DAYS CARPENTER WORK

1st TIMBER STAY, DESHUTTERING, BRACKET


FIXING, SHUTTERING VERTICAL PANNELS
2nd DESHUTTERING & SHUTTERING VERTICAL
PANNELS
3rd BEAM DECKING & DESHUTTERING OF
PREVIOUS SLAB & PROPS REFIX
4rth SLAB DECKING, SHUTTERING WORK, STAIRCASE
SHUTTERING
5th LEVEL CHECKING, SHUTTERING SHOULD BE
COMPLETE WITH SUPPORTING
SUNK SHUTTERING FIXING CHECKING OF
6th
ALUFORM

WALL TIES & EXTRA PIN WEDGES FIXING,


7th
SUPPORTING, LINE WORK & CLIENT CHECKING
FITTER WORK

STEEL SHIFTING, COLUMN STEEL BINDING

COMLETE COLUMN STEEL BINDING

EVENING STEEL SHIFTING FOR BEAM R/F


BINDING

BEAM STEEL BINDING WORK

STAIRCASE, SLAB STEEL BINDING

SLAB STEEL BINDING, NS WALL BINDING


CHECKING,CONDUITING WORK

COVERING FOR STEEL, HOUSEKEEPING


LABOUR WORK

LAITANCE CHIPPING,CLEANING, CURING

CURING, WALL TIE SLEEVE REMOVING, REPAIRING, ETC

CURING, CLEANING, HOLE FILLING, OUTER AREA & LIFT

HOLE FILLING, REPAIRING TIE ROD PVC CONE REMOVING,


BARRICATION
HOLE FILLING, HOUSE KEEPING, SAND, CEMENT SHIFTING
FOR WATA(BUNDS) MAKING FOR MIVAN

WATA MAKING FOR MIVAN & HOUSE KEEPING

FOAM FILLING IN SUNK & OTHER HOUSEKEEPING WORK