PROJECT: ADMIN BLOCK NBWCCC, AT KOLKATA.

Sl No Description of item Unit Quantity Duration Start Date Completion Date

Earth Excavation
Tank (1,2,3,4) Excavation Work Nos 4 2 03/11/2023 05/11/2023
Pile Cap (Column No- C16,C13,C9,C6& C3) Nos 5 2 06/11/2023 08/11/2023
Pile Cap (Column No- C15,C12,C8,C5& C2) Nos 5 2 09/11/2023 11/11/2023
Pile Cap (Column No- C14,C11,C7,C4& C1) Nos 5 2 12/11/2023 14/11/2023
P.C.C. Work
Tank (1,2,3,4) P.C.C. Work Nos 4 1 06/11/2023 07/11/2023
Pile Cap (Column No- C16,C13,C9,C6& C3) Nos 5 1 09/11/2023 10/11/2023
Pile Cap (Column No- C15,C12,C8,C5& C2) Nos 5 1 12/11/2023 13/11/2023
Pile Cap (Column No- C14,C11,C7,C4& C1) Nos 5 1 15/11/2023 16/11/2023
Tank & Pile Cap Reinforcement
Tank (1,2,3,4) Botom Reinforcement Nos 4 2 08/11/2023 10/11/2023
Tank (1,2,3,4) Vertical Reinforcement Nos 4 2 15/11/2023 17/11/2023
Tank (1,2,3,4) Top Reinforcement Nos 4 2 18/11/2023 20/11/2023
Pile Cap (Column No- C16,C13,C9,C6& C3) Nos 5 3 11/11/2023 14/11/2023
Pile Cap (Column No- C15,C12,C8,C5& C2) Nos 5 3 15/11/2023 18/11/2023
Pile Cap (Column No- C14,C11,C7,C4& C1) Nos 5 3 18/11/2023 21/11/2023
Tank & Pile Cap Shuttering Work
Tank (1,2,3,4) Raft Side Shuttering Nos 4 2 11/11/2023 13/11/2023
Tank (1,2,3,4) Wall Shuttering Nos 4 4 18/11/2023 22/11/2023
Tank (1,2,3,4) Top Shuttering Nos 4 4 21/11/2023 25/11/2023
Pile Cap (Column No- C16,C13,C9,C6& C3) Nos 5 3 15/11/2023 18/11/2023
Pile Cap (Column No- C15,C12,C8,C5& C2) Nos 5 3 19/11/2023 22/11/2023
Pile Cap (Column No- C14,C11,C7,C4& C1) Nos 5 3 22/11/2023 25/11/2023
Tank & Pile Cap Casting Work
Tank (1,2,3,4) Raft Casting Nos 4 1 13/11/2023 14/11/2023
Tank (1,2,3,4) Wall Casting Nos 4 1 22/11/2023 23/11/2023
Tank (1,2,3,4) Top Casting Nos 4 1 25/11/2023 26/11/2023
Pile Cap (Column No- C16,C13,C9,C6& C3) Nos 5 1 18/11/2023 19/11/2023
Pile Cap (Column No- C15,C12,C8,C5& C2) Nos 5 1 23/11/2023 24/11/2023
Pile Cap (Column No- C14,C11,C7,C4& C1) Nos 5 1 26/11/2023 27/11/2023
Pile Cap Dismentaling
Pile (Column No- C16,C13,C9,C6& C3) Nos 13 2 08/11/2023 10/11/2023
Pile (Column No- C15,C12,C8,C5& C2) Nos 20 3 11/11/2023 14/11/2023
Pile (Column No- C14,C11,C7,C4& C1) Nos 14 3 14/11/2023 17/11/2023
Back Filling 29/11/2023
Ground Floor P.C.C Work 30/11/2023