You are on page 1of 1

SOW Quantity SurveyTank 307 Contract #GUP - EC - 23-001

Dated 11/12/2023
Project : Repair of TANK # 307 Dia. : 61 m

Quantity surveyed
Quantity
Serial Estimated SOW Unit Contract Item NO. SOW description as contract on contract Unit Remarks
surveyed
description

Open necessary access at Tank shell to


1 Open Access door 3 SQ.M ITEM # 32 handle piping, plates, reweld and apply SQ.M
heat treatment if needed
Replace and compact oily sand layers
underneath bottom according to the
2 Remove and Replace Oily sand 2930.57 SQ.M ITEM# 4 specification of oily sand (layer thickness SQ.M
from 50 to 80 mm). Gupco will provide
oily sand.
Apply internal painting system according
3 Sandblasting and painting underneath bottom plates 2932.86 SQ.M ITEM# 49 to company specification including SQ.M
sandblasting and washing
Supply and Re-bottoming tank plate
Replace bottom plates completely 6 mm
4 2685.56 SQ.M ITEM # 8 -amount shall be added for each 2 mm
SQ.M
increment
supply material, fabricate and replace
new
5 Replace Annular plates 280.72 SQ.M ITEM # 9 annular plates completely 8 mm. SQ.M
-amount shall be added for each 2 mm
increment.
Supply material, fabricate and replace
sheet(s) from Tank roof 6mm thickness
6 Replace corroded plate of roof 18 SQ.M ITEM # 18 Partially SQ.M

Apply N.D.T (vacuum box test) on bottom Apply N.D.T on all welding phasaes:
7 5000 M.L ITEM # 48 M.L
welds vacuum Box test
Close Man-way, Clean out Door Flanges for Close Man-way, Clean out Door
8 354 Dim.Inch ITEM # 45 Dim.Inch
applying hydro- test Flanges for applying hydro- test
Supply, Fabricate ,Installsteel structure for roof Supply, Fabricate ,Installsteel
handrail and wind breaker structure for tank roof
9 900 kg ITEM # 46 kg

Open necessary access at tank roof for Open necessary access at tank roof
inspection and re-weld (open five windows at for inspection and re-weld
10 the upper deck for inspection and repair) outer 67.5 SQ.M ITEM # 33 SQ.M
pontoon

Sandblasting and painting tank externally Apply external painting system according
11 194.5 SQ.M ITEM# 50 to company specification including SQ.M
sandblasting and washing
Apply fiberglass lining system for tank
bottom and water zone of shell
completely including sandblasting and
12 Apply Fiberglass 3161.7 SQ.M ITEM # 52 painting primer - lining thickness 3000 SQ.M
micron (thick film)

Welding Longitudinal Welds at tank Roof,


13 Weld up Longitudinal Welds 3500 FT ITEM # 47 FT
Shell and bottom

14 Excavation 191.5 Qubic meter ITEM E-1 Excavation Qubic meter

Casting Concrete jackets Casting Concrete jackets


15 57.4 SQ.M ITEM E-4 SQ.M

16 Backfilling 191.5 Qubic meter ITEM E-2 Backfilling Qubic meter

Supply material, 4" sch 80 107


fabricate, replace and Supply material, fabricate, replace and
17 M.L ITEM # 42 M.L
install internal and install internal and external pipes
external pipes 6" sch 40 86

Supply material, 6" 28


Supply material, fabricate, replace and
18 fabricate, replace and EACH ITEM # 43
install Fittings
EACH
install Fittings 4" 54

19 Check and evaluate tank shell roudness – out of 1 Each D-DIAM 61-1 Check and evaluate tank shell Each
service roudness – out of service
Dismantling of existing pantograph mechanical Dismantling of existing pantograph
20 seal 1 Each D- DIAM 61 - 5 mechanical seal Each

Supply pantograph mechanical seal Supply pantograph mechanical seal


21 1 Each D- DIAM 61-6 Each

Install pantograph mechanical seal Install pantograph mechanical seal


22 1 Each D- DIAM61 - 9 Each

demolish existing extra bottom layer demolish existing extra bottom layer
23 2920 SQ.M ITEM # 3 SQ.M

G.O.S Onshore Projects Rep. Petromaint Site Manager


Name
Signature
Date

You might also like