Professional Documents
Culture Documents
SOW Quantity Surveytank307
SOW Quantity Surveytank307
Dated 11/12/2023
Project : Repair of TANK # 307 Dia. : 61 m
Quantity surveyed
Quantity
Serial Estimated SOW Unit Contract Item NO. SOW description as contract on contract Unit Remarks
surveyed
description
Apply N.D.T (vacuum box test) on bottom Apply N.D.T on all welding phasaes:
7 5000 M.L ITEM # 48 M.L
welds vacuum Box test
Close Man-way, Clean out Door Flanges for Close Man-way, Clean out Door
8 354 Dim.Inch ITEM # 45 Dim.Inch
applying hydro- test Flanges for applying hydro- test
Supply, Fabricate ,Installsteel structure for roof Supply, Fabricate ,Installsteel
handrail and wind breaker structure for tank roof
9 900 kg ITEM # 46 kg
Open necessary access at tank roof for Open necessary access at tank roof
inspection and re-weld (open five windows at for inspection and re-weld
10 the upper deck for inspection and repair) outer 67.5 SQ.M ITEM # 33 SQ.M
pontoon
Sandblasting and painting tank externally Apply external painting system according
11 194.5 SQ.M ITEM# 50 to company specification including SQ.M
sandblasting and washing
Apply fiberglass lining system for tank
bottom and water zone of shell
completely including sandblasting and
12 Apply Fiberglass 3161.7 SQ.M ITEM # 52 painting primer - lining thickness 3000 SQ.M
micron (thick film)
19 Check and evaluate tank shell roudness – out of 1 Each D-DIAM 61-1 Check and evaluate tank shell Each
service roudness – out of service
Dismantling of existing pantograph mechanical Dismantling of existing pantograph
20 seal 1 Each D- DIAM 61 - 5 mechanical seal Each
demolish existing extra bottom layer demolish existing extra bottom layer
23 2920 SQ.M ITEM # 3 SQ.M