MLM Engineering

Sample Two Storey Residential Building-WBS

Item/Description

1 General Requirements
1.1 Architetural & Engineering Design
1.2 Permits & Licences
1.3 Mobilization/Demobilization
1.4 Temporary Facilities
1.5 Project Management
2 Existing Condition
2.1 Site clearing
2.2 Site Survey/Investigation
3 Earthworks
3.1 Excavation
3.2 Backfilling
4 Concrete
4.1 Footing
4.1.1 Column footing
4.1.1.1
4.1.1.2
4.1.2 Wall footing
4.1.2.1
4.1.2.2
4.1.3 Stair footing
4.1.3.1
4.1.3.2
4.2 Grade beams
4.2.1 Grade 40, Reinforcement bars
4.2.2 Grade 21 Concrete
4.3 Ground slab
4.2.1 Grade 40, Reinforcement bars
4.2.2 Grade 21 Concrete
4.4 Columns
4.2.1 Grade 40, Reinforcement bars
4.2.2 Forms
4.2.3 Grade 21 Concrete
4.5 Floor beams
4.5.1 Grade 40, Reinforcement bars
4.5.2 Forms
4.5.3 Grade 21 Concrete
4.6 Suspended slab
4.6.1 Grade 40, Reinforcement bars
4.6.2 Forms
4.6.3 Grade 21 Concrete
4.7 Stairs
4.7.1 Grade 40, Reinforcement bars
4.7.2 Forms
4.7.3 Grade 21 Concrete
4.8 Roof beams
4.7.1 Grade 40, Reinforcement bars
4.7.2 Forms
4.7.3 Grade 21 Concrete
5 Masonry
5.1 Exterior Walls
5.2 Interior walls
6 Metals
6.1 Structural metals
6.1.1 Structural steel roof trusses and rafters
6.1.2 Purlins
6.2 Architectural metals
6.2.1 Stair railings
6.2.2 Balcony railings
7 Wood, Plastics, and Composites
7.1 Carpentry
7.2 Ceiling
8 Thermal and Moisture Protection
8.1 Roof sheets
8.2 Insulations
8.3 Waterproofing
9 Openings
9.1 Doors
9.2 Windows
10 Finishes
10.1 Plastering
10.2 Painting
10.3 Tiles
11 Plumbing
11.1 Sewer Line
11.2 Cold Waterline
11.3 Storm Drainage
11.4 Sanitary Fixtures
11.4.1 Lavatory
11.4.2 Water Closet
11.4.3 Kitchen Faucet
11.4.4 Lavatory Faucet
11.4.4 Shower head
11.5 Septic Vault
12 Electrical
12.1 Conduits, Boxes and Fittings and Power Outlets
12.2 Wires and Wiring Devices
12.3 Lighting Fixtures
12.4 Panel Board
13 Exterior Improvements
13.1 Landscape
13.2 Fence & Gate
ey Residential Building-WBS

Item/Description UM QTY

Architetural & Engineering Design lot


Permits & Licences lot
Mobilization/Demobilization lot
Temporary Facilities lot
Project Management lot

lot
Site Survey/Investigation lot

cu-m
cu-m

Column footing
Grade 40, Reinforcement bars kg
Grade 21 Concrete cu-m
Wall footing
Grade 40, Reinforcement bars kg
Grade 21 Concrete cu-m
Stair footing
Grade 40, Reinforcement bars kg
Grade 21 Concrete cu-m

Grade 40, Reinforcement bars kg


Grade 21 Concrete cu-m

Grade 40, Reinforcement bars kg


Grade 21 Concrete cu-m

Grade 40, Reinforcement bars kg


sq-m
Grade 21 Concrete cu-m

Grade 40, Reinforcement bars kg


sq-m
Grade 21 Concrete cu-m 10
Suspended slab
Grade 40, Reinforcement bars kg
sq-m
Grade 21 Concrete cu-m
Grade 40, Reinforcement bars kg
sq-m
Grade 21 Concrete cu-m

Grade 40, Reinforcement bars kg


sq-m
Grade 21 Concrete cu-m

sq-m
sq-m

Structural metals
Structural steel roof trusses and rafters kg
lin-m
Architectural metals
Stair railings lot
Balcony railings lot
Plastics, and Composites
lot
sq-m
and Moisture Protection
sq-m
sq-m
sq-m

ea
ea

sq-m
sq-m
sq-m

lin-m
lin-m
lin-m

Lavatory ea
Water Closet ea
Kitchen Faucet set
Lavatory Faucet set
Shower head set
lot

Conduits, Boxes and Fittings and Power Outlets lot


Wires and Wiring Devices lot
ea
ea

sq-m
lot
UNIT PRICE UNIT PRICE UNIT PRICE UNIT PRICE UNIT PRICE
(INDIRECTS) (MATERIALS) (LABOR) (EQUIPMENT) (TOTAL)

3,342.15 1,348.20 378.00 5,068.35


TOTAL PRICE

50,683.50 TRUE