You are on page 1of 2

Checklist of Approval of GAD of ROB/RUB Works :-

Name of Work:-

Sr. Descriptions Remarks/


No. Comments
1. Total TVU
2. ROB Designed for
3. Skew Angle
4. Whether the feasibility has been carried out or not ?
5. Whether the encroachment free Right of Way (ROW) is available?
6. Proposed carriageway width of Bridge/ROB/RUB (including future planning if
any).
7. Existing Right of way (EROW) in meters.
8. Proposed Right of way (PROW). Whether proposed ROB is within available
ROW.
9. Whether any land acquisition involved?
10. Land demarcation done or not.
11. Whether work is approved in railway work programme.
12. Whether provision of RUB/LHS has been taken in case of ROB?
13. Size of LHS
14. Whether the provision of stair case has been taken in case of ROB?
15. Whether any utility shifting like HT Line/ LT Line is involved
including raising for maintenance of requisite clearance? If yes,
provision thereof.
16. Whether any forest clearance is involved? If yes, provision thereof.
17. Whether any utility shifting of sewerage/ water pipeline is involved? If yes,
provision thereof.
18. Whether the provision for alternate route/diversion road has been taken?
19. Whether the design consultant has certified that the design is economical
and a certificate has been incorporated on drawings?
20. Whether all the detailed structural drawings duly proof checked and
structural safety certificate received from IIT/NIT/PEC?
21. Whether the detailed plans/GAD/NOC has been approved by the
competent authority/Railway?
22. Whether any litigation is ongoing w.r.t. the proposed structure / road?
23. Cost born by state or 50: 50 share basis.
Railway portion
24. Total length of R.O.B i/c railway portion
25. Railway boundary
26. Railway span
27. Vertical clearance
28. Total width of ROB in Railway Portion
29. Clear carriage way in Rly. Span
30. Type of Pier
31. Thickness of deck slab.
32. Wearing coat
33. Type of Bearing
34. Type of girder
35. Type of foundation
36. Dia of Pile
37. Depth of Pile
PWD portion
38. Width of ROB in PWD portion
39. Clear carriage way
40. P.W.D via duct portion
41. Span arrangement
42. Type of wall
43. Maximum height of RE-wall/ Retaining wall
44. P.W.D Solid fill portion
45. Treatment under approach
46. Type of Girders
47. Thickness of Deck slab
48. Gradient/ Slope
49. FRL
50. RTL
51. Width of Service Lane
52. Crust detail of service road
53. Wearing coat
54. Diversion Plan

Consultant EE SE