Professional Documents
Culture Documents
1 Objectives of Project:-
a___________ To reduce the consumtion of electric energy as compared to AC
b___________ To eliminate the consumption of water by using a closed heat exchanger system.
c. To provide a economic option to the economic weaker section to enjoy the cool air in scrotching summmers.
d.
2 Outcomes of Project:- (Research Publication/ Patent)
a___________ A patent can be filed as well as research paper can be published.
b___________ The modified deisgned air cooler may be installed in some of the offices and hostels of BFGI.
c___________________________________________________________________________________________
3 Cost demnaded along with detail description:-
S.no Item Name Cost
Proposed Vendors along with Address
Air Cooler 4000/- To be purchased from local market
Refrigerator compressor assembly 4000/- To be purchased from local market
Bombay Metals & Alloys, Gill Rd, opposite SBI Bank, Miller
Heat exchanger aluminum pipes 10,000/-
Ganj, Ludhiana, Punjab 141003
Activity 2 Prearation of air cooler body as per design 6 April to 8 April, 2024
Activity 4 Assembly of refirgerator unit with air cooler 9 April to 15 April, 2024