CHB REINFORCEMENT
* Note : Tile Adhesive coverage (5-7 sq.m. / 25kg bag) Tile Adhesive/cement paste coverage (3kg/sq.m.)
Tile Grout coverage (4-5 sq.m. / 2kg bag)
Tile Grout coverage (10-12 sq.m. / 5kg bag)
PAINT COVERAGE
Kinds of Paint Coverage per sq.m.
Wood Preservation 9.30 - 1 coat
Outside Lead Oil 27.88 - 2 coats
Flat White Paints 27.88 - 2 coats
Floor Oil Paint Stain 55.76 - 1 coat
Enamel Floor 23.23 - 2 coats
Wall Side For Wall Board 27.88 - 1 coat
Aluminum 46.50 - 1 coat
Varnish 55.76 - 1 coat
Labor Estimate
1 Concreting of plain flooring - 2 men pour 1.20 cu.m. concrete /day
2 Concreting of reinf. Flooring - 2 men pour 0.84 cu.m. concrete /day
3 Concreting of column and beam - 2 men pour 0.50 cu.m. concrete /day
4 Finishing of flooring (rough) - 2 men finishes 72 sq.m./day
5 Finishing of CHB joints - 2 men finishes 420 pcs/day
6 Plastering of CHB - 2 men plaster 8 sq.m./day
7 Laying of CHB - 2 men lay 100 pcs/day
8 Laying of glazed tile 4x4 - 2 men lay 100 pcs/day
9 Laying of glazed tile 6x6 - 2 men lay 44 pcs/day
Laying of glazed tile 8x8 - 2 men lay 25 pcs/day
Laying of glazed tile 10x10 - 2 men lay 16 pcs/day
Laying of glazed tile 20x20 - 2 men lay 4 pcs/day
10 Installation of water closet - 2 men install 1 set w.c./2 days
11 Installation of lavatory - 2 men intall 1 set lav/1-1/2 day
12 Installation of GI sheet - 2 men install 11 sheets/day
32x8 on steel frames
13 Installation of GI sheet - 2 men intall 20 sheets/day
32x8 on wooden frames
14 Installation of GI sheet - 2 men install 10 sheets/day
32x12 on steel frames
15 Installation of GI sheet - 2 men install 15 sheets/day
32x12 on wooden frames
16 Installation of door and window jamb - 1 man install 3pcs 2x5x16 or 40 bd.ft./day
17 Installation of door - 1 man install 2pcs door/day
(complete with hinges and knob)
II. FORMWORKS
1 Footing, column - 2.5 manhours/sq.m.
2 Beams, floor slab - 2.8 manhours/sq.m.
3 Roof beams - 3.01 manhours/sq.m.
4 Roof slabs - 3.34 manhours/sq.m.
5 Stairs and landing - 2.48 manhours/sq.m.
III. DEMOLITION
1 Elevated slab
a. with pneumatic breaker - 3.28 manhours/cu.m.
b. by hand with sledge - 16.24 manhours/cu.m.
2 Concrete walls
a. with pneumatic breaker - 1.03 manhours/cu.m.
b. by hand with sledge - 14.41 manhours/cu.m.
Capabilities of Equipment
1 dozer a. clearing - 500 sq.m./hr
b. stripping - 200 sq.m./hr
c. excavation - 25 cu.m./hr
d. quarrying - 50 cu.m./hr
e. pushing - 3 sq.m./hr
ROUGH ESTIMATES
1 Form lumber - 100 bd.ft./cu.m.
2 Cement - 10 bags/cu. in plaster
3 Steel reinforcement - 100 to 130 kgs/cu.m. of concrete
- 80 kgs/manday
4 Roof framing - 14 bd.ft./sq.m. of roof area
5 Ceiling framing - 7 bd.ft./sq.m. of ceiling
6 Nails - 20 kgs/1000 bd.ft.
7 Studdings, 2x3 - 4 bd.ft./sq.m.
8 Siding - 10.7 bd.ft./sq.m.
9 Flooring - 10.8 bd.ft./sq.m.
10 Floor joists, 2x6 - 15 bd.ft./sq.m.
11 Ceiling joists, 2x2 - 4 bd.ft./sq.m.
12 Purlins, 2x4 - 4.4 bd.ft./sq.m.
13 GI sheets, 32x8 - 0.7238 pcs/sq.m.
14 Roof nails, 2-1/2 - 0.082 kgs/sq.m.
15 Rivets, 3/8 x 1/4 - 0.0069 kgs/sq.m.
16
STONE MASONRY
a. Concrete = 40% of volume of stone masonry
Boulders = 60% of volume of stone masonry
b. Volume of concrete
GROUTED RIPRAP
a. Concrete = 30% of volume of stone masonry
Boulders = 70% of volume of stone masonry
b. Volume of concrete
LUMBER FRAME
Plywood Number
(bd.ft. / plywood)
size in m. per sq.m. 1x2 2x2 2x3
0.90 x 1.80 0.81 8.00 16.00 24.00
1.20 x 2.40 0.42 16.00 32.00 48.00
COLUMN BEAM
FLOORING
Lumber Size (bd.ft./ meter ht) (bd.ft./ meter lnth)
Vertical Horizontal Brace Vertical Horizontal (bd.ft./sq.m.)
2" x 2" 4.67 21.00 11.67 4.00 4.67 6.10
2" x 3" 7.00 31.67 17.50 6.00 7.00 9.10
2" x 4" 9.33 42.22 23.33 8.00 9.33 12.10
Equipment Specification Material to be hauled Capacity