You are on page 1of 1

ECONOMIC DIA STATEMENT OF RISING-MAIN

NAME OF WORK:- PROVIDING IRRIGATION FACILITY UNDER HP SHIVA PROJECT FOR CHAUNTRA,GOPALPUR AND DHARAMPUR BLOCKS, DISTRICT MANDI(HIMACHAL PRADESH)- PACKAGE-07
Name of Scheme:- LIS Bairi, Block Dharampur
Rising Main:- Existing Pump House to Existing Tank (Only Pumping Machinery is to be provided)
Jan. Feb. Mar. Apr. May. Jun. Jul. Aug. Sep. Oct. Nov. Dec.

MSERW PIPE (IS/ISO:3183-2007) GMS TUBE (IS:1239-1990/2004 -Part


Daily Water Requirement of 10.44 Hect. (lps) 8.07 8.07 8.07 8.07 8.07 8.07 8.07 8.07 8.07 8.07 8.07 8.07 PIPE RATE
Pumping Hour per day 16.00 16.00 16.00 16.00 16.00 16.00 16.00 16.00 16.00 16.00 16.00 16.00 Dia.of Pipe Rate
Pumping Hour per Month 496.00 448.00 496.00 480.00 496.00 480.00 496.00 496.00 480.00 496.00 480.00 496.00 25 mm 177.70
32 mm 237.00
40 mm 271.30
50 mm 430.50
DATA CALCULATION :- 65 mm 630.00
1 Peak average Daily water requirement = 8.07 lps 1 Water requirement (mld) = 0.697 mld 80 mm 716.00
2 Pumping hour = 16.00 Hrs 2 Annual Pumping Hours = 5840.000 hours 100 mm 930.50
3 Design Discharge = 12.10 lps 3 Average Pumping Hours = 16.000 hours 125 mm 1250.00
4 Length of Rising Main = 200.00 Rmt 4 Static Suction Lift = -0.600 m 150 mm 1955.70
5 R.L. of Highest Discharge Point = 699.36 m 5 Static Delivery head = 204.509 m 200 mm 2778.02
6 Pump Shaft Level = 494.85 m 6 Design Discharge (klpd) = 1045.440 klpd 250 mm 3477.72
7 LWL in the Well/source = 495.45 m 300 mm 4071.21
8 Cost of Pumping Unit /K.W. = 8713.00 /- 350 mm 4546.44
9 Class of Pipe = GI PIPE 400 mm 5205.63
10 Value of 'C' = 100.00 450 mm 5861.54
11 %age of stand bye pumping set = 100.00 % 500 mm 7597.11
12 Design Period of Pumping Machinery = 15.00 Yrs. 600 mm 7839.11
13 Energy Charges per KWH = 3.50 /- 650 mm 9014.97
14 Combined Efficiency of P/Machinery = 0.60 700 mm 10367.22
15 Capital intrest rate = 8.50 % 750 mm 11922.30
16 Residual head = 3.00 m
S. Dia Frictional Velocity Total Losses Total KW Reqd. Cost of Cost of Total cost Annual Capitalised Total captl. Cost Capl. Cost of Total Cap. Most
No. of Losses/ Losses For Bends Head Including pump pipe per of pipe energy energy cost of pump & engy. pump & engy. cost for economical
Pipe 1000 m @ 10% stand-bye metre cost Ist 15 years for Ist 15 Yrs. for next 15 Yrs. 30 years dia
(mm) (m) (m/sec.) (m) (m) (m) (KW) (1000 Rs.) (Rs.) (1000 Rs.) (1000 Rs.) (1000 Rs.) (1000 Rs.) (1000 Rs.) (1000 Rs.) (mm)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
1 100 44.09 1.54 8.82 0.88 216.61 85.76 747.23 930.50 186.10 1752.93 14556.78 15304.01 4501.52 19991.63 0
2 125 14.87 0.99 2.97 0.30 210.18 83.21 725.01 1250.00 250.00 1700.81 14123.95 14848.96 4367.67 19466.63 0
3 150 6.12 0.69 1.22 0.12 208.26 82.45 718.39 1955.70 391.14 1685.28 13994.95 14713.34 4327.78 19432.26 150
4 200 1.51 0.39 0.30 0.03 207.24 82.05 714.90 2778.02 555.60 1677.10 13927.05 14641.95 4306.78 19504.34 0
5 250 0.51 0.25 0.10 0.01 207.02 81.96 714.12 3477.72 695.54 1675.26 13911.78 14625.90 4302.06 19623.50 0
The economical diameter of Rising Main is = 150 mm
DATA :- DESIGN OF PUMPING MACHINERY
1 Peak Design pumping rate = 12.10 lps Suction : Rising Main:
2 Pumping hours = 16.00 hrs 1 Friction Losses in sucn.pipe = 0.0612 m 1 Velocity in R.Main = 0.69 m/s
3 Length of rising main = 200.00 m 2 Velocity in Suction pipe = 0.6847 m/s 2 Friction losses in R.Main = 1.22 m
4 No. of pumping sets required = 1.00 sets 3 Velocity Head V^2/2g = 0.0239 m 3 Losses due to bends @ 5% = 0.06 m
5 Dia of rising main = 150.00 mm 4 Entrance Losses = 0.0112 m 4 Exit losses = 0.32 m
6 Static delevery lift (PSL-Delevery Pt.) = 204.51 m 5 Losses due to sluice Valve = 0.0119 m 5 Rasidual head = 3.00 m
7 Static sucn. Lift (PSL-LWL) = -0.60 m 6 Losses due to foot valve = 0.0000 m 6 Static head = 204.51 m
8 Detail of system :- Suction Delivery 7 Losses due to Bend = 0.0050 m 7 Velocity head(V^2/2g) = 0.02 m
a) Dia of pipe = 150 mm 125 mm 8 Losses due to expender = 0.0000 m Total losses = 209.14 m
b) Length of pipe = 10.00 m 5.00 m 9 Static Suction lift = -0.6000 m Total head = 207.89 m
c) No. of L.R. bends = 1.00 Nos. 1.00 Nos. Total losses = -0.4867 m Total BHP @ 60% efficiency = 61.49 HP
d) Foot valve = 0.00 Nos. 0.00 Nos. = 61.488 HP x 1
As per Ch. Curve
e) Sluce valve = 1.00 Nos. 1.00 Nos. Say = HP x 1
f) Reflux valve = 0.00 Nos. 1.00 Nos. Delivery: NPSHA
g)Unequal T = 0.00 Nos. 1.00 Nos. 1 Velocity in delevery pipe = 0.9860 m/s Losses in NPSH due to V. Pressure = 0.2373 m
h) Expender(increaser) = 0.00 Nos. 1.00 Nos. 2 Friction losses in delry. pipe = 0.0744 m Losses in NPSH due to Atm. Press. = 1.06 m
10 Altitude of Pump house = 880.00 m above MSL 3 Velocity Head V2/2g = 0.0496 m Suction Head for NPSH = 0.00 m
11 Normal water temprature = 20.00 degree C 4 Losses due to sluice Valve = 0.0248 m NPSH available = 9.0367 m
As per Ch. Curve
5 Losses due to reflux valve = 0.0248 m Use 1 sets of HP each
6 Losses due to Bend = 0.0104 m with 1 set as stand-by 1 W + 1 SB
7 Losses due to expander = 0.0496 m Capacity = 12.10 lps each and
Total losses = 0.2334 m Total head = 208.00 meters

You might also like