You are on page 1of 48

INTERNSHIP REPORT 2022-2023

DAY-1& DAY-2 (22/08/2022& 23/08/2022)


1.1 COMPANY DETAILS

Habitat ventures, Banglore’s very own international award winning architect developers, it is a
professional Integrated real estate development company with expertise in conceptualizing
building and operatinginnovative development in Southeren India. In 13 years it has developed
2.5 million sqft. And 15 projects. The principles at Habitat ventures are architects with over two
decades experience in design, consulting and implementation.

1.1.1PROJECTDESCRIPTION:
The internship is done at ongoing project named “HABITAT EDEN HEIGHTS”,
apartment Constructing by HABITAT VENTURES. Habitat Eden Heights, Hoodi,
Bangalore.

The high rise towers of habitat Eden heights offers 2.5,3,3.5 BHK apartments. This well
designed project is ideally located very close to some well- known schools and colleges. This
residential project is spread in an area of more than 4.38 acres and offers 314 units for sale, it
features all the lavish and world class amenities with a safe and secure environment, this society
features intercom facility of parking space, clubhouse, children’s play area, tennis court, golf,
swimming pool and gym etc

Vision: “To emerge as the real estate developer of choice in Southeren India by building quality
relationships through a work culture and promotes integrity respect and loyalty”

Mission: “To provide our client and costumers examplery service in a professional and
Transparent environment and make the entire experience of dealing with Habitat ventures
Pleasant and personal”.

Dept. of Civil Engineering


Page | 1
INTERNSHIP REPORT 2022-2023
1.1.2 ORGANIZATIONCHART
Habitat ventures have well defined organization structure where, the structure works
functionally at top level and below which authority flows in line with staff assistance.
Hence the organization structure can be classified under Staff and Line Organization. In
this company each leadership team member has 2+ decades of relevant experience. The
organization structure of the Habitat Ventures is as follows.

FIG 1.1(b) ORGANISATION CHART

1.1.3 COMPANY PROJECTS


COMPLETEDPROJECTS
The company has already completed 15+ projects across the Bengaluru. Completed
projects are distributed all over the city with prominent access. Followings are some
important projects completed by the company.

RESIDENTIAL PROJECTS
1.HabitatAster-Whitefield 5.HabitatCrest-Whitefield
2.HabitatMayflower-Koramangala 6.Habitat Cedar-Thindlu
3.HabitatOrchid-Basavanagudi 7.Habitat Carnation Chandra layout
4.HabitatOchre-Uttarhalli 8.Habitat Maple-Rajarajeshwarinagar

COMMERCIAL PROJECTS
1.HVP Cypress I & II – VV Puram
2.HVP Arcade – RR Nagar
3.HVP Aster-Whitefield

Dept. of Civil Engineering


Page | 2
INTERNSHIP REPORT 2022-2023
ONGOING PROJECTS :
After completion of more than 15 projects, company now involved itself into major
residential constructions. Now company has 3 major ongoing projects which are of
minimum of 3 acres of total area. Ongoing projects of the company are listed below.
1.HabitatIluminar -Off Mysore Road.
2.Habitat Eden heights-Whitefield.
3.Habitat Aura -Arekere.

1.2 SITE LOCATION

FIG 1.2 (a)HABITAT EDEN HEIGHTS

FIG 1.2(b) LOCATION MAP

Dept. of Civil Engineering


Page | 3
INTERNSHIP REPORT 2022-2023
1.3 PROJECT DETAILS
The residential project Habitat Eden heights is spread in an area of more than 4.38 acres
and offers 314 units for sale. The newly constructed residential apartment really looks like
a dream home, as it has a beautiful interior and latest design. It is located in south
Bangalore and features all the lavish and world class amenities. With a safe and secure
environment this society features intercom facility. Parking space, clubhouse,
Basketball court, tennis court, badminton court, golf, walk ways, amphitheatre children’s
play area, swimming pool etc.

➢ Project name: HABITAT EDENHEIGHTS.


➢ Type: Residential Apartment.
➢ Total no of towers-4.
➢ Total site area: 17755.44Sq.Mtr (4.38acre).
➢ Total built-up area: 58277.42 Sq.Mtr (626971.79Sq.ft)
➢ Basement floor area = 7647.84 Sq.Mtr, GF area = 3137.44 Sq.Mtr, FF area = 2598.46
Sq.Mtr, Even area =2615.42 Sq.Mtr, ODD area = 2620.95 Sq.Mt.

Dept. of Civil Engineering


Page | 4
INTERNSHIP REPORT 2022-2023
Floor
➢ Floor Heights – BF (4.65 mtr) + GF (4.5 mtr) + Typical (3.05 mtr) –
Total heights from GF to Terraceis 59.40mtr.
➢ Total no of flats:314.
➢ Tower no: 1,2,3,4 -Basement+Ground+18 floors RCC framestructure.
➢ Tower 1– 3.5,3, 2.5BHK.
➢ Tower 2 - 2.5BHK.
➢ Tower 3– 3, 2.5BHK.
➢ Tower 4 – 3, 3.5BHK
➢ 1floor -18 flats (2.5BHK -9, 3BHK-7, 3.5BHK).
➢ 2.5 BHK – 1004.22sqft - 152flats.
➢ 3 BHK- 1192.69sqft-126flats.
➢ 3.5 BHK- 1332.12sqft-36flats.
➢ Total Staircase: 05nos.
➢ No of service lifts: 10 nos(8 Passenger’s = 5 nos, 13 Passenger’s = 5nos)
➢ BF Car parking – 208 nos, GF – 94 nos, Open space – 80 nos, Totally– 382nos.
➢ CLIENT: HVPL-Habitat ventures private ltd.
➢ PMC: EDA CONSULTANCYSERVICES.
➢ CONTRACTOR: -S3K Engineers and Contractors LLP.
➢ Total toilets – 978 nos (Except clubhouse & external).
➢ STP – 205KLD, DG – 500KVA - 04 nos, Gas banks – 02 nos, Entry /Exit ramps– 02
➢ In Door Amenities- Club house – 15000 Sqft area at Tower -2: 17th& 18thfloor
level,GYM/YOGA/Aerobics/Indoor games – Cards/Board games/TT room/billiards
room.
➢ Out Door Amenities – Basketball court, Tennis court, Badminton court, Golf, Jogging
tracks, Swimming pools, Walkways, Amphitheatre& children’s play area.

Dept. of Civil Engineering


Page | 5
INTERNSHIP REPORT 2022-2023

FIG 1.3 (a)MASTER PLAN

FIG 1.3 (b)PROECT VIEW

Dept. of Civil Engineering


Page | 6
INTERNSHIP REPORT 2022-2023
DAY-3 ( 24/08/2022)

MATERIALS

2.1MATERIALS USED AT SITE


At the construction site following materials were being used:

2.1.1 Cement:

Cement is a binder material a substance used for construction that sets, hardens and adheres to
other material to bind them together. Cement mixed with fine aggregates produces MORTOR for
masonry and mixed with sand and gravel produces CONCRETE. Cement used in construction
are usually inorganic, often lime or calcium silicate. Quality of cement is based on grade of
cement. The grade of cement are: 33 grade,43 grade,53 grade. At the site Portland cement of 53
grade is used. The initial setting time of cement =30 min and final setting time of cement =
below 10 hrs.

FIG 2.1(a) CEMENT

2.1.2Aggregates:

Aggregate is a broad category of course to medium grained particulate material used in


construction, including sand, gravel, crushed stone.

Types of aggregates: fine and coarse aggregate.

Fine aggregate, which passes through 4.75mm and retains of 75 mics IS sieve are used in
concrete mix is to fill up the voids existing in the coarse aggregate and to obtain a dense
and strong concrete with less quantity of cement and increase the workability of the
concrete mix.
Coarse aggregate, which passes through 75mm and retains on 4.75mm IS sieve. Gravel
constitute the majority of course aggregate used in concrete with crushed stone making
up most of the remainder.

Dept. of Civil Engineering


Page | 7
INTERNSHIP REPORT 2022-2023

FIG 2.1(b) AGGREGATES

2.1.3 M sand:
Manufactured sand is a substitute of river sand for concrete construction. M Sand is
produced from hard granite stone by crushing. The crushed sand is of cubical shape with
grounded edges, washed and graded to as a construction material. The size of M Sand is
less than 4.75mm

FIG 2.1(c) M SAND

Dept. of Civil Engineering


Page | 8
INTERNSHIP REPORT 2022-2023
2.1.4 Porotherm blocks
Porotherm blocks are clay bricks used for non-load bearing partition walls or infill
masonry.

Advantages:

• 60% less weight than a solid concrete block.


• Compressive strength >3.5N/mm2.
• Density of approx. 694 to 783kg/m3.
• Weight. 11KG
• Excellent thermal insulation.
• Water absorption ~15%.
• Reduction of dead loads.
• Saving on structural costs.
• Faster construction.
• Temperature difference +/-50c

➢ SIZE OF BLOCKS USED IN CONSTRUCTION

• 400x200x200mm FIG 2.1(d) POROTHERMBLOCKS


• 400x150x200mm
• 400x100x200mm
[Cite your source here.]

2.1.5Solid blocks:
Concrete blocks, also called cement blocks comes in wide varieties of shapes and sizes. They are
made out of Portland cement, sand, gravel and water.

• The weight of block is 35kg.


• The compressive strength is 5 N/mm2.
• Water absorption is~20%.

➢ SIZE OF BLOCKS USED IN CONSTRUCTION

• 400x150x200
• 400x100x200

FIG 2.1(e) SOLIDBLOCKS

Dept. of Civil Engineering


Page | 9
INTERNSHIP REPORT 2022-2023
2.1.6 Reinforcement:

The material that develops a good bond with concrete in order to increase its strength is called
reinforcement.Steel bars are highly strong in tension, shear, bending moment, torsion and
compression.

Function of reinforcement:

Reinforcement working as a tension member because concrete is good in compression


and week in tension so reinforcement resists the tensile strength in the concrete
members. At the site high strength steel bars and T.M.T (Thermo mechanically treated)
bars of diameter 8mm, 12mm, 16mm, 20mm, 25mm, 32mm is used as per requirement
of design. The bars were of grade Fe500D were used. The bars were of brand TATA
TISCON. The main reason of using steel bars in RCC is that, the co-efficient of thermal
expansion of steel bars and concrete is of approximately equal value .

FIG 2.1(f) Fe-500D STEEL FIG 2.1(g) TEST CERTIFICATE

2.1.7 Gypsum Plaster:

When dry POP powder is mixed with water it hardens. This material which can be
applied over brick, block or concrete surface to form a smooth surface is called gypsum
plaster. Earlier, a 6 mm coat of gypsum plaster (termed as POP punning) is usually
applied on the top of cement plaster to give a smooth finish to it before painting.This
process is slowly being replaced by a direct application of single coat of gypsum plaster.
In gypsum plaster, readymade POP powder is mixed with water & applied directly on
wall. Gypsum plaster has good insulation properties, fire resistant and impact resistant

Dept. of Civil Engineering


Page | 10
INTERNSHIP REPORT 2022-2023

FIG 2.1(h) Gypsum plaster bag Retarder

FIG 2.1(i) Gypsum plaster mesh

BPM plaster mesh reduces the risk of cracking on the wall caused by the movements
under plaster surface. This product has a proven track record for quality and value.

Technical Specification Of Gypsum Plaster:

Colour of Finished surface: White

Setting Time: 25-30 Minutes

Freezing Period: 40 Minutes

Plaster/Water Ratio: 10 kg to 6-6.5 litres of water

Coverage area (considering 12mm thickness): 21 sq.ft per 25 Kgs Bag

Compressive Strength: 60-70 kg/cm2

Bulk Density: 770 gram/litre

Dept. of Civil Engineering


Page | 11
INTERNSHIP REPORT 2022-2023

2.1.8 Ramco Super Plaster- Premixed Dry Mortar with graded sand, binders and
additives for

• Internal & External Application (General Purpose Plaster),


• External Application & bathroom walls (Water Repellent Plaster) and for
• Ceiling and brick laying Application (Ceiling Plaster)
➢ Features

• Compressive Strength at the age of 28 Days: 12-15Mpa


• Plot life: 1hour
• The initial setting time of cement =30min.
• Quantity of bag = 40Kg

➢ Applications

• Interior Walls
• Exterior Walls
• Ceiling Areas
• Brick Joints

➢ Benefits

• Uniform and better finish


• Reduction in cracks
• Enhanced durability and workability,Easy applications.

FIG 2.1(j) Super Plaster

Dept. of Civil Engineering


Page | 12
INTERNSHIP REPORT 2022-2023
DAY- 4(25/08/2022)

2.2 EQUIPMENTS
2.2.1Towercrane
In high raised buildings, tower crane plays an
important role in transportation of construction
materials to different levels at site. In this project 2
tower cranes are installed at different locations
depending on their maximum reach, details of
which are as fallows.

Company : ZOOM LION


Maximum height: 80m
Maximum reach : 75m
Maximum lifting: 3-3.5ton-m
Counterweights : 20tons
FIG 2.2(a) TOWER CRANE

2.2.3. Concrete pump


In high raised buildings, to cast upper floors concrete pump is must to transport concrete to the
different levels. Details of concrete pump used in this project are as fallows.
Company: SCHWING
Output :80-90m3/hour
Hopper Capacity: 0.6m3
Maximum horizontal distance: 800m
Maximum vertical distance: 200m

FIG 2.2(b) CONCRETE PUMP

Dept. of Civil Engineering


Page | 13
INTERNSHIP REPORT 2022-2023
2.2.4 Rotary mixer for transporting R.M.C / TRANSITMIXER
In this project ready mix concrete (RMC) is used for the construction. To transfer
concrete from RMC plant to site, transit mixers are used, where concrete will be kept in
continuous motion by means of drum rotation. Details of transit mixer are as fallows.
Company : TATA

Capacity : 6cum

Water tank : 600liters

Drum angle :30o

FIG2.2(c)TRANSIT MIXER

2.2.5Vibrator

Needle Vibrators are most commonly used vibrator for concrete. It consists of a steel tube having
an eccentric vibrating element inside it.

This steel tube called poker is connected to an electric motor or a diesel engine through a flexible
tube. They are available in size varying from 40 to 100 mm diameter. The frequency of vibration
varies up to 15000 rpm. However a range between 3000 to 6000 rpm is suggested as a desirable
minimum with an acceleration of 4g to 10g.

Dept. of Civil Engineering


Page | 14
INTERNSHIP REPORT 2022-2023

FIG 2.2(d) VIBRATOR& NEEDLE

2.2.7 HAULINGVEHICLES
Hauling vehicles are must in any construction work. These vehicles help in process of
transportation of construction materials from manufacturer to site and from site to dump
yard. Details of different hauling vehicles used in the projects are as follows.

FIG 2.2(e) TIPPER FIG 2.2(f) TRACTOR

a) TIPPER b) TRACTOR
Company: TATA Company: MAHENDRA
Capacity:13 to 45 tons Capacity:5-8tons
Heap capacity: 3.5 m3 Heap capacity : 24m3

Dept. of Civil Engineering


Page | 15
INTERNSHIP REPORT 2022-2023
DAY- 5 (26/8/2022)

SAFETY MEASURES
3.1 Safety at site
Safety us very important part of any work. Most accidents can be prevented by taking
simple measures or adopting proper working procedures. It is very important to discuss
issues on safety and health that should be paid attention to on construction sites.

It is important to educate everyone in the site regarding safety for the following purpose.

• Workers safety
• Construction progress
• Standard procedure
• Legal case
• Working efficiency

Two standard guidelines are followed for health and environment safety

• ISO14001-2004
• OHSAS18001-2007

3.2 Precautions at site for safety:

• Wear protective equipment.

• Do not drink or drugs while working.


• Pay attention to personal hygiene.
• Do not play in workplace.
• Report to your supervisor immediately if you notice any unsafe condition.
• Areas of responsibility are defined and lines of communication are clear.
• Educate the workers on safe work practices on a regular basis.
• Goodhousekeepingofmaterialsthroughpropermethodofstackingavoidsaccidents.

Dept. of Civil Engineering


Page | 16
INTERNSHIP REPORT 2022-2023
3.3 Equipment used for safety at construction site

FIG 3.3(a) SAFETY HELMETS

FIG 3.3(b) SAFETY NETS

Dept. of Civil Engineering


Page | 17
INTERNSHIP REPORT 2022-2023
DAY-6 (27/08/2022)

DESIGN AND CONSTRUCTION WORKS

4.1 Design brief


Structural system
The structural system is of RCC beam-columns with rigid joint. Lift walls are
considered as RCC shear walls. Foundation system is isolated footings and combined
footings.

Analysis method

Each of blocks is analyzed using principles of FEM by using ETABS.beams and


columns are modeled as “Frame Elements” majority of the floor objects as
“Membrane/shell elements”. The shear walls are modeled by using the shell element.
The floor slabs are idealized “Rigid Diaphragms to effectively transfer the lateral forces.
Floor system comprises of conventional beams and slab. Approximate loads and its
combination as per relevant clauses as per IS codes, for must unfavourable effects are
chosen for design.

Foundation
As per recommendations from soil report NO. GF011002 point NO. 6.1. The foundation
system will be isolated/combined footing. Allowable bearing pressure in KN/m 2 for a
minimum footing width of 1m is mention below.

ALLOWABLE BEARING PRESSURE KN/m2 DEPTH FROM GROUND


LEVEL,m
200
1.5
250
2.5
300
3.5
400
4.5
800
IN WEATHERED ROCK

Dept. of Civil Engineering


Page | 18
INTERNSHIP REPORT 2022-2023
As per soil report point NO 6.2- The minimum depth of foundation should be at least
1.5m below the natural ground level. For the present structure the minimum depth of
foundation is 1.5m below the ground level or 1m below the basement floor level. Water
table is not encountered.

4.1.1 Design loads


1. Load combinations

• Deadload: weight of materials shall be calculated on the basis of unit weights


given in IS:875(part-1)-1987.
• Super imposed loads: consists of PCC/filling if any.
• Finishes: consists of floor finishes.
• Partition/ledge wall load: All the internal partition walls/ledge walls loads
considered and applied over the slab.
• Walls:Porotherm walls are considered except in toilet area where fixture are
available 150mm/200mm thick solid concrete block are considered.
• Live load: The imposed load or otherwise live loads area assessed based on the
occupancy classifications asIS:875(part-2)-1987.

• FLOOR Live load in Finishes Floor system


LOADIND AS Kn/m2 Kn/m2
• PER
IS:875(PART2)-
1987
Ground floor 75mm Screed
Stacked car parking 5 1.5 conventional
beam & slab
150mm fill on
Ramp 5 1.5 podium

Stair 3 1.5

Lobby/Corridor 3
1.5

Podium
15
2.5
(Fire Tender)

Dept. of Civil Engineering


Page | 19
INTERNSHIP REPORT 2022-2023

First Floor to 18th Floor


All rooms and kitchens 2 1.5 Conventional
beam and slab
Stair 3 1.5
Lobby/corridor 3 1.5
Toilet 2 1.5
Partition 1
Terrace
Floor 1.5 2.25 110mm thick
Stair 3 1.5
LMR 2 10 Conventional
beam and slab

Water tank 25(2.5m Conventional


height) 2.25 beam and slab
Club house
Indoor games, 5.0 1.5 Conventional
multipurpose hall, beam and slab
gym, aerobics/yoga room,
electrical panel room,
reading room, shops.

2.Wind load
Bangalore is in the south of India basically having winds with the high wind speed of
33m/wind loads and pressures are calculated based on the static design wind
pressure. This pressure has been considered for the load analysis and applied
Basic wind speed = 33m/sec
3.Earthquake load: The loading due to earthquake is assessed on the provision
of IS:1893-2002.
Seismic zone = II

Zone factor=0.1

Response reduction factor=3

Importance factor=1

Dept. of Civil Engineering


Page | 20
INTERNSHIP REPORT 2022-2023
4.1.2 Design life
The design life of the structure is assumed as 50 years. This requirement is not
applicable to replaceable material.

Retaining walls
Retaining walls are the structures use it to support earth which would not able to stand
vertically unsupported. The retaining walls shall be designed for a soilpressure.

REINFORCEMENT

Steel reinforcement shall be of grade Fe500 confirming to IS:1786-2008

ITEM GRADE OF CONCRETE GRADE OF STEEL


FOUNDATION M30 Fe500D
COLOUMN-AT ALL LEVELS M30 Fe500D
SHEAR WALLS-AT ALL M30 Fe500D
LEVELS
COMPOUND M20 Fe500D
RETAINING WALLS
BUILDING M30 Fe500D
RETAININGWALLS
BEAM-AT ALL LEVELS M30 Fe500D
SLAB-AT ALL LEVELS M30 Fe500D
OVERHEAD TANK M25 Fe500D
UNDER GROUND SUMP M25 Fe500D
TANK,STP

COVER TO REINFORCEMENT: MODERATE EXPOSURE


The nominal cover to main reinforcement shall be as follows:

Raft/Footing-50mm
Coloumns-40mm
Lift shear wall-25mm
Beam-30mm Slab – 25mm
For elements not specified above, clear cover shall be as per the clause 26.4 of IS:456-
2000

DAY-7 (28/08/2022) – SUNDAY [HOLIDAY]

Dept. of Civil Engineering


Page | 21
INTERNSHIP REPORT 2022-2023
DAY-8 (29/08/2022)

4.2 Foundation
Dimensions of foundations used at site

Block ID Depth below 3.0mfrom 2 Depth of foundation below


NGL SBC in KN/m Basement
B-1 600 1.5M
B-2 600 1.5M
B-3 600 3.6M
B-4 600 1.5M
B-5 600 2.55M
B-6 600 3.05M

DAY-9 (30/08/2022) – GOWRI FESTIVAL [HOLIDAY]


DAY -10 (31/08/2022) – GANESHA CHATHURTHI [HOLIDAY]

DAY -11 (01/09/2022)

4.3 Formwork
Form work is temporary mould into which concrete is poured and formed. Formwork
holds the concrete until it hardens to required shape and size.

Types of formwork

Timber formwork
Plywood formwork

Steel formwork
Aluminium formwork

FIG 4.3(a) FORM WORK


Formwork constitutes 30% of cost and 60% of time in concrete construction.

Before shuttering
• Cover blocks are given in 4sides
• Cover blocks are provided at a height of 1 to 1.2m.
• Foam sheet is provided for starters.
• Lubricant oil is applied.

Dept. of Civil Engineering


Page | 22
INTERNSHIP REPORT 2022-2023
During shuttering
• Using plumb ply boards are fixed.
• Fix the tie rods to prevent bulging.
• Form work is checked for right angles.

Shuttering procedure
• Fixing of column boards-Runner (2x3inch of 75mm) and plywood(75mm)
• Niles 2, 3, 5inches
• Fix tie rods, right angle, jacks, C clamp and foam sheet is provided. Check plum
and right angle.

4.3.1 FORMWORK FOR BEAMS


Beam formwork consists of open through section and because it is not closed at the top,
more supporting frame work is needed to restrain slides.The supports need to be
maintained to the soffit and also provide lateral support to the sides. Metal panels are
used with corner pieces, forms are provided for vertical support.

4.3.2 FORMWORK FOR SLABS


• Floors require large area of formwork to be provided from beam to beam.
• Timber floor formwork consists of timber boards or plywood sheets supported
on a formwork and resisting on a series of timber joint.
• As per drawing prepared layout beam bottom check will be done.
• T – Type jack is provided in bottom and in joints jacks must be provided.
• Then beam bottom is checked after side boards are fixed and checked.

FIG 4.3(b) SHUTTERING FIG 4.3(c) SHUTTERINGBOARDS

Dept. of Civil Engineering


Page | 23
INTERNSHIP REPORT 2022-2023
DAY-12 (02/09/2022)

4.4 Concreting
Concrete is a composite material composed of fine and coarse aggregate bonded together
with a fluid cement that hardens over time. The density of concrete is 2400kg/m3.

During concreting following equipment’s are used:

• Concrete mixer.
• Mounted concrete pump.
• Concrete vibrators.

During concreting work following instructions should be followed:

• There should be proper compaction of poured concrete.


• There should be spacers to provide cover to reinforcement.

FIG 4.4PUMPING OF CONCRETE

Dept. of Civil Engineering


Page | 24
INTERNSHIP REPORT 2022-2023
DAY-13 (03/09/2022)

4.5 Reinforcement
Reinforcing means the action of strengthening or encouraging something.
Reinforcement should be provided at designed spacing. Steel bars of designed grade
should be used. Slab thickness-150mm, sunken area- 125mm.

Reinforcing of beams, columns, slabs

• The lapping length for columns and beams 37d and 50d are
considered.
• Stirrups are provided c/c distance as per design and binded by binding
wires (mild steel).
• The first step is location of columns and beams in field as per
drawing.

COVER TO REINFORCEMENT
The nominal cover to main reinforcement shall be as follows:
• Raft footing –50mm
• Columns-40mm
• Retaining wall-30mm
• Lift shear wall-25mm ,Beams-30mm
• Slabs-25mm.

Dept. of Civil Engineering


Page | 25
INTERNSHIP REPORT 2022-2023

FIG 4.5(a) REINFORCEMENT FIG 4.5(b) REINFORCING OF SLABS

FIG 4.5(c) REINFORCING OF FIG 4.5(d) REINFORCING OF LIFT


COLUMNS COLUMNS

Dept. of Civil Engineering


Page | 26
INTERNSHIP REPORT 2022-2023
DAY – 14(04/09/2022) – SUNDAY[HOLIDAY]

DAY -15 (05/09/2022)


4.6Expansion joint
Normally structures exceed 45m in length are designed with one or more expansion
joint. Structures adjacent to the joint should preferably be supported on separate
columns or walls but not necessarily on separate foundations. Joints provided to
accommodate the expansion of adjacent building. 100mm width of expansion joints are
considered between the two blocks.

In building construction, an expansion joint is a midstructure separation designed to


relieve stress of building movement included by:

• Thermal expansion and construction caused by temperature changes.


• Sway caused by wind
• Seismic events
• Static load deflection
• Live load deflection

FIG 4.6(a) SUPREME BOARD MATERIAL FIG 4.6(b) EXPANSION JOINT


USED AS EXPANSION JOINT

Dept. of Civil Engineering


Page | 27
INTERNSHIP REPORT 2022-2023
DAY-16 (06/09/2022)
4.7Masonary works

Masonry work is a process that includes laying of brick or stone with mortar. Types of
masonry: Brick masonry, stone masonry, concrete blocks etc.
Steps of masonry works are as follows:
• Basecourse
• Check the base course as per plan
• Check room dimensions
• Laying of blocks on basecourse
• Check the plum line after laying each course
• A mortar of 12 to 15 mm thickness is provided.

FIG 4.7(a) LAYING OFBASE COARSE FIG 4.7(b) PLUMCHECKING

FIG4.7(c) MASONRYWORK FIG 4.7(d) RISING OF WALLBYCOARSE

Dept. of Civil Engineering


Page | 28
INTERNSHIP REPORT 2022-2023
DAY-17 (07/09/2022)

FINISHING WORKS

5.1 PLASTERING
Plastering is the process of covering rough walls and uneven surface in the construction
of houses and other structures with a material called plaster, which is a mixture of lime
or cement concrete and sand along with the required quantity of water.

Steps of plastering are as follows:


• Preparation of surface for plastering: Surface and all joints should be
cleaned and rough to give a good bonding to hold plaster.
• Ground work for plaster: To get uniform thickness check the level surface
by level pods.
• Applying first coat: The thickness of first coat plaster is generally of 12mm.
• Applying of finishing coat: The thickness of finishing coat of 1:4 to 1:6 ratio
is provided.The finishing coat should be applied starting from top towards
bottom and complete in one operation to eliminate joining marks.

After the completion of the plastering work, it is kept wet by sprinkling water for at
least 7 days in order to develop strength.

FIG 5.1(a) SCOOPINGOF PLASTER FIG 5.1(b) SMOOTH STROKES BY TROWEL

Dept. of Civil Engineering


Page | 29
INTERNSHIP REPORT 2022-2023
5.1.1 Gypsum plastering
Gypsum plastering is most commonly used in internal wall plastering and has been
widely replacing the traditional cement mortar plastering. Although gypsum plaster is
easy to apply and require less experienced manpower as compared to the traditional
cement mortar, it is important to properly prepare the wall surface and properly apply
gypsum plaster to ensure no cracks, peel offs etc.

SPECIFICATION OF GYPSUM PLASTER:


• Setting time: 25-30 min.
• Color: White
• Coverage area (Considering 12mm thickness):21sqft. per 25 kg bag
Compressive strength: 60-70 kg/cm2

PROCEDURE FOR APPLYING GYPSUM PLASTER:


• Surface preparation: The joints are filled with non-shrink mortar a day before the
application of chicken mesh.
• Electrical conduits and plumbing lines are placed inside the brickwork.
• Mesh should be fixed tightly at the joint of brickwork and RCC.
• Concrete and brick surface have to been properly cured before applying gypsum
plaster.
• All bricks work surface has to be cured properly for at least 7days.
• Check the verticality of wall surface using plumb level and remove undulations.
• Painting work should be only be started once surface has become complete dry.

FIG 5.1(c) GYPSUM PLASTERING FOR FIG 5.1(d) GYPSUM COATING


CEILING FOR WALLS

Dept. of Civil Engineering


Page | 30
INTERNSHIP REPORT 2022-2023
DAY-18 (08/09/2022)
5.2Flooring and skirting
Flooring is the general term for a permanent covering of a floor or the work of installing
such a floor covering, finished material applied over the floor structure to provide a
walking surface.

5.2.1Flooring procedure
• Clean the floor of dust and debris.
• Snap chalk lines to find center of room
• Layout tile with spacers for dry run
• Mix the thin-set mortar
• Apply the mortar
• Work in small sections to keep mortar from drying
• Use tile cutter to mark and make cuts on tiles.

Wall tiling of dimension 300x300 mm, 6mm thickness is used in this project.
➢ Flooring tile -vitrified tiles of 800x800mm,8mm thickness issued.
➢ Cement mortar -1:3 screed shall be spread with recommended thickness of
mortar should be in range of 20-25mm.

5.2.2Skirting

• Vitrified tiles of height 100mm and 100mm thick is used.


• They are checked for right angle with floor tile.

FIG 5.2(a)LAYING OF TILES FIG.5.2(b) SKIRTING

Dept. of Civil Engineering


Page | 31
INTERNSHIP REPORT 2022-2023
DAY-19 (09/09/2022)

5.3 CURING
Curing of concrete is defined as the process of maintaining the moisture content and
temperature conditions of concrete for hydration reaction to normally so that concrete
develops hardened properties over time. The main components which need to be taken
care are moisture, heat and time during curing process. The curing process is vital to
quality and has a strong influence on concrete properties such as durability, strength,
water tightness, resistance, volume and freezing and thawing resistance.

Types of curing
• Covering Concrete Surfaces with Gunny Bags.
• Sprinkling of Water.
• Ponding Method.
• Membrane Curing.
• Steam Curing.

Ponding curing:
In ponding method, small rectangular or square artificial ponds are built with using
bunds of clay or lean mortar along the concrete surface. This method is commonly used.

FIG 5.3(a) POND CURING

Dept. of Civil Engineering


Page | 32
INTERNSHIP REPORT 2022-2023
Curing using gunny bags:
This is a widely used method of curing particularly for structural concrete. Thus,
exposed surface of concrete is prevented from drying out by covering it with gunny bags
to retain water. The covering over vertical and sloping surfaces should be secured
properly. These are periodically wetted.

FIG 5.3(b) CURING USING GUNNY BAGS

• As per the IS Standards the curing time of concrete is 28days until it achieves its
nominal strength.
• Minimum of 7 days and 14 days of curing should be done for columns , slabs.
• Most of concrete reaches approximately 80% of its compressive strength within
7 days.
• If concrete does not contain fly ash, GGBS, micro silica, the slab needs to be
cured for a minimum period of 7 days. If they contain this compound it should
be cured for 14 days.
• To prevent surface damage, concrete should be covered with the fabric as soon as it
has hardened.
• The entire surface including the edges and joints of the slab should be kept covered
so that these parts are not left inadequately cured.
• The fabric retains water for a great period of time. Therefore, the fabric must always
be kept wet or moist so that concrete surface is in contact with water throughout the
curing period of concrete.

Dept. of Civil Engineering


Page | 33
INTERNSHIP REPORT 2022-2023
DAY-20(10/09/2022)

SERVICES

6.1 FIRE FIGHTING SYSTEM


Fire-Fighting System, Automatic. A system of equipment used to prevent, extinguish, localize,
or block fires in enclosed spaces. Automatic fire-fighting systems are installed in buildings and
rooms where the fire hazard is comparatively high.

FIRE RATING

This structure is designed for 2 hours fire rating for all structural elements in structure.

6.1.1 FIRE RATED DOORS


Fire-rated doors provide around-the-clock protection to help ensure people can safely evacuate a
building in the event of a fire. When they’re not called upon to limit the spread of fire and
provide safe egress, they serve as a regular door pathway, making good visibility crucial.

DOOR SPECIFICATION:

➢ Door weight-45Kg
➢ Height - 7 feet 3 inches.
➢ Thickness- 47mm
➢ Type - Honeycomb
➢ Closing time- 5secs
➢ Evacuation time- 30-45mins.
➢ Fire door may be made up of Galvanized steel.
➢ It can withstand up to 500KG of load.
➢ It has glass sections including Vision panel.
➢ Edges of a fire door usually need to have fire rated seals of Ceramic gasket so it doesn’t
emit smoke.
➢ It can withstand Max. heat of 1200’C.

Dept. of Civil Engineering


Page | 34
INTERNSHIP REPORT 2022-2023
FIRE HYDRANT SYSTEM

A fire hydrant is a connection point by which firefighters can tap into a water supply. It is a
component of active fire protection. Fire hydrant pump systems (also known as fire pumps,
hydrant boosters, firewater pumps) are high pressure water pumps designed to increase the
firefighting capacity of a building by boosting the pressure in the hydrant service when mains is
not enough, or when tank fed.

EQUIPMENTS

• Water pumps
• Pipes
• Diameters of pipes –60,50,40,25mm
• Sprinklers

FIG 6(a) SPRINKLERS FIG 6(b) SPRINKLER

FIG 6(c) PIPES WITH SPRINKLER FIG 6(d) HYDRANT PIPES

Dept. of Civil Engineering


Page | 35
INTERNSHIP REPORT 2022-2023
DAY-21(11/09/2022) – SUNDAY[HOLIDAY]

DAY-22 (12/09/2022)

TESTS

7.1 TESTS CONDUCTED AT SITE

1. Slump test:
The slump test is a means of assessing the consistency of fresh concrete. It is used, indirectly, as
a means of checking that the correct amount of water has been added to the mix. It is testing
fresh concrete.
There are 4 types of slumps can be seen,

• True slump.
• Shear slump.
• Collapse slump.
• Zero slump.

FIG 7(a) SLUMP TEST

Dept. of Civil Engineering


Page | 36
INTERNSHIP REPORT 2022-2023

FIG 7(b) FILLING SLUMP CONE FIG 7(c) SHEAR SLUMP(140mm)

2. Cube test:
Concrete is very strong in compression. It is assumed that whole of the compression will be
taken up by the concrete while designing any RCC structure. The most important strength test for
concrete is the compression test. This test is not only important from structural point of view but
also other properties such as fatigue, impact, shrinkage, creep, deformation and thermal
sensitivity bear some relationship with it.

FIG 7(d) UTM MACHINE

Dept. of Civil Engineering


Page | 37
INTERNSHIP REPORT 2022-2023
DAY-23 (13/09/2022)

SITE TOUR WITH MD AND ARCHITECT

Dept. of Civil Engineering


Page | 38
INTERNSHIP REPORT 2022-2023
DAY-24(14/09/2022)
GUIDE VISIT

GUIDE NAME: Mr.MANJUNATH M KATTI

Dept. of Civil Engineering


Page | 39
INTERNSHIP REPORT 2022-2023
DAY-25(15/09/2022)

BUILDING INSURANCE
Home insurance or property insurance secures the structure along with its content against
unwanted events like fire, theft, natural calamities (storm, cyclone, etc.) or man-made activities
(riots and terrorism). With the arrival of auspicious occasions, it is advisable for you to invest in
a home insurance policy, as securing your assets is one of the best things to do during this festive
time. An unfortunate incident can cause irreversible damage, leading to vulnerable financial
losses; hence, it is wise to buy property insurance.

The Insurance Regulatory and Development Authority of India (IRDAI) has made it mandatory
for every insurer to offer a standard home insurance policy known as Bharat Griha Raksha from
April 1, 2021. Bharat Griha Raksha provides coverage against loss, damage, or destruction of the
home building and its contents due to unforeseen circumstances.

Our nation is prone to natural calamities and constant fire incidences, which lead to irreversible
damages. For example, in 2021, cyclone yaas in Odisha and a major fire incident in Kullu,
Himachal Pradesh in December 2021, gutted 15 houses and led to severe destruction of property.

Bharat Griha Raksha

Bharat Griha Raksha provides coverage for home building and its content. This policy has been
made mandatory by the Insurance Regulatory and Development Authority of India (IRDAI) for
every insurer to offer with effect from April 1, 2021. The IRDAI announced the introduction of
Bharat Griha Raksha standard home insurance policy on January 4, 2021 that it will cover the
risk of fire and allied perils for certain risks. Bharat Griha Raksha is basically a home insurance
cover that provides coverage for loss, damage or destruction of the home building along with its
content and jewellery. In Bharat Griha Raksha the policy can be extended up to 10 years.
Valuable content of the house can also be covered with Bharat Griha Raksha under different
optional covers.

Homeowners looking for an ideal HOME INSURANCE COVER can opt for the Bharat Griha
Raksha policy, which will secure the home structure and its content appropriately. Even tenants
should consider buying the Bharat Griha Raksha policy to insure the belonging against any sort
of unforeseen event.

Dept. of Civil Engineering


Page | 40
INTERNSHIP REPORT 2022-2023
REFLECTION

In this chapter we reflect on the internship. Regarding your learning goals we shortly discuss
our experiences, if we have achieved our goal, and the technical as well as the non-technical
outcomes of the internship Program.

Internship is a class healed at site to provide an enhanced understanding of the outside


working environment before the student graduate. Student like civil and urban engineering
and other fields also take this practice. The main aim of this practice (internship) is that to
teach students communication with different workers or employees, to improve practical
skill what they learned at class, up grading the theoretical knowledge in addition to the class,
improve their leadership skill, team playing skill and etc.
The use of skills and knowledge gained in the university and the skills and knowledge
gained in my study could be put to use to practice in our internship. At the beginning we did
not have any experience of about construction. Although we had seen one, we now
understand better about the construction procedure and building material testing

8.1 CHALLENGES AT THE SITE


• Communication
• Co-ordination
• Study of Drawing

8.2 LEARNING OUTCOMES


TECHNICAL OUTCOMES OF INTERNSHIP
• Study of different types of drawings, Work order.
• Important criteria considered for the design of a structure:
• Types of slabs
• Beams and Columns
• Block work
• Finishing works
• Studied about Services

Dept. of Civil Engineering


Page | 41
INTERNSHIP REPORT 2022-2023
NON-TECHNICAL OUTCOMES OF INTERNSHIP
• Improving practical knowledge
• Upgrading theoretical knowledge
• Improving interpersonal communication skill
• Teamwork
• Leadership and decision making
• Time Management

1.IMPROVING PRACTICALKNOWLEDGE:
During my internship period, I had great opportunity to get to know things in practical.
There is a vast gap between theoretical and practical knowledge. It only through experience
can one gain knowledge and this helps in handling critical situations at site. In the company,
discussions carried out with the staffs helped me to gain practical knowledge regarding the
methodology at site, handling the site situations. Each site I visited during my internship was
invaluable experience. The practical knowledge I gained in the internship now gives me a
clear idea of several civil engineering concepts which would otherwise remain undigested
throughout.

2.UPGRADINGTHEORETICALKNOWLEDGE:
In the company, discussions carried out with the staffs helped me to find new areas of
references to improve my theoretical knowledge. Theoretical knowledge gets a newer
dimension once practical knowledge is gained. The link between theory and practice can be
established.

3.IMPROVINGINTERPERSONALCOMMUNICATIONSKILL:
Communication skill is very important in all aspects of life. The way we communicate a
particular information has greater impact on the listener. Since ours is construction field and
we will be dealing with labours as well as officials so it is very important for an engineer to
have good communication skill so that the message is conveyed in an efficient manner and
work progress can be faster.

Dept. of Civil Engineering


Page | 42
INTERNSHIP REPORT 2022-2023
4.TEAMWORK:
For the growth of any organization, teamwork is the most important and it cannot be
neglected. A team consists of members from different background, qualifications, way of
thinking, etc.In the company, I observed that without teamwork it almost becomes
impossible to carry out some works at site. There will be several works that have to be
performed before the commencement of work at site. All the tasks can be performed without
any delay when there is good teamwork. It’s because of good teamwork that field and
laboratory tests are conducted and reports can be given to client in time.

5.LEADERSHIP AND DECISIONMAKING:


In civil engineering field, site conditions will be different at each site. It is really important
to have good leader to decide the way in which work should be performed and completed in
specific duration of time. A leader has to think about welfare of team members and also
make sure that the work is not delayed in prolongation of any activities.
A particular site is first visited by the leader, the site conditions are observed thoroughly and
crucial points are noted down if found any. The conditions at site are discussed with
respective client and chairman of the company.
Right decisions at right time helps to complete the work in scheduled time. Decisions to be
taken keeping in mind the safety of structure coming over the soil.

Dept. of Civil Engineering


Page | 43
INTERNSHIP REPORT 2022-2023
OVER ALL INTERNSHIP EXPERIENCE

JOINING THE COMPANY


After finishing our 6th semester exam we were eagerly waiting to do our
internship in any construction company, we searched many companies in which
some of them were charging huge ransom of money and some of them did not
accept us, luckily with the help of our professor , we got an offering at one of the
prestigious construction company HABITAT EDEN HEIGHTS, BANGALORE. We
got the internship letter from our department. The next day we visited the
construction site where the company’s work was in progress and we met the site
engineer Mr.ELDO gave he gave us orientation about the overall work, gave some
technical notes to study, and instructed us to carry safety helmets and to put tough shoes
while entering the site, as he told us we began the work from next day and joined the
company.

SECTION OF THE COMPANY WE HAD WORKED


Our company has many projects in our country as I have mentioned in the
company profile. Thus, from the listed we were working in one of the
Bangalore’s project “Habitat Eden Heights”. Since our company was the
consultant of Habitat Ventures apartment, we had an opportunity to work at
different departments.

They are:

1. Junior engineer.
2. Assistant quality surveyor.
3. Assistant quantity controller.

Dept. of Civil Engineering


Page | 44
INTERNSHIP REPORT 2022-2023
CONCLUSION

It is not only to get experience on technical practices but also to observe management
practices and to interact with field workers. It is easy to work with sophisticated
machines, but not with people. The only chance that an undergraduate has to have this
experience is through internship period. We feel we got the maximum out of that
experience. Also, we learnt the way of work in an organization, the importance of
maximum commitment and the importance of team spirit. The internship program was a
lot more useful than staying at one place throughout the whole 30 days. In our opinion,
we have gained lots of knowledge and experience needed to be successful in a great
engineering challenge, as engineering is after all a challenge, and not a job.

As we are the undergraduates of CIT college of Engineering, Gubbi we would like to


say that this internship program was an excellent opportunity for us to get to the ground
level and experience the things that we would have never gained going straight through
a job. We are grateful to CIT college of Engineering, Gubbi and Habitat Ventures,
Bangalore for giving us this wonderful opportunities.

REFERENCE

1. Dr. B.C. Punmia Er. Ashok Kumar Jain, Dr.Arun K Jain, “R.C.C.
Designs(Reinforced Concrete Structures)”.
2. IS: 456-2000, ―Indian Standard Plain and Reinforced Concrete – Code of practice.
3. Drawings from
company
4. Company Project Profile.
5. Safety manual.

Dept. of Civil Engineering


Page | 45
INTERNSHIP REPORT 2022-2023

ANNEXURE

WITH INTERNAL AND EXTERNAL GUIDE

Dept. of Civil Engineering


Page | 46
INTERNSHIP REPORT 2022-2023

SITE TOUR WITH MD

WITH SBI INSURANCE AGENTS

Dept. of Civil Engineering


Page | 47
INTERNSHIP REPORT 2022-2023

CAD DWG OF BLOCKWORK

Dept. of Civil Engineering


Page | 48

You might also like