You are on page 1of 2

NATIONAL INSTITUTE OF TECHNOLOGY ROURKELA

Department of Electrical Engineering


Power System Operation and Control (EE3100)
Session: 2022 - 2023 (Spring)
B.Tech. 6th Semester

Mid Semester Examination


Number of Pages: 2 Full Marks: 30 Duration: 2 Hours

AL INSTITUTE OF TECHNOLOGY
Figures at the right hand margin indicate marks. All parts of a question should be answered at one place.

ROURKELA
All symbols carry usual meaning. Assume standard value for any missing data.
Answers should be brief and to the point. Irrelevant answer may lead to negative marking.

Q1. (a) Starting from the positive, negative and zero sequence equivalent network of a power 5
system, derive the expressions of I¯af1 , I¯af2 and I¯af0 for a double line-to-ground fault at a
bus.

(b) A generator having solidly grounded neutral and rated 50 MVA, 30 kV has positive, 5
negative and zero sequence reactances of 25, 15 and 5 percent, respectively. What
reactance must be placed in the generator neutral to limit the fault current for a bolted
double line-to-ground fault to that for a bolted three-phase fault ?

Q2. Derive the Z-bus building rule for Type-4 modification. 5

Q3. Consider the power system shown below. 6+4

PV Bus
PQ Bus

PQ Bus Slack Bus

Find

(a) B ′′ matrix.
(b) Active and reactive power delivered by the generator at bus 3.

Continued on the next page


EE3100 Mid Semester Examination Page 2 of 2

Q4. The transformer of the below network has on-line tap-changer at both sides. Form the 5
Y -bus matrix of the system.

End of question paper. ALL THE BEST.