2. Alternate heading to be intercept ±120° or From OBS set ±60° 3. CDI move center 4. 2 Dot before come out heading
Cut 90 (60-89°)
1. Alternate heading radial to be intercept ±90° or from OBS set ±90°
2. OBS set to reciprocal radial to be intercept 3. CDI moves, OBS set ±20° follow CDI 4. CDI move to center, back to ±20° before 5. Make Simple Procedure
Parallel (90-179°)
1. Alternate heading radial to be intercept
2. OBS set reciprocal radial to be intercept 3. Abeam - Timing 90” - Check distance at 60” 4. CDI move or passing center, Make Simple procedure 5. If CDI not move, make Cut 90 Procedure
VOR OUTBOND
Simple (0-119°)
1. Alternate heading radial to be intercept ±60°
2. OBS set equal radial to be intercept 3. CDI move to center 4. Set heading equal heading to be intercept
Paralel (120-179°)
1. Alternate heading equal radial to be intercept
2. OBS set equal radial to be intercept 3. After Abeam, sensing FROM 4. Make Simple Procedure