Professional Documents
Culture Documents
Plan
Information Technology
05007-PLN-P990000-06-00040 Revision 2
Prepared for
17 September 2015
Appendices
APPENDIX A ................................................................................................................................................... 27
APPENDIX B ................................................................................................................................................... 41
APPENDIX C ................................................................................................................................................... 46
Tables
Table 3-1. Workshops Example............................................................................................................... 7
Table 5-1. AIA Level of Development Overview Applicable to Expo 2020 ............................................. 9
Table 5-2. Responsibilities for Design Consultants and Contractors .................................................... 10
Table 6-1. Software Usage Table Overview .......................................................................................... 12
Table 7-1. COBie Sheets and Data Drop Requirements ........................................................................ 14
Figures
Figure 2-1. Level One Process Map Example .......................................................................................... 3
Figure 3-1. Information Exchange Worksheet Extract ............................................................................ 6
Figure 5-1. Model Element Definition Worksheet Extract.................................................................... 11
Figure 7-1. COBie Information Structuring ........................................................................................... 14
Acronym/Abbreviation Expansion
BIM Building Information Modelling
CAD Computer-aided Design
CFD Computational Fluid Dynamics
COBie Construction Operations Building Information Exchange
DLTM Dubai Local Transverse Mercator
EX20 Bureau Expo Dubai 2020
FF&E Furniture, Fixtures and Equipment
GIS Geographic Information System
IFC Industry Foundation Classes
LOD Level of Development
MEP Mechanical, Electrical and Plumbing
PMC Programme Management Consultant
PMDS Programme Management Delivery System
PEP Project Execution Plan
WBS Work Breakdown Structure
Definitions
Term Definition
2D Two-dimensional graphical data.
Cost / Quantification (5D) Generate accurate quantity take-offs and cost estimates. Providing
‘what if’ analysis capabilities to assess modifications to design or
programme.
Family Type Different elements belonging to a family may have different values
for some or all of their parameters, but the set of parameters (their
names and meanings) is the same. These variations within the
family are called family types or types.
FM and Asset Management 3D model based system that will efficiently aid in the maintenance
and operation of a facility and its assets.
Level Bentley term used to separate graphic elements for display control
in drawing files. See Layer.
Level of Development Refers to five basic levels of development created by the American
Institute of Architects in reference to model content.
PDF Portable Document Format – A file format that captures all the
elements of a printed document as an electronic image that you can
view, navigate, print or forward. PDF files are views using Acrobat
Reader available from Adobe.
Reference File Term used to refer to files that are displayed for reference purposes
from another file.
Every element of a project does not need to be present to be valuable therefore, it is important to
only define the model elements that are necessary to implement BIM for each BIM use. If a receiver
of information wants to be sure he or she can utilise the information received, the sender and
receiver need to agree on which information to exchange. For example, an architect needs to be
sure that they receive information from the structural engineer in regard to which walls and columns
are structurally load-bearing. Similarly, the structural engineer needs to know the use characteristic
of the enclosures in order to calculate the correct design loads.
In addition, for BIM to be implemented successfully, it is critical that team members consider the
future use of the information that they are developing – cost/quantities, schedule, etc.
Each Discipline Lead Review Model Output items and Workshop to occur at each project
identify the exchange, responsible stage to ensure each area has the
party, format, version, etc. information needed to develop a
collaborative BIM model
Model Authoring
Existing
Conditions
Modelling
Engineering
Analysis
Visualisation
Space
Programming
Design Reviews
3D Coordination
Cost Estimation /
Quantification
(5D)
Sustainability
Schedule
Sequencing (4D)
Construction
Progress
Monitoring
Record
Modelling
Facilities
Management &
Asset
Management
The BIM Use ‘Facilities and Asset Management’ is a requirement for applicable COBie drops. It is only in the
Operation stage that the digitally enabled FM solution shall be developed.
COBie Sheets
Component
Connection
Coordinate
Document
Data Drop
Assembly
Resource
Attribute
Completion of Phase
Contact
System
Facility
Impact
Space
Spare
Floor
Issue
Zone
Type
Job
Concept 0 x
Developed Design 1 x x x x x x x x x x
Technical Design 2 x x x x x x x x x x x x x x x
Construction 3 x x x x x x x x x x x x x x x
Handover and Closeout 4 x x x x x x x x x x x x x x x x x x
For an example of the COBie worksheet and the data required refer to ‘Appendix C’. All parameters
to fulfil the COBie requirements shall be included in BIM model objects for the authoring of the
design. These parameters shall be used by the design consultant as shared parameters to ensure the
appropriate output of the information upon completion of the design stages. The shared parameter
file shall be handed over to the Contractor for completion during the construction phase of the
project.
7.2 3D Coordination
Models from the design authoring stage will be combined in a multi-disciplinary environment to
enable clash detection to be deployed. This section of the BIM PEP needs to detail
(description/diagram) the agreed strategy. The colour table below is to be implemented as a basis to
support the easy differentiation of the trades contained in a consolidated model it is subject to
revision or further refinement by the project team:
Table 7-2. Coordination Colours
Drainage DRA 0 64 0 0%
Minor Group
Minor Group
Major Group
Designator
Discipline
Hyphen
Hyphen
Hyphen
Hyphen
Status
Required Optional
AR - W A L L
AR - W A L L - F U L L
AR - W A L L - F U L L - T E X T
AR - W A L L - F U L L - T E X T - N
Description of Modules
Layer/Level names consist of up to 5 components:
• Discipline Designators: Character code to identify the discipline to be used.
- (ex: 04 = Architectural)
• Major Group: Four character code to identify a major building system type.
- (ex: 04-WALL = Architectural Wall)
• Minor Group 1: Optional four character code to further define the Major Group.
- (ex: 04-WALL-FULL = Architectural Full Height Wall)
• Minor Group 2: Optional four character code to further define Minor Group 1.
- (ex: 04-WALL-FULL-TEXT = Architectural Full Height Wall, Text)
• Status: Identifies the status or phase of the layer/level.
- (ex: 04-WALL-FULL-TEXT-N = Architectural Full Height Wall, Text, New)
Code Description
BEAM Beams
BRAC Bracing
BRDG Bridge
CASE Casework
CLNG Ceiling
COLS Columns
COMM Communications
Code Description
DECK Decking
DOOR Doors
DRIV Driveways
EQPM Equipment
FENC Fences
FLOR Floor
FNDN Foundation
FNSH Finishes
FURN Furnishings
GLAZ Glazing
HVAC HVAC
JNTS Joints
JOIS Joists
MILL Millwork
Code Description
POWR Power
PRTN Partitions
PVMT Pavement
ROOF Roof
RRAP Riprap
SLAB Slab
SOIL Soils
STRS Stairs
SWLK Sidewalks
WALL Walls
WATR Water
Code Description
ACCS Access
BOTD Bottom
BRCK Brick
BRGX Bridging
CASE Casework
CIRC Circuit
CONC Concrete
CURB Curbs
DEVC Devices
DISC Discharge
DMPR Damper
DOOR Door
Code Description
DRAN Drainage
DUCT Ductwork
ELECT Electrical
EQPM Equipment
FNSH Finishes
FRAM Framing
FREE Freestanding
FTNG Footings
GRAT Grates
HORZ Horizontal
Code Description
HRDW Hardware
Instrumentation (meters,
INST transformers)
INTR Interior
JACK Jacks
LOWR Lower
MHOL Manhole
MILL Millwork
MISC Miscellaneous
Movable equipment or
MOVE elements
MSNW Masonry
OBJT Objects
Code Description
OVHD Overhead
PANL Panels
PILE Piles
POLE Pole
POST Posts
PRCH Porch
RAIS Raised
RISR Riser
SEAT Seating
SHLF Shelving
SIGN Signage
SILL Sill
SLVE Sleeve
STEL Steel
Code Description
STOR Storage
STRC Structures
SUSP Suspended
SWCH Switches
UNDR Underground
UTIL Utilities
VALV Valves
VENT Vent
VERT Vertical
WIRE Wiring
WOOD Wood
XFMR Transformers
Fenceline1
Gas Line
Hydraulic
Table 9-3. Weight
10 Abbreviations
10.1 Overview
The standard abbreviations shall be used consistently on all drawings to clearly specify information
and conserve space. See BIM Drawing Standards Manual, Appendix C (Doc. Ref. No: 05007-GDL-
P000000-06-00090) for a complete list of standard abbreviations.
Term Definition
3D Micro Coordination Coordination within a discipline
3D Macro Coordination Conflict resolution and coordination between all disciplines and
across the project
Virtual Prototype Assemblies for manufacturing; energy analysis, structural
analysis, etc. to reduce time to market
Historical Site Information Historical Site Information Includes any elements above the
surface and all underground utilities, horizontal and vertical
datum, control points, etc.
Laser Scanning Used to rapidly capture existing shapes of objects, buildings,
etc. delivering information in point clouds
Point Cloud Survey A method of generating a BIM model from an existing building
through the use of laser technology. It creates a digital 'cloud' of
geometric points. This data can be generated to create the
geometry of a building, objects, etc.
Parametric Modelling Parametric Modelling Using the computer to design objects by
modelling their components with real-world behaviours and
attributes. Parametric Modelling uses parametric constraints to
define and easily modify part features, and to create
relationships between these features in order to create
intelligent part models. These virtual parts can then be
combined to form assembly models.
Information Exchange Bidirectional information sharing; identification of model
elements that will be exchanged and who is responsible to
ensure that exchange occurs.
Composite Model The compilation of multiple models referenced together to
create a single model showing all elements collaboratively.
Coordination Model A composite model used for clash detection, design reviews
and simulated walk-throughs.
Design Review Information Documented actions as a result of the design review meeting.
Note who is responsible to adjust model elements that were
identified as conflicts or
Map 1.1 – BIM Process Overview Map - DESIGN Process Map/BIM Workflow
A.01_BIM_PlanningProcessMap.ppt [Q22-APW-CMN-PMC-REP-0257]
DC DC
Concept Design QA/QC Developed Design QA/QC Technical Design Process subject to further development
Author Model Author Model Update Space
Programme
Concept Create 4D Sequencing Create 4D Sequencing
Design All
Map 2.1 Model All Disciplines Map 2.1 Model Architecture Map 2.4
Disciplines
Perform 3D Coordination
All All
Map 2.6 Map 2.6
Disciplines Disciplines
Estimation
Action ARC MEP 3D Design ARC MEP ARC MEP
Model Model Review Model Model 4D.Model
Model
Model Model 4D.Model
Lead Task
Structural Structural
Analysis Analysis Construct.
Abbreviations:: STR CIV Model Review
STR CIV Model
STR CIV
ARC - Architecture Model Model Model
3D Visual- Model Model 3D Design
Model Model
STR - Structure Review
ization 3D Design
MEP- Mech./Elec./Plumb. Model
Review
CIV - Civil works Model
Exist. 3D Visual-
PM - Project Manager COBie COBie
Cond. ization COBie
DC - Design Consultant data data
Model data
MC - Main Contractor
Map 1.2 – BIM Process Overview Map - CONSTRUCTION Process Map/BIM Workflow
A.01_BIM_PlanningProcessMap.ppt [Q22-APW-CMN-PMC-REP-0257]
Design
Process subject to further development
Infor-
mation
DC
QA/QC
Evaluate Sustainability Perform Cost Estimate
DC parameters
PM Cost Map 2.7
QA/QC MC All Consultant
TBD
Disciplines
BIM USES
Perform 3D Coordination
Sustain.
Analysis
Model
Shop 3D
4D Progress Handover FM and
Drawings 3D Coord. Model Record
Asset Model
Model Documents Model
Legend:
ARC MEP 5D Cost
Model Model Estimation
ARC MEP
Phase
OUTPUT
Model Model
Action 3D Design
Review
Model
Lead Task STR CIV
Model Model Digital STR CIV
Fabrication Model Model
Abbreviations:: Model
ARC - Architecture Constr.
STR - Structure Planning
MEP- Mech./Elec./Plumb. COBie Model
COBie
CIV - Civil works Data 3
Data 4
PM - Project Manager
DC - Design Consultant
MC - Main Contractor
Map 2.1 – Model Authoring Process Map/BIM Workflow
A.03_BIM_DesignAuthoringProcessMap.ppt [Q22-APW-CMN-PMC-REP-0257]
BIM PMP
Require-
Existing
Conditions
Concept
Parametric
Modelling
Space Process subject to further development
Design Validation
INPUT
Create STR Model Update STR Model Update STR Model Update STR Model
DC DC
PROCESS STEPS
DC
QA/QC QA/QC
Create ARC Model QA/QC Update ARC Model Update ARC Model
NO
NO NO
Architect Architect Architect
Coordinate Interface
Identify Required Identify Information Points Between Venue, YES
YES Model meets Model meets YES
Design Models Exchanges Infra and Transport Model meets
requirements? requirements?
requirements?
All Disciplines All Disciplines PM/Discipline Leads
START END
PROCESS
Create MEP Model Update MEP Model Update MEP Model PROCESS
Legend:
Information Concept Design Developed Design Technical Design
Exchange
Action Worksheet
OUTPUT
Abbreviations::
ARC - Architecture
STR - Structure STR CIV STR CIV STR CIV
MEP- Mech./Elec./Plumb. Model Model Model Model Model Model
CIV - Civil works
PM - Project Manager
DC - Design Consultant
MC - Main Contractor
Map 2.2 – Existing Conditions Modelling Process Map/BIM Workflow
Historical Existing
Geotechnical Site/ Qatar
Topo Data Services
Report Facilities GIS Data
Data
Information
DC
PROCESS STEPS
QA/QC
Survey Existing Facilities
START END
PROCESS TBD PROCESS
Collect Current Site Create Existing Complete Existing
Conditions Data Conditions Model Conditions Information
TBD
Legend: Existing
Conditions
Survey
Information
Action Model
Model
OUTPUT
(GIS)
Lead
Abbreviations::
ARC - Architecture
STR - Structure
MEP- Mech./Elec./Plumb.
CIV - Civil works
PM - Project Manager
DC - Design Consultant
MC - Main Contractor
Map 2.3 – Engineering Analysis Process Map/BIM Workflow
Seismic
Soil Data Wind Loads Concept
Loads
Model
PROCESS STEPS
DC
QA/QC
NO
START END
PROCESS PROCESS
Export Model to Export Model to
Generate Structural Generate Structural Update Structural Design
Structural Analysis Analyze Model Results YES Structural Design
Layout Design Model Model
Application Accep- Application
table?
Structural Engineer Structural Engineer Structural Engineer Structural Engineer Structural Engineer Structural Engineer
Legend:
Action
OUTPUT
STR
Lead STR STR
Design
Analysis Design
Model
Model Model
Abbreviations:: (Draft)
ARC - Architecture
STR - Structure
MEP- Mech./Elec./Plumb.
CIV - Civil works
PM - Project Manager
DC - Design Consultant
MC - Main Contractor
Map 2.4 – Space Programming Process Map/BIM Workflow
Existing
Site
Conditions
Information
Model
Identify Building
PROCESS STEPS
Use/Type
Owner NOT
Acceptable
START Start Design END
PROCESS Programming PROCESS
Identify Area Validate Clients Generate Conceptual
Create Program Acceptable
Requirements Space Requirements Building Layout Program
Validation
Owner
Legend:
Space Space
Action Validation Program
OUTPUT
Lead
Abbreviations::
ARC - Architecture
STR - Structure
MEP- Mech./Elec./Plumb.
CIV - Civil works
PM - Project Manager
DC - Design Consultant
MC - Main Contractor
Map 2.5 – Design Reviews Process Map/BIM Workflow
Q22
Process subject to further development
INPUT
Contract Design
Project Design
Require- Renders and
BIM Models
ments Animations
PMP
Return to current
Design Authoring
Compile Design
Review Design
Review Feedback
Brief Compliance
All Disciplines
PM/Client
Review Space
Program
PM/Client
PROCESS STEPS
NO
Consolidate
Develop Schedule Define the Models Identify review Prepare Model for Review Create Action
Design Model for
for Design Review for Design Review issues Design Review Sustainability Plan Design YES END
Design Review acceptable PROCESS
DC BIM DC BIM ?
All Disciplines All Disciplines PM / DC All Disciplines All Disciplines
START Coordinator Coordinator
PROCESS Input to further
Design
Perform Value
Engineering
Review
PM / DC / MC
Legend:
Action
Design
OUTPUT
Review
Lead Information
Abbreviations::
ARC - Architecture
STR - Structure
MEP- Mech./Elec./Plumb.
CIV - Civil works
PM - Project Manager
DC - Design Consultant
MC - Main Contractor
Map 2.6 – 3D Coordination (Clash Detection) Process Map/BIM Workflow
Q22
Process subject to further development
Contract IE
INPUT
Project Design
Require- Require-
BIM Model
ments ments
PMP
DC
QA/QC
Establish a
PROCESS STEPS
Define IE
Develop Schedule Define the Models Compile Perform Clash Review and Identify Solutions
requirement for Protocol to YES Phase YES
for Coordination for Coordination Composite Model Detection Any classify clashes relevant to Clashes
Discipline Models Address Clashes clashes? clashes?
All Disciplines All Disciplines All Disciplines All Disciplines BIM Coordinator BIM Coordinator All Disciplines All Disciplines
START Start Design
PROCESS NO NO
Coordination
Process
END END
PROCESS PROCESS
Coordi- Clashes
nation Coordin
Legend: for suc-
Model by ation
cessing
Discipline Model
Phase
Action
OUTPUT
Lead
Abbreviations::
ARC - Architecture
STR - Structure
MEP- Mech./Elec./Plumb.
CIV - Civil works
PM - Project Manager
DC - Design Consultant
MC - Main Contractor
Map 2.7 – Cost Estimation (5D) Process Map/BIM Workflow
Native
Cost Analysis Cost
Intelligent
Reports Method Database
3D Models
Incorporate
Contingencies/
Overhead
DC
PROCESS STEPS
QA/QC
NO NO NO
Legend:
Action Cost
Quantity
OUTPUT
Estimate
Takeoff for
Lead for
Assemblies
Assemblies
Abbreviations::
ARC - Architecture
STR - Structure
MEP- Mech./Elec./Plumb.
CIV - Civil works
PM - Project Manager
DC - Design Consultant
MC - Main Contractor
Map 2.8 – Schedule Sequencing (4D) Process Map/BIM Workflow
3D Productivity
Lead Times
Models Information
PROCESS STEPS
All Disciplines Planning Engineer BIM Coordinator All Disciplines All Disciplines
Update 3D Model
START END
to Accommodate
PROCESS Schedule Needs PROCESS
DC / MC
All Disciplines
Legend:
Action
4D Model
OUTPUT
Abbreviations::
ARC - Architecture
STR - Structure
MEP- Mech./Elec./Plumb.
CIV - Civil works
PM - Project Manager
DC - Design Consultant
MC - Main Contractor
Map 2.9 – Construction Progress Monitoring Process Map/BIM Workflow
4D Schedule
Model Baseline
Review discre-
pancies and agree
revision
PROCESS STEPS
PM / GC
QA/QC NO
Legend:
Action 4D
Progress 4D Earned
OUTPUT
Progress
monitoring Progress Value
Lead Model
approach Model analsis
(Draft)
Abbreviations::
ARC - Architecture
STR - Structure
MEP- Mech./Elec./Plumb.
CIV - Civil works
PM - Project Manager
DC - Design Consultant
MC - Main Contractor
Map 2.10 – Record Modelling Process Map/BIM Workflow
Equipment Shop
Manage- Require-
Information Drawing
ment Plan ments
Model
PROCESS STEPS
MC
QA/QC
No
START END
PROCESS PROCESS
Identify Information Survey As-Built Update BIM to As-Built Complete Information Generate Additional Create COBie data
Model YES
Requirements conditions conditions in BIM Required Information accept- sheets from BIM
able?
Main Contractor Main Contractor Main Contractor Main Contractor Main Contractor Main Contractor
Legend:
As-Built /
COBie data
Record
sheets
Model
Action
OUTPUT
Lead
Abbreviations::
ARC - Architecture
STR - Structure
MEP- Mech./Elec./Plumb.
CIV - Civil works
PM - Project Manager
DC - Design Consultant
MC - Main Contractor
Appendix B
Information Exchange and Model Element
Definition Worksheets
APPENDIX B
MODEL ELEMENT DEFINITION (MOD)
Gateway 1) Preparation and Brief 2) Concept Design 3) Developed Design 4) Technical Design 5) Construction 6) Handover and Closeout
LOD as per Resp. Party Notes LOD as per Resp. Party Notes LOD as per Resp. Party Notes LOD as per Resp. Party Notes LOD as per Resp. Party Notes LOD as per Resp. Party Notes
Model Element Breakdown
Discipline Discipline Discipline Discipline Discipline Discipline
10 Substructure
General 100 100 200 300 300 300
Standard Foundations 100 100 200 300 300 300
Specialist Foundations 100 100 200 300 300 300
Special Foundations 100 100 200 300 300 300
Slab on Grade 100 100 200 300 300 300
Basement Excavation 100 100 200 300 300 300
Basement Retaining Walls 100 100 200 300 300 300
Lowest Floor Construction 100 100 200 300 300 300
20 Superstructure
General 100 100 200 300 300 300
Frame 100 100 200 300 300 300
Upper Floors 100 100 200 300 300 300
Roofs 100 100 200 300 300 300
Stairs and Rams 100 100 200 300 300 300
External Walls 100 100 200 300 300 300
Windows and External Doors 100 100 200 300 300 300
Internal Walls and Partitions 100 100 200 300 300 300
Internal Doors 100 100 200 300 300 300
25 Specialist Install
General 100 100 200 300 300 300
Gondola 100 100 200 300 300 300
TBC 100 100 200 300 300 300
TBC 100 100 200 300 300 300
30 Internal Finishes
General 100 100 200 300 300 300
Wall Finishes 100 100 200 300 300 300
Ceiling Finishes 100 100 200 300 300 300
Fittings, Furnishings and Equipment 100 100 200 300 300 300
40 Services
General 100 100 200 300 300 300
Sanitary Appliances 100 100 200 300 300 300
Services Equipment 100 100 200 300 300 300
Disposal Installations 100 100 200 300 300 300
Water Installations 100 100 200 300 300 300
Heat Source 100 100 200 300 300 300
Space Heating and air conditioning 100 100 200 300 300 300
Ventilation Systems 100 100 200 300 300 300
Electrical Installations 100 100 200 300 300 300
Gas and other fuel installations 100 100 200 300 300 300
Lift and Conveyor installations 100 100 200 300 300 300
Fire and lighting protection 100 100 200 300 300 300
Communication, security and control systems 100 100 200 300 300 300
Specialist Installations 100 100 200 300 300 300
Builders Work in Connections 100 100 200 300 300 300
Testing and Commissioning 100 100 200 300 300 300
Gateway 1) Preparation and Brief 2) Concept Design 3) Developed Design 4) Technical Design 5) Construction 6) Handover and Closeout
LOD as per LOD as per LOD as per LOD as per LOD as per LOD as per
Model Element Breakdown Resp. Party Notes Resp. Party Notes Resp. Party Notes Resp. Party Notes Resp. Party Notes Resp. Party Notes
Discipline Discipline Discipline Discipline Discipline Discipline
50 Prefab Buildings
General 100 100 200 300 300 300
Prefab Buildings 100 100 200 300 300 300
60 Renovation Works
General 100 100 200 300 300 300
Minor Demolition Works 100 100 200 300 300 300
70 External Works
General 100 100 200 300 300 300
Site Preparation 100 100 200 300 300 300
Roads, Paths and Pavings 100 100 200 300 300 300
Planting 100 100 200 300 300 300
Fences, Rails and Walls 100 100 200 300 300 300
Site/Street Furniture and Equipment 100 100 200 300 300 300
External Drainage 100 100 200 300 300 300
External Services 100 100 200 300 300 300
Minor Building Works and Ancillary Buildings 100 100 200 300 300 300
75 Utilities
General 100 100 200 300 300 300
DCP 100 100 200 300 300 300
Sub-stations 100 100 200 300 300 300
TSE 100 100 200 300 300 300
Thermal Storage 100 100 200 300 300 300
Communications 100 100 200 300 300 300
Emergency Services 100 100 200 300 300 300
Data Centre 100 100 200 300 300 300
Pumping Station 100 100 200 300 300 300
80 Facilitating Works
BIM Use Title Model Authoring Sustainability 3D Coordination Design Reviews Visualisation Schedule Sequencing Construction Progress Space Programming Cost Estimation / Existing Condition Engineering Analysis Record Modelling FM and Asset
(4D) Monitoring Quantification (5D) Modelling Management
Project Stage
Information Receiver
Model Element Breakdown LOD Resp. Notes LOD Resp. Notes LOD Resp. Notes LOD Resp. Notes LOD Resp. Notes LOD Resp. Notes LOD Resp. Notes LOD Resp. Notes LOD Resp. Notes LOD Resp. Notes LOD Resp. Notes LOD Resp. Notes LOD Resp. Notes
Party Party Party Party Party Party Party Party Party Party Party Party Party
10 Substructure
General
Standard Foundations
Specialist Foundations
Special Foundations
Slab on Grade
Basement Excavation
Basement Retaining Walls
Lowest Floor Construction
20 Superstructure
General
Frame
Upper Floors
Roofs
Stairs and Rams
External Walls
Windows and External Doors
Internal Walls and Partitions
Internal Doors
25 Specialist Install
General
Gondola
TBC
TBC
30 Internal Finishes
General
Wall Finishes
Ceiling Finishes
Fittings, Furnishings and Equipment
40 Services
General
Sanitary Appliances
Services Equipment
Disposal Installations
Water Installations
Heat Source
Space Heating and air conditioning
Ventilation Systems
Electrical Installations
Gas and other fuel installations
Lift and Conveyor installations
Fire and lighting protection
Communication, security and control
Specialist Installations
Builders Work in Connections
Testing and Commissioning
50 Prefab Buildings
General
Prefab Buildings
BIM Use Title Model Authoring Sustainability 3D Coordination Design Reviews Visualisation Schedule Sequencing Construction Progress Space Programming Cost Estimation / Existing Condition Engineering Analysis Record Modelling FM and Asset
(4D) Monitoring Quantification (5D) Modelling Management
Project Stage
Information Receiver
Model Element Breakdown (Uniformat) Info Resp. Notes Info Resp. Notes Info Resp. Notes Info Resp. Notes Info Resp. Notes Info Resp. Notes Info Resp. Notes Info Resp. Notes Info Resp. Notes Info Resp. Notes Info Resp. Notes Info Resp. Notes Info Resp. Notes
Party Party Party Party Party Party Party Party Party Party Party Party Party
60 Renovation Works
General
Minor Demolition Works
70 External Works
General
Site Preparation
Roads, Paths and Pavings
Planting
Fences, Rails and Walls
Site/Street Furniture and Equipment
External Drainage
External Services
Minor Building Works and Ancillary
75 Utilities ildi
General
DCP
Sub-stations
TSE
Thermal Storage
Communications
Emergency Services
Data Centre
Pumping Station
80 Facilitating Works
General
Toxic and Hazardous Material Removal
Major Demolition Works
Specialist Ground Works
Temporary Diversion Works
Extraordinary Site Investigation Works
90 Preliminaries
General
Site logistics
95 Event Management
General
Security
Parking
Datum
Grid
Levels
Origin
Appendix C
COBie Worksheet
APPENDIX C.01
COBie Parameters
Responsible Party DC MC
Construction
Tech.Design
Dev.Design
Handover
Concept
Sheet /
Table Attribute Description Data Type
Column
Contact
A Contact Email E-Mail Adress as unique identifier for contact xs:uri N U U U U
B Contact CreatedBy COBie entry created by N U U U U
C Contact CreatedOn COBie entry created on N U U U U
D Contact Category Job type xs:string N U U U U
E Contact Company Name of the company the contact works for xs:string N U U U U
F Contact Phone Phonenumber of contact xs:string N U U U U
G Contact ExtSystem link to BIM file N U U U U
H Contact ExtObject link to BIM file N U U U U
I Contact ExtIdentifier link to BIM file N U U U U
J Contact Department Department within the company xs:string N U U U U
K Contact OrganizationCode Code for company xs:string N U U U U
L Contact GivenName First name of contact xs:string N U U U U
M Contact FamilyName Last name of contact xs:string N U U U U
N Contact Street Company contacts data Street located at xs:string N U U U U
O Contact PostalBox Company contact data Postal Code xs:string N U U U U
P Contact Town Company contacts data city located in xs:string N U U U U
Q Contact StateRegion Company contacts data state/region located in xs:string N U U U U
R Contact PostalCode Company contacts data state/region located in xs:string N U U U U
S Contact Country Company contacts data country located in xs:string N U U U U
Facility
A Facility Name Name of Facility xs:string N U U U
B Facility CreatedBy COBie entry created by N U U U
C Facility CreatedOn COBie entry created on N U U U
D Facility Category Type of Facilty xs:string N U U U
E Facility ProjectName Project Name: Official Name xs:string N U U U
F Facility SiteName Site Name: Official name xs:string N U U U
Unit for the messurement of distances between two points for
G Facility LinearUnits xs:string N U U U
the entire project
H Facility AreaUnits Unit for space messurements for the entire project xs:string N U U U
I Facility VolumeUnits Unit for volume messurement for the entire project xs:string N U U U
J Facility CurrencyUnit Units for currencies for the entire project xs:string N U U U
K Facility AreaMeasurement xs:string N U U U
L Facility ExternalSystem link to BIM file N U U U
M Facility ExternalProjectObject link to BIM file N U U U
N Facility ExternalProjectIdentifier link to BIM file N U U U
O Facility ExternalSiteObject link to BIM file N U U U
P Facility ExternalSiteIdentifier link to BIM file N U U U
Q Facility ExternalFacilityObject link to BIM file N U U U
R Facility ExternalFacilityIdentifier link to BIM file N U U U
S Facility Description Description of Facility xs:string N U U U
T Facility ProjectDescription Description of Project xs:string N U U U
U Facility SiteDescription Description of Site xs:string N U U U
Every COBie Handover describes the project status at a specific
V Facility Phase point of the project. This defines the lifecycle phase of this data xs:string N U U U
drop.
Floor
A Floor Name Floor name / should indicate the Level xs:string N U U U
B Floor CreatedBy COBie entry created by N U U U
C Floor CreatedOn COBie entry created on N U U U
D Floor Category Type of Floor xs:string N U U U
E Floor ExtSystem link to BIM file N U U U
F Floor ExtObject link to BIM file N U U U
G Floor ExtIdentifier link to BIM file N U U U
H Floor Description Description of floor xs:string N U U U
I Floor Elevation Level just as nummerical value xs:long N U U U
J Floor Height entire floor height including slab xs:double N U U U
N = New Information if applicable Required as per COBie
U = Updated / extended Information Reference to other sheet or pick list
External reference
Required as per project
Work sheet titles
Responsible Party DC MC
Construction
Tech.Design
Dev.Design
Handover
Concept
Sheet /
Table Attribute Description Data Type
Column
Contact
Space
space name / should indicate level / spaces must not contain
A Space Name xs:string N U U U
more than one level
B Space CreatedBy COBie entry created by N U U U
C Space CreatedOn COBie entry created on N U U U
D Space Category Type of Space xs:string N U U U
E Space FloorName N U U U
F Space Description Description of space xs:string N U U U
G Space ExtSystem link to BIM file N U U U
H Space ExtObject link to BIM file N U U U
I Space ExtIdentifier link to BIM file N U U U
Room Name for operational / should be the same as
J Space RoomTag xs:string U U U
space.name
K Space UsableHeight height from floor to ceiling xs:double U U U
total floor area inside a building, including external walls,
L Space GrossArea xs:double U U U
excluding the roof
M Space NetArea usable are xs:double N U U U
Zone
A Zone Name Name for a group of spaces xs:string N U U U
B Zone CreatedBy COBie entry created by N U U U
C Zone CreatedOn COBie entry created on N U U U
D Zone Category Type of Zone xs:string N U U U
E Zone SpaceNames N U U U
F Zone ExtSystem link to BIM file N U U U
G Zone ExtObject link to BIM file N U U U
H Zone ExtIdentifier link to BIM file N U U U
I Zone Description Description of Zone xs:string N U U U
Type
A Type Name Name should characterize Product xs:string N U U U
B Type CreatedBy COBie entry created by N U U U
C Type CreatedOn COBie entry created on N U U U
D Type Category Type of Construction Product xs:string N U U U
E Type Description Description of Type (Familiy) xs:string N U U U
F Type AssetType xs:string N U U U
Company that produces Component, could be realized as link to
G Type Manufacturer xs:string N U
contact list
H Type ModelNumber Model number for the specific building element type xs:string N U
Organization acting as guarantor of parts warranty, could be
I Type WarrantyGuarantorParts xs:string N U
realized as link to contact list
J Type WarrantyDurationParts Duration of parts warranty xs:string N U
Organization acting as guarantor of labor warranty, could be
K Type WarrantyGuarantorLabor xs:string N U
realized as link to contact list
L Type WarrantyDurationLabor Duration of labor warranty xs:string N U
M Type WarrantyDurationUnit Unit for warranty xs:string N U
N Type ExtSystem link to BIM file N U U U
O Type ExtObject link to BIM file N U U U
P Type ExtIdentifier link to BIM file N U U U
Q Type ReplacementCost An indicative cost for unit replacement xs:double N U
R Type ExpectedLife estimation for life span xs:double N U U
S Type DurationUnit Unit for duration of life span xs:string N U
T Type WarrantyDescription Description of Warranty xs:string N U
U Type NominalLength Typically the larger or primary horizontal dimension xs:double N U U
Nominal width of product, typically the characteristic or
V Type NominalWidth xs:double N U U
secondary horizontal or characteristic dimension.
W Type NominalHeight Typically the vertical or secondary characteristic dimension xs:double N U U
X Type ModelReference xs:string N U U
Y Type Shape Characteristic shape of product xs:string N U U
Z Type Size Characteristic size of product xs:string N U
AA Type Color Characteristic or primary color of product xs:string N U U
N = New Information if applicable Required as per COBie
U = Updated / extended Information Reference to other sheet or pick list
External reference
Required as per project
Work sheet titles
Responsible Party DC MC
Construction
Tech.Design
Dev.Design
Handover
Concept
Sheet /
Table Attribute Description Data Type
Column
Contact
AB Type Finish Characteristic or primary finish of product xs:string N U U
AC Type Grade Standard grading which the product corresponds xs:string N U U
AD Type Material Characteristic or primary material of product xs:string N U U
AE Type Constituents Optional constituent features, parts or finishes xs:string N U U
Other important characteristics or features relevant to product
AF Type Features xs:string N U U
specification
AG Type AccessibilityPerformance xs:string N U U
AH Type CodePerformance Is the element type tested against any Perfomance Code. What xs:string N U U
AI Type SustainabilityPerformance xs:string N U U
Component
A Component Name Unique Identifier xs:string N U U
B Component CreatedBy COBie entry created by N U U
C Component CreatedOn COBie entry created on N U U
D Component TypeName N U U
E Component SpaceNames N U U
F Component Description Description of Component xs:string N U U
G Component ExtSystem link to BIM file N U U
H Component ExtObject link to BIM file N U U
I Component ExtIdentifier link to BIM file N U U
The serial number assigned to an occurrence of a product by
J Component SerialNumber xs:string N
the manufacturer
K Component InstallationDate The date the component was installed xs:date N
L Component WarrantyStartDate The date on which the warranty commences. xs:date N
The tag number assigned to an occurrence of a product ( by the
M Component TagNumber xs:string N
occupier)
The identity of the bar code (or rfid) given to an occurrence of
N Component BarCode xs:long N
the product
The asset identifier assigned to an occurrence of a product
O Component AssetIdentifier xs:string N
(prior to handover).
Assembly
Grouping of Components with some similar attributes for
A Assembly Name xs:string N U U
example Material (layer structure in BIM)
B Assembly CreatedBy COBie entry created by N U U
C Assembly CreatedOn COBie entry created on N U U
D Assembly SheetName N U U
E Assembly ParentName The general class, which should be subclassified. xs:string N U U
F Assembly ChildNames classifying element xs:string N U U
G Assembly AssemblyType Type of Assembly xs:string N U U
H Assembly ExtSystem link to BIM file N U U
I Assembly ExtObject link to BIM file N U U
J Assembly ExtIdentifier link to BIM file N U U
K Assembly Description Outline of Assembly xs:string N U U
System
Name for a system, (e.g. Irrigation system floor 3) System is a
A System Name xs:string N U U
group of components / one component can be included in
B System CreatedBy COBie entry created by N U U
C System CreatedOn COBie entry created on N U U
D System Category Type of System xs:string N U U
E System ComponentNames N U U
Coordinate
The Coordinate name is supposed to be a combination of the
A Coordinate Name xs:string N U U U
Component the Coordinate belongs to as well as the shape this
N = New Information if applicable Required as per COBie
U = Updated / extended Information Reference to other sheet or pick list
External reference
Required as per project
Work sheet titles
Responsible Party DC MC
Construction
Tech.Design
Dev.Design
Handover
Concept
Sheet /
Table Attribute Description Data Type
Column
Contact
B Coordinate CreatedBy COBie entry created by N U U U
C Coordinate CreatedOn COBie entry created on N U U U
D Coordinate Category shape type the coordiate belongs to xs:string N U U U
E Coordinate SheetName N U U U
F Coordinate RowName N U U U
G Coordinate CoordinateXAxis Coordinate on the x-Axis xs:double N U U U
H Coordinate CoordinateYAxis Coordinate on the y-Axis xs:double N U U U
I Coordinate CoordinateZAxis Coordinate on the z-Axis xs:double N U U U
J Coordinate ExtSystem N
K Coordinate ExtObject N
L Coordinate ExtIdentifier N
M Coordinate ClockwiseRotation rotation arround the x-Axis (unit needs to be agreed) xs:double N U U U
N Coordinate ElevationalRotation rotation arround the y-Axis (unit needs to be agreed) xs:double N U U U
O Coordinate YawRotation rotation arround the z-Axis (unit needs to be agreed) xs:double N U U U
Attribute
Name of Attribute, should include attribute characteristics (by
A Attribute Name xs:string N U U U
using new names, new attributes get defined)
B Attribute CreatedBy COBie entry created by N U U U
C Attribute CreatedOn COBie entry created on N U U U
D Attribute Category Categoriezes xs:string N U U U
E Attribute SheetName N U U U
F Attribute RowName N U U U
G Attribute Value Value for Attribute xs:string N U U U
H Attribute Unit Unit for Attribute xs:string N U U U
I Attribute ExtSystem link to BIM file N
J Attribute ExtObject link to BIM file N
K Attribute ExtIdentifier link to BIM file N
L Attribute Description Description of Attribute xs:string N U U U
limitation for Values, resulting of value type or real world
M Attribute AllowedValues xs:string N U U U
restrictions
Job
A Job Name Name that characterizes job xs:string N
B Job CreatedBy COBie entry created by N
C Job CreatedOn COBie entry created on N
D Job Category Job Type (task) xs:string N
E Job Status status of job xs:string N
F Job TypeName N
G Job Description task description xs:string N
H Job Duration needed time for one duration of the job xs:double N
I Job DurationUnit Unit for duration xs:string N
J Job Start N
K Job TaskStartUnit N
L Job Frequency for recurring processes, the frequency xs:double N
M Job FrequencyUnit Unit of frequency for recurring xs:string N
N Job ExtSystem link to BIM file N
O Job ExtObject link to BIM file N
P Job ExtIdentifier link to BIM file N
Q Job TaskNumber according to the internal identification number xs:string N
R Job Priors N
S Job ResourceNames N
Resource
A Resource Name Name that identfies Resources by their characteristics xs:string N
B Resource CreatedBy COBie entry created by N
C Resource CreatedOn COBie entry created on N
D Resource Category Type of Ressource (Tools, man-power, …) xs:string N
E Resource ExtSystem link to BIM file N
F Resource ExtObject link to BIM file N
N = New Information if applicable Required as per COBie
U = Updated / extended Information Reference to other sheet or pick list
External reference
Required as per project
Work sheet titles
Responsible Party DC MC
Construction
Tech.Design
Dev.Design
Handover
Concept
Sheet /
Table Attribute Description Data Type
Column
Contact
G Resource ExtIdentifier link to BIM file N
H Resource Description Description: Also what gets the Resource used for. xs:string N
Spare
A Spare Name Name that characterizes spare elements xs:string N
B Spare CreatedBy COBie entry created by N
C Spare CreatedOn COBie entry created on N
D Spare Category How is the spare organized. xs:string N
E Spare TypeName N
F Spare Suppliers N
G Spare ExtSystem link to BIM file N
H Spare ExtObject link to BIM file N
I Spare ExtIdentifier link to BIM file N
J Spare Description Description of spare part, also what it is meant for. xs:string N
K Spare SetNumber number to identify a group of spare elements xs:string N
L Spare PartNumber number to identify a single element xs:string N
Document
A Document Name Document name xs:string N U U U
B Document CreatedBy COBie entry created by N U U U
C Document CreatedOn COBie entry created on N U U U
D Document Category Document type xs:string N U U U
E Document ApprovalBy could be realized as link to contact list xs:string N U U U
F Document Stage xs:string N U U U
G Document SheetName N U U U
H Document RowName N U U U
path where the file is located, needs also to be consistent after
I Document Directory xs:uri N U U U
moving COBie file
J Document File file name including extension xs:uri N U U U
K Document ExtSystem link to BIM file
L Document ExtObject link to BIM file
M Document ExtIdentifier link to BIM file
N Document Description What kind of information includes the document xs:string N U U U
O Document Reference references the document to other documents xs:string N U U U
Connection
Name of the connection, should contain the purpose of the
A Connection Name xs:string N U U
connection
B Connection CreatedBy COBie entry created by N U U
C Connection CreatedOn COBie entry created on N U U
D Connection ConnectionType Type of Connection xs:string N U U
E Connection SheetName N U U
F Connection RowName1 N U U
G Connection RowName2 N U U
H Connection RealizingElement xs:string N U U
If the connection is done via opening, it is supposed to be
I Connection PortName1 xs:string N U U
named here.
If the connection is done via opening, it is supposed to be
J Connection PortName2 xs:string N U U
named here.
K Connection ExtSystem link to BIM file N U U
L Connection ExtObject link to BIM file N U U
M Connection ExtIdentifier link to BIM file N U U
N Connection Description xs:string N U U
Issue
A Issue Name Name of issue that characterizes it xs:string N U U U
B Issue CreatedBy COBie entry created by N U U U
C Issue CreatedOn COBie entry created on N U U U
N = New Information if applicable Required as per COBie
U = Updated / extended Information Reference to other sheet or pick list
External reference
Required as per project
Work sheet titles
Responsible Party DC MC
Construction
Tech.Design
Dev.Design
Handover
Concept
Sheet /
Table Attribute Description Data Type
Column
Contact
D Issue Type classify issue xs:string N U U U
E Issue Risk estimated risk for project xs:string N U U U
F Issue Chance occurrent chance of issue xs:string N U U U
G Issue Impact how is the impact on the project xs:string N U U U
H Issue SheetName1 N U U U
I Issue RowName1 N U U U
J Issue SheetName2 N U U U
K Issue RowName2 N U U U
L Issue Description Issue Description xs:string N U U U
M Issue Owner N U U U
N Issue Mitigation Is their any advice to solve the issue xs:string N U U U
O Issue ExtSystem link to BIM file N U U U
P Issue ExtObject link to BIM file N U U U
Q Issue ExtIdentifier link to BIM file N U U U
Impact
Name for Impact (combination of ComponentName,
A Impact Name xs:string N U U
ImpactType, ImpactStage
B Impact CreatedBy COBie entry created by N U U
C Impact CreatedOn COBie entry created on N U U
D Impact ImpactType what kind of impact? xs:string N U U
E Impact ImpactStage when does the impact happen? xs:string N U U
F Impact SheetName N U U
G Impact RowName N U U
H Impact Value Value for Impact N U U
I Impact ImpactUnit Unit of Impact xs:string N U U
J Impact LeadInTime time to lead in (unit definition not provided) xs:double N U
K Impact Duration duration (unit definition not provided) xs:double N U
L Impact LeadOutTime time to lead out (unit definition not provided) xs:double N U
M Impact ExtSystem link to BIM file N U
N Impact ExtObject link to BIM file N U
O Impact ExtIdentifier link to BIM file N U
How gets the impect measured? If not clear, what kind of
P Impact Description xs:string N U U
Impact.
CH2M HILL International B.V.
Mace International Limited
CH2M HILL Mace JV Programme Office
19th Floor Boulevard Plaza, Tower 2
PO Box 2020
Dubai, UAE