You are on page 1of 1

customer's copy

LESTARI ENERGY SDN BHD


(1084153-M)
Our reference : LE/NEM/24-027
Your reference : LE/NEM/24-PAKA-MALIKI
Quotation date : 23/04/2024 Form Ref No : LE/NEM/24-027
Validity : 15 days
Name : EN MALIKI BIN AB. WAHAB
Address : PT 11808 , LOT L25, JLN SANTONG
PAKA, 23100, DUNGUN
TERENGGANU
E-mail : N/A
Telephone : 019-988 8105
QUOTATION FOR SOLAR PV SYSTEM (RETROFIT) SUITABLE FOR NET ENERGY METERING (NEM) REQUIREMENT
With reference to the above, we are pleased to submit the quotation as follows:-
Minimum Roof Size
No Description Unit Qty Requirement Price (RM)
(sq. feet/ sq. metre)
PACKAGE : 12.0 kW ( 13.2 kWp)
1 550W PV Module (or equivalent) Pcs 24
517 ft² / 48m² 38,280.00
2 12kW on-grid Inverter c/w all required acessories Set 1
3 .Skylift (If applicable) Day 1 500.00
4 Documentation / Design, Authority approval & NEM meter application (TNB) L/S 1 200.00
TOTAL RM 38,780.00
The above package quoted is inclusive of the following items and scope of work:
DC/AC connector, fuses, surge protection devices, switches c/w all required accessories and
i
support system, double insulated fire resistant solar DC cables ;
ii Solar PV mounting structures (retrofit)
iii Installation of PV modules, wiring c/w all required accessories and support system
iv Design, liaison with authority, Suruhanjaya Tenaga, SEDA Malaysia
v Testing and commissioning, NEMCD documentation
Warranty Workmanship : 2 Years

Product
Solar Inverter : 10 Years : Back to back warranties with Manufacturer
PV Module : 12 Years
Terms and Conditions
Prices : Quoted price is inclusive tax and port handling
Delivery : 6-10 Weeks from date of Purchase Order
Payment Terms : Commitment fee RM 300 (Processing and documentation for NEM quota application)
60% Payment for preliminary works, liason with authority & procurement.
35% Payment upon completion of installation works.
5% Payment after testing and commissioning.

* Kindly note that the quotation includes max. of 20 metres of 6mm DC cable per string, max. 60 metres
of 10 mm AC cable and max. of 12 metres of 6 mm AC cable.
* Any additional machinery and(or) cables/accessories for special wiring type required will be charged
to the client.
* Commitment fee (CF) will be deducted from final payment. In case of cancellation made by client due to
invalid reason, the CF is not refundable
Trusting the above is in order, we look forward to your favorable reply.
Thank you.
Yours sincerely, Confirmed by,
LESTARI ENERGY SDN BHD
Azroul ……………………………………………..
LOT 2589, JALAN TOK ADIS,TAMAN ADIS INDAH,20400 KUALA TERENGGANU, TERENGGANU DARUL IMAN
Tel: +609-6310172 ; Email : lestar1.3nergy@gmail.com FB page : https://www.facebook.com/lestarienergy/