Professional Documents
Culture Documents
Engineering Structures
journal homepage: www.elsevier.com/locate/engstruct
Study on composite beams with prefabricated steel bar truss concrete slabs T
and demountable shear connectors
⁎
Hao Du, Xiamin Hu , Yanfei Meng, Guohui Han, Kaikai Guo
College of Civil Engineering, Nanjing Tech University, Nanjing 211816, China
A R T I C LE I N FO A B S T R A C T
Keywords: In the conventional steel-concrete composite beams, the composite action is achieved by welded stud connectors
Composite beam which are encased into the cast-in-place concrete slab. This makes the deconstruction and reuse of the structural
Steel bar truss concrete slab components almost impossible. A sustainable and prefabricated composite structural system was developed in
Demountable shear connector this study wherein the steel beam is attached to the prefabricated steel-bars truss concrete slab using the de-
Prefabricated
mountable bolted connectors. Twelve push-out specimens were designed and tested to assess the shear behavior
Push-out test
Load carrying capacity
of the bolted connectors. The test results showed that the shear bearing capacity of the bolted connectors with
the prefabricated steel-bars truss concrete slab increased 7.0% over that of the bolted connectors with the
prefabricated normal concrete slab. Three full-scale composite beams with various shear connection ratios were
constructed and loaded to failure. For direct comparison, a similar composite beam was constructed with the
same section size and shear connectors, but using the cast-in-place concrete slab. The flexural capacity of the
composite beams with 68% shear connection and full shear connection increased 9.8% and 15.8% compared to
the composite beam with 46% shear connection, respectively. The mechanical behavior of the composite beam
with the prefabricated concrete slab was comparable with that of the composite beam with cast-in-place concrete
slab. The load carrying capacity of the composite beam can be predicted by the simplified model in Eurocode 4
and the plastic model.
⁎
Corresponding author.
E-mail address: huxm_njtech@163.com (X. Hu).
https://doi.org/10.1016/j.engstruct.2020.110419
Received 30 September 2019; Received in revised form 19 January 2020; Accepted 21 February 2020
Available online 27 February 2020
0141-0296/ © 2020 Elsevier Ltd. All rights reserved.
H. Du, et al. Engineering Structures 210 (2020) 110419
Concrete
Top bars
Support bars
Cross bars
Bottom bars
Bottom sheet
294
100
washer
120 120
140
130
140
400
8
460
140
200
190
130
Connector
pocket 12 12
50
2
H. Du, et al. Engineering Structures 210 (2020) 110419
400 Table 4
Test results for push-out specimens.
100 200 100
Specimens Maximum load (kN) Slip at maximum load Failure mode
Top bar(8 mm) (mm)
Cross bar(4.5 mm)
Test Average Test Average
15 90
2. Push-out tests
Test Machine
2.1. Description of Push-out specimens
Test specimen
Four groups of push-out specimens were designed and tested, and
three replicate specimens were included in each group. The main
parameters of the specimens are listed in Table 1. The test series DBC1
and DBC2 were designed to study the influence of the concrete strength
of the connector pocket on the shear behavior of the demountable
bolted connectors. For direct comparison, the test series DBC3 was
constructed with the same section size and shear connectors, but using
the prefabricated normal concrete slab without steel bar truss deck. The
test series DBC4 was constructed with the cast-in-place steel bar truss
Dispalcement Dispalcement concrete slab. Each test specimen consisted of one rolled H-section steel
transducer transducer beam and two concrete slabs, as shown in Fig. 3. The concrete slabs
were 460 mm high, 400 mm wide and 120 mm thick. Two Grade
8.8 M20 bolted connectors were installed on each side of the steel beam
Fig. 5. Push-out test setup.
using a wrench to apply pretension force of 120 kN [30]. The bolted
connectors had embedded depth of 100 mm inside the concrete slabs.
analyses were conducted to investigate the influences of longitudinal The connector pocket in the precast concrete slabs was 140 mm wide
reinforcement ratio, bolt spacing, diameter of hole and bolt pretension and 140 mm high. The details of steel bar truss deck used in the con-
on the mechanical behavior. crete slab are shown in Fig. 4.
The steel bar truss concrete slab is a composite of concrete, corru-
gated sheet and steel bar truss which can replace wood formwork to
bear the construction loads in the construction phase and bear the 2.2. Material properties
structure load during the service stage [27]. Fig. 1 presents the details
of the steel bar truss concrete slab. In the prefabricated construction of Tables 2–3 present the mechanical properties of each structural
steel-concrete buildings and bridges, the steel bar truss concrete slabs component obtained from material tests. The yield strength and ulti-
can be utilized, which shorten the construction time and reduce tem- mate tensile strength for the bolted connector, the steel reinforcement
porary support. In addition, the steel bar truss concrete slab has good and steel beam were evaluated through the tensile coupon tests [31].
performance of cracking resistance and fire resistance [28,29]. The cubic compression tests on the concrete were conducted based on
A sustainable and prefabricated composite structural system was GB/T 50081 [32].
3
H. Du, et al. Engineering Structures 210 (2020) 110419
Table 5
Comparison between the experimental and calculated results.
Authors Specimens Test Vu,t (kN) Theoretical Vu,c (kN) Vu,c/Vu,t
4
H. Du, et al. Engineering Structures 210 (2020) 110419
Two types of failure modes of demountable bolted connectors were connectors, the load carrying capacity was improved along with the
observed: crushing failure of concrete and fracture failure of bolted bolt strength and bolt diameter increasing. The analytical models for
connectors (Fig. 6). The failure mechanism of DBC1, DBC3 and DBC4 calculating the load carrying capacity of bolted connectors were pro-
was crushing failure of concrete coupled with bending deformation of posed based on the various failure modes. When the failure mode was
bolted connectors (Fig. 6(a)). For test series DBC2, it was observed that crushing failure of concrete, the shear bearing capacity VuI can be cal-
when the applied load reached its peak, the shear failure of the bolted culated as:
connectors suddenly occurred (Fig. 6(b)).
VuI = 0.22(h/ d )0.4Ad fc Ec (1)
The load-slip curves of demountable bolted connectors are shown in
Fig. 7. During the early loading period, the relative slip at the interface
where fc is the axial compressive strength of concrete; h is the em-
increased linearly as the applied load increased. When the load reached
bedded length of bolted connectors into the concrete slab ; d is the
approximately 70% of the maximum load, the slips increased rapidly
diameter of bolt connectors; Ad is the section area of bolted connectors;
with the increase of the load. The shear stiffness of the bolted con-
Ec is the elastic modulus of concrete.
nectors decreased continuously throughout this process. After reaching
The corresponding theoretical method for the fracture failure of
the ultimate load, the different failure modes of bolted connectors ex- bolted connectors VuII was based on EN1993-1-8 [34] as follows:
hibited various load-slip behavior. When the crushing failure of con-
crete occurred on the bolted connectors, the load decreased slowly as VuII = α v Ad fu (2)
the slip increased. When the failure mechanism was shear failure of the
bolted connectors, the load dropped sharply with the increase of slip. where fu is the tensile strength of bolted connectors; αv = 0.6 for classes
Overall, the demountable bolted shear connectors in the composite 4.6, 5.6 and 8.8; αv = 0.5 for classes 4.8, 5.5, 6.8 and 10.9.
beam showed good ductility performance, owning to the bending de- Table 5 shows the comparisons between the experimental results of
formation of the bolted connectors. the bolted connectors obtained from this paper, Dai et al. [13], Hawkins
[15] and Ataei et al. [24] and the calculated results. The effects of
concrete strength, bolt diameter, embedded length of bolt into concrete
3. Calculation methods for shear resistance of bolted connectors were considered in the calculation method for load carrying capacity of
bolted connectors. The results showed that the calculation method can
Push-out tests were conducted to study the shear performance of be used to predict the load carrying capacity of bolted connectors.
bolted connectors in the composite beam having cast-in-place concrete
slab in previous research [33]. The results showed that when the 4. Bending tests on composite beams
crushing failure of concrete occurred on the bolted connectors, the load
carrying capacity of bolted connectors was improved with the increase 4.1. Composite beam specimens
of concrete strength, bolt diameter and embedded length of bolt into
concrete. When the failure mode was shear failure of the bolted Three full-scale composite beams (PCB1, PCB2 and PCB3) with
5
H. Du, et al. Engineering Structures 210 (2020) 110419
various shear connection ratios were constructed and loaded to failure equivalent to that of composite beam PCB1.
(Fig. 8). Composite beam PCB1 was designed with full shear connec- The yield strength and ultimate tensile strength of the steel beam
tion. A total of forty Grade 8.8 M20 bolted connectors were installed obtained from the tensile coupon tests were 256 MPa and 429 MPa,
along with the beam (Fig. 9(a)). Composite beam PCB2 was designed respectively. The compressive strength of the concrete slab obtained
with 68% shear connection, constructed with a total of thirty bolted from the cubic compression tests was 30.3 MPa. The compressive
connectors (Fig. 9(b)). Composite beam PCB3 was designed with 46% strength of the concrete used in the connector pockets was 29.4 MPa.
shear connection, constructed with a total of twenty-two bolted con-
nectors (Fig. 9(c)). For direct comparison, a fully connected composite
beam CB1 was constructed with the cast-in-place concrete slab. The 4.2. Test setup and procedure
spacing and number of bolted connectors for composite beam CB1 was
Fig. 10 shows the static destructive test setup of the composite
6
H. Du, et al. Engineering Structures 210 (2020) 110419
Table 6
Reaction frame Hydraulic servo actuator Test results of composite beams.
Specimen Degree of Py (kN) Pu (kN) δy (mm) δu (mm) Failure mode
Spreader beam
shear
connection
Composite beam
CB1 100 363.6 629.7 17.1 67.9 CC + FS
PCB1 100 373.7 637.7 17.4 69.7 CC + FS
PCB2 68 350.2 604.4 18.8 83.5 CC + FS
PCB3 46 320.5 550.6 16.4 67.11 CC + FS
Notes: CC: crushing failure of concrete slab; FS: flexural failure of steel beam.
Roller support Pin support
strain distributions across mid-span section of the composite beam.
Fig. 10. Configuration of bending test set-up. 4.3. Test results and discussion
beams. The composite beam specimens were placed under simply 4.3.1. Failure mode
supported boundary condition through the roller and pin supports in- The experimental results of four composite beam specimens are
stalled at the end of beams. Two-point symmetric loading were adopted presented in Table 6, where: Py is the applied load when the bottom
on the composite beams by using a 1000 kN hydraulic servo actuator. flange of the steel beam yielded, Pu is the ultimate load, δy is the de-
The length of pure bending zone was 1200 mm. To assess the perfor- flection of the composite beam at the mid-span when the steel beam
mance of the bending test set-up and the measuring instruments, the yielded, δu is deflection of the composite beam at mid-span upon
applied load was increased at a rate of 0.5 kN/s until 10% of the esti- reaching the maximum load.
mated maximum load was reached, then unloaded. The applied load It was found that the crack pattern and failure mode of the com-
was then increased with the rate of 10 kN per step until the load posite beam specimens were similar. When the load reached approxi-
reached 80% of the estimated maximum load. Finally, the displacement mately 54% of the maximum load, the first cracking appeared on the
control mode with a rate of 2 mm/min was adopted to apply further concrete slab at the mid-span of the composite beams. As the increase of
load. applied load, more flexural cracks occurred on the concrete slab around
The displacement transducers and strain gauges were placed at the mid-span and the cracks further expanded, as shown in Fig. 12(a).
different positions along the composite beams to quantify the structural When the load reached to approximately 80% of the maximum load,
performance, as shown in Fig. 11. The support settlement and the de- the horizontal cracks were observed on the concrete slab at mid-span.
flection deformation at the mid-span were measured with three trans- Upon reaching the ultimate load, the crushing failure of concrete slab
ducers. To evaluate the relative slip at the steel-concrete interface, six and the flexural failure of steel beam were observed (Fig. 12(b), (c)).
displacement transducers were installed along longitudinal direction of There were clearly visible interface slips at the end of composite beam
the composite beams. Eleven strain gauges were also used to obtain the PCB2 and PCB3, as shown in Fig. 12(d).
4000
Load
Strain gauge
7
H. Du, et al. Engineering Structures 210 (2020) 110419
(a) Cracks on the side of concrete slab (b) Crushing failure of concrete slab
(c) Overall flexural failure (d) Relative slip at the steel-concrete interface
Fig. 12. Failure mode of composite beam PCB2.
800 capacity of the composite beams with 68% shear connection and full
CB1
shear connection increased 9.8% and 15.8% over that of the composite
700 PCB1
PCB2 beam with 46% shear connection, respectively. In effect, the flexural
600 PCB3 capacity of composite beams was improved with the degree of shear
connection increasing. The flexural capacity of composite beam
500 PCB1with prefabricated concrete slab was approximately equal to that
Load (kN)
8
H. Du, et al. Engineering Structures 210 (2020) 110419
5.5 5.5
5.0 P/Pu=0.2 5.0 P/Pu=0.2
4.5 P/Pu=0.4 4.5 P/Pu=0.4
4.0 P/Pu=0.6 4.0 P/Pu=0.6
P/Pu=0.8 P/Pu=0.8
3.5 3.5
P/Pu=0.9 P/Pu=0.9
Slip (mm)
Slip (mm)
3.0 3.0
P/Pu=1.0 P/Pu=1.0
2.5 2.5
2.0 2.0
1.5 1.5
1.0 1.0
0.5 0.5
0 200 400 600 800 1000 1200 1400 1600 1800 2000 0 200 400 600 800 1000 1200 1400 1600 1800 2000
Distance to the mid-span (mm) Distance to the mid-span (mm)
(a) Composite beam CB1 (b) Composite beam PCB1
5.5 5.5
5.0 P/Pu=0.2 5.0 P/Pu=0.2
4.5 P/Pu=0.4 4.5 P/Pu=0.4
P/Pu=0.6 P/Pu=0.6
4.0 4.0
P/Pu=0.8 P/Pu=0.8
3.5 3.5
P/Pu=0.9 P/Pu=0.9
Slip (mm)
0 200 400 600 800 1000 1200 1400 1600 1800 2000 0 200 400 600 800 1000 1200 1400 1600 1800 2000
Distance to the mid-span (mm) Distance to the mid-span (mm)
(c) Composite beam PCB2 (d) Composite beam PCB3
Fig. 14. Load-slip curves of composite beam specimens.
almost continuous during the early loading period, which demonstrated the cross section of the concrete slab ( fc be hc ⩾ fy As ), the plastic stress
that full composite action was produced at the steel-concrete interface. distributions of the composite cross section are presented in Fig. 16(a).
The top flange of steel beam was subjected to tension and the neutral The depth of the compressive zone of the concrete can be determined
axis of the composite beam fell into the concrete slab as the load in- by:
creased. The strain distribution at the interface exhibited small dis-
fy As
continuity owning to the interface slips. The section strain of the fully x=
connected composite beams as one unit were according with the plane fc be (3)
section assumption.
The load carrying capacity of the fully connected composite beam
The discontinuity of the strain distributions of composite beams
Mu, f can be taken as:
PCB2 and PCB3 became more prominent due to the larger interface slip.
The plane section assumption was inapplicable for the composite cross- Mu,f = fc be xy (4)
section as one unit, but the section strains of each component were in
accordance with the plane section assumption. The top flange of the where: fc is the compressive strength of concrete, be is the effective
steel beam experienced compressive strains and the neutral axis gra- width of the concrete slab, hc is the thickness of the concrete slab, As is
dually moved downwards as the applied load further increased until the cross-sectional area of the steel beam, fy is the yield strength of the
about 20 mm below the interface. In addition, the separation of the two steel beam in tension or compression, x is the distance from the top of
neutral axes in the concrete slab and the steel beam increased as the the concrete slab to the neutral axis, y is the distance from the tensile
degree of shear connection decreased. resultant force of the steel beam to the compressive resultant force of
the concrete slab.
When the neutral axis is located in the cross section of the steel
5. Plastic model for load carrying capacity of composite beam
beam ( fc be h c < fy As ), the plastic stress distributions of the composite
cross section are presented in Fig. 16(b). The cross section area of the
5.1. Composite beam with full shear connection steel beam under compressive Ac is calculated as the following equa-
tion:
The mechanical performance of the composite beams is significantly
influenced by the degree of shear connection. In the structural analysis fy As − fc be hc
Ac =
of the fully connected composite beam, the plane section assumption 2fy (5)
was applicable for the cross section as one unit, and the tensile strength
of the concrete was not considered. When the neutral axis is located in The load carrying capacity of the fully connected composite beam
9
H. Du, et al. Engineering Structures 210 (2020) 110419
150 150
-150 -150
-200 -200
-250 -250
-300 -300
-5000 0 5000 10000 15000 20000 -5000 0 5000 10000 15000 20000
Strain(με) Strain(με)
(a) Composite beam CB1 (b) Composite beam PCB1
150 150
-150 -150
-200 -200
-250 -250
-300 -300
-5000 0 5000 10000 15000 20000 -5000 0 5000 10000 15000 20000
Strain(με) Strain(με)
(c) Composite beam PCB2 (d) Composite beam PCB3
Fig. 15. Strain distributions at mid-span of composite beams.
10
H. Du, et al. Engineering Structures 210 (2020) 110419
Neutral axis
fc
_ f cbex
x
hc
M
y
+
fyAs
hs
fy
fc
f cb ex
_
hc
x
_ fyAc
fy
fy(As-Ac)
hs
Neutral axis +
fy
M
hc
_ fybfx1
fy
x1
tf
bf fy
y1
fybf tf M
y2
_
x1
y3
fy fytw(x1-tf)
tw Steel neutral axis
hs
+
fy(As-Ac)
tf
bf fy
where: bf is the flange width of the steel beam, Vu is the shear bearing neutral axis to the top of the concrete slab x2 can be determined by:
capacity of the shear connector, n is the number of the shear con-
nectors, tf is the flange thickness of the steel beam. nVu
x2 =
When the neutral axis of steel beam is assumed to be in the web fc be (11)
( fy As − 2fy bf t f > nVu ), the plastic stress distributions of the composite
cross section are presented in Fig. 17(b). The distance from the concrete The distance from the steel neutral axis to the top of the steel beam
x1 is calculated as:
11
H. Du, et al. Engineering Structures 210 (2020) 110419
Mu, p = fy (As − Ac ) y3 − fy tw (x1 − t f ) y2 − fy bf t f y1 (13) Hao Du: Conceptualization, Methodology, Data curation,
Investigation, Writing - original draft. Xiamin Hu: Writing - review &
where: y1 is the distance from compressive resultant force of the steel
beam flange to the compressive resultant force of the concrete slab, editing. Yanfei Meng: Investigation. Guohui Han: Validation. Kaikai
t x
y1 = 2f + hc − 22 , y2 is the distance from compressive resultant force of Guo: Investigation, Supervision.
the steel beam web to compressive resultant force of the concrete slab,
x +t −x
y2 = hc + 1 2f 2 , y3 is the distance from tensile resultant force of the Declaration of Competing Interest
steel beam to compressive resultant force of the concrete.
We declare that we have no conflicts of interest to this work. We
5.3. Comparisons between test results and theoretical results declare that we do not have any commercial or associative interest that
represents a conflict of interest in connection with the work submitted.
Table 7 shows the comparisons between the experimental results
and the calculated results, where: Mu,t is the test results of the flexural Acknowledgements
capacity of the composite beams, Mu,c1 is the calculated results based on
the simplified model in Eurocode 4, Mu,c2 is the calculated results de- The research was supported by National Key Research and
termined by the plastic model. The comparisons indicated that the load Development Program of China (No. 2017YFC0703405) and National
carrying capacity of the composite beam can be predicted by the sim- Natural Science Foundation of China (No. 51678295), (No. 51478220).
plified model in Eurocode 4 and the plastic model. The calculated re- The authors also thank Associate Mrs. Tong Zhang for revising and
sults based on the plastic model were more accurate than those de- proofreading this manuscript.
termined by the simplified model in Eurocode 4. However, the
simplified model in Eurocode 4 is simple in computation and usable in References
application.
[1] Han Q, Wang Y, Xu J, Xing Y. Static behavior of stud shear connectors in elastic
concrete–steel composite beams. J Constr Steel Res 2015;113:115–26.
6. Conclusions [2] Xing Y, Han Q, Xu J, Guo Q, Wang Y. Experimental and numerical study on static
behavior of elastic concrete-steel composite beams. J Constr Steel Res
In this study, a total of twelve push-out tests on bolted shear con- 2016;123:79–92.
[3] Xu C, Kunitomo S. Analytical investigation on failure development of group studs
nectors were conducted and bending tests on four full-scale composite shear connector in push-out specimen under biaxial load action. Eng Fail Anal
beams were carried out to evaluate the mechanical performance of the 2014;37:75–85.
composite beams with prefabricated steel bar truss concrete slabs and [4] Kim JS, Kwark J, Joh C, Yoo SW, Lee KC. Headed stud shear connector for thin
ultrahigh-performance concrete bridge deck. J Constr Steel Res 2015;108:23–30.
demountable bolted connectors. The conclusions can be summarized as [5] Luo Y, Hoki K, Hayashi K, Nakashima M. Behavior and strength of headed stud-
follows: SFRCC shear connection I: Experimental study. J Struct Eng 2016;142(2):04015112.
[6] Luo Y, Hoki K, Hayashi K, Nakashima M. Behavior and strength of headed stud-
SFRCC shear connection II: Strength evaluation. J Struct Eng
(1) The push-out test results showed that the shear bearing capacity of 2016;142(2):04015113.
the bolted connectors with concrete strength of 40 MPa in the [7] Qi J, Wang J, Li M, Chen L. Shear capacity of stud shear connectors with initial
connector pockets increased 24.2% over that of the bolted damage: Experiment, FEM model and theoretical formulation. Steel Compos Struct
2017;25(1):79–92.
12
H. Du, et al. Engineering Structures 210 (2020) 110419
[8] Wang J, Guo J, Jia L, Chen S, Dong Y. Push-out tests of demountable headed stud retrofitted with postinstalled shear connectors. J Bridge Eng 2011;16(4):536–45.
shear connectors in steel-UHPC composite structures. Compos Struct [23] Moynihan MC, Allwood JM. Viability and performance of demountable composite
2017;170:69–79. connectors. J Constr Steel Res 2014;99:47–56.
[9] Huo J, Wang H, Zhu Z, Liu Y, Zhong Q. Experimental study on impact behavior of [24] Ataei A, Bradford MA, Liu X. Experimental study of composite beams having a
stud shear connectors between concrete slab and steel beam. J Struct Eng precast geopolymer concrete slab and deconstructable bolted shear connectors. Eng
2018;144(2):04017203. Struct 2016;114:1–13.
[10] Wang J, Qi J, Tong T, Xu Q, Xiu H. Static behavior of large stud shear connectors in [25] Liu X, Bradford MA, Chen QJ, Ban H. Finite element modelling of steel–concrete
steel-UHPC composite structures. Eng Struct 2019;178:534–42. composite beams with high-strength friction-grip bolt shear connectors. Finite Elem
[11] Xu X, Liu Y, He J. Study on mechanical behavior of rubber-sleeved studs for steel Anal Des 2016;108:54–65.
and concrete composite structures. Constr Build Mater 2014;53:533–46. [26] Lam D, Dai X, Ashour A, Rahman N. Recent research on composite beams with
[12] Xue D, Liu Y, Yu Z, He J. Static behavior of multi-stud shear connectors for steel- demountable shear connectors. Steel Constr 2017;10(2):125–34.
concrete composite bridge. J Constr Steel Res 2012;74(8):1–7. [27] GB/T 368-2012: Steel-bars truss deck, Standardization Administration of China,
[13] Dai XH, Lam D, Saveri E. Effect of concrete strength and stud collar size to shear China, 2012.
capacity of demountable shear connectors. J Struct Eng 2015;141(11):04015025. [28] Chen A, Wan H, Sun L, Feng R. Experimental study on bending behavior of steel bar
[14] Liu XP, Bradford MA, Lee MSS. Behavior of high-strength friction-grip bolted shear truss composite slab. Build Struct 2015;45(8):59–63. [in Chinese].
connectors in sustainable composite beams. J Struct Eng 2015;141(6):04014149. [29] Liu P, Wan H. Experimental study on steel bar truss concrete composite beams.
[15] Hawkins N. Strength in shear and tension of cast-in-place anchor bolts. Anchorage Struct Eng 2016;32(3):155–61. [in Chinese].
Concrete 1987;SP-103:233–55. [30] ANSI/AISC 360-05. Specification for structural steel buildings. USA: American
[16] Yang F, Liu Y, Jiang Z, Xin H. Shear performance of a novel demountable steel- Institute of Steel Construction; 2005.
concrete bolted connector under static push-out tests. Eng Struct 2018;160:133–46. [31] ASTM A370-05: Standard test methods and definitions for mechanical testing of
[17] Dallam LN. High strength bolt shear connectors-Pushout tests. ACI J steel products, West Conshohocken, PA; 2005.
1968;65(9):767–9. [32] GB/T 50081: Standard for test method of mechanical properties on ordinary con-
[18] Kwon G, Engelhardt MD, Klingner RE. Behavior of post-installed shear connectors crete, Standardization Administration of China, China; 2016.
under static and fatigue loading. J Constr Steel Res 2010;66(4):532–41. [33] Du H, Zhang B, Hu X, Kou L, Xia Y. Experimental study on shear behavior of bolt
[19] Kwon G, Engelhardt MD, Klingner RE. Parametric studies and preliminary design connectors in steel-concrete composite beams. J Building Struct
recommendations on the use of postinstalled shear connectors for strengthening 2017;38(S1):308–14. [in Chinese].
noncomposite steel bridges. J Bridge Eng 2012;17(2):310–7. [34] EN1993-1-8: 2005, Eurocode 3: Design of steel structures-part 1-8: Design of joints,
[20] Pavlović M, Marković Z, Veljković M, Buđevac D. Bolted shear connectors versus European Committee for Standardization, Brussels, Belgium; 2005.
headed studs behaviour in push-out tests. J Constr Steel Res 2013;88:134–49. [35] EN 1994-1-1: 2004, Eurocode 4: design of composite steel and concrete structures-
[21] Chen YT, Zhao Y, West JS, Walbridge S. Behaviour of steel-precast composite gir- Part 1-1: General Rules and Rules for Buildings, European Committee for
ders with through-bolt shear connectors under static loading. J Constr Steel Res Standardization, Brussels, Belgium; 2004.
2014;103:168–78. [36] Nie J, Jian F, Cai CS. Experimental study of partially shear-connected composite
[22] Kwon G, Engelhardt MD, Klingner RE. Experimental behavior of bridge beams beams with profiled sheeting. Eng Struct 2018;30:1–12.
13