Name of village: Warapoka Village
Team leader: Hillary Henry
Presenter: Newton Wilson
NAME OF VILLAGE PROJECT: WARAPOKA ECO-TOURISM
EXECUTIVE SUMMARY
Warapoka Eco tourism were birthed in 2016. This initiative was to
introduced to village council and residents at village generals
meeting and stake holder’s gatherings. The executive board was
formed with eight persons; these persons includes a secretary,
tourism manager, treasurer and committee members. Training and
capacity building were done in areas of Accounting & Financial
management, Tour guiding, Culinary, birding, management and
hospitality.
PROJECT DECRIPTION
Goals
safe access to farmland and harpy nesting site
Objectives
- Famers to safely transport crops/produce
- Guest to traverse safely to and fro from the harpy eagle nesting site
- Provide safe access for educational tours i.e. school children
Activities/Methods
Building of 480 feet bridge across the source of the Warapoka source:
Creating a draft estimate of materials necessary for the bridge
A draft of a blue print for the bridge
Selection of skilled persons by management committee and village
council
Procuring of materials- wood etc.
Construction of bridge
Commissioning of the bridge
Time line
The project is estimated to take 5 months from commences to when it ends.
Key personnel
Role Level of effort Roles and Is this proposed candidate part of
responsibilities under the organization at the moment
the project ( yes/ no)
Project 100% Streamlined the
manager project Yes
Delegate duties
and
responsibilities
Ensure funding
is correctly
spent
Secretary 80% Enlisting names
of workers to Yes
carry out
project.
Reporting on
the general
aspect of the
project
Keep and store
financial records
of the projects
Treasurer 60% Make payments
Assist in Yes
preparing
proposals and
budgets
Financial
reporting to
funders
Construction 100% Measuring of
Workers the length and Yes
width of the
bridge.
Preparation of
building site
Construction of
the bridge
Tourism
manager
Building Materials
480 2x12x4 flooring 3840 bm 250 960,000
98 4x4x8- posts 1046 bm 250 261,500
26 2x6x20-length beam 260 bm 250 65,000
48 2x4x20-Railing 640 bm 250 160,000
50 2x6x6- cross beam 300 bm 250 75,000
98 2x5x12 braces 980 bm 250 245,000
48 3x8x6- anchors 576 bm 250 144,000
294 Bolts and nuts Each 600 176,000
4 Gallons tar Per 5,000 20,000
40 lbs. 4” galvanise spikes Each 700 28,000
30 lbs. 2 ½ wire nails Per 400 12,000
10 Gallons oil paint Each 7000 70,000
8 Paint brush 4 “ Each 1,000 8,000
Manual Labor
3 persons 45 days Each 18,000 810,000
1 leader 45 days Each 7,000 315,000
Transportation
3 Georgetown for 3 days Each 93,333 280000
Communication
20 $ 1000 Phone cards Each 1000 20000
Accommodation
3 Hotel Each 23000 69000
Meals
3 3 days- Meals Each 2000 20000
MACHINERY Rental
20 Machinery 4000 80000
2 20 days -Labourers 5000 200000
5 Gallons Gas 1700 8500
Sub total 4,110,900
Cover Letter
Date: 30/03/2022
Than you
HILLARY HENRY
Secretary tourism committee.