sq. Cement Bag / sq.m. Brass
Sand / cu.m.
Size m. Class A B div/sq.m.
8x8 25 0.340 0.220 0.018 11.00
9x9 20 0.340 0.220 0.018 10.00
10 x 10 16 0.340 0.220 0.018 9.00
12 x 12 12 0.340 0.220 0.018 8.00
14 x 14 8.5 0.340 0.220 0.018 6.00
16 x 16 6.5 0.340 0.220 0.018 5.90

* Note : Tile Adhesive coverage (5-7 sq.m. / 25kg bag) Tile Adhesive/cement paste coverage (3kg/sq.m.)
Tile Grout coverage (4-5 sq.m. / 2kg bag)
Tile Grout coverage (10-12 sq.m. / 5kg bag)

PAINT COVERAGE
Kinds of Paint Coverage per sq.m.
Wood Preservation 9.30 - 1 coat
Outside Lead Oil 27.88 - 2 coats
Flat White Paints 27.88 - 2 coats
Floor Oil Paint Stain 55.76 - 1 coat
Enamel Floor 23.23 - 2 coats
Wall Side For Wall Board 27.88 - 1 coat
Aluminum 46.50 - 1 coat
Varnish 55.76 - 1 coat

Labor Estimate
1 Concreting of plain flooring - 2 men pour 1.20 cu.m. concrete /day
2 Concreting of reinf. Flooring - 2 men pour 0.84 cu.m. concrete /day
3 Concreting of column and beam - 2 men pour 0.50 cu.m. concrete /day
4 Finishing of flooring (rough) - 2 men finishes 72 sq.m./day
5 Finishing of CHB joints - 2 men finishes 420 pcs/day
6 Plastering of CHB - 2 men plaster 8 sq.m./day
7 Laying of CHB - 2 men lay 100 pcs/day
8 Laying of glazed tile 4x4 - 2 men lay 100 pcs/day
9 Laying of glazed tile 6x6 - 2 men lay 44 pcs/day
Laying of glazed tile 8x8 - 2 men lay 25 pcs/day
Laying of glazed tile 10x10 - 2 men lay 16 pcs/day
Laying of glazed tile 20x20 - 2 men lay 4 pcs/day
10 Installation of water closet - 2 men install 1 set w.c./2 days
11 Installation of lavatory - 2 men intall 1 set lav/1-1/2 day
12 Installation of GI sheet - 2 men install 11 sheets/day
32x8 on steel frames
13 Installation of GI sheet - 2 men intall 20 sheets/day
32x8 on wooden frames
14 Installation of GI sheet - 2 men install 10 sheets/day
32x12 on steel frames
15 Installation of GI sheet - 2 men install 15 sheets/day
32x12 on wooden frames
16 Installation of door and window jamb - 1 man install 3pcs 2x5x16 or 40 bd.ft./day
17 Installation of door - 1 man install 2pcs door/day
(complete with hinges and knob)

Construction Work Capacities in Manhours


I. EARTHWORK
1 Excavation - 1.82 to 2.89 mahours/cu.m.
2 Backfill - 134 manhours/cu.m.

II. FORMWORKS
1 Footing, column - 2.5 manhours/sq.m.
2 Beams, floor slab - 2.8 manhours/sq.m.
3 Roof beams - 3.01 manhours/sq.m.
4 Roof slabs - 3.34 manhours/sq.m.
5 Stairs and landing - 2.48 manhours/sq.m.

III. DEMOLITION
1 Elevated slab
a. with pneumatic breaker - 3.28 manhours/cu.m.
b. by hand with sledge - 16.24 manhours/cu.m.
2 Concrete walls
a. with pneumatic breaker - 1.03 manhours/cu.m.
b. by hand with sledge - 14.41 manhours/cu.m.

IV. REINFORCING BARS - 80 kgs/manday

Capabilities of Manual Labor per Hour


1 Man a. excavating loam or sand - 0.76 cu.m.
b. excavating clay or heavy soil - 0.61 cu.m.
c. excavating rock - 0.38 cu.m.
d. backfilling - 1.22 cu.m.
e. spreading, tamping and grading - 2.09 cu.m.
f. from vangie - 1.50 cu.m/manday

2 1 mason a. laying of CHB - 22 pcs


& b. cement finish - 28 sq.m.
1 helper

3 1 carpenter a. erecting forms - 1.86 sq.m.


& b. removing forms - 1.86 sq.m.
1 helper

Capabilities of Equipment
1 dozer a. clearing - 500 sq.m./hr
b. stripping - 200 sq.m./hr
c. excavation - 25 cu.m./hr
d. quarrying - 50 cu.m./hr
e. pushing - 3 sq.m./hr

2 grader a. sub-grading - 300 sq.m./hr


b. spreading - 40 cu.m./hr

3 payloader a. loading - 30 cu.m./hr

4 crane shovel a. loading - 35 cu.m./hr

5 roller a. vibratory rolling - 135 cm/hr


(4 passes-15cm lift)

6 5-T dump truck a. hauling common borrow - 3.5 cu.m./truck


b. hauling selected borrow base coarse - 5 cu.m./truck

6 5-T dump truck a. hauling common borrow - 3.5 cu.m./truck

7 water truck a. watering - 1000 sq.m./hr.

8 a. clearing and grubbing - 2400 sq.m./day

ROUGH ESTIMATES
1 Form lumber - 100 bd.ft./cu.m.
2 Cement - 10 bags/cu. in plaster
3 Steel reinforcement - 100 to 130 kgs/cu.m. of concrete
- 80 kgs/manday
4 Roof framing - 14 bd.ft./sq.m. of roof area
5 Ceiling framing - 7 bd.ft./sq.m. of ceiling
6 Nails - 20 kgs/1000 bd.ft.
7 Studdings, 2x3 - 4 bd.ft./sq.m.
8 Siding - 10.7 bd.ft./sq.m.
9 Flooring - 10.8 bd.ft./sq.m.
10 Floor joists, 2x6 - 15 bd.ft./sq.m.
11 Ceiling joists, 2x2 - 4 bd.ft./sq.m.
12 Purlins, 2x4 - 4.4 bd.ft./sq.m.
13 GI sheets, 32x8 - 0.7238 pcs/sq.m.
14 Roof nails, 2-1/2 - 0.082 kgs/sq.m.
15 Rivets, 3/8 x 1/4 - 0.0069 kgs/sq.m.
16

STONE MASONRY
a. Concrete = 40% of volume of stone masonry
Boulders = 60% of volume of stone masonry

b. Volume of concrete

Cement = volume of concrete x 17.90 + 3% (wastage factor)


Sand = volume of concrete x 1.00 + 5% (wastage factor)

GROUTED RIPRAP
a. Concrete = 30% of volume of stone masonry
Boulders = 70% of volume of stone masonry

b. Volume of concrete

Cement = volume of concrete x 13.00 + 3% (wastage factor)


Sand = volume of concrete x 1.00 + 5% (wastage factor)
Table 5.2 QUANTITY OF PLYWOOD FORM AND ITS FRAME
FOR COLUMNS PER SQ.M. LATERAL AREA
Frame or Ribs
Plywood
No. of Pcs (bd.ft./sq.m.)
size in m. 2x2 2x3
0.90 x 1.80 0.842 12.71 18.96
1.20 x 2.40 0.488 12.71 18.96

Table 5.3 QUANTITY OF LUMBER FORM FOR CIRCULAR COLUMN

BD. FT. / plain GI sheet


Lumber Size Spacing of frame
10.00 cm 12.50 cm 15.00 cm 20.00 cm
1" x 2" 11.70 10.00 8.50 6.50
2" x 2" 23.39 20.00 17.00 13.00
2" x 3" 35.08 30.00 25.50 19.50
1" x 8" 7.70 7.70 7.70 7.70
1" x 10" 9.62 9.62 9.62 9.62
1" x 12" 11.54 11.54 11.54 11.54
1" x 14" 13.47 13.47 13.47 13.47

Table 5.4 FORM FOR BEAMS AND GIRDERS

LUMBER FRAME
Plywood Number
(bd.ft. / plywood)
size in m. per sq.m. 1x2 2x2 2x3
0.90 x 1.80 0.81 8.00 16.00 24.00
1.20 x 2.40 0.42 16.00 32.00 48.00

Table 5.5 QUANTITY OF LUMBER FOR SCAFFOLDING OR


STAGING

COLUMN BEAM
FLOORING
Lumber Size (bd.ft./ meter ht) (bd.ft./ meter lnth)
Vertical Horizontal Brace Vertical Horizontal (bd.ft./sq.m.)
2" x 2" 4.67 21.00 11.67 4.00 4.67 6.10
2" x 3" 7.00 31.67 17.50 6.00 7.00 9.10
2" x 4" 9.33 42.22 23.33 8.00 9.33 12.10
Equipment Specification Material to be hauled Capacity

1 Cargo truck 195 hp, 6-8 tons cement 150 bags/trip


plywood 250 shts/trip
lumber 4,000 bd.ft./trip
DRB, CWN, tie wire 6,000 kgs/trip

2 Dump truck 220hp, 6 cu.m. sand/gravel 6 cu.m./trip

3 Loader WA120-3, 1.15-1.45 cu.m. sand/gravel 80 cu.m./hr

You might also like